Aspects of Surveying inConstruction
CIVIL ENGINEERING DESIGN 1forSTRUCTURAL STEELWORK DESIGN
2011
-
8/3/2019 Aspect of Surveying in Construction 2
2/28
3. THE PROJECTThe SitePutra interstate coach terminal is located at
Jalan Putra, Kuala Lumpur, latitude 3 degree10 2 North of the Equator and longitude 101
degree 41 25 East of the Prime Meridian.
Any Project has Spatial Aspect
-
8/3/2019 Aspect of Surveying in Construction 2
3/28
Spatial Aspect of Project
b) The Brief
i) Brief Manifesto
The brief calls for the design of a high rise mixed-used
tower building to be situated at Terminal Putra, KualaLumpur.
The students are expected to contain the site limitationor boundaries are as per the existing footprints of thePutra Coach terminal respecting all statutory and theDewan Bandaraya Kuala Lumpur Urban Designguidelines (UDG).
-
8/3/2019 Aspect of Surveying in Construction 2
4/28
List of Surveys Activities
Recce survey
Topo survey/plan
Original Ground Level (OGL)
Boundary Survey Pre-construction plan
Setting out survey/plan
Building pegging Construction survey
As-built plan
-
8/3/2019 Aspect of Surveying in Construction 2
5/28
Why Require Survey ?
Requirement by Law
Pre-construction
Setting-out
Requirement by Practice
Topo survey
Boundary survey
As-built plan
Construction survey
-
8/3/2019 Aspect of Surveying in Construction 2
6/28
Requirement by Law
Uniform Building by-Law 1984 Part II Submission of Plans For Approval
Para 10. Plans required.
-
8/3/2019 Aspect of Surveying in Construction 2
7/28
Pre-construction survey plan
-
8/3/2019 Aspect of Surveying in Construction 2
8/28
-
8/3/2019 Aspect of Surveying in Construction 2
9/28
-
8/3/2019 Aspect of Surveying in Construction 2
10/28
The site of the proposed building lot
-
8/3/2019 Aspect of Surveying in Construction 2
11/28
The means of access to the site from the street and thename of the street.
-
8/3/2019 Aspect of Surveying in Construction 2
12/28
Complete lines of surface water and foulwater drainage
-
8/3/2019 Aspect of Surveying in Construction 2
13/28
Requirement by Law
Para 23. Notice of Completion of settingout
(1)As soon as the setting out of building has been
completed, the qualified person shall give written noticeto the local authority in Form C in the Second Schedule
Hence requires setting out plan
-
8/3/2019 Aspect of Surveying in Construction 2
14/28
-
8/3/2019 Aspect of Surveying in Construction 2
15/28
Setting Out Plan
-
8/3/2019 Aspect of Surveying in Construction 2
16/28
Setting Out Plan
-
8/3/2019 Aspect of Surveying in Construction 2
17/28
Setting Out Plan
-
8/3/2019 Aspect of Surveying in Construction 2
18/28
Setting Out Data
585.10
200.153200.149600.176400.184dist22
"'52.151222
40816.0tan8.9
4
N 184.400
E 149.200
N 176.600E 153.200
CP
P1
Dist CP to P1 is 10.585 mBearing CP to P1 is
3334747.4
-
8/3/2019 Aspect of Surveying in Construction 2
19/28
Requirement by Practice Topo survey
Boundary survey As-built plan
Construction survey
-
8/3/2019 Aspect of Surveying in Construction 2
20/28
Boundary Survey
Correct site
Project within the boundary of proposedsite
the site limitation or boundaries are as per the existing
footprints of the Putra Coach terminal
-
8/3/2019 Aspect of Surveying in Construction 2
21/28
Topo, Boundary, OGL (other details?)
-
8/3/2019 Aspect of Surveying in Construction 2
22/28
From Topo Survey
Engineer and architect will base theirdesign
Retaining wall required?
Cut and fill required?
Point of discharge of proposed drains
etc
-
8/3/2019 Aspect of Surveying in Construction 2
23/28
Construction Start
Construction survey
Control of verticality
-
8/3/2019 Aspect of Surveying in Construction 2
24/28
-
8/3/2019 Aspect of Surveying in Construction 2
25/28
As-built plan (building, road, sewerage)
-
8/3/2019 Aspect of Surveying in Construction 2
26/28
Spatial aspectOf project
Recce survey
Topo survey
Pre-const survey
design
Setting-out survey/Building pegging
ConstructionTake place
Construction survey
As-built survey plan
-