docket no. 43695 application of southwestern …...2 a. i have an associate degree in applied...
TRANSCRIPT
-
Bellinghausen Direct – Revenue Requirement Page 1
DOCKET NO. 43695
APPLICATION OF SOUTHWESTERN
PUBLIC SERVICE COMPANY FOR
AUTHORITY TO CHANGE RATES
§
§
§
PUBLIC UTILITY COMMISSION
OF TEXAS
DIRECT TESTIMONY
of
ALAN L. BELLINGHAUSEN
on behalf of
SOUTHWESTERN PUBLIC SERVICE COMPANY
(Filename: BellinghausenRRDirect.doc)
Table of Contents
GLOSSARY OF ACRONYMS AND DEFINED TERMS................................................ 2
LIST OF ATTACHMENTS ............................................................................................... 3
I. WITNESS IDENTIFICATION AND QUALIFICATIONS .................................. 4
II. ASSIGNMENT AND SUMMARY OF TESTIMONY AND
RECOMMENDATIONS ........................................................................................ 7
III. AFFILIATE EXPENSES FOR THE TRANSMISSION &
SUBSTATIONS CLASS OF SERVICES .............................................................. 9
A. SUMMARY OF AFFILIATE EXPENSES FOR THE TRANSMISSION &
SUBSTATIONS CLASS OF SERVICES .............................................................. 9
B. THE TRANSMISSION & SUBSTATIONS CLASS OF SERVICES ARE
NECESSARY SERVICES ............................................................................... 18
C. THE TRANSMISSION & SUBSTATIONS CLASS OF SERVICES ARE
PROVIDED AT A REASONABLE COST .......................................................... 23
1. OBJECTIVE EVIDENCE (BENCHMARKING) ........................................... 23
2. BUDGET PLANNING ............................................................................. 24
3. COST TRENDS ...................................................................................... 25
4. STAFFING TRENDS ............................................................................... 26
5. COST CONTROL AND PROCESS IMPROVEMENT INITIATIVES ................ 27
D. THE COSTS FOR THE TRANSMISSION & SUBSTATIONS CLASS OF
SERVICES ARE PRICED IN A FAIR MANNER ................................................. 28
IV. CONCLUSION ..................................................................................................... 33
AFFIDAVIT ..................................................................................................................... 34
RR10 - Page 197 of 502 04565
-
Bellinghausen Direct – Revenue Requirement Page 2
GLOSSARY OF ACRONYMS AND DEFINED TERMS
Acronym/Defined Term
Meaning
Costs or costs
O&M expenses and administrative and general
expenses collectively
FERC
Federal Energy Regulatory Commission
NERC North American Electric Reliability Corporation
O&M
operation and maintenance
Operating Companies
Northern States Power Company, a Minnesota
corporation; Northern States Power Company, a
Wisconsin corporation; PSCo; and SPS
Operating Company One of the Operating Companies
PSCo Public Service Company of Colorado, a Colorado
corporation
SAIDI System Average Interruption Duration Index
SPP Southwest Power Pool
SPS Southwestern Public Service Company, a New
Mexico corporation
Test Year July 1, 2013 through June 30, 2014
Total Company or total
company
Total SPS (before any jurisdictional allocation)
TRO Transmission Resource Optimization
Xcel Energy Xcel Energy Inc.
XES Xcel Energy Services Inc.
RR10 - Page 198 of 502 04566
-
Bellinghausen Direct – Revenue Requirement Page 3
LIST OF ATTACHMENTS
Attachment
Description
ALB-RR-1
Organization Chart - Transmission
(Non-native format)
ALB-RR-A Summary of XES Expenses to SPS by Affiliate
Class and Billing Method
(Filename: ALB-RR-A.xls)
ALB-RR-B XES Expenses to all Affiliates by Affiliate Class,
Activity, Billing Method and FERC Account
(Filename: ALB-RR-B.xls)
ALB-RR-C Exclusions from XES Expenses to SPS by Affiliate
Class and FERC Account
(Filename: ALB-RR-C.xls)
ALB-RR-D Pro Forma Adjustments to XES Expenses by
Affiliate Class and FERC Account
(Filename: ALB-RR-D.xls)
RR10 - Page 199 of 502 04567
-
Bellinghausen Direct – Revenue Requirement Page 4
DIRECT TESTIMONY
OF
ALAN L. BELLINGHAUSEN
I. WITNESS IDENTIFICATION AND QUALIFICATIONS 1
Q. Please state your name and business address. 2
A. My name is Alan L. Bellinghausen. My business address is 600 South Tyler 3
Street, Amarillo, Texas 79101. 4
Q. On whose behalf are you testifying in this proceeding? 5
A. I am filing testimony on behalf of Southwestern Public Service Company 6
(“SPS”), a New Mexico corporation and wholly-owned electric utility subsidiary 7
of Xcel Energy Inc. (“Xcel Energy”). Xcel Energy is a registered holding 8
company that owns several electric and natural gas utility operating companies.1 9
Q. By whom are you employed and in what position? 10
A. I am employed by SPS, as Regional Director, Substation Operations and 11
Maintenance. 12
Q. Please briefly outline your responsibilities as Regional Director, Substation 13
Operations and Maintenance. 14
A. I am responsible for the operation and maintenance (“O&M”) of SPS’s 15
transmission and distribution substations in Texas and New Mexico, and 16
transmission-only facilities in Oklahoma and Kansas. 17
1 Xcel Energy is the parent company of four wholly-owned electric utility operating companies:
Northern States Power Company, a Minnesota corporation; Northern States Power Company, a Wisconsin
corporation; Public Service Company of Colorado, a Colorado corporation (“PSCo”); and SPS
(collectively, “Operating Companies”; individually, “Operating Company”). Xcel Energy’s natural gas
pipeline subsidiary is WestGas InterState, Inc. Xcel Energy also has two transmission-only operating
companies, Xcel Energy Southwest Transmission Company, LLC and Xcel Energy Transmission
Development Company, LLC, which are regulated by the Federal Energy Regulatory Commission
(“FERC”).
RR10 - Page 200 of 502 04568
-
Bellinghausen Direct – Revenue Requirement Page 5
Q. Please describe your educational background. 1
A. I have an Associate Degree in Applied Science Management Development from 2
Amarillo College in Amarillo, Texas. 3
Q. Please describe your professional experience. 4
A. I have worked in the electric utility industry since 1975. All of my experience has 5
been with Xcel Energy and its predecessor companies. From 1975 to 1992, I 6
worked in the Substation Construction Department, starting as an apprentice 7
electrician and becoming substation general foreman in 1986. From 1993 to 8
1996, I was employed as the division supervisor for the Panhandle Substation 9
Operations and Maintenance department. In 1996, I worked on a one-year 10
assignment in support of the SPS and PSCo merger, following which I worked as 11
the manager for the Texas North Substation Operations and Maintenance 12
department through 2006. In 2007, I became interim manager for SPS Substation 13
Construction, Operations and Maintenance, and in 2008, I became the Regional 14
Director, Substation Construction Operations and Maintenance for the SPS 15
region. As of 2012, my title was changed to Regional Director, Substation 16
Operations and Maintenance, and my responsibilities for Substation Construction 17
were shifted to the Transmission Field Operations organization. 18
Q. Are you a member of any professional organizations? 19
A. Yes. I am a Senior Member of the Institute of Electrical and Electronics 20
Engineers. 21
RR10 - Page 201 of 502 04569
-
Bellinghausen Direct – Revenue Requirement Page 6
Q. Have you filed testimony before any regulatory authorities? 1
A. Yes. I filed testimony at the Public Utility Commission of Texas in Docket Nos. 2
40824 and 42004 on the Transmission & Substations class of affiliate costs and in 3
Docket No. 38147 on the Transmission & Substations and the Safety classes of 4
affiliate costs. 5
RR10 - Page 202 of 502 04570
-
Bellinghausen Direct – Revenue Requirement Page 7
II. ASSIGNMENT AND SUMMARY OF TESTIMONY AND 1 RECOMMENDATIONS 2
Q. What is your assignment in this proceeding? 3
A. I support the Test Year (July 1, 2013 through June 30, 2014, “Test Year”) O&M 4
expenses and the administrative and general expenses (collectively, “costs” or 5
“Costs”) for the Transmission & Substations class of affiliate services. In regard 6
to this affiliate class, my testimony will: 7
describe the services included in the class; 8
explain that those services are reasonable and necessary for SPS’s 9 operation; 10
explain that the costs for those services are reasonable and necessary; 11
explain that these services do not duplicate services that SPS provides 12 to itself through its own employees or that are provided from any other 13
source; and 14
explain that charges from Xcel Energy Services Inc. (“XES”), the 15 service company subsidiary of Xcel Energy, to SPS for those services 16
are no higher than the charges to SPS affiliates for the same or similar 17
services. 18
Q. Please summarize the recommendations and conclusions in your testimony. 19
A. The Test Year costs that SPS seeks to recover for the services of the Transmission 20
& Substations affiliate class of $5,257,125 (total SPS before jurisdictional 21
allocations, “total company” or “Total Company”) are reasonable and necessary 22
because they support SPS’s ability to provide electric service to its Texas retail 23
customers. 24
The costs are for services provided by XES that are necessary to the 25 planning, siting, design, construction, operation, and maintenance of 26
SPS’s transmission assets. 27
RR10 - Page 203 of 502 04571
-
Bellinghausen Direct – Revenue Requirement Page 8
The costs are reasonable because they are shared with other affiliates, 1 consist primarily of reasonable personnel costs, and are subjected to 2
rigorous budgeting and cost control processes. 3
SPS does not provide these services for itself, and the services do not 4 duplicate services provided by others. 5
The charge from SPS’s affiliate for these services is no higher than the 6 charge by that affiliate to any other entity for the same or similar 7
service, and the costs reasonably approximate the affiliate’s cost to 8
provide the service. 9
RR10 - Page 204 of 502 04572
-
Bellinghausen Direct – Revenue Requirement Page 9
III. AFFILIATE EXPENSES FOR THE TRANSMISSION & 1 SUBSTATIONS CLASS OF SERVICES 2
Q. Earlier in your testimony, you referred to an “affiliate class.” What do you 3
mean by the terms “affiliate class” or “affiliate class of services”? 4
A. A portion of SPS’s costs reflect charges for services provided by a supplying 5
affiliate, specifically XES or one of the Operating Companies. These charges 6
have been grouped into various affiliate classes, or aggregations of charges, based 7
upon the business area, organization, or department that provided the service or, 8
in a few instances, the accounts that captured certain costs. In her direct 9
testimony, SPS witness Janet S. Schmidt-Petree provides a detailed explanation of 10
how the affiliate classes were developed and are organized for this case. 11
Q. Which affiliate class do you sponsor? 12
A. I sponsor the Transmission & Substations class of affiliate services. 13
A. Summary of Affiliate Expenses for the Transmission & 14
Substations Class of Services 15
Q. Where does the Transmission & Substations affiliate class fit into the overall 16
affiliate structure? 17
A. Attachment JSSP-RR-6 to Ms. Schmidt-Petree’s direct testimony provides a list 18
and a pictorial display of all affiliate classes, dollar amounts for those classes, and 19
sponsoring witness for each class. As seen on that attachment, the Transmission 20
& Substations affiliate class was part of the Transmission business area during the 21
Test Year. Attachment ALB-RR-1 to my testimony is an organization chart 22
showing the Transmission organization. 23
RR10 - Page 205 of 502 04573
-
Bellinghausen Direct – Revenue Requirement Page 10
Q. What services are grouped into the Transmission & Substations affiliate 1
class? 2
A. The services that are grouped into the Transmission & Substations affiliate class 3
are the oversight of the planning, siting, design, construction, operation, and 4
maintenance of transmission assets. 5
Q. What is the dollar amount of the Test Year XES charges that SPS requests, 6
on a total company basis, for the Transmission & Substations affiliate class? 7
A. The following table summarizes the dollar amount of the Test Year XES charges 8
for the Transmission & Substations affiliate class. The table headings are 9
explained following the table. 10
Table ALB-RR-1 11
Requested Amount of XES Class Expenses
Billed to SPS (Total Company)
Class of
Services
Total XES
Class
Expenses
Requested
Amount
% Direct
Billed % Allocated
Transmission
& Substations $28,116,097 $5,257,125 67% 33%
12
Total XES Class Expenses
Dollar amount of total Test Year expenses that
XES charged to all Xcel Energy companies for
the services provided by this affiliate class. This
is the amount from Column F in Attachment
ALB-RR-A, which I will discuss in the next
question.
Requested Amount of XES
Class Expenses Billed to SPS
(Total Company)
Requested dollar amount of XES expenses to
SPS (total company) for this affiliate class after
exclusions and pro forma adjustments. This is
the amount from Column L in Attachment
ALB-RR-A.
RR10 - Page 206 of 502 04574
-
Bellinghausen Direct – Revenue Requirement Page 11
% Direct Billed The percentage of SPS’s requested XES
expenses (total company) for this class that were
billed 100% to SPS.
% Allocated The percentage of SPS’s requested XES
expenses (total company) for this class that were
allocated to SPS.
Q. Please describe the attachments that support the information provided in 1
Table ALB-RR-1. 2
A. There are four attachments to my testimony that present information about the 3
requested SPS affiliate expenses for the Transmission & Substations affiliate 4
class. 5
Attachment ALB-RR-A: Provides a summary of the affiliate expenses 6
for this class. The summary starts with the total of the XES expenses to all Xcel 7
Energy affiliates for the services provided by this affiliate class and ends with the 8
requested dollar amount of XES expenses to SPS (total company) for this affiliate 9
class after exclusions and pro forma adjustments. The columns on this attachment 10
provide the following information. 11
Column A — Line number Lists the Attachment line numbers.
Column B —
Business Area
Provides the business area associated
with the affiliate class.
Column C —
Affiliate Class
Lists the affiliate class.
RR10 - Page 207 of 502 04575
-
Bellinghausen Direct – Revenue Requirement Page 12
Column D —
Billing Method
(Work Order)
Shows the billing method code that
XES uses to charge the expenses to the
affiliates, and the billing method short
title. In her direct testimony, Ms.
Schmidt-Petree explains the billing
methods and defines the codes.
Column E —
Allocation Method
Shows the allocation method applicable
to the billing method (work order).
Column F —
Total XES Billings
for Class to all Legal
Entities (FERC Acct.
400-935)
Shows the total XES billings to all
affiliates (i.e., Xcel Energy legal
entities), including SPS, for FERC
Accounts 400 through 935 for the
affiliate class.
Column G —
XES Billings for
Class to all Legal
Entities Except for
SPS (FERC Acct.
400-935)
Shows XES billings to all affiliates,
other than to SPS, for FERC Accounts
400 through 935 for the affiliate class.
Column H —
XES Billings for
Class to SPS (total
company) (FERC
Acct. 400-935)
Shows XES billings to SPS (total
company) for the affiliate class. The
sum of the dollar amounts in Columns
G and H equal the dollar amount in
Column F.
Column I —
Exclusions
Shows the total dollars to be excluded
from Column H. Exclusions reflect
expenses not requested, such as
expenses not allowed or other below-
the-line items.
Column J —
Per Book
Shows XES billings to SPS (total
company), for the affiliate class, after
the exclusions shown in Column I. The
dollar amount in Column J is Column
H plus Column I.
RR10 - Page 208 of 502 04576
-
Bellinghausen Direct – Revenue Requirement Page 13
Column K —
Pro Formas
Shows the total dollar amount of pro
forma adjustments to the dollar amount
in Column J. Pro forma adjustments
reflect revisions for known and
measurable changes to Test Year
expenses.
Column L —
Requested Amount
(total company)
Shows the requested amount (total
company) for the affiliate class. The
dollar amount in Column L is Column J
plus Column K.
Column M —
Percentage of class
charges
Shows the percentage of affiliate class
charges billed using the work order.
In her direct testimony, Ms. Schmidt-Petree describes in detail the 1
calculations that take the dollars of Total XES Billings in Column F to the 2
Requested Amount in Column L. 3
Attachment ALB-RR-B: Provides the detail of the XES expenses for the 4
Transmission & Substations affiliate class that are summarized on Attachment 5
ALB-RR-A. The detail shows the XES expenses for the Transmission & 6
Substations affiliate class, itemized by the amount going to each legal entity 7
receiving the expense (Xcel Energy or one of its subsidiaries), and with each 8
expense listed by individual work order, activity, and billing method. When 9
summed, these amounts tie to the amounts shown on Attachment ALB-RR-A and 10
the detail regarding the expenses is organized to support that attachment. 11
Specifically, the columns on this attachment provide the following information. 12
RR10 - Page 209 of 502 04577
-
Bellinghausen Direct – Revenue Requirement Page 14
1
Column A — Line Number Lists the Attachment line numbers.
Column B —
Legal Entity
Receiving XES
Expense
Shows the legal entity (Xcel Energy or
one of its subsidiaries) that received the
XES expense.
Column C —
Affiliate Class
Lists the affiliate class.
Column D —
Activity
The short title for the activity.
Column E —
Billing Method
(Work Order)
The billing method code and short title.
In her direct testimony, Ms. Schmidt-
Petree explains the billing methods and
defines the codes.
Column F —
FERC Account
Shows the FERC Account in which the
expense was recorded.
Column G —
Total XES Billings
for Class to all Legal
Entities (FERC Acct.
400-935)
Shows the itemized amount of the
listed XES expense that was billed to
the listed legal entity. The itemized
amounts are then summed to show the
total XES billings to all affiliates (i.e.,
Xcel Energy legal entities) by work
order and FERC Account for the
affiliate class. The total dollar amount
for the affiliate class in Column G ties
to the total dollar amount for the
affiliate class in Column F of
Attachment ALB-RR-A.
RR10 - Page 210 of 502 04578
-
Bellinghausen Direct – Revenue Requirement Page 15
Column H —
XES Billings for
Class to all Legal
Entities Except for
SPS (FERC Acct.
400-935)
Shows the same information as
provided in Column G, except that
billings to SPS are excluded from this
column. Therefore, the sum of this
column provides total billings to all
legal entities other than SPS and ties to
the total dollar amount for the affiliate
class in Column G of Attachment
ALB-RR-A.
Column I —
XES Billings for
Class to SPS (Total
Company) (FERC
Acct. 400-935)
Shows the same information as
provided in Column G, except that only
billings to SPS are included. (The
dollar amounts in Columns H and I
equal the dollar amount in Column G.)
Therefore, the sum of this column
provides total billings to SPS and ties to
the total dollar amount for the affiliate
class in Column H of Attachment
ALB-RR-A.
Attachment ALB-RR-C: Both Attachments ALB-RR-A and ALB-RR-B 1
show exclusions to the XES expenses billed to SPS for the Transmission & 2
Substations affiliate class (Attachment ALB-RR-A, Column I; Attachment 3
ALB-RR-B, Column J). Attachment ALB-RR-C provides detail about those 4
exclusions listed on Attachments ALB-RR-A and ALB-RR-B. The columns on 5
this Attachment ALB-RR-C provide the following information. 6
Column A — Line Number Lists the Attachment line numbers.
Column B —
Affiliate Class
Lists the affiliate class.
Column C —
FERC Account
The FERC Account for the expense
that has been excluded.
RR10 - Page 211 of 502 04579
-
Bellinghausen Direct – Revenue Requirement Page 16
Column D —
Explanations for
Exclusions
Brief rationale for the exclusion.
Column E —
Exclusions (total
company)
Dollar amount of the exclusion.
In her direct testimony, Ms. Schmidt-Petree describes the calculations 1
underlying the exclusions. 2
Attachment ALB-RR-D: Both Attachments ALB-RR-A and ALB-RR-B 3
show pro forma adjustments to SPS’s per book expenses for the Transmission & 4
Substations affiliate class (Attachment ALB-RR-A, Column K; Attachment 5
ALB-RR-B, Column L). Attachment ALB-RR-D provides information about 6
those pro forma adjustments shown on Attachments ALB-RR-A and ALB-RR-B. 7
The columns on this attachment provide the following information. 8
Column A — Line Number Lists the Attachment line numbers.
Column B —
Affiliate Class
Lists the affiliate class.
Column C —
FERC Account
The FERC Account affected by the pro
forma adjustment.
Column D —
Explanations for Pro
Formas
Brief rationale for the pro forma
adjustment.
Column E —
Sponsor
The witness or witnesses who sponsor
the pro forma adjustment.
Column F —
Pro Formas (total
company)
Dollar amount of the pro forma
adjustment.
RR10 - Page 212 of 502 04580
-
Bellinghausen Direct – Revenue Requirement Page 17
Q. Does XES bill all of its expenses for the Transmission & Substations affiliate 1
class to SPS? 2
A. No. XES bills the majority of its expenses for the Transmission & Substations 3
affiliate class to affiliates other than SPS. SPS receives approximately 19% of 4
total XES billings for the Transmission & Substations class, as shown on 5
Attachment ALB-RR-A (Columns F, G, and H) and Attachment ALB-RR-B 6
(Columns G, H, and I). 7
Q. Are there any exclusions to the XES billings to SPS for the Transmission & 8
Substations affiliate class? 9
A. Yes. As I mentioned earlier, exclusions reflect expenses not requested, such as 10
expenses not allowed or other below-the-line items. Exclusions are shown on 11
Attachment ALB-RR-A, Column I, and on Attachment ALB-RR-B, Column J. 12
The details for the exclusions are provided in Attachment ALB-RR-C. As I also 13
mentioned earlier, Ms. Schmidt-Petree describes how the exclusions were 14
calculated. 15
Q. Are there any pro forma adjustments to SPS’s per book expenses for the 16
Transmission & Substations affiliate class? 17
A. Yes. As I mentioned earlier, pro forma adjustments are revisions to Test Year 18
expenses for known and measurable changes. Pro forma adjustments are shown 19
on Attachment ALB-RR-A, Column K, and on Attachment ALB-RR-B, 20
Column L. The details for the pro forma adjustments, including the witness or 21
witnesses who sponsor each pro forma adjustment, are provided in Attachment 22
ALB-RR-D. 23
RR10 - Page 213 of 502 04581
-
Bellinghausen Direct – Revenue Requirement Page 18
Q. Attachment ALB-RR-D shows that you are a sponsor for pro forma 1
adjustments that result in a decrease for the Transmission & Substations 2
affiliate class of $2,761. Please explain the adjustments. 3
A. The adjustments that I sponsor remove charges for alcoholic beverages (a 4
decrease of $2,564) and adjust a number of other small charges. 5
B. The Transmission & Substations Class of Services are Necessary 6
Services 7
Q. Are the services that are grouped in the Transmission & Substations affiliate 8
class necessary for SPS’s operations? 9
A. Yes. The services grouped in the Transmission & Substations affiliate class are 10
necessary to ensure that the transmission system, which is essential to bringing 11
safe and reliable electric service to SPS’s customers, is appropriately operated and 12
maintained. They are functions required by all utilities and without which SPS 13
would not be able to provide electric service to its customers. 14
Q. What are the specific services that are provided to SPS by the Transmission 15
& Substations affiliate class? 16
A. The specific services that are provided to SPS by the Transmission & Substations 17
affiliate class are: 18
Managing and directing the O&M of transmission lines and 19 substations located in the Texas Panhandle, eastern and southeastern 20
New Mexico, the Oklahoma Panhandle, and southwestern Kansas. 21
The transmission system has transmission lines and substations that 22
operate at 345, 230, 115, and 69 kilovolts. 23
Managing and directing the Operations Center in Amarillo, Texas, 24 which provides round-the-clock operation of the SPS transmission 25
system. The Operations Center monitors load and generation balance, 26
monitors and controls the transmission system, dispatches switching 27
for equipment maintenance, dispatches outage restoration efforts, 28
maintains and drills emergency operations plans, coordinates 29
RR10 - Page 214 of 502 04582
-
Bellinghausen Direct – Revenue Requirement Page 19
operations with electrically adjacent utilities, and participates in 1
regional reliability activities. 2
Providing engineering and design services, system protection services, 3 right of way procurement, maintenance and operations engineering, 4
and project management services for capital project development. 5
Managing transmission system planning, interconnection contracts, 6 and physical projects necessary to interconnect new generation and 7
new end-use customers to the grid. 8
Coordinating with the Southwest Power Pool (“SPP”) on operations, 9 scheduling, and system development; monitoring the activities of the 10
SPP with regard to the impact on the SPS transmission system, 11
providing input to SPP planning, and developing and executing 12
strategic initiatives. 13
Providing oversight of compliance tracking with respect to the North 14 American Electric Reliability Corporation (“NERC”) and Electric 15
Reliability Organization standards; managing the Transmission O&M 16
budget; and providing oversight of the Transmission Resource 17
Optimization (“TRO”) initiative. 18
Tracking performance, providing technical training, establishing 19 maintenance criteria, and establishing standards for the transmission 20
system (including both lines and substations), the electric distribution 21
system (including both lines and substations), and the metering 22
functions of the transmission and distribution electrical system. 23
Managing the corporate-wide transmission organization. 24
Q. Are any of the Transmission & Substations class of services that are provided 25
to SPS duplicated elsewhere in XES or in any other Xcel Energy subsidiary 26
such as SPS itself? 27
A. No. Within XES, none of the services grouped in the Transmission & Substations 28
affiliate class are duplicated elsewhere. No other Xcel Energy subsidiary 29
performs these services for the Operating Companies. In addition, SPS does not 30
perform these services for itself. Although there are both XES and SPS 31
employees in the Transmission organization, the SPS employees do not perform 32
the same activities as the XES employees and they have separate responsibilities 33
and roles. I described earlier the activities of the XES employees. There are also 34
RR10 - Page 215 of 502 04583
-
Bellinghausen Direct – Revenue Requirement Page 20
approximately 315 SPS employees who perform transmission functions. These 1
include system operators, dispatchers, transmission system planners, engineers, 2
designers, engineering technicians, journeymen linemen, journeyman electricians, 3
relay technicians, heavy equipment operators, mechanics, truck drivers, 4
apprentices, working foremen, office support, and in most instances their 5
respective supervisors. The services provided by these SPS employees are not 6
duplicative of services provided by XES employees, although they work in 7
coordination with and under the direction of the XES Transmission business area 8
management. 9
Q. Do SPS’s Texas retail customers benefit from the services that are part of the 10
Transmission & Substations class of services? 11
A. Yes. The services of the Transmission & Substations affiliate class benefit SPS’s 12
customers by supporting the safe and reliable transmission of energy resources 13
from the generators to the distribution system. For example, the Transmission 14
Line Performance department monitors reliability performance and develops 15
reliability improvement plans for the transmission lines that are used to transport 16
electricity to SPS’s customers. The reliability improvement plan that the 17
department developed for 2010 through 2013 included initiatives for: 18
replacement of poles, cross arms, and switches that were nearing their end of life; 19
reinforcement of poles on transmission lines where replacement was not yet 20
necessary; and enhancement of vegetation management for transmission. The 21
plan developed by the department for 2013 through 2018, includes reliability 22
improvement initiatives that are focused on: patrol-based end of life replacements 23
RR10 - Page 216 of 502 04584
-
Bellinghausen Direct – Revenue Requirement Page 21
on transmission structures and transmission switches; individual circuit renewal 1
and refurbishment on the worst performing circuits; and adding or upgrading 2
transmission lines and developing mitigation plans to improve reliability on high 3
usage lines. 4
Similarly, the Substation System Performance department monitors 5
reliability performance and develops reliability improvement plans for the 6
transmission and distribution substations that are necessary for providing 7
electricity to SPS’s customers. The plan for 2013 through 2018 includes 8
reliability improvement initiatives focused on: infrastructure renewal with the 9
replacement of equipment that is at or near end of life; prioritized maintenance of 10
transmission and distribution circuit breakers, transmission and distribution 11
transformers, distribution voltage regulators, and transmission instrument 12
transformers that are deemed to present the highest risk to the system; installation 13
of substation animal deterrent systems; upgrades of substation perimeter fences; 14
installation of protective schemes to allow reclosing after bus faults caused by 15
animals; and installation of additional Remote Terminal Units at distribution 16
substations. Ongoing maintenance activities include the performance of condition 17
assessments on relay protection schemes and batteries, and diagnostics on circuit 18
breakers, transformers, and regulators. 19
Q. What are the trends with regard to the reliability statistics for the SPS 20
transmission system? 21
A. The primary reliability metric tracked is the System Average Interruption 22
Duration Index (“SAIDI”), which is defined as the average number of minutes 23
RR10 - Page 217 of 502 04585
-
Bellinghausen Direct – Revenue Requirement Page 22
that a customer is interrupted in a given time period due to an outage. SAIDI is 1
tracked at several levels, including distribution line, distribution substation, 2
transmission line, and transmission substation. Table ALB-RR-2 reflects the 3
SAIDI for the previous five years for transmission lines and all substations. 4
Table ALB-RR-2 5
Year Transmission
Line
SAIDI
Transmission
Substation
SAIDI
Distribution
Substation
SAIDI
Total Transmission
& Substation
SAIDI
2013 13.48 3.49 3.48 20.45
2012 7.22 1.50 9.25 17.97
2011 11.41 1.60 15.24 28.25
2010 1.06 0.98 9.13 11.17
2009 10.55 0.19 10.10 20.84
The 2013 SAIDI for transmission lines and substations totaled 20.45 6
minutes which was an increase of 2.48 minutes over the 2012 level. The increase 7
was due to a single outage in Carlsbad, New Mexico that was caused by an oil 8
field truck that ran off the road and significantly damaged a transmission line 9
structure with multiple transmission line circuits. The outage was lengthy 10
because the local law enforcement agency considered the location a crime scene 11
and would not allow SPS crews access to the structure to make repairs for several 12
hours.2 This single event impacted the 2013 SAIDI by 2.92 minutes. Had this 13
event not taken place, the 2013 SAIDI would have been 17.53 which would have 14
been an improvement of 0.44 minutes over the 2012 total of 17.97 minutes. The 15
higher total of 28.25 minutes in 2011 was attributed primarily to two outages on 16
2 The accident occurred when the driver of the truck was stabbed by his estranged wife who was a
passenger.
RR10 - Page 218 of 502 04586
-
Bellinghausen Direct – Revenue Requirement Page 23
radial transmission lines, one caused by a grassfire and the other by a structure 1
that failed during a thunderstorm, and an increased number of outages due to 2
circuit breaker failures that increased the distribution substation SAIDI, 3
conditions which were not repeated in 2012. Weather conditions in 2010 were 4
very mild, and the resulting transmission line SAIDI for that year reflects that 5
phenomenon. Comparisons to 2009 results are therefore more meaningful for 6
trending purposes. 7
C. The Transmission & Substations Class of Services are Provided at 8
a Reasonable Cost 9
Q. Are the costs of the Transmission & Substations class of services reasonable? 10
A. Yes. The costs of the Transmission & Substations class of services are 11
reasonable. XES provides these services on a consolidated basis, which provides 12
SPS with the benefit of a pool of talented professionals, economies of scale, and 13
the distribution of the consolidated costs among the Operating Companies. By 14
managing these functions through XES, resources are used as efficiently as 15
possible across the Operating Companies’ transmission organization, resulting in 16
lower costs overall. 17
1. Objective Evidence (Benchmarking) 18
Q. Is there any objective evidence that supports your opinion that the costs of 19
the Transmission & Substations affiliate class are reasonable? 20
A. Yes. SPS witness Richard D. Starkweather presents a comparison of SPS’s 21
transmission O&M expenses with other utilities’ transmission O&M expenses, as 22
reported on the FERC Form 1. The costs of the Transmission & Substations class 23
are reflected within those transmission O&M expenses. In addition, of the 24
RR10 - Page 219 of 502 04587
-
Bellinghausen Direct – Revenue Requirement Page 24
requested costs for the Transmission & Substations class, 75.50% are 1
compensation and benefits costs for XES personnel. SPS witness Jill H. Reed 2
establishes that the level of Xcel Energy’s compensation and benefits is 3
reasonable and necessary. 4
2. Budget Planning 5
Q. Is a budget planning process applicable to the Transmission & Substations 6
class of affiliate costs? 7
A. Yes. Annual O&M budgets are created for the Transmission business area, which 8
includes the Transmission & Substations class of affiliate costs, using guidelines 9
developed at the corporate level. Each manager within the Transmission 10
organization carefully reviews historical spend information, identifies changes 11
that will be coming in the future, and analyzes the costs associated with those 12
changes prior to submitting a proposed budget. The budgeting process is 13
discussed in more detail by SPS witness Raynard A. Gray. 14
Q. During the fiscal year, does the Transmission business area monitor its actual 15
expenditures versus its budget? 16
A. Yes. Actual versus expected expenditures are monitored on a monthly basis by 17
management within each department of the Transmission organization. 18
Deviations are evaluated each month to ensure that costs are appropriate. In 19
addition, action plans are developed to mitigate variations in actual to budgeted 20
expenditures. These mitigation plans may either reduce or delay other 21
expenditures so that overall spending complies with the authorized budget. 22
RR10 - Page 220 of 502 04588
-
Bellinghausen Direct – Revenue Requirement Page 25
Q. Are employees within the Transmission business area held accountable for 1
deviations from the budget? 2
A. Yes. All management employees in the Transmission business area have specific 3
budgetary targets that are measured on a monthly basis to ensure adherence to the 4
targets and provide for action plan development to address variances. All XES 5
Transmission management employees are required to manage their expenses to 6
support the budgetary goals established by their manager. 7
3. Cost Trends 8
Q. Please state the dollar amounts of the actual charges (per book) from XES to 9
SPS for the Transmission & Substations class of services for the three fiscal 10
years preceding the end of the Test Year and the Test Year. 11
A. The following table shows, for the fiscal years 2011, 2012, and 2013 (calendar 12
years) and for the Test Year, the actual per book affiliate charges (Column J on 13
Attachment ALB-RR-A) from XES to SPS for the services grouped in the 14
Transmission & Substations affiliate class: 15
Table ALB-RR-3 16
Actual (Per Book) Charges Over Time
Class of
Services 2011 2012 2013 Test Year
Transmission
& Substations $3,136,849 $3,959,570 $4,996,222 $5,318,567
Q. What are the reasons for this trend? 17
A. The increase in costs from 2011 to 2012 was primarily related to increases in 18
staffing as a result of the seven new departments created in 2010 and additional 19
RR10 - Page 221 of 502 04589
-
Bellinghausen Direct – Revenue Requirement Page 26
staffing in the Transmission Training group. The increase in costs between 2012 1
and 2013 was the result of additional labor costs and employee expenses related 2
to employees transferred from other Operating Companies to XES, and new 3
employees primarily in the engineering, project management, and project control 4
departments that were necessary to meet the demands of the aggressive capital 5
build out of the SPS transmission system. The increase in costs between 2013 6
and the Test Year was due to the additional labor and employee expenses related 7
to the increased headcount in the engineering and project management 8
departments to support the capital build out, as well as consulting fees for 9
validation of facility ratings of the transmission system and system performance 10
following the loss of a single bulk electric system element to be compliant with 11
NERC and FERC requirements.3 12
4. Staffing Trends 13
Q. Please provide the staffing levels for the Transmission & Substations class of 14
services for the three fiscal years preceding the end of the Test Year and the 15
Test Year. 16
A. The following table shows, for the fiscal years 2011, 2012, and 2013 (calendar 17
years) and for the Test Year, the average of the end of month staffing levels for 18
the Transmission & Substations class of services. 19
3 Reliability Standard FAC-008-3 (Facility Ratings), adopted under 137 FERC ¶ 61,123, Docket No.
RD11-10-000 (Nov. 17, 2011) available at http://www.nerc.net/standardsreports/standardssummary.aspx#; FERC
Order 754 (Interpretation of Transmission Planning Reliability Standard), adopted under 136 FERC ¶ 61,186, Docket
No. RM10-6-000 (September 15, 2011), available at http://www.ferc.gov/whats-new/comm-meet/2011/091511/E-
4.pdf.
RR10 - Page 222 of 502 04590
-
Bellinghausen Direct – Revenue Requirement Page 27
Table ALB-RR-4 1
Average End of Month # of Staff
Class of Services 2011 2012 2013 Test Year
Transmission &
Substations 166 206 265 274
Q. What are the reasons for this trend? 2
A. The increases in average staffing levels between 2011 and 2012 were the result of 3
the establishment and staffing of new departments and staff additions in the 4
Transmission Training group in 2012. There were also increases in staffing of 5
several departments created in 2011 and 2012 to bring them up to appropriate 6
staffing levels. The increase in average staffing levels between 2012 and 2013 7
was primarily related to adding staff to support the capital build out in the SPS 8
territory by transferring employees and their management from other Operating 9
Companies to XES and adding employees in the engineering, project 10
management, and project controls departments. The increase in average staffing 11
levels between 2013 and the Test Year was the result of adding employees in the 12
engineering and project management departments to support the capital build out. 13
5. Cost Control and Process Improvement Initiatives 14
Q. Separate from the budget planning process, does the Transmission & 15
Substations affiliate class take any steps to control its costs or to improve its 16
services? 17
A. Yes. The Transmission organization has several initiatives that are focused on 18
driving productivity and effectiveness. For example, the TRO initiative, a 19
long-term process improvement program, encompasses maintenance activities as 20
RR10 - Page 223 of 502 04591
-
Bellinghausen Direct – Revenue Requirement Page 28
well as capital projects. It establishes an organizational framework, management 1
philosophy, and a focus on improving processes and more clearly defining roles 2
and responsibilities. These efforts assist in controlling costs and improving 3
services. 4
D. The Costs for the Transmission & Substations Class of Services 5
are Priced in a Fair Manner 6
Q. For those costs that XES charges (either directly or through use of an 7
allocation) to SPS for the Transmission & Substations class of services, does 8
SPS pay any more for the same or similar service than does any other Xcel 9
Energy affiliate? 10
A. No. 11
Q. Why do you answer “no”? 12
A. The XES charges to SPS for any particular service are no higher than the XES 13
charges to any other Xcel Energy affiliate. The costs charged for particular 14
services are the actual costs that XES incurred in providing those services to SPS. 15
A single, specific billing method, rationally related to the costs drivers associated 16
with the service being provided, is used with each work order. In her direct 17
testimony, Ms. Schmidt-Petree discusses the selection of billing methods and 18
XES’s method of charging for services in more detail. 19
Q. How are the costs of the Transmission & Substations affiliate class billed to 20
SPS? 21
A. My Attachment ALB-RR-B shows all of the costs in this class broken out by 22
activity and shows the billing method associated with each activity. 23
RR10 - Page 224 of 502 04592
-
Bellinghausen Direct – Revenue Requirement Page 29
Q. What are the predominant billing methods used for the costs that SPS seeks 1
to recover for the Transmission & Substations affiliate class of services? 2
A. Of the requested XES charges to SPS for this class, 98.55% were charged using 3
one of the following two methods: 4
Direct Billing – 67.34% of XES charges to SPS - $3,539,960.89; and 5
Electric Transmission Plant – 31.21% of XES charges to SPS - 6 $1,640,914.85 7
Q. Why is the “Direct Billing” method appropriate for assigning the costs 8
captured in the work orders that use that billing method? 9
A. For the work orders that are assigned using the “Direct Billing” method, the costs 10
normally reflect work that was performed specifically for SPS only. In some 11
cases, however, the direct billing occurred after the application of an off-line 12
allocator that tracks the relevant cost drivers. In either situation, the work orders 13
charged using the “Direct Billing” method are appropriate because the assignment 14
of costs is in accordance with the distribution of benefits for the services received. 15
For example, the labor and employee expense costs associated with regional 16
planning activities for SPS’s transmission system were assigned using the “Direct 17
Billing” method. The cost of these services benefitted SPS, the work was 18
performed specifically for SPS alone, and the cost drivers were the regional 19
planning activities and associated load studies required for SPS. Thus, the “Direct 20
Billing” method is appropriate because it assigns costs in accordance with cost 21
causation and benefits received. For the work orders that assign costs using 22
Direct Billing, the per unit amounts charged by XES to SPS are no higher than the 23
RR10 - Page 225 of 502 04593
-
Bellinghausen Direct – Revenue Requirement Page 30
unit amounts billed by XES to other affiliates for the same or similar services and 1
represent the actual costs of the services. 2
Q. Why is it appropriate to allocate costs based upon the “Electric Transmission 3
Plant” method for the costs captured in the work orders that uses that billing 4
method? 5
A. For the Work Orders that use the “Electric Transmission Plant” method as the 6
allocator, the costs are driven by the transmission assets of all of the Operating 7
Companies. For example, Work Order 442, which captures the labor costs 8
associated with developing standards, evaluating performance, and establishing 9
criteria for maintaining transmission plant assets of all of the Operating 10
Companies, uses the “Electric Transmission Plant Asset” method as the allocator. 11
Thus, the costs in this work order are allocated among the Operating Companies 12
based on each Operating Company’s proportionate share of total Operating 13
Company transmission plant assets (i.e., the transmission plant assets of a 14
particular Operating Company as a percentage of the total transmission plant 15
assets of all of the Operating Companies). This allocation reflects cost causation 16
and the distribution of the benefits of the services received. For the work orders 17
that assign costs based upon this billing method, the per unit amounts charged by 18
XES to SPS as a result of the application of this billing method are no higher than 19
the unit amounts billed by XES to other affiliates for the same or similar services 20
and represent the actual costs of the services. 21
RR10 - Page 226 of 502 04594
-
Bellinghausen Direct – Revenue Requirement Page 31
Q. You have covered the billing methods used to bill 98.55% of the costs 1
associated with this affiliate class. Why have you not specifically covered the 2
remaining 1.45% of the costs of this class? 3
A. I have described the predominant billing methods associated with this affiliate 4
class. The remaining costs are billed using 10 different allocators, no one of 5
which is used to bill more than 0.9% of the costs. In light of the number of 6
remaining allocators, work orders, and relative dollar amounts, I have not gone 7
into a detailed discussion of these other billing methods in order to keep the 8
discussion to a manageable level. The work orders and billing methods used to 9
charge the remaining 1.45% of the costs in this class, however, are presented in 10
my Attachment ALB-RR-B, discussed earlier. A reader may reference that 11
attachment and then refer to the specific work order summary provided in Ms. 12
Schmidt-Petree’s Attachment JSSP-RR-14 for an explanation of the particular 13
allocators used and the cost drivers for the activities reflected in that particular 14
work order. 15
Q. Have you determined that the costs reflected in the remaining 1.45% of costs 16
associated with this class of services have been billed using an appropriate 17
billing method? 18
A. Yes. I have reviewed each of the work orders and the associated allocators used 19
to bill the remaining 1.45% of the costs of this class. The cost drivers reflected in 20
the billing method used to bill the costs of each work order are consistent with 21
and reflect the cost drivers of the services captured in each particular work order. 22
Therefore, the billing methods are appropriate because the allocation of costs is in 23
RR10 - Page 227 of 502 04595
-
Bellinghausen Direct – Revenue Requirement Page 32
accordance with the distribution of the benefits received by SPS and are no higher 1
than the per unit costs charged to other affiliates for the same or similar types of 2
services. 3
RR10 - Page 228 of 502 04596
-
Bellinghausen Direct – Revenue Requirement Page 33
IV. CONCLUSION 1
Q. Were Attachments ALB-RR-1, and ALB-RR-A through ALB-RR-D 2
prepared by you or under your direct supervision and control? 3
A. Yes, as to Attachment ALB-RR-1. Attachments ALB-RR-A through ALB-RR-D 4
were prepared by Ms. Schmidt-Petree and her staff. I and my staff have reviewed 5
these attachments and I believe them to be accurate. The same information is 6
presented in Ms. Schmidt-Petree’s Attachments JSSP-RR-A through JSSP-RR-D 7
and the information is attached to my testimony for the convenience of those 8
reviewing my testimony. 9
Q. Does this conclude your pre-filed direct testimony? 10
A. Yes. 11
RR10 - Page 229 of 502 04597
-
RR10 - Page 230 of 502 04598
-
TR
AN
SM
ISS
ION
- O
RG
AN
IZA
TIO
N C
HA
RT
AS
OF
JU
NE
30
, 2
01
4
Sen
ior
Vic
e P
resi
den
t,
Op
era
tio
ns
Vic
e P
resi
den
t,
Tra
nsm
issi
on
Dir
ecto
r,
Su
bst
ati
on
Op
era
tio
ns
Ma
inte
na
nce
Dir
ecto
r,
Tra
nsm
issi
on
Po
rtfo
lio
Del
iver
y
Dir
ecto
r,
Sy
stem
Su
sta
ina
bil
ity
Dir
ecto
r,
Tra
nsm
issi
on
Fie
ld
Op
era
tio
ns
Exec
uti
ve
Ad
min
istr
ati
ve
Ass
ista
nt
Dir
ecto
r, T
ran
smis
sio
n
Pla
nn
ing
& B
usi
nes
s
Rel
ati
on
s
Dir
ecto
r,
Bu
sin
ess
Op
era
tio
ns
Dir
ecto
r,
Str
ate
gic
Tra
nsm
issi
on
Init
iati
ves
Dir
ecto
r,
Tra
nsm
issi
on
Inv
estm
ent
Dir
ecto
r,
Sy
stem
Op
era
tio
ns
Attachment ALB-RR-1 Page 1 of 1
Docket No. 43695
RR10 - Page 231 of 502 04599
-
Su
mm
ary
of
XE
S E
xp
ense
s to
SP
S b
y A
ffil
iate
Cla
ss a
nd
Bil
lin
g M
eth
od
For
Tw
elv
e M
on
ths
end
ed J
un
e 3
0, 2
01
4
Ala
n B
elli
ng
ha
use
n
(A)
(B)
(C)
(D)
(E)
(F)
(G)
(H)
(I)
(J)
(K)
(L)
(M)
Lin
e
No.
Bu
sin
ess
Are
aA
ffli
ate
Cla
ss B
illi
ng
Met
ho
d (
Wo
rk
Ord
er)
All
oca
tio
n M
eth
od
To
tal
XE
S B
illi
ng
s
for
Cla
ss t
o a
ll
Leg
al
En
titi
es
(FE
RC
Acc
t. 4
00
-
93
5)
XE
S B
illi
ng
s fo
r
Cla
ss t
o a
ll L
ega
l
En
titi
es E
xce
pt
for
SP
S (
FE
RC
Acc
t.
40
0-9
35
)
XE
S B
illi
ng
s fo
r
Cla
ss t
o S
PS
(T
ota
l
Co
mp
an
y)
(FE
RC
Acc
t. 4
00
-93
5)
Ex
clu
sio
ns
Per
Bo
ok
P
ro F
orm
as
Req
ues
ted
Am
ou
nt
(To
tal
Co
mp
an
y)
% o
f C
lass
Ch
arg
es
1T
ran
smis
sion
Tra
nsm
issi
on
&
Su
bst
ati
on
s
10
41
3 D
ynam
ic E
MS
Phas
e 2
Ele
ctri
c P
rod
uct
ion
Pla
nt/
Ele
ctri
c
Tra
nsm
issi
on P
lant/
Ele
ctri
c D
istr
ibu
tion
Pla
nt
35
,51
3.1
9$
29
,86
8.3
1$
5
,64
4.8
8$
-
$
5,6
44
.88
$
2
85
.44
$
5
,93
0.3
2$
0.1
1%
21
04
73
Pow
er S
ou
rce
Phas
e
2
Ass
ets/
Rev
enu
e/N
o.
of
Em
plo
yee
s
4,6
96
.53
4,1
34
.81
5
61
.72
-
56
1.7
2
-
5
61
.72
0
.01
%
31
04
79
Ente
rpri
se S
olu
tion
Sel
ecti
on
Ass
ets/
Rev
enu
e/N
o.
of
Em
plo
yee
s
54
,04
6.0
5
47
,58
1.9
2
6
,46
4.1
3
-
6,4
64
.13
(2
3.5
9)
6,4
40
.54
0
.12
%
41
04
93
Work
and
Ass
et
Man
agem
ent
Ph1
No.
of
Pas
sport
Inven
tory
, P
assp
ort
Work
Man
agem
ent
&
Pas
sport
Pu
rchas
ing
Tra
nsa
ctio
ns
plu
s N
o.
of
Max
imo U
sers
46
,09
3.7
1
37
,57
8.3
9
8
,51
5.3
2
-
8,5
15
.32
(1
9.6
0)
8,4
95
.72
0
.16
%
51
04
98
Su
bst
atio
n A
sset
Mg
mt
Ele
ctri
c T
ransm
issi
on
Pla
nt
54
4.2
4
41
7.4
2
1
26
.82
-
12
6.8
2
-
1
26
.82
0
.00
%
61
05
07
Com
mon B
luep
rint
-
Op
erat
ions
No.
of
Pas
sport
Inven
tory
, P
assp
ort
Work
Man
agem
ent
&
Pas
sport
Pu
rchas
ing
Tra
nsa
ctio
ns
plu
s N
o.
of
Max
imo U
sers
1,3
59
.14
1,1
12
.28
2
46
.86
-
24
6.8
6
(0.9
1)
2
45
.95
0
.00
%
71
05
15
ER
-Eng
inee
ring
Des
ign &
Est
ima
No.
of
Pas
sport
Inven
tory
, P
assp
ort
Work
Man
agem
ent
&
Pas
sport
Pu
rchas
ing
Tra
nsa
ctio
ns
plu
s N
o.
of
Max
imo U
sers
1,9
46
.31
1,5
92
.83
3
53
.48
-
35
3.4
8
-
3
53
.48
0
.01
%
81
20
Acc
tg,
Rp
tg &
Tax
esA
sset
s/R
even
ue/
No.
of
Em
plo
yee
s
13
.96
12
.11
1
.85
-
1.8
5
(1.8
5)
-
0.0
0%
91
21
Acc
tg.
& R
ptg
(C
orp
Gov)
Ass
ets/
Rev
enu
e/N
o.
of
Em
plo
yee
s
18
7.5
4
16
5.1
0
2
2.4
4
-
22
.44
(22
.44
)
-
0.0
0%
10
12
9 G
en/P
rop
Tra
din
g -
Bac
k O
ffic
e
Bas
ed o
n l
abor
hou
r
allo
cati
on b
y
Com
mer
cial
Op
erat
ions
front
off
ice
trad
ing
acti
vit
ies,
gen
erat
ion
(pu
rchas
e an
d s
ales
)
and
pro
pri
etar
y,
wit
h
the
pro
pri
etar
y
allo
cati
on t
o N
SP
M,
PS
Co &
SP
S.
Pro
pri
etar
y t
rad
ing
doll
ars
are
allo
cate
d
bas
ed o
n t
he
Join
t
Op
erat
ing
Ag
reem
ent.
4.1
2
3.2
8
0
.84
-
0.8
4
(0.8
4)
-
0.0
0%
Attachment ALB-RR-A Page 1 of 2
Docket No. 43695
RR10 - Page 232 of 502 04600
-
Su
mm
ary
of
XE
S E
xp
ense
s to
SP
S b
y A
ffil
iate
Cla
ss a
nd
Bil
lin
g M
eth
od
For
Tw
elv
e M
on
ths
end
ed J
un
e 3
0, 2
01
4
Ala
n B
elli
ng
ha
use
n
11
14
4 P
rop
Tra
din
g -
Frt
/Mid
Off
ice
Join
t O
per
atin
g
Ag
reem
ent
10
.49
7.6
3
2
.86
-
2.8
6
(2.8
6)
-
0.0
0%
12
17
1 L
egal
(C
orp
Gov)
Ass
ets/
Rev
enu
e/N
o.
of
Em
plo
yee
s
67
6.6
5
59
5.5
1
8
1.1
4
-
81
.14
(81
.14
)
-
0.0
0%
13
18
0 C
om
mu
nic
atio
ns
(Corp
Gov)
Ass
ets/
Rev
enu
e/N
o.
of
Em
plo
yee
s
25
7.6
6
22
5.2
1
3
2.4
5
-
32
.45
(32
.45
)
-
0.0
0%
14
19
0 H
R
(Div
ersi
ty/S
afet
y/E
mp
Rel
)
No.
of
Em
plo
yee
s2
2,4
41
.26
1
9,3
12
.24
3,1
29
.02
-
3
,12
9.0
2
1
.56
3
,13
0.5
8
0.0
6%
15
42
3 C
&F
O C
onst
r, O
&M
Ele
ctri
c T
ransm
issi
on
Pla
nt/
Ele
ctri
c
Dis
trib
uti
on P
lant/
Gas
Tra
nsm
issi
on
Pla
nt/
Gas
Dis
trib
uti
on P
lant
26
,60
9.4
4
23
,29
8.0
9
3
,31
1.3
5
-
3,3
11
.35
3
3.5
0
3
,34
4.8
5
0.0
6%
16
44
1 D
istr
ibu
tion E
lect
ric
FE
RC
58
0
Ele
ctri
c D
istr
ibu
tion
Pla
nt
44
2,2
46
.57
39
4,7
06
.50
4
7,5
40
.07
-
47
,54
0.0
7
(39
4.3
0)
4
7,1
45
.77
0.9
0%
17
44
2 T
ransm
issi
on E
lect
ric
FE
RC
56
0
Ele
ctri
c T
ransm
issi
on
Pla
nt
7,1
81
,11
3.3
3
5
,53
8,9
44
.28
1
,64
2,1
69
.05
(4,4
84
.49
)
1,6
37
,68
4.5
6
(10
,25
1.3
6)
1,6
27
,43
3.2
0
3
0.9
6%
18
44
3 D
istr
ibu
tion G
as
FE
RC
87
0 (
E&
S
Gas
Dis
trib
uti
on
Pla
nt
35
.47
35
.47
-
-
-
-
-
0.0
0%
19
44
9 T
ransm
Ele
c 5
60
NS
PM
& N
SP
W
Ele
ctri
c T
ransm
issi
on
Pla
nt
2,5
54
,02
5.1
2
2
,55
4,0
25
.12
-
-
-
-
-
0.0
0%
20
45
1 T
ransm
Ele
c F
ER
C
56
1.5
Ele
ctri
c T
ransm
issi
on
Pla
nt
57
,81
1.5
8
44
,47
7.4
2
1
3,3
34
.16
-
13
,33
4.1
6
20
.67
13
,35
4.8
3
0
.25
%
21
46
6 E
nvir
o P
oli
cy S
erv
Sou
th
Ele
ctri
c P
rod
uct
ion
Pla
nt/
Ele
ctri
c
Tra
nsm
issi
on P
lant/
Ele
ctri
c D
istr
ibu
tion
Pla
nt/
Gas
Tra
nsm
issi
on P
lant/
Gas
Dis
trib
uti
on
Pla
nt
1,6
32
.09
1,2
10
.22
4
21
.87
-
42
1.8
7
-
4
21
.87
0
.01
%
22
50
0 B
usi
nes
s S
yst
ems
No.
of
Com
pu
ters
1,6
30
.64
1,4
52
.34
1
78
.30
-
17
8.3
0
-
1
78
.30
0
.00
%
23
52
6 E
MS
- T
ransm
issi
on
Ele
ctri
c T
ransm
issi
on
Pla
nt
20
7.3
3
15
9.0
2
4
8.3
1
-
48
.31
(48
.31
)
-
0.0
0%
24
Dir
ect
17
,68
2,9
95
.07
1
4,0
90
,34
8.9
9
3
,59
2,6
46
.08
(1,7
81
.07
)
3,5
90
,86
5.0
1
(50
,90
4.1
2)
3,5
39
,96
0.8
9
6
7.3
4%
25
To
tal
- W
itn
ess
Ala
n
Bel
lin
gh
au
sen
28
,11
6,0
97
.49
$
2
2,7
91
,26
4.4
9$
5
,32
4,8
33
.00
$
(6,2
65
.56
)$
5,3
18
,56
7.4
4$
(61
,44
2.5
9)
$
5,2
57
,12
4.8
5$
1
00
.00
%
Am
ounts
may
not
add o
r ti
e to
oth
er
sched
ule
s due
to
roundin
g
Attachment ALB-RR-A Page 2 of 2
Docket No. 43695
RR10 - Page 233 of 502 04601
-
XE
S E
xp
ense
s to
all
Aff
ilia
tes
by A
ff C
lass
, A
ctiv
ity,
Bil
lin
g M
eth
od
, an
d F
ER
C A
ccou
nt
For
Tw
elve
Mon
ths
En
ded
Ju
ne
30,
2014
Ala
n B
elli
ngh
au
sen
(A)
(B)
(C)
(D)
(E)
(F)
(G)
(H)
(I)
(J)
(K)
(L)
(M)
Lin
e N
o.
Legal
En
tity
Receiv
ing
XE
S E
xp
en
ses
Aff
ilia
te C
lass
Acti
vit
yB
illi
ng M
eth
od
(W
ork
Ord
er)
FE
RC
Accou
nt
Tota
l X
ES
Bil
lin
gs
for C
lass
to a
ll L
egal
En
titi
es
(FE
RC
Acct.
400-9
35)
XE
S B
illi
ngs
for
Cla
ss t
o a
ll L
egal
En
titi
es
Excep
t fo
r
SP
S (
FE
RC
Acct.
400-9
35)
XE
S B
illi
ng
s fo
r
Cla
ss t
o S
PS
(T
ota
l
Com
pa
ny
) (F
ER
C
Acct.
40
0-9
35
)
Exclu
sion
s P
er B
ook
P
ro F
orm
as
Req
uest
ed
Am
ou
nt
(Tota
l
Com
pa
ny
)
11480 W
elto
n,
Inc.
Tra
ns
& S
ubst
711142 P
roductive L
abor
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.7
4$
0.7
4$
-$
-
$
-
$
$
-
-
$
21480 W
elto
n,
Inc.
Tra
ns
& S
ubst
711143 R
eg L
abor
Loadin
g-N
onP
roductiv
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.1
20.1
2-
-
-
-
-
31480 W
elto
n,
Inc.
Tra
ns
& S
ubst
711144 R
eg L
abor
Loadin
g-P
ensio
n&
401K
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.1
40.1
4-
-
-
-
-
41480 W
elto
n,
Inc.
Tra
ns
& S
ubst
711145 R
eg L
abor
Loadin
g-I
nsura
nce
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.1
40.1
4-
-
-
-
-
51480 W
elto
n,
Inc.
Tra
ns
& S
ubst
711160 R
eg L
abor
Load-I
ncentive
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.2
40.2
4-
-
-
-
-
61480 W
elto
n,
Inc.
Tra
ns
& S
ubst
712110 C
ontr
act
Labor
10479-E
nte
rpri
se S
olu
tion S
ele
ction
010.6
310.6
3-
-
-
-
-
71480 W
elto
n,
Inc.
Tra
ns
& S
ubst
713050 C
ontr
act
LT
Outs
ide V
endor
10473-P
ow
er
Sourc
e P
hase 2
01.0
61.0
6-
-
-
-
-
81480 W
elto
n,
Inc.
Tra
ns
& S
ubst
714000 M
ate
rials
121-A
cctg
. &
Rptg
(C
orp
Gov)
00.0
40.0
4-
-
-
-
-
91480 W
elto
n,
Inc.
Tra
ns
& S
ubst
714000 M
ate
rials
171-L
egal (C
orp
Gov)
00.1
40.1
4-
-
-
-
-
10
1480 W
elto
n,
Inc.
Tra
ns
& S
ubst
714100 P
rint/
Copy-O
ther
180-C
om
munic
ations (
Corp
Gov)
00.0
50.0
5-
-
-
-
-
11
1480 W
elto
n,
Inc.
Tra
ns
& S
ubst
721020 E
E E
xp M
ileage
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.1
20.1
2-
-
-
-
-
12
1480 W
elto
n,
Inc.
Tra
ns
& S
ubst
721045 E
E E
xp P
ark
ing
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.0
10.0
1-
-
-
-
-
13
1480 W
elto
n,
Inc.
Tra
ns
& S
ubst
764000 P
ayro
ll T
axes
10479-E
nte
rpri
se S
olu
tion S
ele
ction
00.0
70.0
7-
-
-
-
-
14
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11366834-A
cquis
itio
n o
f R
OW
Lin
e 0
973
426.9
(1,5
83.4
7)
(1,5
83.4
7)
-
-
-
-
-
15
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11374194-9
73 3
45K
V M
ON
TIC
ELLO
- Q
UA
RR
Y426.9
(60.2
8)
(60.2
8)
-
-
-
-
-
16
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11441912-9
54 Q
UA
RR
Y -
ALE
XA
ND
RIA
345K
V426.9
(26,2
47.3
5)
(26,2
47.3
5)
-
-
-
-
-
17
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11443917-A
cquir
e 6
5 m
iles o
f R
OW
426.9
(2,1
50.5
0)
(2,1
50.5
0)
-
-
-
-
-
18
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11523985-C
AP
X S
hare
d 0
955 N
DB
ord
er-
Bis
o426.9
(2,0
14.5
1)
(2,0
14.5
1)
-
-
-
-
-
19
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11523989-C
AP
X S
hare
d 0
955 A
lex-M
N B
ord
e426.9
(5,5
22.7
3)
(5,5
22.7
3)
-
-
-
-
-
20
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11524004-C
AP
X (
SH
AR
ED
) 0955 A
LE
X -
MN
BO
426.9
(33,7
20.8
3)
(33,7
20.8
3)
-
-
-
-
-
21
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11524010-C
AP
X S
HA
RE
D 0
955 N
D B
OR
DE
R T
O426.9
(6,6
39.6
0)
(6,6
39.6
0)
-
-
-
-
-
22
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11683987-C
AP
X L
AX
0964 H
-NR
345K
V L
INE
426.9
(1,4
75.3
3)
(1,4
75.3
3)
-
-
-
-
-
23
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11685093-C
AP
X L
AX
0965 N
R-M
R 3
45K
V L
INE
426.9
(54,0
13.0
4)
(54,0
13.0
4)
-
-
-
-
-
24
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11685105-C
AP
X L
AX
5309 N
R-C
161K
V L
INE
426.9
(1,2
44.9
7)
(1,2
44.9
7)
-
-
-
-
-
25
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11685109-C
AP
X L
AX
5310 N
R-N
H 1
61K
V L
INE
426.9
(4,6
09.7
7)
(4,6
09.7
7)
-
-
-
-
-
26
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11688318-5
310 N
Roch-N
Hills
Share
d,
RO
426.9
(1,1
78.0
6)
(1,1
78.0
6)
-
-
-
-
-
27
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11689756-5
309 N
Roch-C
heste
r, S
hare
d,R
O426.9
(1,9
13.9
3)
(1,9
13.9
3)
-
-
-
-
-
28
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11689836-9
64 H
am
pto
n-N
Roch,
Share
d,
R426.9
(10,7
13.8
5)
(10,7
13.8
5)
-
-
-
-
-
29
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11699724-9
65 N
Roch-M
iss R
iver
Shd,R
OW
426.9
(7,8
57.9
0)
(7,8
57.9
0)
-
-
-
-
-
30
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11756673-B
BS
B-P
erm
itting P
re-C
on S
hare
d426.9
(55,8
78.0
2)
(55,8
78.0
2)
-
-
-
-
-
31
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
0 C
WIP
Pro
ductive L
abor
NS
P-M
N11888155-C
AP
X L
A C
RO
SS
E M
ISS
RIV
ER
MN
S426.9
(1,4
23.2
1)
(1,4
23.2
1)
-
-
-
-
-
32
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11366834-A
cquis
itio
n o
f R
OW
Lin
e 0
973
426.9
(1,2
11.3
5)
(1,2
11.3
5)
-
-
-
-
-
33
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11374194-9
73 3
45K
V M
ON
TIC
ELLO
- Q
UA
RR
Y426.9
(45.3
5)
(45.3
5)
-
-
-
-
-
34
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11441912-9
54 Q
UA
RR
Y -
ALE
XA
ND
RIA
345K
V426.9
(19,9
32.9
9)
(19,9
32.9
9)
-
-
-
-
-
35
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11443917-A
cquir
e 6
5 m
iles o
f R
OW
426.9
(1,6
41.2
1)
(1,6
41.2
1)
-
-
-
-
-
36
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11523985-C
AP
X S
hare
d 0
955 N
DB
ord
er-
Bis
o426.9
(1,5
37.6
2)
(1,5
37.6
2)
-
-
-
-
-
37
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11523989-C
AP
X S
hare
d 0
955 A
lex-M
N B
ord
e426.9
(4,2
09.5
1)
(4,2
09.5
1)
-
-
-
-
-
38
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11524004-C
AP
X (
SH
AR
ED
) 0955 A
LE
X -
MN
BO
426.9
(25,7
41.2
3)
(25,7
41.2
3)
-
-
-
-
-
39
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11524010-C
AP
X S
HA
RE
D 0
955 N
D B
OR
DE
R T
O426.9
(5,0
42.0
1)
(5,0
42.0
1)
-
-
-
-
-
40
CA
PX
2020 J
t V
ent
Tra
ns
& S
ubst
730390.7
2 C
WIP
Pro
ductive L
abor
GR
E11775695-C
AP
X C
MA
Bro