distributed generation benefits and planning challenges crepc/spsc resource planners’ forum...
TRANSCRIPT
Distributed Generation Benefits and Planning
Challenges
CREPC/SPSC Resource Planners’ ForumOctober 3, 2012
Arne Olson
Energy and Environmental Economics, Inc.
E3 has operated at the nexus of planning, policy and markets since it was founded in 1989
E3 advises utilities, regulators, government agencies, power producers, energy technology companies, and investors on a wide range of critical issues in the electricity and natural gas industries
Offices in San Francisco, CA and Vancouver, B.C.
Developed “High DG” cases for CPUC, SPSC
2
Agenda
1. What is DG, and what does it do for us?
2. Is DG more cost-effective than central station generation? (Hint: it depends on your perspective.)
3. Challenges in harvesting DG values: how current planning practices account for DG (or not).
4. Concluding Thoughts
3
What is DG, and what does it do for us?
What is DG?
5
distributed
adjective
spread out or scattered about or divided up [ant: concentrated] WordNet® 3.0, © 2006 by Princeton University.
DG has been defined in manydifferent ways depending on the context
DG dimensions:
• Size: 1 kW up to … 50 MW?
• Location: customer side vs. utility side of meter
• Interconnection point: distribution, sub-transmission, bulk transmission
• Proximity to load: behind-the-meter, same distribution feeder, in a load pocket, remote from load
• Technology type: PV, CHP, micro wind, fuel cells, microturbines, reciprocating engines
Which of These are DG?
6
20 MW near substationsLarge commercial rooftopsResidential rooftops
Illustrative Example of Distributed Solar PVRemote 20 MW sites identified by California’s RETI
Why DG?
Ratepayer benefits:
• High locational energy value in load pocket
• Reduced losses (~7% average, up to 15% on peak)
• Reduced need for new transmission
• Reduced need for new distribution
Non-ratepayer benefits:
• Reduced electricity bills for customer-side DG
• Reduced land-use footprint in sensitive ecological regions
• Local jobs in economically-depressed areas?
• Increased consumer choice & autonomy?
• More tangible/real than remote RE?
7
DG has a number of potential benefits relative to central
station generation
Spectrum of DG Interconnection Points
8
Existing HighVoltageSystem
Renewable energyzone
Sub-Trans.Substation
DistributionSubstation
Gen Step-upSubstation
2
3 4
5
6
ReferencePoint forCosting
$A $B
$C
-$E
-$F
Meter
1
230kV+69kV to138kV
4kV to21kV
Non-existingTransmission
NetworkTransmission
230kV+
$D
Since DG can have many definitions, it is better to focus on the benefits that generation can provide at different interconnection points
DG Interconnection Points
Home
Neighborhood CommunityRemote, new transmission
Remote, existing transmission
DG Benefits Depend on Interconnection Point
Interconnection Point
DG Benefit HomeNeighbor-
hood Community
Remote, existing
transmission
Remote, new
transmission
Locational energy value ● ● ● - -
Reduced Losses ● ● ● - -
Reduced need for distribution ● ● - - -
Reduced need for transmission ● ● ● - -
Environmental/other benefits ● ● ● ● ?
Reduced bills for DG system owners ● - - - -
9
Rate
payer
Benefits
Oth
er
Ben
efits
Is DG More Cost-Effective Than Central Station
Generation?
Solar PV Costs Can Vary Dramatically by Location
$105
$121
$154
$231
Source: CPUC 33% RPS Calculator, April 2012
Residential rooftop (4 kW)
Large, ground-mount
(150 MW)
Small, ground-mount
(5-20 MW)$167
Small, ground-mount
(1-5 MW)
Installed cost varies due to resource quality, size, installation type (shown as levelized $/MWh)
11
Example Values by Interconnection Point
Interconnection Point
DG BenefitHome(5 kW)
Neighbor-hood
(1-5 MW)Community(5-20 MW)
Remote, existing Tx(150 MW)
Remote, new Tx
(150 MW)
Levelized Cost $231 $167 $154 $121 $105
Locational energy value -$39 -$39 -$39 -$34 -$34
Reduced Losses -$3 -$3 -$1 - -
Capacity Value -$35 -$35 -$35 -$38 -$38
Reduced need for distribution
-$26 -$26 - - -
Reduced need for transmission
-$7 -$7 -$7 - +$20
Net Ratepayer Cost $121 $57 $72 $49 $53
Environmental/other benefits
? ? ? ? ?
12
Values using CPUC “net cost” approach ($/MWh)
Values based largely on CPUC RPS Calculator
0 200 400 600 800 1000 1200$0.00
$0.05
$0.10
$0.15
$0.20
$0.25
$0.30
$0.35
$0.40
SCEPG&ESDG&ESMUDLADWPSolar Rooftop PV LCOE
Monthly Consumption (kWh)
$/kW
h
DGPV Can Be Cost-Effective for Net Metered Customers
Typical California residential rates
13
South Coast Rooftop PV LCOE
Challenges in Harvesting DG Values
Accounting for DG in Resource Planning
DG is typically considered as a load modifier
• Base load forecast developed via econometric estimation
• Load modifiers to reflect demand-side policies and programs
Remaining net load served with least-cost portfolio of supply-side resources
• Wires savings and other locational values of demand-side resources frequently not considered
15
Utility-side DG has not historically been cost-competitive enough to
merit full consideration in IRP
Accounting for DG in Transmission Planning
Transmission planning is done for multiple purposes, not all of which reference local value of DG
• Interconnection: respond to service requests (DG does not help)
• Economic: relieve congestion (DG can help)
• Reliability: serve load in local area (DG can help)
DG not considered as transmission option, but may be reflected in load forecast
16
Local area studies are typically based on
meeting NERC criteria (N-1, G-1)
Accounting for DG in Distribution Planning
Distribution planning typically done with “small area” study
• Focuses on peak demand on distribution elements (feeders, transformers) in a defined area
• Trends that affect small area growth may be different from trends affecting utility-wide growth
• Utility might forecast “terminal load” based on land use plan
Harvesting distribution deferral value requires that investments actually be deferred
• Distribution engineers may be reluctant to consider effects of DG due to asymmetric risk (cost vs. blackout)
• DG investments may not be occurring outside of fast-growing areas
17
Vineyard
05
1015202530
1999 2001 2003 2005 2007
Pro
ject
s (M
W)
Las Positas
05
1015202530
1999 2001 2003 2005 2007
Pro
ject
s (M
W)
San Ramon / Dublin
05
1015202530
1999 2002 2005 2008
Pro
ject
s (M
W)
DG must be serving load downstream on distribution
feeder in order to defer distribution investments
Concluding Thoughts
Concluding Thoughts
Dramatic reduction in cost of PV has made DG a “live” option for the first time
• We can now plausibly ask the question “Is it cost-effective to develop distributed resources close to load that do not require new transmission infrastructure?”
• However, PV module cost reductions also affect cost of central station solar resources
DG can have significant additional value relative to central station resources in specific situations
• Highest locational value occurs where resources are serving load downstream in a fast-growing area
There are challenges in harvesting these values due to utility planning and procurement practices
19
Thank You!Energy and Environmental Economics, Inc. (E3)
101 Montgomery Street, Suite 1600
San Francisco, CA 94104
Tel 415-391-5100
Web http://www.ethree.com
Arne Olson ([email protected])