dewa testing procedure (1)

Upload: ram

Post on 14-Jan-2016

216 views

Category:

Documents


27 download

DESCRIPTION

testing deatails

TRANSCRIPT

  • Type here

    Transmission Commissioning Department 1/27

    Transmission Commissioning Department

    Protection Test Procedure(For TCD Scope of Work)

  • Transmission Commissioning Department 2/27

    Index

    SerialNo

    Description PageNo

    1 CT Test Procedures 32 VT Test Procedures 113 Relays Definitions 154 Test Setup for Auxiliary / Trip Relays 165 Procedure for Auxiliary Relay Tests 176 Procedure for Trip Relay Tests 217 Procedure for Meter Tests 238 Relay wiring diagrams 24

  • Transmission Commissioning Department 3/27

    Testing of Current Transformers (CTs)

    1. General Checks:

    The following general checks are performed before proceeding with the CT Test:

    GENERAL VISUAL INSPECTION FOR ANY DAMAGES/ PROPER MOUNTING NAME PLATE VERIFICATION WITH DRAWING TIGHTNESS CHECK AT CT SEC. TERMINALS TIGHTNESS CHECK AT CT SEC. TB LV COMPARTMENT/ LCCPOSTION OF P1 - TOWARDS BUS/FEEDER STAR FORMATION - S1/S2 COLOUR CODED CYLINDERS USED IN TERMINALS FOR TESTS

    EARTHING OF STAR FORMATION The IEC Standard applicable is 60044-1.

  • Transmission Commissioning Department 4/27

    1.1 Precautions:1.1.1 follow the test sequence of Test Formats. It is important to perform

    mag. Curve test after winding resistance measurement and polarity test.

    1.1.2 Never keep the CT Secondary open while injecting current in the primary of CT. Failure to observe this precaution would result in fatal injury and/or CT Failure.

    1.1.3 There is risk of electric shock during CT Tests. Observe necessary safety precautions.

    1.2 Test Instruments required: 1.2.1 Insulation Tester 1.2.2 Low Resistance Ohmmeter 1.2.3 Polarity Kit 1.2.4 Mag. Curve Set Up (Variac, Step up Transformer, Multimeters, Test Leads 1.2.5 Primary Injection Kit 1.2.6 Tong Tester

    2. Insulation Resistance Test:

    2.1 This test is performed to confirm that no insulation detoriation has taken place during transportation or installation. 2.2 The insulation resistance is measured between core to earth and across the core as appropriate (Primary to secondary). The duration of test can be few second till a reasonable good value is obtained. 2.3 Ambient temperature must be recorded with a calibrated temperature meter. 2.4 Generally any IR Value above 100M: is acceptable as there is no IEC Standard

    Criteria for this test. The CT Test Results with low IR Value must be investigated for insulation damage or dust contamination on terminals.

    Example:IR Values shall be measured up CT terminal blocks .

  • Transmission Commissioning Department 5/27

    3. Winding Resistance Measurement: The CT Secondary Winding resistance is measured in ohms and corrected to 75qC. Temperature - t 0C and Humidity

    R Phase Y Phase B Phase CTTERMINLAS

    Ter.Block

    R at t0C (

    R at 750C (

    R at t0 C (

    R at 750C (

    R at t0 C (

    R at 750 C (

    T7L ( 1S1 - 1S2)

    XC

    Resistance at 750 C = R t ( 1 + 0.00393 ( 75 t ) )

    4. Polarity Test

    The CT Polarity Test is performed to verify that the primary and secondary polarity markings are correct. Any wrong polarity will result in wrong measurement and protection mal-function. The positive and Negative Supply of low DC Voltage (9V) is applied to P1 and P2 (Primary Terminals) of the CT respectively. The Galvanometer positive and negative terminals are connected to S1 and S2 (Secondary Terminals) of CT, should give a forward deflection. Reverse deflection indicates a wrong polarity.

    Refer to below sketch for test set up.

    DC V applied R Phase Y Phase

    BPhase

    T7L Sec. to Primary 2.5kVT7L1 Sec. to Primary 2.5kVT8L Sec. to Primary 2.5kVT8L1 Sec. to Primary 2.5kVT7L to T7L/1+T8L+T8L/1+Earth 500VT7L/1 to T7L+T8L+T8L/1+Earth 500VT8L to T7L+T7L1+T8L/1+Earth 500VT8L/1 to T7L+T7L1+T8L+Earth 500V

  • Transmission Commissioning Department 6/27

    POLARITY CHECKS. R Phase Y Phase B Phase

    CT Terminals At CT Ter. Blocks in LV/LCC Comp

    At CT Ter. Blocks in LV/ LCC Comp

    At CT Ter. Blocks in LV/ LCC Comp

    (1S1 - 1S2) (2S1 - 2S2) (3S1 - 3S2) (4S1 - 4S2)

    5. Test Procedure for Magnetization Curve of Current Transformer:

    5.1 Objective of the Test: To identify the knee-point Voltage (Vk) of a Current Transformer and to verify whether the Mag. Curve Characteristics are matching with relay application requirements.

    5.2 Test Equipment:

    The test is carried out with a variable voltage applied to the secondary of the current transformer. The test voltage can be obtained from a variable voltage source or through a variable autotransformer. Voltmeter and Ammeter are required to measure the voltage and current respectively in the secondary circuit.

    5.3 Principle of Operation:

    The core of the current transformer gets magnetized due the primary current flowing in the circuit and this helps in faithful reproduction of the quantity in the secondary circuit. However, it is a property of the magnetic core to get saturated, due to high value of currents.

  • Transmission Commissioning Department 7/27

    In case of core saturation, the CT will not reproduce the primary current into the exact secondary current. In some application where primary protection relays are connected, the CT has to remain unsaturated up to a desired value of primary current. This property of the CT is designated with a parameter called as Knee-point voltage.

    Knee-point voltage of the current transformer is defined as the voltage at which 10% increase in secondary voltage results in 50% increase in the magnetization current, with the other windings (i.e., primary & test) in open circuited condition.

    The objective of this test is to plot the magnetization curve of the CT there by, locating the knee-point voltage, Vk. This value of Vk is compared with the manufacturers design value.

    5.4 Test Procedure: 5.4.1 Visual Check: Ensure that the surface of the transformer is clean and the wires properly terminated.

    Drawings checks for star point formation / ferrules /shorting link location.

    The secondary circuit earthing lead is temporarily isolated from the ground.

    5.4.4 Ensure that the primary circuit is open ie., the circuit breaker in the primary circuit is kept open.

    5.4.5 A typical test connection for a magnetization curve of current transformer is shown below figure:

    Fig.: Typical test connection for CT Mag. Curve test.

  • Transmission Commissioning Department 8/27

    5.4.6 Voltage is applied in the secondary core of the CT under test. The voltage is slowly increased and the current (mA) in the secondary is noted.

    5.4.7 This process is continued until the core saturates. The core saturation in indicated by steep increase in the secondary current for a marginal increase in the secondary voltage.

    5.4.8 The values are plotted in a log scale and the knee-point voltage obtained. The obtained value of Vk should be equal to or greater than the design value specified on the CT nameplate.

    5.4.9 Ensure a gradual increase or decrease of the secondary voltage during the test, as a sudden variation in the voltage may produce dangerous flux variation which may damage the secondary insulation.

    5.4.10 A typical CT mag curve and Vk are shown in fig below. 5.4.11 The same procedure is repeated for the other phase CTs.5.4.12 After completion of the test, ensure that all the CT secondary connections are restored

    back.

    MAGNETIZING CURVES FOR Vk.

    Recored the test results in the following table:

  • Transmission Commissioning Department 9/27

    Frequency of supply Hz Function:Magnetizing Current measured in mA

    CO

    RE

    Rat

    io

    Term

    inal

    PH Sec. Wdg. ResistanceAt 750C V

    at 1

    A

    R

    Y

    B

    5.5 Result:

    This test establishes the actual value of Vk of the CT core. Also this test establishes that correct core is used for the required application and also ensures that there is no mix-up of cores.

    5.6 Ratio Test

    The ratio check is carried out by injecting current into the primary of CT and measuring the secondary current. The results must be within the accuracy limits specified in the name plate of CT.This measured ratio should match with ratio specified in the CT Nameplate.

    Refer to the below figure for Test Setup.

  • Transmission Commissioning Department 10/27

    Record the test results in the following table:

    R Phase Y Phase B Phase

    CO

    RE

    Rat

    io

    Pri-Amps Sec-Amps Pri-Amps Sec-Amps Pri-Amps Sec-Amps

    T7L

    4

    00 /

    1

  • Transmission Commissioning Department 11/27

    Testing of Voltage Transformers (VTs)

    1. General Checks:

    The following general checks are performed before proceeding with the VT Test:

    R Phase Y Phase B Phase

    GENERAL VISUAL INSPECTION

    NAME PLATE

    TIGHTNESS OF CONNECTIONS AT VT SEC. TERMINALS TIGHTNESS OF CONNECTIONS AT VT SEC. TERMINAL BLOCKS EARTHING OF PRIMARY NEUTRAL TERMINAL SECONDARY EARTHING CORE1/CORE2CONFIRMATION OF RATING OF FUSES IN VT TERMINAL BOX AS SPECIFIED IN DRAWINGS

    SINGLE POINT EARTHINGFERRULES MATCHING WITH DRAWINGCOLOUR CODED CYLINDERS USED IN TERMINALS FOR TESTS

  • Transmission Commissioning Department 12/27

    The IEC Standard applicable is 60044-2.

    2. Insulation resistance Test:

    This test is performed to confirm that no insulation detoriation has taken place during transportation or installation. The insulation resistance is measured between core to earth and across the core as appropriate. The reasonable duration of test can be 5 seconds. Generally any IR Value above 100M: is acceptable as there is no IEC Standard Criteria for this test. The VT Test Results with low IR Value must be investigated for insulation damage or dust contamination on terminals. Confirm Isolation of links of VT Terminal Blocks. Confirm isolation Primary neutral earthingTime duration of test voltage applied 5.. Secs. Ambient Temperature Humidity

    DCVoltageApplied

    R Phase Y Phase B Phase

    Primary to Earth 2.5kVPrimary to Sec. Core 1 2.5kV

    Sec. Core 1 to Earth 500V

    3. Winding Resistance Measurement:The Primary Winding Resistance is measured in k:. It is normally measured with a Digital Multimeter. The secondary winding resistance is measured generally in milli:. It is normally measured with a low resistance Ohmmeter. There are no specific criteria for passing the test results. The results (at 75qC) must be close to the factory test values by r 10%.

    Ambient Temperature - t 0C

    CORE R Phase Y Phase B Phase

    R at t0 C (

    R at 750C (

    R at t0 C (

    R at 750C (

    R at t0 C (

    R at 750C (

    Primary

    Seconday

    Resistance at 750 C = R t ( 1 + 0.00393 ( 75 t )

  • Transmission Commissioning Department 13/27

    4. Polarity Test:

    The VT Polarity Test is performed to verify that the primary and secondary polarity markings are correct. Any wrong polarity will result in wrong measurement and protection mal-function. The positive and Negative Supply of low DC Voltage is applied to P1 (or terminal A in the sketch) and P2 (or terminal N in the sketch) , the Primary Terminals of the VT respectively. The Galvanometer positive and negative terminals are connected to terminal a and terminal b, the Secondary Terminals of VT, should give a forward deflection.

    The test results must be recorded in the format given below:

    R PHASE Y Phase B Phase

    VTAt VT Sec.Terminals

    At VT Ter.Blocks

    At VT Sec.Terminals

    At VT Ter.Blocks

    At VT Sec.Terminals

    At VT Ter. Blocks

    Core 1

    5. Magnetizing Current Measurement

    The magnetizing current must be measured and recorded in the below format.There are no specific criteria for passing this test. The results may be compared with factory values (if available).

    6. Ratio Test

    The ratio of a VT is checked out by applying voltage to the primary winding and measuring the voltage across the secondary winding. The measured ratio should match with ratio specified in the CT Nameplate

    The ratio error must be calculated and it is defined as:

    (Kn Vs) X 100% Vp

  • Transmission Commissioning Department 14/27

    Where:

    Kn is the nominal ratio Vp is the primary voltage Vs is the secondary voltage The error must be within limits specified in the nameplate.

    Record the test results in the following table:

    R Phase-Neutral

    Y Phase- Neutral

    B Phase- NeutralCore Pri-

    VoltsSec-Volts

    Pri-Volts

    Sec-Volts

    Pri-Volts

    Sec-Volts

    Core1Core2

  • Transmission Commissioning Department 15/27

    RELAYS DEFININTIONS

    DefinitionsAuxiliary relayAn electrical relay energized via the contacts of another relay for example an overcurrent relay for the purpose of providing higher rated contacts or introducing a time delay.

    Self Reset RelayThe contact operates when the voltage is applied and resets when the voltage is removed.

    Hand or Electrical Reset RelaysIn these relays, the contact remains operated condition even after the voltage is removed. The relay can be reset either by hand or by an auxiliary electromagnetic element.

    Pick-upA relay picks up when it changes from the unenergized position to energized position.

    Drop-outA relay drops out when it changes from the energized position to un-energized position.

    Operating TimeWith a relay de-energized and in its initial condition, the time which elapses between the application of a characteristic quantity (e.g., voltage) and the instant the relay operates.

    Resetting or Drop-out TimeWith a relay energized and in operated condition, the time which elapses between the removal of the characteristic quantity (e.g., voltage) and the instant the relay resets (de-energizes)Make ContactA make contact closes when the relay picks up.

    Break ContactA Break Contact opens when the relay picks up.

  • Transmission Commissioning Department 16/27

    Test Set Up for Auxiliary / Trip Relay Tests

  • Transmission Commissioning Department 17/27

    Test Procedure for Auxiliary Relay

    1. General

    1.1 For random test contractor has to complete 100% internal testing and test reports must be ready before starting random test.

    1.2 Get information from contractor about problems and defects noticed during internal tests.

    1.3 Check the relay datas (type, model, and contact details) with drawings and test report.

    1.4 Check the drawings for output contact configuration and function with reference sheets (e.g., Z sheet of drawings).

    1.5 Select the random relays (20% of total relays). 1.6 Check IR value with 500 V Megger with respect to body/case. 1.7 Check the test setup then start the voltage injection slowly and linearly when

    relay changes the status record. Record the current and voltage at the time of pickup or drop off. (Refer the test setup attach).

    1.8 Compare the operating voltage and operating current with technical specification.

    1.9 Follow the test sequence in the test formats. 1.10 Check the operating time of the relay (use the contact to stop the timer which is

    used for alarm). By injecting 0V to rated voltage. 1.11 Check the resetting voltage, current and operating, resetting time for relay. By

    reducing the voltage from 110v to 0V or 110V to reference voltage according to manufacturer recommendations. The resetting (drop-off) time must be as per manufacturers specification.

    1.12 Ensures that output contact resistance, make, and brake and change over contact. Contact resistance must be less than 1 ohm.

    1.13 Check the wiring and other data on at LV / Relay panels such as label, Relay Identification etc.

  • Transmission Commissioning Department 18/27

    Test Format (Typical) for Supply Supervision RelayRelay Data.

    Relay Type Aux DC Supply Model No. MVAA11

    General Inspection and Checks.

    i. Correctness of Installation and wiring. ii. Earthing connection for Relay case to Earth Bar

    iii. IR of relay circuit & associated wiring to earth (500V Megger) iv. Operation of Output contacts v. Operation of Mechanical Flag and Resetting arm vi Sr.No. on Modules, Case and Cover Identical

    No. of NO Contacts - v Contact Configuration No. of NC Contacts - Relay Test Results.

    Currentat 110 Vm A

    Timings at Rated Voltage

    OperationatPick Up Drop OFF RelayDesignation &

    Sr No.

    Volts mA Volts m A

    OperatetimemSec

    Resettime(msec)

    88V 150V

    Operating time at 110V DC- < 25 mSec.

    Note:Slight chattering at the time of pick up may be acceptable. There should not be any chattering within the operating range of the relay rated voltage.

  • Transmission Commissioning Department 19/27

    Test Format (Typical) for Trip Circuit Supervision Relay

    Relay Data. Relay Type Aux DC Supply Model No. MVAX31

    General Inspection and Checks. i. Correctness of Installation and wiring. ii. Earthing connection for Relay case to Earth Bar

    iii. IR of relay circuit & associated wiring to earth (500V Megger)

    iv. Operation of Output contacts & Contact Resistancev. Operation of Mechanical Flag and Resetting arm vi Sr.No. on Modules, Case and Cover Identical

    No. of NO Contacts vii Contact configuration No. of NC Contacts Relay Test Results.

    PICK UP DROP OFF RelayDesignation & Sr. No.

    COIL

    V mA V mA

    Currentat 110V mA

    OperatingTimeinmSec.

    Resettime m Sec at 110V

    ResettingTime in mSec.(C+A)/(C+B)

    C 27-28A13-14B 21-22C 27-28A13-14B 21-22

    Expected Operating Time < 70 msec. ; Resetting Time > 400 msecResetting time (C+A) or (C+B) )

  • Transmission Commissioning Department 20/27

    Test Format (Typical) for Voltage Supervision Relay

    Relay Data. Relay Type Rating of relay Model No. Relay

    DesignationMVAP22

    General Inspection and Checks. i. Correctness of Installation and wiring. ii. Earthing connection for Relay case to Earth Bar

    iii. IR of relay circuit & associated wiring to earth (500V Megger) iv. Operation of Output contacts v. Operation of Mechanical Flag and Resetting arm vi Sr.No. on Modules, Case and Cover Identical vII Contact Configuration No. of CO Contacts 3

    Relay Test Results. Apply 3 phases voltage to the relay and check relay operation

    1 Check Phase Rotation 2 Apply 80% of Vn and check voltage on terminals: 15,16, 22

    23 - 15 25 - 16 3 Check Phasing terminals 27 - 22

    4 With R Phase removed, apply 80 % of Vn and check across terminals 16-22

    5 With R Phase restored, apply 125 % of Vn and check across terminals: 15, 16, 22 6 Test (same as 4) with Y Phase 7 Test (same as 5) with Y Phase 8 Test (same as 4) with B Phase 9 Test (same as 5) with B Phase

    10 Check rated Voltage Vn on terminals: 15, 16, 22 (Inject voltage at: 17 18 24)

    17 - 15 18 - 16 11 Check Phasing Terminals 24 - 22

    12 Check for fuse failure operation for R, Y, B Phase Relay operation checked by reducing one phase voltage only

    13Operates approximately 50% of rated voltage

  • Transmission Commissioning Department 21/27

    Test Procedure for Trip Relays

    1. General

    1.1 For random test contractor has to complete 100% internal testing and test reports must be ready before starting random test.

    1.2 Get information from contractor about problems and defects during internal tests. 1.3 Check the relay datas (type, model, and contact details) with drawings and test report. 1.4 Check the drawings for output contact configuration and function with reference sheets

    (compare Z sheet). 1.5 Select the random relays (20% of total relays). 1.6 Check IR value with 500 V Megger with respect to body/case. 1.7 Check the test setup then start the voltage injection slowly and linearly when relay

    changes the status record. Record the current and voltage at the time of pickup or drop off. (Refer to the test setup).

    1.8 Compare the operating voltage and operating current with technical specification of relay manufacturer.

    1.9 Check the current at 110 V which must be zero or very low value (confirm cut-off or economizer function of the relay)

    1.10 Zero (0) or low current as per specification of the manufacturer if the relay is high burden. Low burden relays check the technical specification.

    1.11 Check the operating time of the relay (use the contact to stop the timer which is used for tripping).

    1.12 The expected operating time is 8 ms for AREAVA Trip relays. ( at Rated Voltage) 1.13 The expected operating time is 10 ms for VA Tech Trip relays. ( at Rated Voltage) 1.14 Check the resetting voltage, current and operating, resetting time for relay has reset

    coil or self reset trip relays. Compare the test results with technical specification. 1.15 Confirm that the cut-off contact is present in both trip coil & Reset coil. 1.16 Confirm minimum one spare NO contact available. 1.17 Check the capacitance discharge test for High Burden trip relay. Relay should not trip.

    with Capacitor connected (Refer test setup). 1.18 For Areva relays there is a shorting across 22 and 24 for high burden application. 1.19 First charge the capacitor to 150V 1.20 Discharge the capacitor through relay. Relay should not operate. 1.21 Ensures that output contact resistance, make, and brake and change over contact.

    Contact resistance must be less than 1 ohm. 1.22 Check the wiring and other data on at LV Compartment/ Relay panels such as label,

    Relay Identification etc. 1.23 During pick up and drop off test the capacitor (of test setup) circuit must be in OFF

    Condition.1.24 Capacitor must be connected to correct polarity during capacitor discharge test.

  • Transmission Commissioning Department 22/27

    Test Format (Typical) for a Trip Relay

    Relay Data. Relay Type Aux DC Supply Model No. MVAJ 055 General Inspection and checks. i. Correctness of Installation and wiring. ii. Earthing connection for Relay case to Earth Bar

    iii. IR of relay circuit & associated wiring to earth (500V Megger)

    iv. Operation of Output contacts & Contact Resistancev. Operation of Mechanical Flag and Resetting arm vi Sr.No. On Modules, Case and Cover Identical

    No. of NO Contacts 4v Contact configuration

    No. of NC Contacts 1Relay Test Results

    Operating Coil PICK UP

    Reset coilPICK UP

    Operating Time in mSec. at Voltage Relay Designation

    Sr. No. VOLTS mA

    VOLTS mA

    Currentat 110V mA 110V 66 V 150 V

    Capacitor Discharge Withstand test: Operation on Discharge of 150 Volts with 10 F Capacitor Operated Not Operated. If operated at 150 V, The discharge voltage below 150 V at which relay not operated must be recorded.

    Mechanical Reset Test: Reset the relay with front cover closed and check all contacts resetting properly. Operating time at 110V DC < 8 mSec.

    Note:1. The reset test is not applicable for Hand reset relays. 2. There would be chattering at the time of pick up. This is acceptable. There should not

    be any chattering within the operating range of the relay rated voltage.

  • Transmission Commissioning Department 23/27

    Testing of Meters

    1. Objective:

    The objective of test is to verify whether the measurement is within the accuracy class specified by the manufacturer and DEWA.

    2. General:

    Verify the nameplate details (e.g., range, CT/VT Ratio, Accuracy Class etc are matching with the specification given in the approved drawings).

    3. Calibration

    3.1 Connect the meter to be tested (e.g., a 0 1200A, CTR 1000/1A Ammeter) to the test kit. 3.2 Inject current till the meter dial under test reads 1200A. Record it in the test format Actual

    Reading.3.3 Note down the current injected in the Input current. (e.g. 0.99A) 3.4 Calculate the expected current by multiplying the input current with CT Ratio. It would be

    990A (for this example). Record this value in the Expected Current. 3.5 Calculate the Percentage Error with the following equation:

    Actual Reading Expected Reading X 100% Full Scale Reading 3.6 Record 3 to 4 Readings (e.g., at 20%, 50%, 75%, 100% and Full Scale of readings).

    AMMETER TYPE: ACCURACY CLASS: RATING:

    CT RATIO : FULL SCALE READING :

    FEEDERNO.

    AMMETER SR NO.

    INPUTCURRENT(mA)

    EXPECTEDREADING (A)

    ACTUALREADING(A) %ERROR

  • Transmission Commissioning Department 24/27

    Wiring diagram: Typical Trip Circuit Diagrams

  • Transmission Commissioning Department 25/27

    Wiring diagram: Typical Trip Circuit Supervision Relay Type MVAX 31

  • Transmission Commissioning Department 26/27

    Wiring Diagram: Typical Trip Relay Type MVAJ055

  • Transmission Commissioning Department 27/27

    Wiring Diagram: Typical Voltage Supervision Relay Type MVAP22

    Diagrams: Courtesy Areva