DESIGN SERVICES FOR BALLSTON- MU METRO STATION AREA IMPROVEMENTS 90% PLAN PRESENTATION: DECEMBER 2015

Upload: dangxuyen

Post on 07-Feb-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

DESIGN SERVICES FOR BALLSTON-

MU METRO STATION AREA

IMPROVEMENTS90% PLAN PRESENTATION: DECEMBER 2015

PRESENTATION OUTLINE

The purpose of this presentation is:

1. Update on the status of the plans for the Ballston Metro Station Area project

2. to discuss next steps

AGENDA:

Background – WHERE WE’VE BEEN

Briefing on Proposed Final Plan – WHERE WE ARE NOW

Discussion and Follow Up Issues – WHAT’S NEXT

BACKGROUND TO THIS PROJECT

2010-2013 Multimodal

Improvements Study

Established purpose & goals

Developed 3 Alternative Concepts

Chose preferred Alternative

2014-2016 Design Services for

Ballston MU Metro Station

Improvements

Design development of Preferred

Alternative

30% - 60% - 90% Construction Plans

Final Construction Plans &

Construction Management

PROJECT AREA BOUNDARIES

EXISTING CONDITIONS

ISSUES ADDRESSED

Bus & Pedestrian Congestion

Improve management of curbside operations

Enhance bus passenger and pedestrian amenities

Minimize conflicts

ISSUES ADDRESSED

Safety

Shuttle pick up / drop off

Minimize pedestrian and vehicular conflicts

Improve safety of all users

EARLY IMPLEMENTATION – SHUTTLE RELOCATION

NEW SHUTTLE LOCATIONSFORMER ISSUES WITH

SHUTTLES

ISSUES ADDRESSED

Multimodal Access

Kiss and ride

Bike parking

ADA/pedestrian access improvements

ISSUES ADDRESSED

Amenity

Enhance user experience & amenities

Enhance viability of retail

Maximize green space / Low Impact Design

INPUT & GUIDANCE ALONG THE WAY

Technical Committee

Concepts

2014 20162015

30% Design 90% Design 100% Design60% Design

Stakeholders

Public

90% CONSTRUCTION PLAN

90% PLAN – AERIAL PERSPECTIVE

FAIRFAX FRONTAGE

ISSUES WITH CURRENT PLAZA

INADEQUATE BUS SHELTERS

SEPARATION OF WAITING AREAS

POORLY DEFINED CIRCULATION

LIMITED RETAIL ACCESSIBILITY

SITE PLAN

PLAZA & TREE SAVE AREA

Use of planting and

paving to distinguish

clear circulation

zones

BUS BAYS – BEFORE / AFTER

Additional bus

bay and wider

shelters with

ADA access

width to

address bus

area congestionBEFORE AFTER

BIKE PARKING STRUCTURE

PRIOR “AMPHITHEATER” DESIGN

FOR BIKE PARKING STRUCTURE

CURRENT BIKE PARKING

REDESIGNED WMATA PROTOTYPE BIKE & RIDE PARKING STRUCTURE

BIKE PARKING STRUCTURE

Bike structure redesigned & relocated

Keeps hotel visibility

PRIOR “AMPHITHEATER”

DESIGN

PLANTER AREAS

TYPICAL PLANTER AREA

CURRENT CONDITIONS PROPOSED PLANTER AREA

Use of greener strategies – new

planters / rain gardens

STUART ST. FRONTAGE

ISSUES WITH CURRENT FRONTAGE

INADEQUATE BUS SHELTERS / WAITING AREA

CIRCULATION CONFLICT WITH WAITING AREASPEDESTRIAN SAFETY AND BUS BAY /

BUILDING ENTRY ALIGNMENT

STUART ST. FRONTAGE

SITE PLAN

PROPOSED CROSS SECTION

Clear delineation of

circulation zones

PLANTERS / BUS WAITING AREAS

PROPOSED CONDITION

EXISTING CONDITION

STUART ST. FRONTAGEPROPOSED CONDITION

EXISTING CONDITION

STUART ST. FRONTAGE

PROPOSED CONDITION

EXISTING CONDITION

Align mid block crossing with entrance

of 901 Stuart St. to avoid bus bays

STUART ST. FRONTAGE

PROPOSED CONDITION

EXISTING CONDITION

Former plan proposed reworking

curbside uses and street width

STAFFORD ST. FRONTAGE

Current plan proposes only cross walk and curb

extension to address ADA compliance

STREET FURNITURE & AMENITIES

BUS SHELTERS/BENCHES

COUNTY STANDARD BUS SHELTER

AND BENCH

BENCH PROPOSED IN PLAN (B.I.D.

STANDARD)

INFORMATION SIGN

ELEMENTS

BIKE RACK

PROPOSED IN PLAN

(B.I.D. STANDARD)

LIGHTING

LIGHTING STANDARD

PROPOSED IN PLAN – USE

OF LED’S

COUNTY LIGHTING STANDARD -

CARLISLE

TRASH CANS

COUNTY STANDARD WASTE

RECEPTACLE–VICTOR STANLEY SD-42

TRASH CAN PROPOSED IN PLAN

(B.I.D. STANDARD)

NEWSPAPER MACHINES

CURRENT CONDITION PROPOSED CONDITION

CONSTRUCTION PHASING

PHASE 1 WORK AREA

PHASE 2 WORK AREA

WILL PRESERVE A.D.A

ACCESSIBLE

PEDESTRIAN ACCESS TO

METRO AND

BUSINESSES

THROUGHOUT

CONSTRUCTION

ISSUES & NEXT STEPS

December 16th, 2015 - Public Meeting NRECA Building, 4301 Wilson Blvd

To present 90% plans and hear comments and follow up issues

January to April 2016 - Permits, easements, ownership & maintenance

agreements

March to June 2016 - Contractor procurement

Late summer 2016 through early 2018 - Construction

FOR MORE INFO:

FULL REPORT CAN BE FOUND AT:

arlingtonva.us

Search: Ballston multimodal

PROJECT MANAGER CONTACT INFO:MARK SCHNAUFER, AICP

Sr. transit planner/project management coordinator

Arlington county Dept. of Environmental Services

2100 Clarendon Boulevard, suite 900

Arlington, VA 22201

703-228-3935

[email protected]