Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

Upload: others

Post on 10-Feb-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Design Review of Facility Improvement Projects

Eastern Pulaski Community School Corporation

Page 2: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Agenda

Board Meeting Schedule Scope of Work Summary Overall Building Plans and Scope Summary Update on Areas of Design Development

• Programming and Space planning layouts

2

Page 3: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Board Meeting Schedule

The goal of the school board meetings is to provide information allowing the Superintendent and School Board to be confident the project planning and design is proceeding in the manner best for the students of the Corporation

3

Page 4: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Scope of Work Summary This Summary is a “working document” Will be updated periodically throughout the

design phase of the project The preliminary costs are estimate budgets Budgets for each scope of work listed may go

down or up in cost as more information and design collaboration occurs

Gibraltar and EPCSC continue to monitor the progress and establish final cost estimate budget verification PRIOR to projects Issue for Bidding

4

Page 5: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Summary Building Plans

Page 6: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Eastern Pulaski Elementary School

6

Page 7: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Eastern Pulaski Elementary School New Secure Main Entry

• Replace existing storefront • Carpet • Ceiling and lighting • Create access control

Renovate Existing Main Office

• Reconfigure to improve functionality

• Incorporate Community Health Clinic

• Wall finishes • Carpet • Ceiling and lighting • Update electrical/data distribution • Reconfigure HVAC

7

Conf Princ Clinic

Recept Clinic T Wait

Wkroom Files

Counselor

Page 8: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Eastern Pulaski Elementary School

Art and Learning Lab • Reconfigured to improve

space utilization • Wall finishes • Carpet and VCT • Ceiling and lighting • Update electrical/data

distribution • Reconfigure HVAC

8

Art Learning Lab

Page 9: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Eastern Pulaski Elementary School Classroom Improvements

− Main Academic Wing • Replace wall finishes, carpet,

ceiling and lighting • Reconfigure/add electrical

convenience outlets • Replace windows • Replace chalkboards with

markerboards • Enclose Classroom Pod Areas

(Alternate Bid) Restroom Renovations

• Provide ADA compliance • Replace ceiling, lighting,

partitions, fixtures, and finishes

9

Classroom Pod

Page 10: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Eastern Pulaski Elementary School

Coat Rooms • Two-tier lockers for better

hygiene • Doors for better supervision • Equipment storage • Wall finishes • Ceiling and lighting

10

Coats

Page 11: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Eastern Pulaski Elementary School

Gym Improvements • Replace Bleacher Drive Units • Replace gym floor (Alternate Bid)

Mechanical/Electrical Improvements

• AHU and VAV terminal replacement • Galvanized piping replacement • Replace lighting (Exception: Gym) • Replace fire alarm • Replace emergency lighting and exit signs • Update technology infrastructure

11

Page 12: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community MS/HS First Floor

12

Page 13: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community MS/HS Second Floor

13

Page 14: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

New Secure Main Entry • Update access control • Secure main entries

Renovate Existing Main

Office • Reconfigure to improve

functionality • Wall finishes • Carpet • Ceiling and lighting • Update electrical/data

distribution • Reconfigure HVAC

14

Clinic

T

Princ

Files

Conf

Wkroom Recept

T

Page 15: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

Restroom Improvements

• Provide ADA compliance • Renovate existing facilities

15

Page 16: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

1st and 2nd Floor Classroom Improvements

• Replace chalkboards (markerboards)

• Doors • Wall finishes • Ceiling • Carpet • Lighting • Outlets

16

Page 17: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

Socialtorium • Expand restrooms • Provide ADA

accessibility to facility • Relocate Dressing

Rooms • Replace seats • Doors • Wall finishes • Ceiling paint • Carpet and stage

flooring • General lighting • Replace HVAC system

17

Page 18: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

Science Rooms • Reconfigure rooms to

accommodate educational needs • New student lab stations • Reuse existing casework • Wall finishes • Ceiling pads and lighting • Update electrical/data distribution

Gym Improvements • Replace heating only AHUs with

new heating/cooling units • Install new gym floor

Four Science

Classroom Renovation

18

Page 19: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

Family and Consumer Sciences • Replace chalkboards (markerboards) • Doors • Wall finishes • Ceiling • Carpet • Lighting • Outlets

19

Page 20: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

Band/Choir • Replace chalkboards

(markerboards) • Doors • Wall finishes • Ceiling • Carpet • Lighting • Outlets

20

Page 21: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community High School

Mechanical/Electrical Improvements • Replace pneumatic building automation system with DDC

(Services the high school and middle school) • Replace chiller plant

(Services the high school and middle school) • Replace electrical service, vault, transformer, etc

(High School, only) • Replace lighting

(Renovated areas: offices, classrooms, etc) • Replace fire alarm • Replace emergency lighting and exit signs • Update technology infrastructure

21

Page 22: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community Middle School

New Secure Main Entry

• Secure main entry • Update access control

22

Vest

Recept/Wait

Page 23: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community Middle School

Restroom Improvements • Provide ADA compliance • Renovate existing facilities

23

Page 24: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community Middle School

Classroom Improvements • Replace chalkboards

(markerboards) • Doors • Wall finishes • Ceiling • Carpet • Lighting • Electrical convenience outlets

MS Science Rooms • Reconfigure/relocate • Replace finishes

(floors, walls, doors and ceilings) • New casework

and furniture

Cla

ssro

oms

24

Page 25: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Winamac Community Middle School

Mechanical/Electrical Improvements

• Replace lighting (Renovated areas: offices, classrooms, etc) • Replace fire alarm • Replace emergency lighting and exit signs • Update technology infrastructure

25

Page 26: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Project Budget

26

Budgeted Cost

Winamac Community High School $5,658,640 Winamac Community Middle School $1,499,230 Eastern Pulaski Elementary School $3,213,010

Total $10,370,880

Page 27: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Proposed Project Schedule

Timeframe Milestone

October 13, 2014 • School Board Meeting – Project Update and Discussion

November 10, 2014 • School Board Meeting – Final Design Approval

December 8, 2014 • School Board Meeting – Approval for Bidding

February 2, 2014 • School Board Meeting – Approve Bids

March 2015 • Begin Construction (Tentative)

September 2016 • Substantial Completion (Tentative)

October 2016 • Project Complete (Tentative)

27

Page 28: Design Review of Facility Improvement ProjectsDesign Review of Facility Improvement Projects Eastern Pulaski Community School Corporation October 13, 2014 Scope of Work Summary This

Design Review of Facility Improvement Projects Eastern Pulaski Community School Corporation

October 13, 2014

Comments