dale drive pedestrian facility improvement project · 2020. 3. 4. · facility improvement project....

19
February 2020 Public Meeting FEBRUARY 26, 2020 PUBLIC MEETING DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT

Upload: others

Post on 12-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

FEBRUARY 26, 2020

PUBLIC MEETING

DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT

Page 2: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

2

• Project Overview

• Project Schedule

• Design Considerations

• Preliminary Design

• Q&A

Outline

Page 3: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

3

• Share the 35% design with the community

• Receive comments on current 35% design

• Answer questions from the community

Meeting Outcomes

Page 4: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

4

Pedestrian Facility on Dale DriveGeorgia Avenue to Colesville Road

Project Overview

LEGENDStudy AreaExisting Trails

4

Page 5: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

5

Proposed Intersection ImprovementsColumbia Boulevard, Luzerne Avenue, Grace Church Road

Project Overview

LEGENDStudy AreaExisting Trails

5

Page 6: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

6

Life

of a

Tra

nspo

rtat

ion

Proj

ect

We

Are

Her

e

Page 7: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

7

• Collected over 140 comments on preferred alternative via online, write-in comment cards, and emails

• Briefed Planning Board on alternative analysis and community feedback

• Recommended Shared Use Path on North Side

• Briefed the County’s T&E Committee on alternative analysis and community feedback

• Selected Shared Use Path on North Side as the preferred alternative towards 35% design

• Developed 35% design plans

Since The Last Meeting…

Page 8: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

8

June 2019

Begin Project

February 2019

June 2020

August 2018

Current Project Milestone Schedule

Project Schedule

Public Workshop

Spring 2020

SWM Concept Plan Approval;

Mandatory Referral

End Facility Planning Study;

Pending Funding Approval For Final Design

We Are Here

February 2020

35% Design Plans;

Public Meeting

February 2020

Preferred Alternative

Page 9: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

9

• Provide a safe pedestrian facility and crossings• Connectivity to existing trails and sidewalks• Minimize impacts

• Residential frontage• Environmental resources• Utilities

• Maintain existing neighborhood aesthetics• Ensure a permittable project• Provide proper drainage and stormwater

management• Consider existing bus/school bus stop locations

Design Considerations

Page 10: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

10

Existing Typical Section

Typical Sections

Page 11: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

11

Georgia Ave to Colesville RdProposed 8’ Sidepath: North Side

Typical Sections: Preferred Alternative

Page 12: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

12

Corwin Drive to Luzerne Ave OnlyProposed 8’ Sidepath: North and South Side

Typical Sections: Preferred Alternative

Page 13: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

13

Columbia BoulevardIntersection Improvements

13

Page 14: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

14

Luzerne AvenueIntersection Improvements

14

Page 15: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

15

Grace Church RoadIntersection Improvements

15

Page 16: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

16

Frequently Asked Questions (FAQ’s)

• I have some comments about the short-term improvements and traffic-related issues. Who should I talk to?

• Are you cutting down any trees? What about the landscaping in front of my house?

• It seems like my property might be impacted from this project. What is going to happen next?

• Is this project going to be built soon?

• I have some comments and suggestions about the long-term improvements on Dale Drive. How do I make sure that my voice is heard?

Page 17: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

17

• Collect additional comments from the community

• Mandatory Referral Review with M-NCPPC• Documentation on findings and

recommendations for next phase of design• Pending funding approval from the County

Council for final design and construction

Next Steps

Page 18: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

18

Contact

Angel Cheng, P.E.Project Manager

240-777-7274

[email protected]

https://www.montgomerycountymd.gov/dot-dte/projects/daledr/index.html

Concerns about traffic operations:[email protected]

Page 19: DALE DRIVE PEDESTRIAN FACILITY IMPROVEMENT PROJECT · 2020. 3. 4. · FACILITY IMPROVEMENT PROJECT. February 2020 ... • Project Schedule • Design Considerations • Preliminary

February 2020Public Meeting

Questions?

19