design of inverted strip fdn. beam
TRANSCRIPT
Design of Reinforced Concrete Elements 275
5.16.14 Example 5.33: Inverted T-Beam Combined Foundation An inverted T-beam combined foundation is required to support two square columns transferring axial loads as shown in Figure 5.125. Using the data provided, design suitable reinforcement for the base.
Design Data: Characteristic dead load on column A 450 kN Characteristic imposed load on column A 450 kN Characteristic dead load on column B 750 kN Characteristic imposed load on column B 750 kN Characteristic concrete strength fcu = 40 N/mm2
Characteristic of reinforcement fy = 460 N/mm2 Net permissible ground bearing pressure pg = 175 kN/m2
Nominal cover to centre of main reinforcement 40 mm Column A dimensions 350 mm × 350 mm Column B dimensions 350 mm × 350 mm
Figure 5.125
5.16.15 Solution to Example 5.33
Contract : Foundations Job Ref. No. : Example 5.33 Calcs. by : W.McK. Part of Structure : Inverted T-Beam, Combined Foundation Checked by : Calc. Sheet No. : 1 of 7 Date :
References Calculations Output
The foundation should be designed as a T-beam between the columns where the rib is in tension and as a rectangular beam at the column positions where the bottom slab is in tension.
Using the service loads it is first necessary to determine a suitable base area and dimensions X and Y such that the centre-line of the base coincides with the centre-of-gravity of the column loads. This ensures a uniform earth pressure under the base.
Gk = 450 kN Qk = 450 kN
Gk = 750 kN Qk = 750 kN
A B
Columns 350 mm × 350 mm
0.6 m 5.0 m X m
400 mm
800 mm
460 mm Y m
Design of Structural Elements 276
Contract : Foundations Job Ref. No. : Example 5.33 Calcs. by : W.McK. Part of Structure :Inverted T-Beam, Combined Foundation Checked by : Calc. Sheet No. : 2 of 7 Date :
References Calculations Output
Base Area: Total service load = (450 + 450 + 750 + 750) = 2400 kN
Minimum area required = pressure bearing epermissibl
load service
= 175
2400 = 13.71 m2
Actual Load System
Equivalent Load System
Equate the moments of the force systems about the centre-line of column B: Mcentre-line column B = (900 × 5.0) = (2400 × x) ∴x = 1.875 m
The centre-line of the base should coincide with this position.
5.0 m
A B
900 kN 1500 kN
xB
Total load = 2400 kN
5.0 m
900 kN 2400 kN
0.6 m 3.125 m 1.875 m X m
1.875 m
B
Design of Reinforced Concrete Elements 277
Contract : Foundations Job Ref. No. : Example 5.33 Calcs. by : W.McK. Part of Structure :Inverted T-Beam, Combined Foundation Checked by : Calc. Sheet No. : 3 of 7 Date :
References Calculations Output
Length of the base = [2 × (3.125 + 0.6)] = 7.45 m ∴ X = (7.45 − 5.6) = 1.85 m
Width of the base Y = (13.71 / 7.45) = 1.84 m
Ultimate bearing pressure: Ultimate load on column A = (1.4 × 450) + (1.6 × 450) = 1350 kN Ultimate load on column B = (1.4 × 750) + (1.6 × 750) = 2250 kN
Ultimate design pressure under the base = ( )( )841457
22501350
.. ×+
= 262.6 kN/m2
The combined base can be regarded as a beam 1.84 m wide. Longitudinal load/m = (262.6 × 1.84) = 483.2 kN/m
Shear force at Q = (483.2 × 0.6) = + 289.9 kN and = (289.9 − 1350) = − 1060 kN
Shear force at R = −1060 + (483.2 × 5.0) = +1356 kN and = (1356 − 2250) = −894.1 kN
Position of zero shear = 2483
1060
. = 2.19 m
Shear force diagram
Bending moment at Q = shaded area
=
× 9289
2
60.
. = 86.8 kNm
1350 kN 2250 kN
483.2 kN/m
0.6 m 5.0 m 1.85 m
P Q R S
894.1 kN
1356 kN
289.9 kN
1060 kN
Design of Structural Elements 278
Contract : Foundations Job Ref. No. : Example 5.33 Calcs. by : W.McK. Part of Structure :Inverted T-Beam, Combined Foundation Checked by : Calc. Sheet No. : 4 of 7 Date :
References Calculations Output
Bending moment at R = shaded area
=
×894
2
851. = 827 kNm
Maximum bending moment at point of zero shear:
= resultant shaded area = 87 −
×1060
2
192.= − 1074 kNm
Design the base as a T-beam between A and B and as a rectangular beam at the column locations.
Assume 32 mm diameter bars for the main steel.
Effective depth: d = (1260 – 40 – 16 ) = 1204 mm (Note: This is the mean effective depth)
Bending between the columns A and B (T-beam):
Design bending moment between the columns = 1074 kNm
Clause 3.4.4.4cufbd
MK
2= =
4012041840
1010742
6
×××
= 0.01 < K´ ( = 0.156)
Section is singly reinforced
827 kNm
1074 kNm
87 kNm
460 mm
1840 mm
400 mm
d =
120
4 m
m
Design of Reinforced Concrete Elements 279
Contract : Foundations Job Ref. No. : Example 5.33 Calcs. by : W.McK. Part of Structure :Inverted T-Beam, Combined Foundation Checked by : Calc. Sheet No. : 5 of 7 Date :
References Calculations Output
x = (d − z)/0.45 = (0.05 × 1204)/0.45 = 133.8 mm < 460 mm The neutral axis lies in the flange
Z =
−+
9025050
.
K..d =
−+
90
01025050
.
...d
= 0.98d The lever arm is limited to 0.95d
As = Zf.
M
y950 =
1204950460950
101074 6
××××
..= 2149 mm2
Design bending moment at column B (Rectangular section):
= ( )
−×2
17508512483
2... = 678 kNm
Clause 3.4.4.4cufbd
MK
2= =
401204400
106782
6
×××
= 0.03 < K´ ( = 0.156)
Section is singly reinforced
Z =
−+
90
03025050
.
...d = 0.96d
The lever arm is limited to 0.95d
As = Zf.
M
y950 =
1204950460950
10678 6
××××
..= 1356 mm2
Table 3.25 Minimum area of steel = hb
A
w
s100= 0.26%
As ≥100
1260400260 ××. = 1310 mm2 < 1356 mm2
The bottom reinforcement required at column A should be determined by the reader.
460 mm
1840 mm
400 mm
d =
120
4 m
m
TopReinforcement
Select:3/32 mm diameter bars providing2410 mm2
BottomReinforcement
Select:3/25 mm diameter bars providing 1470 mm2
Design of Structural Elements 280
Contract : Foundations Job Ref. No. : Example 5.33 Calcs. by : W.McK. Part of Structure :Inverted T-Beam, Combined Foundation Checked by : Calc. Sheet No. : 6 of 7 Date :
References Calculations Output
The reinforcement required to resist transverse bending can be determined in a similar manner. Consider a 1m width strip:
Assume 25 mm diameter bars:
d = (460 − 40 − 25 − 13) = 382 mm
Transverse bending moment =
×
2
7202483
2..
= 125.2 kNm/m width
Clause 3.4.4.4cufbd
MK
2= =
403821000
102.1252
6
×××
= 0.02 < K´ ( = 0.156)
Section is singly reinforced
Z =
−+
90
02025050
.
...d = 0.98d
The lever arm is limited to 0.95d
As = Zf
M
y95.0 =
38295.046095.0
102.125 6
××××
= 789 mm2 /m
Table 3.25 Minimum area of steel = 0.15%
As ≥100
4601000150 ××. = 690 mm2/m < 789 mm2/m
Clause 3.4.5 Shear resistance of the T-beam: Consider shear at the face of Column B Table 3.8 Critical shear stress
db
A
v
s100 =
1204400
2410100
××
= 0.5 ∴ vc = 0.5 N/mm2
Modify to allow for using C40 concrete vc = (0.5 × 1.17) = 0.59 N/mm2
Table 3.7 (vc + 0.4) = 0.99 N/mm2
1.0 m
BottomReinforcement
Select:20 mm diameter bars@ 400 mm centres providing 786 mm2/m
720 mm
483.2 kN/m2
Design of Reinforced Concrete Elements 281
Contract : Foundations Job Ref. No. : Example 5.33 Calcs. by : W.McK. Part of Structure :Inverted T-Beam, Combined Foundation Checked by : Calc. Sheet No. : 7 of 7 Date :
References Calculations Output
Shear force at the face of the column: V = (1356 − (483.2 × 0.175) = 1271.4 kN
v = db
V
v =
1204400
1041271 3
××.
= 2.64 N/mm2
Since (vc + 0.4) < v < 0.8 cuf
< 5.0 N/mm2
Design links are required
Asv ≥yv
cvsv
950
)(
f.
sb υυ −
Assume two-legged 10 mm diameter links ∴ Asv = 157 mm2
Sv ≤ ( )
−×××
590642400
250950157
..
. = 45.5 mm
A similar calculation should be carried out by the reader to determine the links required over the full length of the T-beam.
Clause 3.4.5 Shear resistance of the flange: Consider shear at the face of rib
Table 3.8 Critical shear stress
db
A
v
s100 =
3821000
786100
××
= 0.2 ; d = 382 mm
vc = 0.37 N/mm2 ; modify to allow for using C40 concrete vc = (0.37 × 1.17) = 0.43 N/mm2 (vc + 0.4) = 0.83 N/mm2
Shear force V = (483.2 × 1.0 × 0.72) = 348 kN
v = db
V
v =
3821000
10348 3
××
= 0.91 N/mm2 < 0.8 cuf
< 5.0 N/mm2
Table 3.16 Since the shear stress v is greater than vc shear reinforcement is required. Shear links are not normally provided in slabs.
Alternatives to providing links are to increase the % of reinforcement As and hence increase the value of vc sufficiently, or to increase the thickness of the slab, which will reduce the value of v.
Adopt double 10 mm diameter two-legged links @ 100 mm centres for the 1st
metre from column B
720 mm
483.2 kN/m2