demo 1 - jack-in & soil nailed excavation in fills compatib
TRANSCRIPT
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
1/35
10/22
1
Case Studies of Supportof Open Excavations andDistressed RetainingWalls in Malaysia
Ir. Liew Shaw Shong
2
Type of Case Studies
1 : Jack-In Pipe Anchorage
2 & 3 : Excavation in Fill Ground
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
2/35
10/22
3
Case Study 1
4
Building Boundary
CBP Wall
(5 rows GroundAnchors)
Soldier Pile Wall
(9 rows of Jack-In Anchors)
Soldier Pile Wall(9 rows of Jack-In Anchors)
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
3/35
10/22
5
Jack-In Anchor Installation
Jack-In AnchorsBuilding
CBP Wall Tunnel Construction inprogress
Tunnel Construction inprogress
Ground Anchors
6
GEOLOGY & SUBSOIL CONDITIONS
Meta-sedimentary Kajang formation overlain by somealluvial deposits consisting of sandy clayey silts and fill
0 10 20 30 40SPT'N
30
25
20
15
10
5
0
Depth(m)
16 17 18 19 20
Bulk Unit Weight (kN/m3)
0 40000 80000Young Modulus (kPa)
0 20 40 60 80Atterberg Limits
Legend
LL
PL
MC
Layer 1 -Fill
(ClayeySilt)
Layer 2 -Clayey
Silt
Layer 3 -Sandy Silt
Layer 4 -Sandy Silt
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
4/35
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
5/35
10/22
9
Pull Out Tests for Instrumented Jack-In Anchor
JackedAnchor atLevel 4
JackedAnchor atLevel 7
0 10 20 30Head Displacement (mm)
0
50
100
150
200
250
Pull-OutLoad(kN)
120
80
40
0
ShaftResis
tance(kN/m2)
Pull-Out TestTest 1 ( 6 Days)
04-Mar-2002
Test 2 (14 Days)12-Mar-2002
Test 3 (24 Days)22-Mar-2002
Pipe Shaft Resistance
Test 1: C-D
Test 1: D-E
Test 1: E-F
Test 2: C-DTest 2: D-E
Test 2: E-F
Test 3: C-D
Test 3: D-E
Test 3: E-F
VWSG - C VWSG - D VWSG - E VWSG - F1.6m 4.6m 7.6m 10.6m
0 10 20 30Head Displacement (mm)
0
50
100
150
200
250
Pull-OutLoad(kN)
120
80
40
0
ShaftResistance(kN/m2)
Pull-Out Test
Test 1 ( 5 Days)15-Jan-2002
Test 2 (14 Days)25-Jan-2002
Test 3 (21 Days)1-Feb-2002
Pipe Shaft ResistanceTest 1 :A-B
Test 1 :B-C
Test 1 :C-D
Test 1 :D-E
Test 1 :E-F
Test 2 :A-BTest 2 :B-C
Test 2 :C-D
Test 2 :D-E
Test 2 :E-F
Test 3 :A-B
Test 3 :B-C
Test 3 :C-D
Test 3 :D-E
Test 3 :E-F
VWSG - A VWSG -B VWSG - C VWSG - D VW SG - E V WS G - F
18m
6.0m 9.0m 12.0m 15.0m0.6m 3.0m
10
Jack-in Anchor Load with Time
0 50 100 150 200 250 300
Time (Days)
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
oa
Level 3 - FEM Results
Level 5 - FEM Results
Level 7 - FEM Results
Level 9 - FEM Results
Loading at Jacked Anchors
Level 3
Level 5
Level 7
Level 9
3rd layer : 5/01/2002
Load cell :12/01/2002
5th layer : 19/01/2002
Load cell : 29/01/2002
7th layer : 22/02/2002
Load cell : 6/03/2002
9th layer : 27/03/2002
Load cell : 28/03/2002
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
6/35
10/22
11
Prestressed Ground Anchor Load with Time
0 50 100 150 200 250 300
Time (Days)
0
50
100
150
200
250
300
350
400
450
500
550
600
Load
(kN
)
Level 2 - PLAXIS
Level 3 - PLAXIS
Level 4 - PLAXIS
Level 5 - PLAXIS
Loading at Ground AnchorLevel 2
Level 3Level 4
Level 5
Load cell : 19/01/2002
Load cell : 20/03/2002
Load cell : 19/02/2002
Load cell : 22/02/2002
12
Wall MovementGround Anchor WallJack-In Anchor Wall
0 10 20 30 40 50
Wall Movement (mm)
26
24
22
20
18
16
14
12
10
8
6
4
2
0
epth(m)
Measured Wall DeflectionStage1
Stage2
Stage3
Stage4
Stage5
Final Stage
- Movement (Back analyses) of CBP wall for each stages
1
3
2 45 F
1
0 10 20 30 40
Wall Movement (mm)
26
24
22
20
18
16
14
12
10
8
6
4
2
0
Depth(m)
Measured Wall Deflection
Stage 1
Stage 2
Stage 3
Stage 4
Stage 5
Stage6
Stage 7
Stage 8
Stage 9
Stage 10
1
23
4
5
6
7
9
8
F
- Movement (Back analyses) of CBP wall for each stages
8
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
7/35
10/22
13
Ground Settlement behind CBP Wall
0 20 40 60 80 100 120 140
Time (Days)
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Ground Settlement atJacked Anchor Wall (Measured)
Jacked Anchor Wall (FEM Results)
Ground Anchor Wall (Measured)Ground Anchor Wall (FEM Results)
Jack-In Anchors Wall : dV/dH (wall) = 1.57
Ground Anchor wall : dV/dH (wall) = 3.37
dV : Ground Settlement Behind the Wall
dH : Horizontal Wall Deflection
14
BACK ANALYSES WITH FEM MODELLING
FEM Plane Strain Analysis (PLAXIS)
Hardening Soil Model
Interface Element : To model the SoilInteraction with Wall & AnchorageElements
Temporary Wall and Jacked Anchors :Beam Element (Axial & BendingStiffness)
Consolidate for 6 months after finalexcavation to model Drained Condition
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
8/35
10/22
15
Typical FEM Model
Beam Element (Jack-In Anchors)
Beam Element
(CBP Wall and Soldier Piled Wall)
Interface Element
16
Soil Shear Strain within Jack-In AnchorRetaining System
Relatively larger shear strains ranging between0.26% and 0.38% developed along the
potential slip surface
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
9/35
10/22
17
Total Ground Displacement of Jack-InAnchor Retaining System
The reinforced soil mass has more displacementat the upper portion with gradually reduced
trend towards the lower portion
18
Dimensionless Ground Surface Settlement
0.2
0.15
0.1
0.05
0
Settlement/Excav
ationDepth(%)
25 20 15 10 5 0
Distance from Wall / Excavation Depth
Clough & ORourke
(1990)
Maximum wall movement of CBP wall atfinal excavation is about 0.002H
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
10/35
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
11/35
10/22
21
RECOMMENDATIONS
To avoid flexural effect, straingauges shall be installed in pairs at
jacked anchor section.
Research on generation of excesspore water pressure & itsdissipation around and along the
jacked anchor shall be carried out.
Locked in tensile stress under
compressive injection may increasemovement within reinforced earthmass
22
Case Study 2High rise development
with 5 storeybasement car park
Deep excavation:
7m-14.5m
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
12/35
10/22
23
High rise developmentwith 5 storey
basement car park
Deep excavation:
7m-14.5m
Plan
24
Located at the toeof a filled slope
Soil nail stabilisation worksto facilitate excavation
Cross Section
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
13/35
10/22
25
TOPOGRAPHIC
Original hilly ground with natural valley & stream
Loose sandy silt overlaying a thin deposited softcompressible material at valley area
15m highfilled slope
26
SUBSURFACE CONDITIONSBH-4 BH-IM4 BH-IM1 BH-SP1 BH-3 BH-2 BH-1
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
14/35
10/22
27
SOIL NAILING DESIGN & CONSTRUCTION
6m to 12m soil nail at 1.25m c/c spacings
4V : 1H reinforced gunite facing
sufficient weepholes / subsoil drains
28
Additional Strengthening Works at the Valley Area
2 rows of 18mlong soil nail
anchorage
12m long FSPIIIA sheet pilewall
Permanent RCprops againstbasementstructure
3 rows ofsubsoil drains
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
15/35
10/22
29
INSTRUMENTATION MONITORING
30-10 0 10 20 30 40 50 60 70 80 90 100 110
-40
-38
-36
-34
-32
-30
-28
-26
-24
-22
-20
-18
-16
-14
-12
-10
-8
-6
-4
-2
0
Depth(m)
0 5 10 15 20 25 30 35 40 45 50
Legend
20/9/2004
23/10/2004
04/11/2004
09/11/2004
24/11/2004
21/12/2004
24/01/2005
21/02/2005
22/03/2005
12/11/2005
SPT-N
0 10 20 30 40 50 60 70 80 90 100 110
-40
-38
-36
-34
-32
-30
-28
-26
-24
-22
-20
-18
-16
-14
-12
-10
-8
-6
-4
-2
0
5 10 15 20 25 30 35 40 45 50
Legend
09/11/2004
24/11/2004
21/12/2004
24/01/2005
21/02/2005
22/03/2005
12/11/2005
SPT-N
SPT-N Value
Ground Lateral Displacement (mm)
IM-01 IM-04
Lateral Ground Displacement
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
16/35
10/22
31
Ground Settlement
-160
-150
-140
-130
-120
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
GroundSettlement(mm)
-160
-150
-140
-130
-120
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
01/08/04 10/09/04 20/10/04 29/11/04 08/01/05 17/02/05 29/03/05 08/05/05 17/06/05
Date
01/08/04 10/09/04 20/10/04 29/11/04 08/01/05 17/02/05 29/03/05 08/05/05 17/06/05
LegendSM01
SM02
SM03
SM04
SM05
SM06
SM07
SM08
SM09
SM10
SM11
SM12
Construction Post-Construction
Sheet PileInstallation
32
Date
Groundwater Table
GroundwaterTable(RLm)
01/08/04 20/09/04 09/11/04 29/12/04 17/02/05 08/04/05 28/05/05 17/07/05
41424344454647484950
41424344454647484950
01/08/04 20/09/04 09/11/04 29/12/04 17/02/05 08/04/05 28/05/05 17/07/05
4041424344454647484950
4041424344454647484950
SP 01
SP 03
Post-ConstructionConstruction
Sheet Pile Installation
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
17/35
10/22
33
FEM plane strain analysis
Hardening soil model
Coupled consolidation undrained analysis
Initial stresses were calculated by gravity loading
Back Analysis
34
Soil Parameters
Layer MaterialAve
SPT-N
b(kN/m3)
Su(kPa)
c
(kPa)
()
E
(kPa)
Eur(kPa)
Back
Analysed
E
(kN/m2)
RL57m
RL49m
Sandy
Silt
(Fill)
12 18.5 - 5 32 30,000 90,000 18,000
RL49m
RL43m
Sandy
Silt
(Fill)
9 18.5 - 5 32 22,500 67,500 16,200
RL43m
RL40m
Sandy
Clay
(WeakZone)
2 18 400.5
(5)
#20 32,500 97,500 32,500
RL40m
RL37m
Sandy
Silt10 18.5 - 5 (10) # 32 25,000 75,000 25,000
RL37m
RL21m
Sandy
Silt20 18.5 - 5 (10) # 32 50,000 150,000 50,000
Below RL21mGravelly
Sand50 19.5 - 7 32 125,000 375,000 125,000
# Improved apparent cohesion adopted in FE back analysis at the last few stages.
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
18/35
10/22
35
Lateral Ground Displacement
10 20 30 40 50 60 70
10 20 30 40 50 60 70
10 20 30 40 50 60 70
10 20 30 40 50 60 70
10 20 30 40 50 60 70
10 20 30 40 50 60 70
20
25
30
35
40
45
50
55
60
Legend
Measured
Back-analysed
0 10 20 30 40 50
15
20
25
30
35
40
45
50
55
60
Depth(RLm)
0 10 20 30 40 50
Lateral Ground Displacement (mm)
Stage:Progressive Stage: Post-installation Stage: Completion of
nailing of sheet piles with firstrow of 18m soil nails
excavation and soilnail stabilisation
SPT'N'
12m Soil Nail
18m Soil Nail
Sheet Pile
Shotcrete
Legend
Measured
Back-analysed
36
INTERPRETATION
Youngs modulus (E)
E = 1500 to 1800 x SPTN..for upper loose fills
E = 2500 x SPTN..for weathered Granitic Residual subsoil
Unloading/reloading stiffness, Eur = 3 x E
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
19/35
10/22
37
Ground Settlement
30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0
Distance From Excavation Face (m)
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
Settlement(mm)
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0
Legend
Back-Analysed
Measured
Stage: Completion of excavation
Stage: Post-installation of sheet piles
Stage: Progressive nailing
with first row of 18m long soil nails
and soil nail stabilisation
38
Larger ground settlement as compared to FEback-analysis
Possible reasons:
High compressed air flushing the soil to form openhole (micro tunneling)
Excessive ground loss and stress relief
Ground deformation continues at a decreasing rate
INTERPRETATION
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
20/35
10/22
39
30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0
Distance From Excavation Face (m)
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
Se
ttlemen
t(mm
)
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0
Legend
Back-Analysed
Measured
Stage: Completion of excavation
Stage: Post-installation of sheet piles
Stage: Progressive nailing
with first row of 18m long soil nails
and soil nail stabilisation
Subsidence Trough at Active Wedge
40
Large shear strain developed along thepotential slip surface immediately behind thereinforced soil mass
Settlement trough profile at active wedge
Band of potential slip surface running throughthe soft clayey deposit reinforced soil massslides laterally
Soil nails have restricted the development ofactive zones within the reinforced soil mass
INTERPRETATION OF FEM
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
21/35
10/22
41
CONCLUSION FOR CASE STUDY 2
Successful stabilisation of loose fill by soilnailing technique.
Excessive ground loss due to open-hole drillingin loose fill should be carefully considered.
FE analysis provides good insight view of theinherent failure mechanism in investigating thedistresses and back calculated operatingengineering parameters.
42
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
22/35
10/22
43
Case Study 3
Investigation of Soil Nailed SlopeDistress at Fill Ground & RemedialSolution
Site Location
44
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
23/35
10/22
Site Layout
45
Introductions
4V:1H soil-nailed slope
Entire stretch is approximately60m at uncontrolled fill over avalley
Existing 8m to 11 m high
Reinforced Soil wall was 23maway from soil-nailed slope
46
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
24/35
10/22
Localised Surface Slips
47
Localised Surface Slips
48
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
25/35
10/22
Pocket Pilecap Excavation
Project Site
49
Heterogeneous
Fill
Tension Cracks
50
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
26/35
10/22
Subsoil Profiles
Decayed Wood
51
Instrumentation Schemes
Two (2) inclinometers (namelyIN-1 & IN-2) to monitor thenailed slope performance
Ten (10) ground settlementmarkers were installed
An additional inclinometer (IN-5) was installed
52
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
27/35
10/22
Instrumentation Layout
****GSM-1 (WILL
BE BOLD )
GSM - 1
GSM - 2
GSM - 3
53
Groundwater Level
Two (2) observational wells(SP-1 and SP-2) to measuregroundwater level during periodof unexpected prolonged rainstorm between March and April2008
Groundwater fluctuateddrastically between August andDecember 2008 duringconstruction of soil nailing work
54
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
28/35
10/22
Rain Hyetograph(Kuala Lumpur Rain Gauge Station)
Sheet Pile Installation & Top Row
Anchored Nail InstallationPassive Berm
Excavation
Bottom Row
Anchored
Nail & Horizontal
Drain Installation
Waler Beam
Installation
Abnormal storm
01/04/2008 First
Surface Collapse08/07/2008 SP1
Installation
55
Inclinometers Results
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850
Cumulative Displacement (mm)
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
Towards RS Wall Towards Excavation Side
0 50 1 00
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
Red
ucedLevel(m)
25.04.2008 (Collapsed of loose shallow slip of soil nail slope)
25.05.2008 (Pilecap pocket excavation)
25.06.2008
26.07.2008
25.08.2008 (Nearby piling work, sheet pile installation & heavy downpour)
25.09.2008 (Rectification work of localised collapse)
23.10.2008 (Sheet pile machine broke down & heavy downpour)
27.11.2008
24.12.2008
22.01.2009
SOIL NAILED SLOPE WITHTOE LEVEL AT RL74.0m
IN-1 IN-2
Section A-A
56
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
29/35
10/22
Inclinometer Results
0 20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
320
340
360
380
400
420
440
460
480
500
Cumulative Displacement (mm)
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
ReducedLevel(m)
Towards RS Wall
Towards Excavation Side
16.07.2008 (Installation of IN-5)
15.08.2008
25.08.2008 (Heavy downpour)
03.09.2008 (Extraction of temporary sheet pile)
25.09.200813.10.2008
23.10.2008
11.11.2008 (Maximum monitoring result)
04.12.2008 (Tie back after the installation of anchored nail)
17.12.2008 (Reading had been stabilised)
24.12.2008 (Final measurement before IN-5 was spoiled)
SOIL NAILED SLOPE WITHTOE LEVEL AT RL 74.0m
Permanent Sheet Pile (12 ~ 15m Length)
IN-5
57
Remedial Solutions
Instrumentation Monitoring(During & After Slope Distress)
Additional ten (10) numbers ofdisplacement markers wereinstalled; 5 numbers werelocated near the crest of slopewhile the rest of 5 number werepositioned at lower tier of RSwall
58
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
30/35
10/22
Displacement Markers (DSMs)Monitoring Results & Tension Cracks
Settlement Markers at the Soil Nailed Slope Crest
0
50
100
150
200
250
Displacement(mm)
2 3. 06 .2 00 8 2 6. 06 .2 00 8 3 0. 06 .2 00 8 0 2. 07 .2 00 8 3 0. 07 .2 00 8 1 4. 08 .2 00 8 1 8. 08 .2 00 8
DSM-6 DSM-7 DSM-8 DSM-9 DSM-10
Settlement Markers at Lower Tier of RE Wall
0
50
0 15 30 45 60
Displacement(mm)
1 3. 05 .2 00 8 1 4. 05 .2 00 8 1 7. 05 .2 00 8 2 3. 05 .2 00 8 2 6. 06 .2 00 8 0 8. 08 .2 00 8 1 4. 08 .2 00 8
DSM-5 DSM-4 DSM-3 DSM-2 DSM-1
59
Ground Settlement Markers (GSMs)Monitoring Results
60
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
31/35
10/22
Typical Cross Section
61
Monitoring Results forInstrumented Anchor Nail
08/07/08
11/15/08
02/23/09
27/08/08
16/09/08
06/10/08
26/10/08
05/12/08
25/12/08
14/01/09
03/02/09
15/03/09
04/04/09
Date
0
20
40
60
80
100
120
140
160
180
200
220
Loa
dTrans
ferre
d(kN)
Level A Level B
0
20
40
60
80
100
120
140
160
180
200
220
0 25 50 75 100 125 150 175 200 225 250 275
Elapsed Days
MOBILISED FORCE RESULT OF ANCHORED NAIL
Sheet Pile Installation &Top Row of Anchored Nail Installation
Passive Berm
Excavation
Bottom Row Anchored
Nail & Horizontal
Drain Installation
Waler Beam
Installation
Level C62
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
32/35
10/22
Finite Element Method (FEM)Analyses
Hardening soil model
Anchor nails with littlebending stiffness andmodelled as geotextileelement
Sheet piles modelled as
plate element
63
Soil Material Properties in FEMAnalyses
MaterialAverage
SPT N
Bulk
Density,
b (kN/m3)
Effective
Cohesion,
c (kN/m2)
Effective
Friction
Angle,
(o)
Loose Fill
Material 8 17 0 18
Original Granitic
Residual Soils 20 20 5 31
Very Hard
Weathered
Granite
100 20 0 40
64
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
33/35
10/22
Finite Element Method (FEM)Analyses
Loose Fill:
E= 1500~1800 SPT N(kN/m2)
Original granitic residual soil:
E = 2500 SPT N(kN/m2)
Interpreted effective residualstrength:
c r = 0 kPa and r = 18o
65
Potential locations of tensioncracks and slip surface
Tension
CracksSurface
Slippage
66
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
34/35
10/22
Back Analysis of Potential FailureSlip
Inherent failure mechanisms :TENSION CRACKS becomeAPPARENT during PILECAPEXCAVATION
FEM results confirmed highshear strain in SEMI-CIRCULAR
failure and cutting through theinstalled nails
67
68
5.0 Conclusions
It is IMPERATIVE to study originaltopography and normally, natural valley hashigh potential of retaining SOFT deposit.
Drilling method using HIGH COMPRESSEDAIR as flushing medium shall be carefullyassessed in loose fill ground
PROPERLY & WELL-PLANNEDinstrumentation scheme shall be carried outprior to the commencement of excavation &nailing works
FEM is GOOD geotechnical assessment tool
-
8/10/2019 Demo 1 - Jack-In & Soil Nailed Excavation in Fills Compatib
35/35
10/22
Thank You
69