decision erc case no. 2001-740(erbcaseno.+2000-154)
TRANSCRIPT
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
1/30
WILLIAM L. CHAN,
Complainant,
- versus -
MANILA ELECTRIC COMPANY
(MERALCO),
Respondent.
)( - - - - ~- - - - - - - - - - - - - - - - )(
ERC CASE NO. 2001-743
(ERB CASE NO. 2000-154)
D 0 C,&liil T IiD
Date: ,~.t;~~..~.,~~!5~ : ' V L l
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
2/30
)( ~ - - - )( ~ : V L l
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 2 of 28
This is the underlying reason why a public utility is
required to exercise utmost care and diligence in dealings
with its customers. To paraphrase the principle laid down
by the Supreme Court, apublic utility has dominance over
its market and its customers. Thus, in the regulation
thereof, the State considers the serious consequences
and hardships that a customer may stand to suffer uponservice disconnection as well as his relatively weak
bargaining position as against apublic utility.2
Conversely, a person who, under threat of service
disconnection, was made to settle excessive charges,
must be afforded the full protection of
the laws. Thus, themaxim: Nemo cum alterius detrimento protest (No
person should unjustly enrich himself at the expense
ofanother).
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
3/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Pag e 3 o f 28 .
3. Upon approval of Mr. Chan's application for the supply of
electric power for his ice plant [Service Identification No.
(SIN) 800633901], MERALCO installed the necessary
electrical equipment. Among these are Active Electric
Meter with No. 701 GE00067 and Reactive Electric Meter
with No. 701 DQAD16. Both electric meters were installed
outside the premises of his ice plant;
4. On November 16, 1998, Mr. Chan discovered that one of
his kWh meters was missing and immediately reported
the same to MERALCO. This discovery was made when
he noticed that his monthly energy consumption was
consistently pegged at 165,240 kWh. for three (3)consecutive months, particularly, the billing in the periods
of August 11, 1998 to September 11, 1998, September
11, 1998 to October 12, 1998, and October 12, 1998 to
November 11, 1998. He concluded that MERALCO billed
him based on assumed reading He manifested that the
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
4/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 4 of 28
9. Unsatisfied with the explanations given by MERALCO, he
instituted the foregoing complaints to recover, among
others, the total amount of PhP2,086,479.45, broken
down as follows:
Sep tembe r 11 , 1998 t o Oc tobe r 12 , 1998
Oc tobe r 12 ,1998 t o Novembe r 11 , 1998 *
Oc tobe r 12 , 1998 t o Novem be r 11 , 1998
Per iod
Augus t 11 , 1998 t o Sep tembe r 11 , 1998
N o v e m b e r 1 1 , 19 9 8 to D e c e m b e r 1 1 , 1 9 9 8
541 ,877 .P a id o n O c to b e r 23, 1998, Fu ll P a m e
548 ,656 .P a i d o n O c to b e r 3 0 ,1998, F ull P a m e
389 ,559 .Pa id on Janua 18, 1999, 70% o fPhP 556 ,513 .90
335 ,549 .Fu ll P a me n t - Ma ch in e V a lid a tio
101 ,202 .P i d M 26 1999 F ll P
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
5/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 5 of 28
" Terms and Conditions of Service
x xx.
Customer Liability:
In the event of loss of, or damage to
property of the Company through misuse or
negligence on the part of the Customer or his
employees or household members, the cost of
the necessary repairs or replacement thereof
shall be paid to the Company by theCustomer.
Customers will be held responsible for
tampering, interfering with, or breaking of
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
6/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 6 of 28
Payments:
Bills will be rendered by the Company to
the Customer monthly in accordance with the
applicable rate schedule. Said bills are
payable to collectors or at the main or branch
offices of the Company or its authorized bankswithin ten (10) days after the regular reading
date of the electric meters. The word "month"
as used herein and in the rate schedule is
hereby defined to be the elapsed time
between two succeeding meter readings
approximately thirty (30) days apart. In theevent of the stoppage or the failure by any
meter to register the full amount of energy
consumed, the Customer shall be billed for
such period on an estimated consumption
based upon his use of energy in a similar
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
7/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 7 of 28
12. Based on the foregoing provisions, MERALCO contended
that it has the contractual and legal right to disconnect
electric service for the default of its customers to pay its
regular bills or adjusted bills in those cases where the
meter stopped or failed to register the full amount of
electric energy consumed by Mr. Chan;
13. MERALCO further contended that the use of estimated
consumption in cases where the meter fails to register the
actual consumption is contractually and legally
permissible as long as it is based on a similar period of
like use. It is submitted that the use of a prior
consumption reading on subsequent billing periods iscovered by the above provision and falls under the phrase
"similar period of like use";
14 On its part MERALCO summarized the payments made
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
8/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 8 of 28
15. Thus, MERALCO prayed that the complaints filed by Mr.
Chan be dismissed for lack of merit and that then ERB
recognize the adjusted billings assessed and rendered for
the periods September 11, 1998 to October 11, 1998,
October 12, 1998 to November 11, 1998 and November
11, 1998 to December 11, 1998.
Upon the filing of Mr. Chan's "Letter-Complaint" on May 26,
1999, several conferences were held between him and MERALCO
but no amicable settlement was reached. Thus, the initial hearing
was scheduled on September 18, 2000.
During the September 18, 2000 pre-hearing conference, Mr.Chan and MERALCO failed to appear despite due notice. In view
thereof, said hearing was reset to October 16, 2000.
At th O t b 16 2000 h i f M Ch d
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
9/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 9 of 28
At the continuation of the pre-hearing conference on June 21,
2001, MERALCO presented Ms. Conchita Bolos from. its Power
Billing Department, who explained the basis used in the computation
of Mr. Chan's differential billings. Thereafter, Mr. Chan moved for a
reconsideration of the said computations and requested that the
same be based on the ice plant's consumptions for the previous
months up to the period in question. MERALCO, on the other hand,agreed to present its engineer at the next hearing to enlighten Mr.
Chan with regard to reactive power, to present his billing history,
detailed computation of his differential billings and his re-billings as
well as to verify the name of MERALCO's personnel who conducted
the meter reading on his meter.
At the July 10, 2001 pre-hearing conference, MERALCO
presented Engr. Edgar B. Caras, who explained the basis for the
computation of Mr. Chan's differential billings. On the other hand, Mr.
Chan reiterated his allegation that his meter was removed since
A t 1998 S id ll ti d i d b MERALCO
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
10/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015Page 10 of 28 .
At the May 13, 2002 hearing, Ms. Chan was presented as
witness to corroborate Mr. Chan's testimony relative to the
inspections conducted by several personnel of MERALCO.
MERALCO objected to the presentation of the said witness on the
ground that she was being presented to testify on alleged matters
which were not included in the amended complaint. Nevertheless,
the Commission allowed Ms. Chan to testify subject to the issuanceof a ruling on the matter. In connection therewith, MERALCO
manifested its continuing objection to the presentation of the said
witness and declined to conduct its cross-examination until after the
Commission has ruled on its objection.
On May 22, 2002, the Commission issued an Order denyingMERALCO's objection during the May 13, 2002 hearing for lack of
merit.
During the October 7 2002 hearing Mr Chan and MERALCO
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
11/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 11 of 28
During the July 28, 2004 hearing, only Mr. Chan appeared. As
a result of the unexplained absence of MERALCO, he moved that the
direct testimony as well as the documents identified by Mr.
Valderrama be stricken from the records. Said motion was noted.
At the continuation of the hearing on September 21, 2004
where Mr. Chan was supposed to cross-examine Mr. Valderrama, heasked for the original bill that the witness agreed to bring with him to
the hearing. However, said witness gave a different set of
documents.
As a result, Mr. Chan moved that the testimony of said witness
and the documents he identified during his direct testimony beexpunged from the records. On the other hand, MERALCO
requested that it be given a period of five (5) days within which to file
its comment thereon. Said request was granted.
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
12/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14, 2015
Page 12 of 28
On October 26, 2005, the Commission issued an Order striking
out from the records MERALCO's comments to the motion to strike
testimony of Mr. Valderrama as well as its Exhibits "4", "4-A" , "5", "5-
A', "6", "6-A', "7" and "7-A" and the portion of the said witness'
testimony pertaining to the documents generated from its Customer
Management System.
In the same Order, MERALCO was directed to submit its formal
offer of evidence within fifteen (15) days from receipt thereof.
On February 6, 2006, MERALCO filed a "Partial Motion for
Reconsideration of the Order Dated October 26, 2005",
On March 9, 2006, Mr. Chan filed his "Comment/Opposition (To
Respondent's Partial Motion for Reconsideration Dated February 6,
2006)".
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
13/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 13 of 28
On September 5, 2011, MERALCO filed a "Manifestation
Withdrawing Intention to File Certiorari with Formal Offer of Exhibits".
On October 3, 2011, Mr. Chan filed his "Comment/Objection to
Respondent's Offer of Evidence".
On January 23, 2013, the Commission issued an Order
directing MERALCO to submit, within five (5) days from receipt
thereof, certified true copies of Ms. Chan's Electric Bills (Service
Identification No. 800633901-9) for the periods July 10, 1995 to
December 12, 1995, July 10, 1996 to December 12, 1996, July 10,
1997 to December 12, 1997, and April 10, 1998 to December 12,1998.
Relative thereto, on March 6, 2013, MERALCO submitted its
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
14/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 14 of 28
DISCUSSION
With the admission that MERALCO consistently billed Mr. Chan
with a monthly energy consumption of 165,240 kWh for the periods
August 11, 1998 to September 11,1998, September 11, 1998 toOctober 12, 1998, and October 12, 1998 to November 11, 19983
without actual meter reading, and MERALCO's new kWh meter was
defectively installed and its meter reading was used for the period
November 20 to 26, 19984, and the determination that Mr. Chan fully
and excessively paid under protest his electricity bills for the disputed
periods, the primordial issue that has to be resolved is whether Mr.
Chan is entitled to a total refund ofPhP2, 086,479. 45.
Undeniably, Mr. Chan consumed electricity when he operated
his ice plant during those periods~ sans actual meter reading.
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
15/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 15 of 28
One of the kWh meters (kWh1) installed in the subject
establishment is intended to monitor the monthly energy consumption
and demand of the customer while the other one (kWh2), with phase-
shifting transformers, is intended to monitor the monthly power factor
of the customer. The monthly energy consumption is determined
directly through the kWh1 meter readings while the power factor is
computed accordingly using the general formulae shown below. Thecomputation requires RkVAh reading, which is retrieved from the
kWh2 meter, and the energy consumption (kWh readings), which is
monitored by the kWh1 meter.
!
Formula 1 I Qr = (2 x qr) - Pr
~3-----
I Formula 2 I pf = cos
I
[ tan -1
(~)] I
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
16/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 16 of 28
The missing meter is the kWh1 meter which monitors and
reflects the monthly energy consumption of Mr. Chan. He manifested
that the charges imposed by MERALCO, which was based on
estimated energy consumption, is unacceptable considering that the
ice plant's production decreased during those periods and the fact
that the estimated energy consumption was higher than his averagemonthly consumption.
On November 20, 1998, MERALCO installed a new kWh meter.
Incidentally, on November 26, 1998, it was discovered that the
installation of the new kWh meter was defective. On even date,
MERALCO made the necessary adjustments to rectify the installationdefects.
Despite Mr. Chan's protest, he still paid the corresponding
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
17/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 17 of 28
"x x x. In the event of stoppage or the failure of any
meter to register the full amount of energy consumed, the
customer shall be billed for such period on an estimated
consumption based upon his average use of energy for
the immediately preceding six-month period of like use or
the registration of a check meter subject to the
approval of the Board, except when the utility and thecustomer do not agree on such bill, in which case,
the Board shall resolve the same." (Emphasis
Supplied)
MERALCO submitted two (2) data records of Mr. Chan's
monthly consumption, namely: the Meter Reading Report and theBilling Record6, as summarized in the table below. It can be
observed that there is a discrepancy in the data presented in both
reports, particularly, the period of September 11, 1998 to November
11, 1998. The discrepancy bolstered the claim of Mr. Chan that the
kWh t l d i i id i th t th
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
18/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14, 2015
Page 18 of 28
Table 1. Summary of the Submitted MERALCO Records
MERALCO Mete r Read ing Report MERALCO Bi ll ing Record
No. Reading kWh1 meter kWh2 meter (RkVAh) kWh1 meter (kWh) kWh2 meter (RkVA
Date Readings Difference DemandReadings Difference
(kWh) (kW h) (kW ) Difference Readings R e ad in g s D if fe re n
1 0 1/1 0/9 7 1140 - 2.26 9643 - - - -
2 0 2/1 1/9 7 1909 76 9 2.12 10120 477 - - - 3 0 3/1 1/9 7 2564 655 2.12 10541 42 1 - - -
4 04/11/97 3363 79 9 2.16 11033 492 - - - 5 0 5/1 2/9 7 4422 1,059 2.00 11633 600 - - - 6 0 6/1 1/9 7 5530 1,108 2 .07 12415 78 2 - - - 7 07111/97 6556 1,026 2.11 13112 697 - . - 8 0 8/1 2/9 7 7696 1,140 1.99 13976 86 4 - - - 9 0 9/1 1/9 7 8695 999 1.99 14858 882 - - - 1 0 1 0/1 3/9 7 9914 1,219 1 .99 15943 1,085 - - -
1 1 1 1/1 2/9 7 10377 46 3 1.96 16345 402 - - -
12 12/11/97 10916 539 2.16 16851 50 6 - . -
1 3 0 1/1 2/9 8 11661 74 5 2 .15 17449 59 8 11661 - 17449 14 02/11/98 12391 730 2.14 18059 610 12391 730 18059 1 5 0 3/1 2/9 8 13260 869 2.12 18813 754 13260 86 9 18813 1 6 0 4/1 3/9 8 14249 989 2.07 19686 873 14249 989 19686
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
19/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 19 of 28
There was evident negligence on the part of MERALCO
considering that it did not replace the missing meter when it
conducted its regular monthly meter reading. Had it addressed the
matter immediately, the unregistered consumption should have been
one billing cycle only and the disputed unregistered energy
consumption should have been limited. Thus, it may be fair enough
that the disputed unregistered consumption should be based on thelowest monthly energy consumption within three (3) months upon
replacing the missing kiloWatt-hour (kWh) meter considering that the
prolonged period of unregistered consumption is not due to the fault
of Mr. Chan.
Nevertheless, the energy consumption or the reading of kWh1meter could be determined using the registered consumption
retrieved from kWh2 meter.
The determination of the power factor is correlated and
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
20/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 20 of 28
The basic principle of the above analyses is that the active
energy (kWh) or PT consumed is directly proportional with the
reactive energy (kVARh) or the QT consumed provided that power
factor is constant. An increase in the reactive energy consumption
QT (it is more accurate to say that the power factor is more or less
constant) shall also increase the active energy consumption PT, and
vice versa.
By adopting the lowest/worst power factor (simulation 1) with an
energy consumption of 320,014.57 kWh, it was determined that
MERALCO had excessively billed Mr. Chan for the entire disputed
months by 302,785.43 kWh. MERALCO excessively billed Mr. Chan
with an estimated total energy consumption of 622,800.00 kWh and
made him pay under protest the corresponding bill of
PhP2,020,727.83. Mr. Chan is therefore, rightfully entitled to a refund
from MERALCO.
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
21/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/Septemb er 14,2015
Page 21 of 28
With the approval of the Billing Adjustment and the
determination of the actual amount to be refunded, the Commission is
now constrained to resolve the incidental issue of whether Mr. Chan
is entitled to a cost of money for the entire period which MERALCO
erroneously withheld his money.
The Commission believes that, having already fully and
excessively paid his electricity bills for the September 11, 1998 to
November 26, 1998 billing periods, Mr. Chan already incurred an
opportunity cost of the money he used to advance and pay his
electricity bills. The applicable rate to determine Mr. Chan's legal
interest rate should be six percent (6%) per annum, as embodied inArticle 2209 of the Civil Code of the Philippines, to wit:
"If the obligation consists in the payment of a sum of
mone and the debtor inc rs in dela the indemnit for
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
22/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 22 of 28
interest due shall itself earn legal interest from
the time it is judicially demanded. In the
absence of stipulation, the rate of interest
shalt be 12%per annum to be computed from
default, i.e., from judicial or extrajudicial
demand under and subject to the provisions of
Article 1169
of the Civil Code.
2. When an obligation, not constituting a loan
or forbearance of money. is breached, an
interest on the amount of damages
awarded may be imposed at the discretion
of the court at the rate of 6% per annum.
No interest, however, shall be adjudged on
unliquidated claims or damages except when
or until the demand can be established with
reasonable certainty. Accordingly. where the
demand is established with reasonable
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
23/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 23 of 28
Summarized below is the breakdown of the total amount to berefunded by MERALCO to Mr. Chan:
Amount Paid, PhP
Less: A roved Billin
Difference, PhP
Plus: Legal Interest, PhP
I Total Amount to be Refunded, PhP
2,020,727.83
1,069,411.87
951,315.96
913,263.32
11,864,579.28 I
In computing the total amount of PhP1,864,579.28, the
Commission used the following formula:
A=Px(1 +rt )
Where:
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
24/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 24 of 28
This authority of the Commission to impose interest for the use
of money emanates from its so-called incidental powers. As
discussed by the Supreme Court in C. T. Torres Enterprises,
Incorporated vs. The Hon. Romeo J. Hibionada, Efren Diongon, and
Pleasantville Development Corporation8, it was held that:
'The argument that only courts of justice can
adjudicate claims resoluble under the provisions of the
Civil Code is out of step with ..the fast-changing times.
There are hundreds of administrative bodies now
performing this function by virtue of a valid authorization
from the legislature. This quasi-judicial function, as it iscalled, is exercised by them as an incident of the principal
power entrusted to them of regulating certain activities
falling under their particular expertise.
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
25/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/Septemb er 14,2015
Page 25 of 28
all incidental power, right or privilege. This is so because the greaterincludes the lesser, expressed in the maxim, in eo plus sit, simper
inest et minus.9
Thus, when an administrative agency or body is conferred
quasi-judicial functions, all controversies relating to the subject matter
pertaining to its specialization are deemed to be included within itsjurisdiction since the law does not sanction a split of jurisdiction.1o
Finally, it bears stressing that, MERALCO, as a public utility
imbued with public interest, is expected to discharge its functions with
utmost care and diligence. The utmost care and diligence required of
MERALCO necessitates such great degree of prudence on its part, andfailure to exercise the diligence required means that MERALCO was at fault
and negligent in the performance of its obligation.11
Pr dence dictates that MERALCO taking into consideration
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
26/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/Septemb er 14,2015
Page 26 of 28
thereto), meters and other apparatus which may be required for
the proper measurement of and protection to its service.12
Again, considering the technical skills and expertise involved in
the installation of kWh meters, MERALCO is expected to ensure that
the same is properly installed. Unfort.unately, such was not the case
in the subject complaints. MERALCO should have employed utmostdiligence necessary to warrant that the newly installed kWh meter in
Mr. Chan's ice plant is operating under normal condition as any
defect, either in the meter or installation thereof, cannot easily be
detected by Mr. Chan, more so, by an ordinary consumer.
What is unfathomable is that, despite Mr. Chan havingexcessively paid his electricity bills for the disputed billing periods,
MERALCO imposed threats of service disconnection for its
subsequent billing adjustments for the same billing periods. The
foregoing circumstances are clear manifestations that MERALCO
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
27/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14,2015
Page 27 of 28
Thus, a penalty of One Hundred Thousand Pesos
(PhP100,000.00) is hereby imposed against it pursuant to Section 5,
Article 11/of Resolution NO.3, Series of 2009 on the Guidelines to
Govern the Imposition of Administrative Sanctions in the Forms of
Fines and Penalties pursuant to Section 46 of Republic Act No. 9136,
otherwise known as the Electric Power Industry Reform Act of 2001or the EPIRA13. MERALCO is directed to REMIT the said amount,
either in cash or in check, in the name of the Energy Regulatory
Commission (ERC), within fifteen (15) days from receipt hereof.
SO ORDERED.
Pasig City, September 14, 2015.
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
28/30
ERC Case No. 2001-743 (ERB Case No. 2000-154)
DECISION/September 14, 2015
Page 28 of 28
Copy Furnished:
1. Mr. William Chan
Complainant
No. 537 Arnaiz Avenue, Pasay City .
2. Heffron Esguerra Dy and De Jesus Law Offices
Counsel for the Complainant
Unit 706, Tycoon Center,
Pearl Drive, Pasig City
3. Manila Electric Company (MERALCO)
Respondent
Lopez Building
MERALCO Compound
Orligas Avenue, Pasig c~
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
29/30
SUMMARY OF DATA AND DISPUTED ENERGY CONSUMPTION COMPUTATION
I No Data IntegrityI
ANN
1 12-Jan-1998 1 11-Feb-1998 12-Mar-1998 13-Apr-1998 l1-May-1998 ll -Jun-1998 10-Jul-1998 l l-Au!l -1998 1 l l-Sep-1998 I ll -D ec-1998 1 15-M
Actual Meter 1Meter 1 IActive Energy (KWh) 1 116611 12391 13260 14249 15222 16350 17454 1 88261 202031 1
Readings 1Meter 2 Iq-reading (RKVAh) 1 174491 18059 18813 19686 20542 21532 22496 2 37021 249201 260561
C f 1Meter 1 IActive Energy (KWh) 1 1 730.00 1 869.00 I 989.00 1 973.00 1 1,128.00 I 1,104. 00 1,372. 00 1 1,377. 00 1 Ionsump Ion .
1 610.00 1 873.00 1 856.00 1 990.00 1 1,206.00 I 1,218.00 1 1,136.00 1I Meter 2 Iq-readmg (RKVAh) I 754.00 964.00
I with mulitplier of 120 (x120) I direct reading
Meter 1 IActive Energy (KWh) 1 I 8 7 ,6 00 .0 0 1 1 04 ,2 80 .0 0 1 18 ,6 80 .0 0 I 116,760.00 1 13 5, 36 0. 00 1 1 32 ,4 80 .0 0 1 1 64 ,6 40 .0 0 1 1 65 ,2 40 .0 0 I 4 19 ,3 92 .0 0 IActual
1 with mulitplier of 120 (x120)Consumption
Meter 2 Iq-reading (RKVAh) 1 1 73,200.00 I 90,480.00 I 104,760.00 I 102,720.00 1 118,800.00 I 115,680.00 1 144,720.00 1 146,160.00 I 136,320.00 1 2
Notes: 1) New meter was installed replacing the missing Meter 1 on Nov. 20, 1998 however, said new meter was found defective on Nov. 26, 1998, thus, integrity of KWh data during said period is in question;
2) The new meter replacing Meter 1 is direct reading or it does not require any multiplier;
3) Meter 2 was continuosly used and data was recorded even after replacing Meter 1; and
4) - consumotion based on MERALCO's etimates.
1 12-Jan-1998 1 11-Feb-1998 I 12-Mar-1998 1 13-Apr-1998 1 11-May-1998 1 l1-Jun-1998 I 10-Jul-1998 I l 1-Au!l-1998 I 11-5ep-1998 I l l -D ec-1998 I 15-M
Reactive Energy 1 1 3 3, 948 .2 0 1 4 4, 271 .22 1 5 2, 44 6. 50 1 51,199.42 1 5 9, 02 8. 29 1 5 7, 088 .3 9 1 7 2, 053 .31 1 73 ,36 9. 67 I 1
Power Factor I pf (%)1 1 93.24%1 92.05%1 91.47%1 91.58% 1 91.66%1 91. 84%1 91. 61%1 91.40%1 1Computation for
Total Active Energy Consumption (KWh) for the period of Jan 12, 1998 to Aug 11, 1998 1 859,800.00 1Power Factor
Total Reactive Energy Consumption (KVARh) for the period of Jan 12, 1998 to Aug 11, 1998 1 370,035.33 1
Simulation 1: ILowest Power Factor for the period of Jan 12, 1998 to Aug 11, 1998 I 91.47%1
Simulation 2: IAvraae. Power Factor for the period of Jan 12, 1998 to Aua 11, 1998 1 91.85%1
SIMULATION 1: I l l-Aug-1998 11-Dec-1998
~ctual a-readina (RKVAh) 1 23,702 26,056
KWh consumption ~ctual q-reading wi mull. (x120) - (RKVAh) 1 2,844,240.00 3,126,720.00
of the disputed ~ ct ual T ot al q -r ea din g ( Au g 1 1, 1 99 8 t o De c 11 , 19 98 ) 28 2, 48 0. 00
period using the Lowest Power Fact or (Jan 12, 1998 to Aug 11, 199811 91.47%
lowest power 4-month KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 320,014.57factor of the entire Monthly KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 80,003.64
year No. of Disputed Months (Aug. 11, 1998 to Dec. 11,1998) 4
SIMULATION 2:I 11-Aug-1998 11-D
~ctual a-read ina (RKVAh) 1 23,702
KWh consumption ~ctual q-reading wi mull. (x120) - (RKVAh) 1 2,844,240.00 3,12
of the disputed ~ctual Total q-reading (Aug 11, 1998 to Dec 11, 1998) 2
period using the ~ve. Power Factor (Jan 12, 1998 to Aug 11, 1998) I
average power ~-month KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 323factor of the entire Monthly KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 80
year No. of Disputed Months (Aug. 11, 1998 to Dec. 11,1998)
Pa
-
7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)
30/30
ANNEX
SUMMARY OF THE APPROVED CHARGES
~ Si mul at i on 1 I I Si mul at i on 2 I
W
I Monthly Energy (KWh) II 80,003.64I
W
I Monthly Energy (KWh) II 80,919.931ILoad Factor II 84.13%1 ILoad Factor II 84.13%1
Monthly Demand (KW) I .II 132.081
Monthly Demand (KW) I .
II 133.591MaXimumDemand MaXimumDemand
I Monthly Power Factor-(%) II 91.47%1 I Monthly Power Factor (%) II 91.85%1
-Basic Charges IIConsumption
I I Rates Amount. . .
. . . Energy (KWh) 80,003.64 1.92 153,606.99. . . XCo Demand (KW) 132.08 X 220.00 29,056.89Gl
rn Power Factor Adjustment 182,663.88 x -1.92% (3,507.15)0
Power Factor 91.47% . .. . .Cur renc y Ad just men t 179, 15 6. 73 4.24% 7,596.25. . . x
til PPA 80,003.64 x 0.957 76,563.49: : : : I Demand (KW) 132.08 x 220.00 29,056.890
z Power Factor Adjustment 182,663.88 x -1.92% (3,507.15)0
Power Factor 91.47% . .N
Currency Adjustment 179,156.73 4.58% 8,205.38. . . x. . . PPA 80,003.64 x 1.038 83,043.780
0
I Sub.total Amount I 270,405.89I-, . . . . -Basic Charges IIConsumotion I I Rates Amount. . .
. . .Energy (KWh) 80,003.64 x 1.92 153,606.99
U Demand (KW) 132.08 x 220.00 29,056.89GlC Power Factor Adjustment 182,663.88 x -3.12% (5,699.11)0
Power Factor 91.47% . .. . . Currency Adjustment 176,964.77 3.91% 6,919.32. . . x: > PPA 80,003.64 x 1.065 85,203.880
zI Sub-total Amount I 269,087.97I
, . . . . -
Basi c C ha ra es I I Consu mo ti on I I Rates Amount. . .
. . . Energy (KWh) 80,919.93 1.92 155,366.26. . . xCo Demand (KW) 133.59 x 220.00 29,389.67Gl
rn Power Factor Adjustment 184,755.93 x -1 .9 2% ( 3, 547 .3 1)0
Power Factor 91.85% . .. . .
Currency Adjustment 181,208.62 4.24% 7,683.25. . . xtil PPA 80,919.93 x 0.957 77,440.37: : : : I Demand (KW) 133.59 x 220.00 29,389.670
z Power Factor Adjustment 184,755.93 x -1.92% (3,547.31)0 Power Factor 91.85% . .N
Currency Adjustment 181,208.62 4.58% 8,299.35. . . x. . . PPA 80,919.93 x 1.038 83,994.880
0
I Sub.total Amount I 273,502.86I-. . . B asi c C ha rg es II Consu mpti on I I Rates Amount. . .
Energy (KWh) 80,919.93 x 1 .92 155,366.26U Demand (KW) 133.59 x 220.00 29,389.67GlC Power Factor Adiustment 184,755.93 x - 3. 12% (5 ,7 64. 39)0
Power Factor 91.85% . .. . . Currency Adjustment 178,991.55 3.91% 6,998.57. . . x: > PPA 80,919.93 x 1.065 86,179.720
zI Sub-total Amount I 272,169.84I
Grand Total Amount 1,069,411.871 Grand Total Amount 1,081,659.871
Pa