decision erc case no. 2001-740(erbcaseno.+2000-154)

Upload: elva-agbon-aban

Post on 28-Feb-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    1/30

    WILLIAM L. CHAN,

    Complainant,

    - versus -

    MANILA ELECTRIC COMPANY

    (MERALCO),

    Respondent.

    )( - - - - ~- - - - - - - - - - - - - - - - )(

    ERC CASE NO. 2001-743

    (ERB CASE NO. 2000-154)

    D 0 C,&liil T IiD

    Date: ,~.t;~~..~.,~~!5~ : ' V L l

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    2/30

    )( ~ - - - )( ~ : V L l

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 2 of 28

    This is the underlying reason why a public utility is

    required to exercise utmost care and diligence in dealings

    with its customers. To paraphrase the principle laid down

    by the Supreme Court, apublic utility has dominance over

    its market and its customers. Thus, in the regulation

    thereof, the State considers the serious consequences

    and hardships that a customer may stand to suffer uponservice disconnection as well as his relatively weak

    bargaining position as against apublic utility.2

    Conversely, a person who, under threat of service

    disconnection, was made to settle excessive charges,

    must be afforded the full protection of

    the laws. Thus, themaxim: Nemo cum alterius detrimento protest (No

    person should unjustly enrich himself at the expense

    ofanother).

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    3/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Pag e 3 o f 28 .

    3. Upon approval of Mr. Chan's application for the supply of

    electric power for his ice plant [Service Identification No.

    (SIN) 800633901], MERALCO installed the necessary

    electrical equipment. Among these are Active Electric

    Meter with No. 701 GE00067 and Reactive Electric Meter

    with No. 701 DQAD16. Both electric meters were installed

    outside the premises of his ice plant;

    4. On November 16, 1998, Mr. Chan discovered that one of

    his kWh meters was missing and immediately reported

    the same to MERALCO. This discovery was made when

    he noticed that his monthly energy consumption was

    consistently pegged at 165,240 kWh. for three (3)consecutive months, particularly, the billing in the periods

    of August 11, 1998 to September 11, 1998, September

    11, 1998 to October 12, 1998, and October 12, 1998 to

    November 11, 1998. He concluded that MERALCO billed

    him based on assumed reading He manifested that the

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    4/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 4 of 28

    9. Unsatisfied with the explanations given by MERALCO, he

    instituted the foregoing complaints to recover, among

    others, the total amount of PhP2,086,479.45, broken

    down as follows:

    Sep tembe r 11 , 1998 t o Oc tobe r 12 , 1998

    Oc tobe r 12 ,1998 t o Novembe r 11 , 1998 *

    Oc tobe r 12 , 1998 t o Novem be r 11 , 1998

    Per iod

    Augus t 11 , 1998 t o Sep tembe r 11 , 1998

    N o v e m b e r 1 1 , 19 9 8 to D e c e m b e r 1 1 , 1 9 9 8

    541 ,877 .P a id o n O c to b e r 23, 1998, Fu ll P a m e

    548 ,656 .P a i d o n O c to b e r 3 0 ,1998, F ull P a m e

    389 ,559 .Pa id on Janua 18, 1999, 70% o fPhP 556 ,513 .90

    335 ,549 .Fu ll P a me n t - Ma ch in e V a lid a tio

    101 ,202 .P i d M 26 1999 F ll P

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    5/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 5 of 28

    " Terms and Conditions of Service

    x xx.

    Customer Liability:

    In the event of loss of, or damage to

    property of the Company through misuse or

    negligence on the part of the Customer or his

    employees or household members, the cost of

    the necessary repairs or replacement thereof

    shall be paid to the Company by theCustomer.

    Customers will be held responsible for

    tampering, interfering with, or breaking of

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    6/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 6 of 28

    Payments:

    Bills will be rendered by the Company to

    the Customer monthly in accordance with the

    applicable rate schedule. Said bills are

    payable to collectors or at the main or branch

    offices of the Company or its authorized bankswithin ten (10) days after the regular reading

    date of the electric meters. The word "month"

    as used herein and in the rate schedule is

    hereby defined to be the elapsed time

    between two succeeding meter readings

    approximately thirty (30) days apart. In theevent of the stoppage or the failure by any

    meter to register the full amount of energy

    consumed, the Customer shall be billed for

    such period on an estimated consumption

    based upon his use of energy in a similar

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    7/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 7 of 28

    12. Based on the foregoing provisions, MERALCO contended

    that it has the contractual and legal right to disconnect

    electric service for the default of its customers to pay its

    regular bills or adjusted bills in those cases where the

    meter stopped or failed to register the full amount of

    electric energy consumed by Mr. Chan;

    13. MERALCO further contended that the use of estimated

    consumption in cases where the meter fails to register the

    actual consumption is contractually and legally

    permissible as long as it is based on a similar period of

    like use. It is submitted that the use of a prior

    consumption reading on subsequent billing periods iscovered by the above provision and falls under the phrase

    "similar period of like use";

    14 On its part MERALCO summarized the payments made

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    8/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 8 of 28

    15. Thus, MERALCO prayed that the complaints filed by Mr.

    Chan be dismissed for lack of merit and that then ERB

    recognize the adjusted billings assessed and rendered for

    the periods September 11, 1998 to October 11, 1998,

    October 12, 1998 to November 11, 1998 and November

    11, 1998 to December 11, 1998.

    Upon the filing of Mr. Chan's "Letter-Complaint" on May 26,

    1999, several conferences were held between him and MERALCO

    but no amicable settlement was reached. Thus, the initial hearing

    was scheduled on September 18, 2000.

    During the September 18, 2000 pre-hearing conference, Mr.Chan and MERALCO failed to appear despite due notice. In view

    thereof, said hearing was reset to October 16, 2000.

    At th O t b 16 2000 h i f M Ch d

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    9/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 9 of 28

    At the continuation of the pre-hearing conference on June 21,

    2001, MERALCO presented Ms. Conchita Bolos from. its Power

    Billing Department, who explained the basis used in the computation

    of Mr. Chan's differential billings. Thereafter, Mr. Chan moved for a

    reconsideration of the said computations and requested that the

    same be based on the ice plant's consumptions for the previous

    months up to the period in question. MERALCO, on the other hand,agreed to present its engineer at the next hearing to enlighten Mr.

    Chan with regard to reactive power, to present his billing history,

    detailed computation of his differential billings and his re-billings as

    well as to verify the name of MERALCO's personnel who conducted

    the meter reading on his meter.

    At the July 10, 2001 pre-hearing conference, MERALCO

    presented Engr. Edgar B. Caras, who explained the basis for the

    computation of Mr. Chan's differential billings. On the other hand, Mr.

    Chan reiterated his allegation that his meter was removed since

    A t 1998 S id ll ti d i d b MERALCO

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    10/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015Page 10 of 28 .

    At the May 13, 2002 hearing, Ms. Chan was presented as

    witness to corroborate Mr. Chan's testimony relative to the

    inspections conducted by several personnel of MERALCO.

    MERALCO objected to the presentation of the said witness on the

    ground that she was being presented to testify on alleged matters

    which were not included in the amended complaint. Nevertheless,

    the Commission allowed Ms. Chan to testify subject to the issuanceof a ruling on the matter. In connection therewith, MERALCO

    manifested its continuing objection to the presentation of the said

    witness and declined to conduct its cross-examination until after the

    Commission has ruled on its objection.

    On May 22, 2002, the Commission issued an Order denyingMERALCO's objection during the May 13, 2002 hearing for lack of

    merit.

    During the October 7 2002 hearing Mr Chan and MERALCO

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    11/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 11 of 28

    During the July 28, 2004 hearing, only Mr. Chan appeared. As

    a result of the unexplained absence of MERALCO, he moved that the

    direct testimony as well as the documents identified by Mr.

    Valderrama be stricken from the records. Said motion was noted.

    At the continuation of the hearing on September 21, 2004

    where Mr. Chan was supposed to cross-examine Mr. Valderrama, heasked for the original bill that the witness agreed to bring with him to

    the hearing. However, said witness gave a different set of

    documents.

    As a result, Mr. Chan moved that the testimony of said witness

    and the documents he identified during his direct testimony beexpunged from the records. On the other hand, MERALCO

    requested that it be given a period of five (5) days within which to file

    its comment thereon. Said request was granted.

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    12/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14, 2015

    Page 12 of 28

    On October 26, 2005, the Commission issued an Order striking

    out from the records MERALCO's comments to the motion to strike

    testimony of Mr. Valderrama as well as its Exhibits "4", "4-A" , "5", "5-

    A', "6", "6-A', "7" and "7-A" and the portion of the said witness'

    testimony pertaining to the documents generated from its Customer

    Management System.

    In the same Order, MERALCO was directed to submit its formal

    offer of evidence within fifteen (15) days from receipt thereof.

    On February 6, 2006, MERALCO filed a "Partial Motion for

    Reconsideration of the Order Dated October 26, 2005",

    On March 9, 2006, Mr. Chan filed his "Comment/Opposition (To

    Respondent's Partial Motion for Reconsideration Dated February 6,

    2006)".

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    13/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 13 of 28

    On September 5, 2011, MERALCO filed a "Manifestation

    Withdrawing Intention to File Certiorari with Formal Offer of Exhibits".

    On October 3, 2011, Mr. Chan filed his "Comment/Objection to

    Respondent's Offer of Evidence".

    On January 23, 2013, the Commission issued an Order

    directing MERALCO to submit, within five (5) days from receipt

    thereof, certified true copies of Ms. Chan's Electric Bills (Service

    Identification No. 800633901-9) for the periods July 10, 1995 to

    December 12, 1995, July 10, 1996 to December 12, 1996, July 10,

    1997 to December 12, 1997, and April 10, 1998 to December 12,1998.

    Relative thereto, on March 6, 2013, MERALCO submitted its

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    14/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 14 of 28

    DISCUSSION

    With the admission that MERALCO consistently billed Mr. Chan

    with a monthly energy consumption of 165,240 kWh for the periods

    August 11, 1998 to September 11,1998, September 11, 1998 toOctober 12, 1998, and October 12, 1998 to November 11, 19983

    without actual meter reading, and MERALCO's new kWh meter was

    defectively installed and its meter reading was used for the period

    November 20 to 26, 19984, and the determination that Mr. Chan fully

    and excessively paid under protest his electricity bills for the disputed

    periods, the primordial issue that has to be resolved is whether Mr.

    Chan is entitled to a total refund ofPhP2, 086,479. 45.

    Undeniably, Mr. Chan consumed electricity when he operated

    his ice plant during those periods~ sans actual meter reading.

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    15/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 15 of 28

    One of the kWh meters (kWh1) installed in the subject

    establishment is intended to monitor the monthly energy consumption

    and demand of the customer while the other one (kWh2), with phase-

    shifting transformers, is intended to monitor the monthly power factor

    of the customer. The monthly energy consumption is determined

    directly through the kWh1 meter readings while the power factor is

    computed accordingly using the general formulae shown below. Thecomputation requires RkVAh reading, which is retrieved from the

    kWh2 meter, and the energy consumption (kWh readings), which is

    monitored by the kWh1 meter.

    !

    Formula 1 I Qr = (2 x qr) - Pr

    ~3-----

    I Formula 2 I pf = cos

    I

    [ tan -1

    (~)] I

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    16/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 16 of 28

    The missing meter is the kWh1 meter which monitors and

    reflects the monthly energy consumption of Mr. Chan. He manifested

    that the charges imposed by MERALCO, which was based on

    estimated energy consumption, is unacceptable considering that the

    ice plant's production decreased during those periods and the fact

    that the estimated energy consumption was higher than his averagemonthly consumption.

    On November 20, 1998, MERALCO installed a new kWh meter.

    Incidentally, on November 26, 1998, it was discovered that the

    installation of the new kWh meter was defective. On even date,

    MERALCO made the necessary adjustments to rectify the installationdefects.

    Despite Mr. Chan's protest, he still paid the corresponding

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    17/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 17 of 28

    "x x x. In the event of stoppage or the failure of any

    meter to register the full amount of energy consumed, the

    customer shall be billed for such period on an estimated

    consumption based upon his average use of energy for

    the immediately preceding six-month period of like use or

    the registration of a check meter subject to the

    approval of the Board, except when the utility and thecustomer do not agree on such bill, in which case,

    the Board shall resolve the same." (Emphasis

    Supplied)

    MERALCO submitted two (2) data records of Mr. Chan's

    monthly consumption, namely: the Meter Reading Report and theBilling Record6, as summarized in the table below. It can be

    observed that there is a discrepancy in the data presented in both

    reports, particularly, the period of September 11, 1998 to November

    11, 1998. The discrepancy bolstered the claim of Mr. Chan that the

    kWh t l d i i id i th t th

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    18/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14, 2015

    Page 18 of 28

    Table 1. Summary of the Submitted MERALCO Records

    MERALCO Mete r Read ing Report MERALCO Bi ll ing Record

    No. Reading kWh1 meter kWh2 meter (RkVAh) kWh1 meter (kWh) kWh2 meter (RkVA

    Date Readings Difference DemandReadings Difference

    (kWh) (kW h) (kW ) Difference Readings R e ad in g s D if fe re n

    1 0 1/1 0/9 7 1140 - 2.26 9643 - - - -

    2 0 2/1 1/9 7 1909 76 9 2.12 10120 477 - - - 3 0 3/1 1/9 7 2564 655 2.12 10541 42 1 - - -

    4 04/11/97 3363 79 9 2.16 11033 492 - - - 5 0 5/1 2/9 7 4422 1,059 2.00 11633 600 - - - 6 0 6/1 1/9 7 5530 1,108 2 .07 12415 78 2 - - - 7 07111/97 6556 1,026 2.11 13112 697 - . - 8 0 8/1 2/9 7 7696 1,140 1.99 13976 86 4 - - - 9 0 9/1 1/9 7 8695 999 1.99 14858 882 - - - 1 0 1 0/1 3/9 7 9914 1,219 1 .99 15943 1,085 - - -

    1 1 1 1/1 2/9 7 10377 46 3 1.96 16345 402 - - -

    12 12/11/97 10916 539 2.16 16851 50 6 - . -

    1 3 0 1/1 2/9 8 11661 74 5 2 .15 17449 59 8 11661 - 17449 14 02/11/98 12391 730 2.14 18059 610 12391 730 18059 1 5 0 3/1 2/9 8 13260 869 2.12 18813 754 13260 86 9 18813 1 6 0 4/1 3/9 8 14249 989 2.07 19686 873 14249 989 19686

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    19/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 19 of 28

    There was evident negligence on the part of MERALCO

    considering that it did not replace the missing meter when it

    conducted its regular monthly meter reading. Had it addressed the

    matter immediately, the unregistered consumption should have been

    one billing cycle only and the disputed unregistered energy

    consumption should have been limited. Thus, it may be fair enough

    that the disputed unregistered consumption should be based on thelowest monthly energy consumption within three (3) months upon

    replacing the missing kiloWatt-hour (kWh) meter considering that the

    prolonged period of unregistered consumption is not due to the fault

    of Mr. Chan.

    Nevertheless, the energy consumption or the reading of kWh1meter could be determined using the registered consumption

    retrieved from kWh2 meter.

    The determination of the power factor is correlated and

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    20/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 20 of 28

    The basic principle of the above analyses is that the active

    energy (kWh) or PT consumed is directly proportional with the

    reactive energy (kVARh) or the QT consumed provided that power

    factor is constant. An increase in the reactive energy consumption

    QT (it is more accurate to say that the power factor is more or less

    constant) shall also increase the active energy consumption PT, and

    vice versa.

    By adopting the lowest/worst power factor (simulation 1) with an

    energy consumption of 320,014.57 kWh, it was determined that

    MERALCO had excessively billed Mr. Chan for the entire disputed

    months by 302,785.43 kWh. MERALCO excessively billed Mr. Chan

    with an estimated total energy consumption of 622,800.00 kWh and

    made him pay under protest the corresponding bill of

    PhP2,020,727.83. Mr. Chan is therefore, rightfully entitled to a refund

    from MERALCO.

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    21/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/Septemb er 14,2015

    Page 21 of 28

    With the approval of the Billing Adjustment and the

    determination of the actual amount to be refunded, the Commission is

    now constrained to resolve the incidental issue of whether Mr. Chan

    is entitled to a cost of money for the entire period which MERALCO

    erroneously withheld his money.

    The Commission believes that, having already fully and

    excessively paid his electricity bills for the September 11, 1998 to

    November 26, 1998 billing periods, Mr. Chan already incurred an

    opportunity cost of the money he used to advance and pay his

    electricity bills. The applicable rate to determine Mr. Chan's legal

    interest rate should be six percent (6%) per annum, as embodied inArticle 2209 of the Civil Code of the Philippines, to wit:

    "If the obligation consists in the payment of a sum of

    mone and the debtor inc rs in dela the indemnit for

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    22/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 22 of 28

    interest due shall itself earn legal interest from

    the time it is judicially demanded. In the

    absence of stipulation, the rate of interest

    shalt be 12%per annum to be computed from

    default, i.e., from judicial or extrajudicial

    demand under and subject to the provisions of

    Article 1169

    of the Civil Code.

    2. When an obligation, not constituting a loan

    or forbearance of money. is breached, an

    interest on the amount of damages

    awarded may be imposed at the discretion

    of the court at the rate of 6% per annum.

    No interest, however, shall be adjudged on

    unliquidated claims or damages except when

    or until the demand can be established with

    reasonable certainty. Accordingly. where the

    demand is established with reasonable

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    23/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 23 of 28

    Summarized below is the breakdown of the total amount to berefunded by MERALCO to Mr. Chan:

    Amount Paid, PhP

    Less: A roved Billin

    Difference, PhP

    Plus: Legal Interest, PhP

    I Total Amount to be Refunded, PhP

    2,020,727.83

    1,069,411.87

    951,315.96

    913,263.32

    11,864,579.28 I

    In computing the total amount of PhP1,864,579.28, the

    Commission used the following formula:

    A=Px(1 +rt )

    Where:

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    24/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 24 of 28

    This authority of the Commission to impose interest for the use

    of money emanates from its so-called incidental powers. As

    discussed by the Supreme Court in C. T. Torres Enterprises,

    Incorporated vs. The Hon. Romeo J. Hibionada, Efren Diongon, and

    Pleasantville Development Corporation8, it was held that:

    'The argument that only courts of justice can

    adjudicate claims resoluble under the provisions of the

    Civil Code is out of step with ..the fast-changing times.

    There are hundreds of administrative bodies now

    performing this function by virtue of a valid authorization

    from the legislature. This quasi-judicial function, as it iscalled, is exercised by them as an incident of the principal

    power entrusted to them of regulating certain activities

    falling under their particular expertise.

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    25/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/Septemb er 14,2015

    Page 25 of 28

    all incidental power, right or privilege. This is so because the greaterincludes the lesser, expressed in the maxim, in eo plus sit, simper

    inest et minus.9

    Thus, when an administrative agency or body is conferred

    quasi-judicial functions, all controversies relating to the subject matter

    pertaining to its specialization are deemed to be included within itsjurisdiction since the law does not sanction a split of jurisdiction.1o

    Finally, it bears stressing that, MERALCO, as a public utility

    imbued with public interest, is expected to discharge its functions with

    utmost care and diligence. The utmost care and diligence required of

    MERALCO necessitates such great degree of prudence on its part, andfailure to exercise the diligence required means that MERALCO was at fault

    and negligent in the performance of its obligation.11

    Pr dence dictates that MERALCO taking into consideration

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    26/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/Septemb er 14,2015

    Page 26 of 28

    thereto), meters and other apparatus which may be required for

    the proper measurement of and protection to its service.12

    Again, considering the technical skills and expertise involved in

    the installation of kWh meters, MERALCO is expected to ensure that

    the same is properly installed. Unfort.unately, such was not the case

    in the subject complaints. MERALCO should have employed utmostdiligence necessary to warrant that the newly installed kWh meter in

    Mr. Chan's ice plant is operating under normal condition as any

    defect, either in the meter or installation thereof, cannot easily be

    detected by Mr. Chan, more so, by an ordinary consumer.

    What is unfathomable is that, despite Mr. Chan havingexcessively paid his electricity bills for the disputed billing periods,

    MERALCO imposed threats of service disconnection for its

    subsequent billing adjustments for the same billing periods. The

    foregoing circumstances are clear manifestations that MERALCO

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    27/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14,2015

    Page 27 of 28

    Thus, a penalty of One Hundred Thousand Pesos

    (PhP100,000.00) is hereby imposed against it pursuant to Section 5,

    Article 11/of Resolution NO.3, Series of 2009 on the Guidelines to

    Govern the Imposition of Administrative Sanctions in the Forms of

    Fines and Penalties pursuant to Section 46 of Republic Act No. 9136,

    otherwise known as the Electric Power Industry Reform Act of 2001or the EPIRA13. MERALCO is directed to REMIT the said amount,

    either in cash or in check, in the name of the Energy Regulatory

    Commission (ERC), within fifteen (15) days from receipt hereof.

    SO ORDERED.

    Pasig City, September 14, 2015.

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    28/30

    ERC Case No. 2001-743 (ERB Case No. 2000-154)

    DECISION/September 14, 2015

    Page 28 of 28

    Copy Furnished:

    1. Mr. William Chan

    Complainant

    No. 537 Arnaiz Avenue, Pasay City .

    2. Heffron Esguerra Dy and De Jesus Law Offices

    Counsel for the Complainant

    Unit 706, Tycoon Center,

    Pearl Drive, Pasig City

    3. Manila Electric Company (MERALCO)

    Respondent

    Lopez Building

    MERALCO Compound

    Orligas Avenue, Pasig c~

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    29/30

    SUMMARY OF DATA AND DISPUTED ENERGY CONSUMPTION COMPUTATION

    I No Data IntegrityI

    ANN

    1 12-Jan-1998 1 11-Feb-1998 12-Mar-1998 13-Apr-1998 l1-May-1998 ll -Jun-1998 10-Jul-1998 l l-Au!l -1998 1 l l-Sep-1998 I ll -D ec-1998 1 15-M

    Actual Meter 1Meter 1 IActive Energy (KWh) 1 116611 12391 13260 14249 15222 16350 17454 1 88261 202031 1

    Readings 1Meter 2 Iq-reading (RKVAh) 1 174491 18059 18813 19686 20542 21532 22496 2 37021 249201 260561

    C f 1Meter 1 IActive Energy (KWh) 1 1 730.00 1 869.00 I 989.00 1 973.00 1 1,128.00 I 1,104. 00 1,372. 00 1 1,377. 00 1 Ionsump Ion .

    1 610.00 1 873.00 1 856.00 1 990.00 1 1,206.00 I 1,218.00 1 1,136.00 1I Meter 2 Iq-readmg (RKVAh) I 754.00 964.00

    I with mulitplier of 120 (x120) I direct reading

    Meter 1 IActive Energy (KWh) 1 I 8 7 ,6 00 .0 0 1 1 04 ,2 80 .0 0 1 18 ,6 80 .0 0 I 116,760.00 1 13 5, 36 0. 00 1 1 32 ,4 80 .0 0 1 1 64 ,6 40 .0 0 1 1 65 ,2 40 .0 0 I 4 19 ,3 92 .0 0 IActual

    1 with mulitplier of 120 (x120)Consumption

    Meter 2 Iq-reading (RKVAh) 1 1 73,200.00 I 90,480.00 I 104,760.00 I 102,720.00 1 118,800.00 I 115,680.00 1 144,720.00 1 146,160.00 I 136,320.00 1 2

    Notes: 1) New meter was installed replacing the missing Meter 1 on Nov. 20, 1998 however, said new meter was found defective on Nov. 26, 1998, thus, integrity of KWh data during said period is in question;

    2) The new meter replacing Meter 1 is direct reading or it does not require any multiplier;

    3) Meter 2 was continuosly used and data was recorded even after replacing Meter 1; and

    4) - consumotion based on MERALCO's etimates.

    1 12-Jan-1998 1 11-Feb-1998 I 12-Mar-1998 1 13-Apr-1998 1 11-May-1998 1 l1-Jun-1998 I 10-Jul-1998 I l 1-Au!l-1998 I 11-5ep-1998 I l l -D ec-1998 I 15-M

    Reactive Energy 1 1 3 3, 948 .2 0 1 4 4, 271 .22 1 5 2, 44 6. 50 1 51,199.42 1 5 9, 02 8. 29 1 5 7, 088 .3 9 1 7 2, 053 .31 1 73 ,36 9. 67 I 1

    Power Factor I pf (%)1 1 93.24%1 92.05%1 91.47%1 91.58% 1 91.66%1 91. 84%1 91. 61%1 91.40%1 1Computation for

    Total Active Energy Consumption (KWh) for the period of Jan 12, 1998 to Aug 11, 1998 1 859,800.00 1Power Factor

    Total Reactive Energy Consumption (KVARh) for the period of Jan 12, 1998 to Aug 11, 1998 1 370,035.33 1

    Simulation 1: ILowest Power Factor for the period of Jan 12, 1998 to Aug 11, 1998 I 91.47%1

    Simulation 2: IAvraae. Power Factor for the period of Jan 12, 1998 to Aua 11, 1998 1 91.85%1

    SIMULATION 1: I l l-Aug-1998 11-Dec-1998

    ~ctual a-readina (RKVAh) 1 23,702 26,056

    KWh consumption ~ctual q-reading wi mull. (x120) - (RKVAh) 1 2,844,240.00 3,126,720.00

    of the disputed ~ ct ual T ot al q -r ea din g ( Au g 1 1, 1 99 8 t o De c 11 , 19 98 ) 28 2, 48 0. 00

    period using the Lowest Power Fact or (Jan 12, 1998 to Aug 11, 199811 91.47%

    lowest power 4-month KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 320,014.57factor of the entire Monthly KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 80,003.64

    year No. of Disputed Months (Aug. 11, 1998 to Dec. 11,1998) 4

    SIMULATION 2:I 11-Aug-1998 11-D

    ~ctual a-read ina (RKVAh) 1 23,702

    KWh consumption ~ctual q-reading wi mull. (x120) - (RKVAh) 1 2,844,240.00 3,12

    of the disputed ~ctual Total q-reading (Aug 11, 1998 to Dec 11, 1998) 2

    period using the ~ve. Power Factor (Jan 12, 1998 to Aug 11, 1998) I

    average power ~-month KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 323factor of the entire Monthly KWh Consumption (Aug 11, 1998 to Dec 11, 1998) 80

    year No. of Disputed Months (Aug. 11, 1998 to Dec. 11,1998)

    Pa

  • 7/25/2019 Decision ERC Case No. 2001-740(ERBCaseNo.+2000-154)

    30/30

    ANNEX

    SUMMARY OF THE APPROVED CHARGES

    ~ Si mul at i on 1 I I Si mul at i on 2 I

    W

    I Monthly Energy (KWh) II 80,003.64I

    W

    I Monthly Energy (KWh) II 80,919.931ILoad Factor II 84.13%1 ILoad Factor II 84.13%1

    Monthly Demand (KW) I .II 132.081

    Monthly Demand (KW) I .

    II 133.591MaXimumDemand MaXimumDemand

    I Monthly Power Factor-(%) II 91.47%1 I Monthly Power Factor (%) II 91.85%1

    -Basic Charges IIConsumption

    I I Rates Amount. . .

    . . . Energy (KWh) 80,003.64 1.92 153,606.99. . . XCo Demand (KW) 132.08 X 220.00 29,056.89Gl

    rn Power Factor Adjustment 182,663.88 x -1.92% (3,507.15)0

    Power Factor 91.47% . .. . .Cur renc y Ad just men t 179, 15 6. 73 4.24% 7,596.25. . . x

    til PPA 80,003.64 x 0.957 76,563.49: : : : I Demand (KW) 132.08 x 220.00 29,056.890

    z Power Factor Adjustment 182,663.88 x -1.92% (3,507.15)0

    Power Factor 91.47% . .N

    Currency Adjustment 179,156.73 4.58% 8,205.38. . . x. . . PPA 80,003.64 x 1.038 83,043.780

    0

    I Sub.total Amount I 270,405.89I-, . . . . -Basic Charges IIConsumotion I I Rates Amount. . .

    . . .Energy (KWh) 80,003.64 x 1.92 153,606.99

    U Demand (KW) 132.08 x 220.00 29,056.89GlC Power Factor Adjustment 182,663.88 x -3.12% (5,699.11)0

    Power Factor 91.47% . .. . . Currency Adjustment 176,964.77 3.91% 6,919.32. . . x: > PPA 80,003.64 x 1.065 85,203.880

    zI Sub-total Amount I 269,087.97I

    , . . . . -

    Basi c C ha ra es I I Consu mo ti on I I Rates Amount. . .

    . . . Energy (KWh) 80,919.93 1.92 155,366.26. . . xCo Demand (KW) 133.59 x 220.00 29,389.67Gl

    rn Power Factor Adjustment 184,755.93 x -1 .9 2% ( 3, 547 .3 1)0

    Power Factor 91.85% . .. . .

    Currency Adjustment 181,208.62 4.24% 7,683.25. . . xtil PPA 80,919.93 x 0.957 77,440.37: : : : I Demand (KW) 133.59 x 220.00 29,389.670

    z Power Factor Adjustment 184,755.93 x -1.92% (3,547.31)0 Power Factor 91.85% . .N

    Currency Adjustment 181,208.62 4.58% 8,299.35. . . x. . . PPA 80,919.93 x 1.038 83,994.880

    0

    I Sub.total Amount I 273,502.86I-. . . B asi c C ha rg es II Consu mpti on I I Rates Amount. . .

    Energy (KWh) 80,919.93 x 1 .92 155,366.26U Demand (KW) 133.59 x 220.00 29,389.67GlC Power Factor Adiustment 184,755.93 x - 3. 12% (5 ,7 64. 39)0

    Power Factor 91.85% . .. . . Currency Adjustment 178,991.55 3.91% 6,998.57. . . x: > PPA 80,919.93 x 1.065 86,179.720

    zI Sub-total Amount I 272,169.84I

    Grand Total Amount 1,069,411.871 Grand Total Amount 1,081,659.871

    Pa