Hidroenergia 2008, JH 1
GRP Pipe Solutions in Hydro Power projects.
Hidroenergia 2008, JH 2
GRP Pipe Solutions in Hydro Power projects.
Jarle Hausberg,
APS Norway AS
Hidroenergia 2008, JH 3
History of GRP, (Glass fiber Reinforced Polyester)
GRP composite was developed in USA
before the second world war.
A ”new” material with 70 years history!
From the beginning GRP was used in
pipes for the chemical industry due to
the very good corrosion resistance.
Today GRP is used in more and more
applications also due to the high
strength and low weight.
Flowtite GRP pipes for more
than 40 years!
Hidroenergia 2008, JH 4
•Water Supply
•Sewerage
•Power
•Industrial
•Irrigation
•Desalination
Applications for GRP Pipe
Hidroenergia 2008, JH 5
• DN100 - 4000mm
• PN1-6-10-16-25-32bar
• Standard length:
6 and 12 meter (1-18)
• Full fittings program
GRP Pipe, product range.
Hidroenergia 2008, JH 6
Performance standards for GRP pipes
ASTM American Society for Testing and Materials
ASTM D3517, ASTM D3754, ASTM D3262
AWWA American Water Works Association
AWWA C950 and design manual AWWA M45
ISO International Organization for Standardization
ISO 10639, ISO 10467
CEN Comité Européen de Normalisation EN 1796,
EN 14364
Local, national standards and regulations.
Hidroenergia 2008, JH 7
Water is power… power is
money!
Don't loose it on the
way!
Why GRP Pipes in Penstocks?
Hidroenergia 2008, JH 8
Long service life
• Corrosion-resistant material.
• Low maintenance costs.
• Low Life Cycle Cost
Less head loss
•Best hydraulic characteristic
•Low friction coefficient
•Essentially constant over time.
Why GRP Pipes in Penstocks?
Hidroenergia 2008, JH 9
Economical
• Competitive with other “traditionally” used materials
• Low installation cost, easy to assemble
• Low operating costs and long service life!
Why GRP Pipes in Penstocks?
Hidroenergia 2008, JH 10
GRP pipes are easily transported, low weight.
(1/4 of DIP and 1/10 of concrete)
Environmental friendly, can be nested.
For hydro power penstocks different solutions
to terrain vehicle has been used, including
helicopters.
Handling and installation
Hidroenergia 2008, JH 11
GRP pipes has a unique
feature for cold and hot
climate.
•The mechanical properties
remain the same from +30 to -
60.
•It doe's not get brittle when it is
cold.
•The pipe can be installed
above ground without any
special UV protections!
Why GRP Pipes in Penstocks?
Hidroenergia 2008, JH 12
GRP pipes are often installed on
steep slopes, either buried or above
ground.
The challenges of such installations
must, however, be respected
Installation on steep Slopes
Hidroenergia 2008, JH 13
A high number of GRP
penstocks have been built
around the whole word.
Only in Norway more than 270
Flowtite GRP penstocks.
DN500-2800mm, PN6-32bar.
A proven solution for more
than 40 years!
GRP Pipes in Penstocks, case studies
Hidroenergia 2008, JH 14
GRP Pipes in Penstocks, case studies
Vangpollen Hydropower
Norway
DN700/800mm.
PN6-32bar.
Slope up to 46 °.
Installed 1989
(3,3MW, horisontal
Pelton~14,9GWh)
Hidroenergia 2008, JH 15
Vinkelfallet hydro power station:
Norway
DN1600-1800mm L=1,6km
PN6-16
Installation in 1982
(7,1MW on two Francis turbines,
yearly production 25,6GWh)
GRP Pipes in Penstocks, case studies
Hidroenergia 2008, JH 16
SAFA hydro power station,
Norway
DN2400/2200mm L=250m
PN6/10
Installed 2005
Difficult access downside the
plant required installation with a
crane on a barge.
Pipes painted black after
installation for the environmental
reason.
(2,2MW, 2 Francis turbines, 20GWh)
GRP Pipes in Penstocks, case studies
Hidroenergia 2008, JH 17
LANGFJORDEN
hydro power station,
Norway
DN1200mm L=284m
PN32 (Static pressure 26bar)
Installed 2005
Pipeline on fundaments in
a tunnel from a pressure
shaft in the mountain.
Manhole DN1200/500 PN32
GRP Pipes in Penstocks, case studies
Hidroenergia 2008, JH 18
TWIMBERG hydro power station
Austria
DN1800mm
PN10
L=4,5km (200m in tunnel)
GRP Pipes in Penstocks, case studies
Hidroenergia 2008, JH 19
Fjardara hydro power stations:
Iceland
Station 1:
DN1000mm, L=3,8km
PN6-35bar (static pressure 33,5bar)
(6,4MW)
Station 2:
DN1000mm, L=3,4km
PN6-25bar (static pressure 20bar)
(3,4MW)
Installed in 2007/2008
GRP Pipes in Penstocks, case studies
Hidroenergia 2008, JH 20
Environmental friendly
solutions for the future!
For generations!!
Thank you for your
attention!
GRP Pipes in Penstocks