‘cured in place’
TRANSCRIPT
-
7/31/2019 Cured in place
1/1
AUGUST/SEPTEMBER 2009
APPLICATIONS
www.reinforcedplastics.com REINFORCEDplastics
Superyachttender puts firesafety firstSPECIALISING IN the supply of
custom and semi-custom
tenders to superyachts, UK
company Superyacht Tenders
produces a range of vessels
that focus on fire protection,
functionality and performance.
SP, the marine business of
Gurit, provided the composite
materials to help create a new
Lloyds tested superyachttender compliant with the
requirements of the UK
Maritime and Coastguard
Agency (MCA).
Working in partnership with SP,
the team at Superyacht
Tenders manufactured the hull
using a combination of
engineering materials which
included SPs ST70FR and
Ampreg 21 epoxy wet
laminating system, polyvinyl
chloride (PVC) core, and glass
reinforcements.
ST70FR, a fire retardant hot melt
SPRINT, is ideally suited to the
manufacture of laminates
requiring fire protection. SPRINT
materials consist of a layer of fibre
reinforcement either side of a
precast, precatalysed resin film,
with a light tack film on one face.
ST70FR is reported to be capable
of producing high quality, low
void-content components from a
low cost vacuum bag/oven
curing process. It was selected as
being the most fire retardant of
SPs structural epoxy systems
with the most external fire
testing certification.
The SPRINT format has low
smoke toxicity, is self extin-guishing and halogen-free.
To achieve Lloyds and MCA
compliance the craft had to
successfully withstand a series of
demanding tests, including fire
testing, being swung against a
dock, drop tested from 3 m, and
swamp tested.
The handling and processing
qualities of ST70FR made it ideal
for the manufacture of the MCA
Compliant Superyacht tender,while using Ampreg 21 delivered
significant benefits in our
production with reduced build
times and good health & safety
characteristics, says Paul Jennings,
MD of Superyacht Tenders Ltd.
Superyacht Tenders Ltd;
http://superyachttenders.com
SP; www.gurit.com/marine
Superyacht Tenders craft is MCA compliant.
Cured in placepipe lining systemA CURED in place composite pipe
lining system (CIPP) has been
used for a major sewer repair
project in Reno, Nevada, USA.
The project was carried out by
pipelining specialist Pipenology
Inc and involved lining a total
7.7 km of 20-183 cm diameter
sewer pipes both in the busy
downtown and rural areas of
Reno. With the CIPP process the
repairs were carried out via
existing manhole access points.
This approach was not only fasterthan more traditional pipe lining
methods but also eliminated
disruptive and potentially
damaging excavation work.
CIPP technology repairs ageing or
damaged pipelines by
constructing a new liner inside
the existing host pipe. In the case
of the Reno project liner
construction began with a special
felt tube of predetermined
dimensions and length. The felt
was impregnated AOCs Vipel
corrosion-resistant resin and then
inserted into the pipe via existing
manholes in order to eliminate or
minimise the need for excavation.
Pressurised water was then intro-
duced into the resin-impregnated
tube to invert it and move it
along and against the sides of the
host pipe. When the entire length
of tube was turned inside out, the
water used during the insertion
was heated to cure the resin.
Pipenology Inc;
www.pipenologyinc.com
AOC; ww.aoc-resins.com
http://www.pipenologyinc.com/http://ww.aoc-resins.com/http://ww.aoc-resins.com/http://www.pipenologyinc.com/