cost fluctuation sheet (1)
DESCRIPTION
costTRANSCRIPT
NDCM/QS Contract Administration 1
COST FLUCTUATIONS Section 12.8 12.8.1 What is a cost fluctuation?
• After the close of _________.
• Increase (decrease) costs external to the contracting parties but
affecting the Contract Price
e.g. Council ______, law or regulation, toll, ________ etc.
How do you administer a cost fluctuation claim?
• Claim as for a____________
• Excludes adjustments for day works, prime cost sums, variations
payments based on actual costs or current prices, advances made
(A3, pg 67).
• The claim is for an increase (decrease) in _________
because of events subsequent to the Contract signing that have
impacted on costs.
• Dayworks, prime cost sums, variations payments based on actual
costs or current prices, advances etc removed from the tender sum –
they are based on actual costs.
• The claim is as a variation to the Contract.
• The claim is based on a formula which takes into account the
proportionate change in Labour costs and Material costs over the time
period.
NOTE: 0.4 and 0.6 above are standard fixed amounts.
M
MM
L
LLV
6.04.0
L portion M portion
Adjusted Sum
M
MM
L
LLV
6.04.0
Q change in Labour Costs
Q change in Materials Costs
Previous quarter’s Costs
NDCM/QS Contract Administration 2
Simple Calculation:
Details
Tender closed June 2005
Claim for June 2006
Valuation of work to date $1,128,000
Prime Cost Sums $50,000
Variations to date $40,500
Cost Fluctuation Claim: June 2006
Step 1
Tender closed June 2005
Valuation of work to date $1,128,000
Prime Cost Sums less $50,000
Variations to date less $40,500
Valuation subject to fluctuation $_________
Step 2 From NZ Statistics (see http://www.stats.govt.nz )
Labour Cost Index Materials Cost Index
• Dec 2005
• Dec 2006
1107
1153
• Dec 2005
• Dec 2006
1285
1407
Step 3
Calculate the amount of fluctuation from the above formula and the relevant statistics
from NZ Statistics.
For this example use the cost indices above
=
=
=
This is added to the claim in the “Other claims” part of the monthly claim.
M
MM
L
LLV
6.04.0
NDCM/QS Contract Administration 3
If you are assessing a fluctuation claim check:
1) The Special Conditions of Contract do not make other provisions for
fluctuations.
2) The current claim to date has had the Prime Cost Sums, variations,
dayworks etc removed.
3) The correct Labour and Material Cost Indices are being used.
4) The calculations have been done correctly.
EXERCISE
Tender Amount Details
Tender closed June 2007
Final Claim June 2009
Contract Sum $3,642,000
Included Sums $90,000
Cost Fluctuation Claim: June 2010
Step 1
Tender closed June 2007
Tender Contract Sum $ 3,782,500.00
Less Included Sums $ 90,000.00
Less Variations to date $ 121,500.00
Less Other Claims $ 23,000.00
Valuation subject to fluctuation $___________
Labour Cost Index Materials Cost Index
• June 2007
• June 2009
1132
1244
• Dec 2007
• Dec 2006
1423
1515