Project ID Core Goals / Related Projects and Project Status 1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. Core Goal: Project Name Project Leader Planned Start: Stage Target Build Project Disposition End Start End: Actual P-2005-03 High-Resolution Precipitation Estimator (HPE) Kitzmiller, David 6/2/2008 5/30/2008 9/5/2008 5 OB8.3 Awaiting deployment Build: Priority Primary? Core Goal 1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green 3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green P-2005-04 Radar Based Probabilistic Quantitative Precipitation Estimates (PQPE) Kitzmiller, David 2/23/2005 4/6/2005 2 . Idle Build: Priority Primary? Core Goal 1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green 8. Quantify the uncertainty of our forecast information 1 - Blue 10. Provide, then improve, gridded water resource data production capability 1 - Blue P-2005-06 Dual-Polarization Radar Precip Estimates Stein, Daniel 6/20/2007 10/6/2009 4 EXRAD On-track or active Build: Priority Primary? Core Goal 1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green P-2005-08 Next-Generation Multisensor Quantitative Precipitation Analysis (NMQ) Kitzmiller, David 7/3/2008 8/1/2008 2 . On-track or active Build: Priority Primary? Core Goal 1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green 10. Provide, then improve, gridded water resource data production capability 1 - Blue Thursday, September 18, 2008 Page 1 of 28

Upload: nguyenkhuong

Post on 27-Jul-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc.Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-03 High-Resolution Precipitation Estimator (HPE)

Kitzmiller, David 6/2/20085/30/2008 9/5/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

P-2005-04 Radar Based Probabilistic Quantitative Precipitation Estimates (PQPE)

Kitzmiller, David 2/23/2005 4/6/20052 . IdleBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

8. Quantify the uncertainty of our forecast information 1 - Blue

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-06 Dual-Polarization Radar Precip Estimates

Stein, Daniel 6/20/2007 10/6/20094 EXRAD On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

P-2005-08 Next-Generation Multisensor Quantitative Precipitation Analysis (NMQ)

Kitzmiller, David 7/3/2008 8/1/20082 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

Thursday, September 18, 2008 Page 1 of 28

Page 2: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc.Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-18 Data Assimilator for Research Dist. Hydrologic Model (RDHM)

Lee, Haksu 7/1/20077/31/2006 2/15/20083 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-31 Daily QC into MPE Lawrence, Bryon 5/30/2008 9/5/20085 OB8.1 Awaiting deploymentBuild: Priority Primary? Core Goal

1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

P-2005-35 High Resolution Precipitation Nowcaster (HPN)

Kitzmiller, David 3/18/20083/18/2008 9/30/20084 OB9 On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-36 Snow Modeling - Data Quality Research Smith, Michael 10/1/20073/23/2007 4/18/20072 . Sr. Scientist ReviewBuild: Priority Primary? Core Goal

1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

Thursday, September 18, 2008 Page 2 of 28

Page 3: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc.Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-38 Extrapolative Statistical Rainfall QPF 0-3 Hour Prediction

Kitzmiller, David 12/14/20052 . IdleBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

P-2005-39 NWSRFS Gridded Temperature Forecast Input

Kitzmiller, David 3/21/2005 4/6/20051 . IdleBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2006-01 Test Improvements to QPE in the TAR River Basin

Van Cooten, Suzanne

1/10/20071/10/2007 9/27/20073 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

21. Define and coordinate Hydrology Program requirements with other NOAA programs (conductive external project) 2 - Green

P-2008-03 Dual-Polarization Solutions to Partial Radar Beam Blockage

Miller, Dennis 6/4/2008 8/15/20083 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 1 - Blue

Thursday, September 18, 2008 Page 3 of 28

Page 4: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc.Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2008-04 High Resolution Radar Precipitation Evaluation

Miller, Dennis 8/1/2007 8/20/20083 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 1 - Blue

P-2008-05 Test Space-Based Radar Calibrated (GOES) Precipitation Impacts on Streamflow Forecasting

Zhang, Yu 6/30/20076/30/2007 8/30/20103 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 1 - Blue

P-2008-07 Develop Requirements for Adding Wind Modeling Capabilities into HEC-RAS

Mashriqui, Hassan 9/12/20086/4/2008 8/30/20082 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 1 - Blue

P-2008-09 2 Dimensional Modeling of River-Estuary-Ocean Interactions to Enhance Operational River Forecasting

Mashriqui, HassanHassan

9/8/20087/29/2008 9/30/20082 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 1 - Blue

Thursday, September 18, 2008 Page 4 of 28

Page 5: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc.Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2008-10 Update the High Resolution Precipitation Estimator (HPE) to use Dual-Polarization Products

Fresch, Mark 9/2/20089/2/2008 9/30/20081 . Gate PendingBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

Thursday, September 18, 2008 Page 5 of 28

Page 6: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts)Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-11 Interactive Calibration Program (ICP) Replacement

Vo, Ai 1/8/20081/8/2008 6/15/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

P-2005-12 Data Quality Model Calibration - IDMA Smith, Michael 3/16/20053/16/20052 . On-holdBuild: Priority Primary? Core Goal

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

P-2005-13 Snow Modeling Intercomparison II (Snow MIP II)

Smith, Michael 3/23/20073/23/2007 4/18/20072 . Waiting for inputBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-15 Distributed Model Intercomparison Project (DMIP) 2

Smith, Michael 11/15/2006 1/15/20083 . Waiting for inputBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

Thursday, September 18, 2008 Page 6 of 28

Page 7: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts)Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-18 Data Assimilator for Research Dist. Hydrologic Model (RDHM)

Lee, Haksu 7/1/20077/31/2006 2/15/20083 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-22 VAR Verification, Validation & Enhancement

Seo, DongJun 9/26/20059/26/2005 11/30/20073 . Re-work RequestedBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

8. Quantify the uncertainty of our forecast information 1 - Blue

16. Verify our forecast and uncertainty information 1 - Blue

P-2005-36 Snow Modeling - Data Quality Research Smith, Michael 10/1/20073/23/2007 4/18/20072 . Sr. Scientist ReviewBuild: Priority Primary? Core Goal

1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

Thursday, September 18, 2008 Page 7 of 28

Page 8: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts)Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2007-10 Change HL-RDHM to Interpolate Inputs Smith, Michael 4/17/2007 6/16/20072 . On-track or activeBuild: Priority Primary? Core Goal

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2007-16 Modify HL-RDHM to Generate Lateral Inflows for FLDWAV

Smith, Michael 10/1/2007 11/23/20072 . On-holdBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

P-2007-23 Lumped and Distributed Model Parameterization

Smith, Michael 11/1/20075/26/2007 5/30/20083 . On-track or activeBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2008-01 Operational Distributed Hydrologic Modeling (DHM) Build 1 (Phase 3)

Vo, Ai 5/30/2008 9/5/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal10. Provide, then improve, gridded water resource data production capability 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

Thursday, September 18, 2008 Page 8 of 28

Page 9: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status3. Improve forecasts of fast response hydrologic events including debris flowCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-03 High-Resolution Precipitation Estimator (HPE)

Kitzmiller, David 6/2/20085/30/2008 9/5/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

P-2005-15 Distributed Model Intercomparison Project (DMIP) 2

Smith, Michael 11/15/2006 1/15/20083 . Waiting for inputBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-23 Implementation of VAR into Site Specific Hydrologic Predictor (SSHP)

Gobs, Chip 7/11/20077/11/2007 11/21/20073 OB9 Re-work RequestedBuild:

Priority Primary? Core Goal3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

P-2005-27 Evaluation of Hydrologic Forecasts in Puerto Rico based on the use of USGS

Smith, Michael 1/18/200612/28/2005 1/30/20062 . IdleBuild:

Priority Primary? Core Goal3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

Thursday, September 18, 2008 Page 9 of 28

Page 10: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status3. Improve forecasts of fast response hydrologic events including debris flowCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-35 High Resolution Precipitation Nowcaster (HPN)

Kitzmiller, David 3/18/20083/18/2008 9/30/20084 OB9 On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-38 Extrapolative Statistical Rainfall QPF 0-3 Hour Prediction

Kitzmiller, David 12/14/20052 . IdleBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

P-2006-01 Test Improvements to QPE in the TAR River Basin

Van Cooten, Suzanne

1/10/20071/10/2007 9/27/20073 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

21. Define and coordinate Hydrology Program requirements with other NOAA programs (conductive external project) 2 - Green

P-2006-15 Flash Flood Monitoring and Prediction (FFMP) - Advance Design

Mullusky, Mary 1/2/2008 4/2/20084 OB8.3 On-track or activeBuild:

Priority Primary? Core Goal3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

Thursday, September 18, 2008 Page 10 of 28

Page 11: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status3. Improve forecasts of fast response hydrologic events including debris flowCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2008-01 Operational Distributed Hydrologic Modeling (DHM) Build 1 (Phase 3)

Vo, Ai 5/30/2008 9/5/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal10. Provide, then improve, gridded water resource data production capability 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

P-2008-10 Update the High Resolution Precipitation Estimator (HPE) to use Dual-Polarization Products

Fresch, Mark 9/2/20089/2/2008 9/30/20081 . Gate PendingBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

Thursday, September 18, 2008 Page 11 of 28

Page 12: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status4. Improve forecasts based on the effect of dam failuresCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2008-08 Develop Improved Guidance for Dam Break Forecasting

Moreda, Fekadu 3/15/2008 9/30/20082 . On-track or activeBuild:

Priority Primary? Core Goal4. Improve forecasts based on the effect of dam failures 3 - Yellow

Thursday, September 18, 2008 Page 12 of 28

Page 13: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status5. Improve hydrologic forecasts impacted by reservoirs and regulation (outsource)Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-34 NWSRFS Reservoir Tools Enhancement Hsu, Kuang-shen 1/8/20081/8/2008 6/15/20085 OB8.3 Awaiting deploymentBuild: Priority Primary? Core Goal

5. Improve hydrologic forecasts impacted by reservoirs and regulation (outsource) 1 - Blue

P-2007-04 Integration of HEC ResSim Model into NWSRFS

Hsu, Kuang-shen 3/27/2007 5/14/20083/27/2007 10/1/20074 . Conditional ApprovalBuild:

Priority Primary? Core Goal5. Improve hydrologic forecasts impacted by reservoirs and regulation (outsource) 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

Thursday, September 18, 2008 Page 13 of 28

Page 14: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status6. Improve the routing techniques used to connect forecast locations (includes coastal effects) - Hydraulics ModelsCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-26 Simple Hydraulic Routing Technique (SHRT)

Reed, Seann 9/29/2005 9/30/20053 . On-holdBuild:

Priority Primary? Core Goal6. Improve the routing techniques used to connect forecast locations (includes coastal effects) - Hydraulics Models 2 - Green

7. Improve flood forecast inundation maps 3 - Yellow

P-2007-07 Deriving Improved & Higher Resolution Slope & Flow Direction Grids for DHM

Reed, Seann 11/13/20072 . On-holdBuild:

Priority Primary? Core Goal6. Improve the routing techniques used to connect forecast locations (includes coastal effects) - Hydraulics Models 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2007-21 Transition from FLDWAV to HEC-RAS; Forecast Implications & Transition Tools

Gutierrez, Angelica

5/21/2008 8/15/20093 . On-track or activeBuild:

Priority Primary? Core Goal6. Improve the routing techniques used to connect forecast locations (includes coastal effects) - Hydraulics Models 2 - Green

Thursday, September 18, 2008 Page 14 of 28

Page 15: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status7. Improve flood forecast inundation mapsCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-26 Simple Hydraulic Routing Technique (SHRT)

Reed, Seann 9/29/2005 9/30/20053 . On-holdBuild:

Priority Primary? Core Goal6. Improve the routing techniques used to connect forecast locations (includes coastal effects) - Hydraulics Models 2 - Green

7. Improve flood forecast inundation maps 3 - Yellow

P-2007-08 Dynamic Inundation Mapping Evaluation Reed, Seann 10/1/2006 11/30/20073 . Sr. Scientist ReviewBuild: Priority Primary? Core Goal

7. Improve flood forecast inundation maps 3 - Yellow

P-2008-11 Develop Database of NWS Forecast Point Characteristics for Hydraulic Model & Inundation Mapping

Aschwanden, Cecil

6/1/2008 10/8/20082 . On-track or activeBuild:

Priority Primary? Core Goal7. Improve flood forecast inundation maps 3 - Yellow

Thursday, September 18, 2008 Page 15 of 28

Page 16: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status8. Quantify the uncertainty of our forecast informationCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-04 Radar Based Probabilistic Quantitative Precipitation Estimates (PQPE)

Kitzmiller, David 2/23/2005 4/6/20052 . IdleBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

8. Quantify the uncertainty of our forecast information 1 - Blue

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-05 Ensemble Post Processor Evaluation Regonda, Satish 12/12/2006 12/31/20073 . On-track or activeBuild: Priority Primary? Core Goal

8. Quantify the uncertainty of our forecast information 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

P-2005-19 Hydrologic Ensemble Hindcaster Demargne, Julie 9/15/2005 7/9/20089/15/2005 7/31/20073 . Conditional ApprovalBuild: Priority Primary? Core Goal

8. Quantify the uncertainty of our forecast information 1 - Blue

16. Verify our forecast and uncertainty information 1 - Blue

P-2005-20 Hydrologic Ensemble Preprocessor II Wu, Limin 8/24/20058/24/2005 9/29/20073 XEFS-1 On-track or activeBuild: Priority Primary? Core Goal

8. Quantify the uncertainty of our forecast information 1 - Blue

Thursday, September 18, 2008 Page 16 of 28

Page 17: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status8. Quantify the uncertainty of our forecast informationCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-22 VAR Verification, Validation & Enhancement

Seo, DongJun 9/26/20059/26/2005 11/30/20073 . Re-work RequestedBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

8. Quantify the uncertainty of our forecast information 1 - Blue

16. Verify our forecast and uncertainty information 1 - Blue

P-2005-30 Ensemble Preprocessor for Global Forecasting System (GFS)

Schaake, John 9/24/20057/27/2005 9/24/20053 XEFS-1 Waiting for inputBuild:

Priority Primary? Core Goal8. Quantify the uncertainty of our forecast information 1 - Blue

P-2006-10 Hydrologic Ensemble Preprocessor 3 Schaake, John 12/5/200512/5/2005 2/20/20061 XEFS-1 Waiting for inputBuild: Priority Primary? Core Goal

8. Quantify the uncertainty of our forecast information 1 - Blue

P-2007-19 Experimental Ensemble Forecast System (XEFS)

Dietz, Christine 7/19/2007 8/10/20071 . Waiting for inputBuild:

Priority Primary? Core Goal8. Quantify the uncertainty of our forecast information 1 - Blue

Thursday, September 18, 2008 Page 17 of 28

Page 18: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status10. Provide, then improve, gridded water resource data production capabilityCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-04 Radar Based Probabilistic Quantitative Precipitation Estimates (PQPE)

Kitzmiller, David 2/23/2005 4/6/20052 . IdleBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

8. Quantify the uncertainty of our forecast information 1 - Blue

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-08 Next-Generation Multisensor Quantitative Precipitation Analysis (NMQ)

Kitzmiller, David 7/3/2008 8/1/20082 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-10 Flash Flood Forecasting - New Distributed Modeling Techniques

Reed, Seann 11/23/200511/23/2005 9/30/20083 . Waiting for inputBuild:

Priority Primary? Core Goal10. Provide, then improve, gridded water resource data production capability 2 - Green

P-2005-13 Snow Modeling Intercomparison II (Snow MIP II)

Smith, Michael 3/23/20073/23/2007 4/18/20072 . Waiting for inputBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

Thursday, September 18, 2008 Page 18 of 28

Page 19: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status10. Provide, then improve, gridded water resource data production capabilityCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-15 Distributed Model Intercomparison Project (DMIP) 2

Smith, Michael 11/15/2006 1/15/20083 . Waiting for inputBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-18 Data Assimilator for Research Dist. Hydrologic Model (RDHM)

Lee, Haksu 7/1/20077/31/2006 2/15/20083 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-35 High Resolution Precipitation Nowcaster (HPN)

Kitzmiller, David 3/18/20083/18/2008 9/30/20084 OB9 On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

Thursday, September 18, 2008 Page 19 of 28

Page 20: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status10. Provide, then improve, gridded water resource data production capabilityCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-36 Snow Modeling - Data Quality Research Smith, Michael 10/1/20073/23/2007 4/18/20072 . Sr. Scientist ReviewBuild: Priority Primary? Core Goal

1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2005-39 NWSRFS Gridded Temperature Forecast Input

Kitzmiller, David 3/21/2005 4/6/20051 . IdleBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2007-07 Deriving Improved & Higher Resolution Slope & Flow Direction Grids for DHM

Reed, Seann 11/13/20072 . On-holdBuild:

Priority Primary? Core Goal6. Improve the routing techniques used to connect forecast locations (includes coastal effects) - Hydraulics Models 2 - Green

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2007-10 Change HL-RDHM to Interpolate Inputs Smith, Michael 4/17/2007 6/16/20072 . On-track or activeBuild: Priority Primary? Core Goal

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

Thursday, September 18, 2008 Page 20 of 28

Page 21: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status10. Provide, then improve, gridded water resource data production capabilityCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2007-23 Lumped and Distributed Model Parameterization

Smith, Michael 11/1/20075/26/2007 5/30/20083 . On-track or activeBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

10. Provide, then improve, gridded water resource data production capability 1 - Blue

P-2008-01 Operational Distributed Hydrologic Modeling (DHM) Build 1 (Phase 3)

Vo, Ai 5/30/2008 9/5/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal10. Provide, then improve, gridded water resource data production capability 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

Thursday, September 18, 2008 Page 21 of 28

Page 22: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status13. Software refresh – enhance the usability and/or internal workings of existing softwareCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-05 Ensemble Post Processor Evaluation Regonda, Satish 12/12/2006 12/31/20073 . On-track or activeBuild: Priority Primary? Core Goal

8. Quantify the uncertainty of our forecast information 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

P-2005-11 Interactive Calibration Program (ICP) Replacement

Vo, Ai 1/8/20081/8/2008 6/15/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

P-2007-04 Integration of HEC ResSim Model into NWSRFS

Hsu, Kuang-shen 3/27/2007 5/14/20083/27/2007 10/1/20074 . Conditional ApprovalBuild:

Priority Primary? Core Goal5. Improve hydrologic forecasts impacted by reservoirs and regulation (outsource) 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

P-2007-17 Community Hydrologic Prediction System (CHPS)

Dietz, Christine 5/15/2007 11/20/20073 . On-track or activeBuild:

Priority Primary? Core Goal13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

Thursday, September 18, 2008 Page 22 of 28

Page 23: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status13. Software refresh – enhance the usability and/or internal workings of existing softwareCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2008-01 Operational Distributed Hydrologic Modeling (DHM) Build 1 (Phase 3)

Vo, Ai 5/30/2008 9/5/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal10. Provide, then improve, gridded water resource data production capability 1 - Blue

13. Software refresh – enhance the usability and/or internal workings of existing software 1 - Blue

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

Thursday, September 18, 2008 Page 23 of 28

Page 24: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status15. Archive information required to support the Hydrology Program now and in the futureCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2006-13 Synchronize RFC Archive DB with IHFS Database Metadata

Erb, Russ 5/30/2008 9/5/20085 OB8.3 Awaiting deploymentBuild:

Priority Primary? Core Goal15. Archive information required to support the Hydrology Program now and in the future 2 - Green

P-2008-02 River Forecast Center (RFC) Archive System (RAX) Technology Refresh Initiative

Meyer, Julie 6/10/2008 12/9/20083 AWIPS On-track or activeBuild:

Priority Primary? Core Goal15. Archive information required to support the Hydrology Program now and in the future 2 - Green

Thursday, September 18, 2008 Page 24 of 28

Page 25: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status16. Verify our forecast and uncertainty informationCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2005-19 Hydrologic Ensemble Hindcaster Demargne, Julie 9/15/2005 7/9/20089/15/2005 7/31/20073 . Conditional ApprovalBuild: Priority Primary? Core Goal

8. Quantify the uncertainty of our forecast information 1 - Blue

16. Verify our forecast and uncertainty information 1 - Blue

P-2005-22 VAR Verification, Validation & Enhancement

Seo, DongJun 9/26/20059/26/2005 11/30/20073 . Re-work RequestedBuild:

Priority Primary? Core Goal2. Improve river forecasts by improving hydrologic models (Note: “river forecasts” include water supply forecasts) 3 - Yellow

8. Quantify the uncertainty of our forecast information 1 - Blue

16. Verify our forecast and uncertainty information 1 - Blue

Thursday, September 18, 2008 Page 25 of 28

Page 26: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status17. Provide science and software training on Hydrology Program applications throughout the research to operations cycleCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2007-18 Develop HOSIP Training Plan, HOSIP Charts

Andre, Marylin 11/3/20061 . On-track or activeBuild:

Priority Primary? Core Goal17. Provide science and software training on Hydrology Program applications throughout the research to operations cycle 3 - Yellow

19. Improve the efficiency and effectiveness of Hydrology Program management, including an understanding of logistical measures 2 - Green

P-2008-06 HOSIP Web Page Renovation Project Chen, Ruiming 3/14/20083/14/2008 5/16/20083 . On-track or activeBuild: Priority Primary? Core Goal

17. Provide science and software training on Hydrology Program applications throughout the research to operations cycle 3 - Yellow

19. Improve the efficiency and effectiveness of Hydrology Program management, including an understanding of logistical measures 2 - Green

Thursday, September 18, 2008 Page 26 of 28

Page 27: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status19. Improve the efficiency and effectiveness of Hydrology Program management, including an understanding of logistical measuresCore Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2007-18 Develop HOSIP Training Plan, HOSIP Charts

Andre, Marylin 11/3/20061 . On-track or activeBuild:

Priority Primary? Core Goal17. Provide science and software training on Hydrology Program applications throughout the research to operations cycle 3 - Yellow

19. Improve the efficiency and effectiveness of Hydrology Program management, including an understanding of logistical measures 2 - Green

P-2008-06 HOSIP Web Page Renovation Project Chen, Ruiming 3/14/20083/14/2008 5/16/20083 . On-track or activeBuild: Priority Primary? Core Goal

17. Provide science and software training on Hydrology Program applications throughout the research to operations cycle 3 - Yellow

19. Improve the efficiency and effectiveness of Hydrology Program management, including an understanding of logistical measures 2 - Green

Thursday, September 18, 2008 Page 27 of 28

Page 28: Core Goals / Related Projects and Project Status fileProject ID Core Goals / Related Projects and Project Status Core Goal: 1. Improve the quality of physical inputs and forcings,

Project ID

Core Goals / Related Projects and Project Status21. Define and coordinate Hydrology Program requirements with other NOAA programs (conductive external project)Core Goal:

Project Name Project LeaderPlanned

Start:StageTarget Build Project DispositionEndStartEnd:

Actual

P-2006-01 Test Improvements to QPE in the TAR River Basin

Van Cooten, Suzanne

1/10/20071/10/2007 9/27/20073 . On-track or activeBuild:

Priority Primary? Core Goal1. Improve the quality of physical inputs and forcings, e.g. QPE, QPF, temperature, snow, evapotranspiration, soil conditions, burn data, etc. 2 - Green

3. Improve forecasts of fast response hydrologic events including debris flow 2 - Green

21. Define and coordinate Hydrology Program requirements with other NOAA programs (conductive external project) 2 - Green

Thursday, September 18, 2008 Page 28 of 28