control of well limits: how much is enough?

23
Control of Well Limits How Much is Enough? Presented by: Special Thanks to: G.S. Bryan & Associates, Inc. and

Upload: buicong

Post on 02-Jan-2017

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Control of Well Limits: How Much is Enough?

Control of Well LimitsHow Much is Enough?

Presented by: Special Thanks to:

G.S. Bryan & Associates, Inc.and

Page 2: Control of Well Limits: How Much is Enough?

COST OF CONTROLCOST OF CONTROLHow does it work?

1

Page 3: Control of Well Limits: How Much is Enough?

Overview of Well Control Policy and Main Policy Sections

What and who does the policy cover? Unregulated forms; they all vary slightly – but generally

the same Sections

– Well out of Control– S&P– Redrill– Sub limit for Care, Custody, & Control, 3rd Party

Equipment on Well site, including rig legal liability, sound location.

2

Page 4: Control of Well Limits: How Much is Enough?

 

As product prices rise, then it is incentive to drill.

So Operators drill more wells,

So they can sell more product,

So they can make more money,

So they can hire more rigs,

So they can drill more wells,

Which requires still more rigs,

Which “thins out” crews, and

Wears out rigs…………

All of which leads to more losses – And they are more costly than ever!

What Affects Losses?

3

Page 5: Control of Well Limits: How Much is Enough?

Blowout! 4

Page 6: Control of Well Limits: How Much is Enough?

Scenario 1 – “Typical” Claim:Exploratory Well #1 TVD: 10,000 FeetAFE: $1,000,000 Dry Hole Cost100% Working Interest Insured by Operator Client (Insured)Rate: $0.50 pfd = $5,000 Premium

$100,000 Retention

Insured will pay costs related to Well Control.

Policy Limit $3MM Each Occurrence

(For 100% Interest)CCC Limit $500,000 5

Page 7: Control of Well Limits: How Much is Enough?

WEEKS ONE and TWO: Expenses after the Blowout A Snubbing crew arrives, then after three days, operator hires a Well Control Contractor. Total bills already $500,000 in the first two weeks.

Costs of Control Fighting the Fire

$500kPolicy Limit $3MM Each Occurrence

Retention: $100,000(For 100% Interest)CCC Limit $500,000 6

Page 8: Control of Well Limits: How Much is Enough?

WEEKS THREE & FOUR: Expenses after the Blowout An environmental remediation contractor is hired to clean up Farmer Brown’s cattle tanks, fishing creek, and Hog pens. The invoice totals $350,000.

Costs of Control Fighting the Fire

$500k

Seepage & Pollution

$350k

Policy Limit $3MM Each Occurrence

Retention: $100,000(For 100% Interest)CCC Limit $500,000 7

Page 9: Control of Well Limits: How Much is Enough?

WEEKS FIVE through TEN:Expenses after the Blowout Well is under control. TX RRC leaves the operator alone, but the joint venture partners want the operator to replace the well to get whatever blew it out in the first place. After fishing and sidetracking for ten days the operator gives up, skids the rig over and starts over –another $1,800,000 to reach T.D.

Seepage & Pollution

$350k

RestorationRedrill

$1.8m

$500k

Costs of Control Fighting the Fire

Policy Limit $3MM Each Occurrence

Retention: $100,000(For 100% Interest)CCC Limit $500,000 8

Page 10: Control of Well Limits: How Much is Enough?

RestorationRedrill

$1.8m Care, Custody & Control

$450k

WEEK ELEVEN: Expenses after the BlowoutWell achieves TD. Rental tool companies and various vendors to the original well ask the operator to pay for their equipment that was never recovered. “CCC” endorsement pays because the CGL won’t - $450,000.

Seepage & Pollution

Costs of ControlFighting the Fire

$350k

$500kPolicy Limit $3MM Each Occurrence

Retention: $100,000(For 100% Interest)CCC Limit $500,000 9

Page 11: Control of Well Limits: How Much is Enough?

CCC – 3rd Party Equipment on Site

10

Page 12: Control of Well Limits: How Much is Enough?

COST:

Premium Paid for this Well:

Retention born by Insured:

Total Costs:

RECOVERY:

Costs of Well Control:

Seepage and Pollution / Clean-up and Containment:

Sidetrack, Restoration,Redrilling Expenses:

Care, Custody, & Control (CCC):

Less CCC Deductible:

TOTAL RECOVERY:

What Insured Paid Versus What Insured Got Paid:

11$ 3,050,000

$ 5,000

$ 100,000

$ 105,000

$ 500,000

$ 350,000

$ 1,800,000$ 2,650,000 [Policy Limit was $3,000,000 excess of the Retention]

$ 450,000 [CCC Limit was $500,000]

$ (50,000)

Page 13: Control of Well Limits: How Much is Enough?

Scenario 2 – “Non-Typical” Claim:Well #2TVD: 8,000 FeetTMD: 8,911 FeetAFE: $1,850,000 Dry Hole Cost100% Working Interest Insured by Operator

$250,000 Retention

$100,000 in respect of CCC.

Policy Limit $15MM Each Occurrence

(For 100% Interest)CCC Limit $1,000,000 12

Page 14: Control of Well Limits: How Much is Enough?

Scenario 2 – “Non-Typical” Claim

Day 1-5 Well out of control below ground.

13

Well out of control above ground.

Fishing under pressure from the well.

Rig Released, more fishing with snubbing unit.

Operations suspended due to hurricane.

Cement plugging, well pressure required multiple attempts. Well pressure required full plug and abandonment without salvaging original well bore.

Day 5-9

Day 10-15

Day 16-45

Day 46-48

Day 49-77

Page 15: Control of Well Limits: How Much is Enough?

Day 50-57 Spud Redrill Well, Set Surface Casing @ 2719’.

14

Drill to 7197’.

Circulate well flow, open hole squeeze to counter lost circulation, no further progress drilling.

Run 7 5/8’ int. casing to 6668’, cement, nipple up B.O.P’s, change out drill pipe, normal operations.Drill out of int. casing lose full returns, squeeze cementand kick off plug @ 6775’, all abnormal operations.

Circulate gas cut mud, drill to 7873’, non routine drilling.

Day 58-60

Day 61-73

Day 74-79

Day 80-88

Day 89-93

Scenario 2 – “Non-Typical” Claim

Page 16: Control of Well Limits: How Much is Enough?

Day 94-96 Run 5 ½’ int. liner casing and cement same, varies from original well plan but required for hole stability andpressure integrity.

15

Drill out of liner casing, shoe test failed, squeeze cementliner casing seat.

Reinitiated drilling & encountered problems with liner hanger seal assembly.Finally remedied & drilled to original loss depth19 weeks after original loss date.

Day 97

Day 98

Day 133

Scenario 2 – “Non-Typical” Claim

Page 17: Control of Well Limits: How Much is Enough?

Costs of Well Control:

RECOVERY:

16

$ 8,139,000

$ -0-

$ 4,443,000

$ 12,582,000 [Policy Limit $15,000,000 excess of Retention]

$ 750,000 [CCC Limit was $1,000,000]

$ 13,332,000

[Original AFE was $1,850,000]

Seepage and Pollution / Clean-up and Containment:

Sidetrack, Restoration,Redrilling Expenses:

Care, Custody, & Control (CCC):

TOTAL RECOVERY:

Page 18: Control of Well Limits: How Much is Enough?

17

Scenario 3 – “Non-Typical” Claim:Well #3TVD: 21,000 FeetTMD: 21,900 FeetAFE: $28,740,000 Dry Hole Cost100% Working Interest Insured by Operator

Policy Limit $75MM Each Occurrence

(For 100% Interest)CCC Limit $1,000,000

$750,000 Retention

$100,000 in respect of CCC.

Page 19: Control of Well Limits: How Much is Enough?

18

Scenario 3 – “Non-Typical” Claim

Day 1 Well out of control above ground.Well was at 20,406’ depth.

At this point, $72,500,000 had been expended in Control of Well costs. The Insured approached Underwriters to reinstate the policy limits

prior to the redrill.

Extensive well control effort.

Move rig off location, a side track of the original well.

Rig up snubbing unit on another barge.

Snubbing operation.

Fishing operations.

Day 2-26

Day 26-40

Day 41-52

Day 52-94

Day 95-289

Page 20: Control of Well Limits: How Much is Enough?

19

Day 290-430 Redrill to original loss depth. Redrill began 9 ½ months after original loss.This Redrill cost $21,700,00.

While redrilling below the 1st redrill depth, theredrill well lost control. Second occurrence.

Second loss depth reached. Overall,the Redrill involved 2 sidetracks.

Day 477

Day 586

Scenario 3 – “Non-Typical” Claim

Page 21: Control of Well Limits: How Much is Enough?

1st Costs of Well Control:

Seepage and Pollution / Clean-up and Containment:

Sidetrack, Restoration, Redrilling Expenses:

1st OEE Claim:

2nd Cost of Control / Redrill :

Care, Custody, & Control (CCC):

TOTAL RECOVERY:

RECOVERY:

20

$ 72,500,000

$ -0-

$ 21,700,000

$ 94,200,000 [Policy Limit $75,000,000 excess of Retention]$ 22,685,000

$ 1,900,000

$ 23,585,000 [Policy Limit $75,000,000 excess of Retention.

Contained in 1st layer]

Page 22: Control of Well Limits: How Much is Enough?

What is an “AFE” and how is it used to establish a Well Control Limit?

Other considerations for determining a limit.– Location– Well Pressure– Depth– Offset Well Data

Intangibles

Limits – How Much???

21

Page 23: Control of Well Limits: How Much is Enough?

“Anything that can go wrong,

22

will go wrong.”- Murphy’s Law

Hopes for the best

Underwriter = Pessimist

Oilman = Optimist

Expects the worst

Plan, Design, Plan Some More