KC Soccer Stadium construction update from Turner Construction.TRANSCRIPT
Building the Future
Current Activities this Week:
Mass Excavation:
Grading is ongoing in Area 3. Backfilling of on-grade
is ongoing in Area 1.
Site Utilities:
Installation of the new electrical ductbank is ongoing.
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive.
Foundations:
Area 2 Field Level – Footing installation will be complete
to Column Line 12 by the end of the day.
Area 1 Mezzanine Level – Installation of Elevator Pit walls
are complete.
Area 4 Mezzanine Level – Installation of Drilled Piers
are ongoing.
Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-1 is nearly
complete. Sequence 1-2 has started and is currently
being erected in the Column Line 27/26 Bay.
Decking is nearly complete in sequence 1-1 on
Mezzanine and Concourse Levels.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 5.12.2010
Re: Wizards Stadium Project
Update – Week of
5.10.2010
Field Level Area 2 – A-Line and Field Wall
Footings ready for concrete placement.
France Family Drive – Storm Line 6000
installation is ongoing.
Field Level Area 3 – Drilled Pier installation is
ongoing.
Building the Future
Underground Electrical:
Secondary service ducts is complete from Electrical Room
01.34.04 south past Column Line 25.
Installation of secondary service ducts at Column Line D
are ongoing.
Projected Activities occurring next Week:
Mass Excavation:
Grading at Truck Dock Area will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue.
Deep Underground Plumbing:
Sanitary in Area 3 will begin.
Foundations:
Area 2 Field Level – Placement of foundation walls east of
Stage will begin.
Area 3 Field Level – Footing excavation will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-2 will continue.
Area 1 – Structural Steel Erection at West
Building continues. B-Line Columns being
set at Column Lines 26 and 27.
Field Level Area 1 – Shot looking north from
Concourse Level.
Concourse Level Area 1 – Decking installed
at Main Club.
Building the Future
Additional Photos:
Mezzanine Level Area 1 – VIP Entrance
taking shape.
Field Level Area 2 – Foundations taking
shape at Stage.
Field Level Area 1 – Shot of the Stadium
Suite from Column Line 30 (Field Level).
Concourse Level Area 2 – E-Line Footings
installed to Column Line 20.
Area 1 – Shot looking North West showing
West Building Structural Steel.
Concourse Level Area 2 – Electrical ductbank
installation is ongoing.