Sarasota Memorial HospitalCampus Improvement Plan

Neighborhood Advisory Council October 12, 2010

Construction Update

Project Phasing 1 & 2: Demolish CEP, Pre-Moves, New Garage Entry/Exit

Demolish Old CEPTemporary Entry/Exit at Waldemere Garage

Central Receiving Complete – 1-Waldemere

New CEP Completed

Information Systems Complete – 5-Service

Wound Care – 2-Waldemere

Observation Complete – 9-East

Surgery/CS Vertical Expansion

On-Call – 4-Central

Interim Moves for Surgery Support & Pathology

Temporary ECC Turn-around & Canopy

Temporary Main Entrance Canopy

2

Legend: Green box means that portion will be completed in that phase. Beige box is ongoing.

2

Project Phasing 3 & 4: Temporary Drive, Complete Fall 2010

Temporary ECC Turn-around & Canopy Complete

Wound Care – 2-Waldemere

Surgery/CS Vertical Expansion

Moves for Surgery Support & Pathology Complete

Sitework & Temporary Drive

Demolish Portion of Critical Care Tower

3

Legend: Green box means that portion will be completed in that phase. Beige box is ongoing.

3

Temp Main Entry Turn-around & Canopy

On-Call 3-East

Project Phasing 5: Demolish Northeast Wing and Main Entry, Begin Bridge

Sitework & Temporary Drive

Temp Main Entry Turn-around & Canopy

ECC Vestibule, Canopy and Drop-off Complete

Demolish Northeast Tower Main Entry Canopy

Structure for Bridge, Elevator & Stair

Surgery/CS Vertical Expansion

4

Legend: Green box means that portion will be completed in that phase. Beige box is ongoing.

4

Project Phasing 6: Patient Tower Foundations, South Connector

Complete Winter 2010 - 2011

Surgery/CS Vertical Expansion & Connector to So. Garage

New Patient Tower Foundations

Structure for Bridge, Elevator & Stair

5

Legend: Beige box is ongoing.

5

Project Phasing 7: Patient Tower Structure, Surgery / CS,

Surgery/CS Vertical Expansion & Connector Complete

New Patient Tower Structure

6

Legend: Green box means that portion will be completed in that phase. Beige box is ongoing.

6