construction update 09-8-2010
TRANSCRIPT
Building the Future
Current Activities this Week:
Underground Utilities:
Area 3 - Deep underground Plumbing continues.
on the east side of France Family Drive. Installation of
the gas service has commenced.
Foundations:
Area 4 Field Level – Upper Field wall forms are being
installed.
Concrete Flatwork:
Area 2 Concourse – Concrete placement for slab at
South Concession Buildings is complete to column line
15.
Structural Steel Erection:
Area 2 – Main Canopy Truss Erection are set to Column
Line 6. Area 4 – Structural Steel in Sequence 3-3 is
erected to column line 39.
MEP Rough-in:
Area 3 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite and Press Levels
are ongoing. Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Suite and Press Levels. Electrical rough-in is ongoing on
Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 9.8.2010
Re: Wizards Stadium Project
Update – Week of
9.6.2010
Area 3 – Underground plumbing installation
is ongoing at the lower dock area.
Area 4 – Structural Steel Erection Sequence
3-3 has been set to column line 39.
Area 2 – CMU wall installation has started at
Stage.
Building the Future
and sheathing installation is ongoing at Field, Suite, and
Press Levels.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas E, F, G and H.
Area 1, 2 Concourse Level – Masonry wall installation at
Main Concourse Buildings are underway.
Curtainwall:
Area 1 – Curtainwall framing installation will continue
at West Elevation. Installation of Curtainwall glass is
ongoing.
Projected Activities occurring next Week:
Underground Utilities:
Deep Plumbing installation will continue in Area 3.
Foundations:
Area 4 Field Level – Foundation wall installation for Main
Stair will begin.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade at upper dock area will begin. Prep work for slab-
on-grade for lower dock area will begin.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Area 2 – Canopy truss installation at East side of Stadium
will continue.
MEP Rough-in:
MEP Rough-in at Suite and Press Levels will continue.
Ductwork installation on Press Level will continue. Fire
Sprinkler installation will continue on Suite and Press Levels.
Field Level Area 3 – Formwork of Main Stair
support walls are being set.
Area 1 – Filled and polished CMU Block walls
at the Stair 4 and Restrooms.
Area 3 – Canopy Truss erection is complete
in Sequence 2-2 (installation of Truss to 6
Line shown).
Building the Future
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Curtainwall:
Area 1 – Curtain Framing and Glass installation will
continue.
Area 1 – Installation of curtainwall framing
and Glass at West Building is ongoing.
Area 1 – Shot of the west building showing
the progress of the canopy decking on
trusses.
Building the Future
Additional Photos:
Suite Level Area 1 – Shot looking through
the glass at Suite Level Club.
Area 1 – Shot of Suite fronts from roof of
Stadium Suite.
Area 1 – Curtainwall framing installation at
south face of Club Areas.
Concourse Level Area 1 – Masonry
installation continues on Concourse
Buildings.
Field Level Area 3 – Installation of cast-in-
place risers continue on east side.
Field Level Area 3 – Upper dock slab edge
formwork is installed.