Building the Future Current Activities this Week : Underground Utilities : Area 3 - Deep underground Plumbing continues. on the east side of France Family Drive. Installation of the gas service has commenced. Foundations : Area 4 Field Level – Upper Field wall forms are being installed. Concrete Flatwork : Area 2 Concourse – Concrete placement for slab at South Concession Buildings is complete to column line 15. Structural Steel Erection : Area 2 – Main Canopy Truss Erection are set to Column Line 6. Area 4 – Structural Steel in Sequence 3-3 is erected to column line 39. MEP Rough-in: Area 3 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite and Press Levels are ongoing. Plumbing rough-in is ongoing on Suite and Press Levels. Fire Protection rough-in is ongoing on Suite and Press Levels. Electrical rough-in is ongoing on Suite and Press Levels. Metal Stud Framing : Area 1 – Metal stud framing for Field, Concourse, Suite and Press Levels are ongoing. Exterior metal stud framing To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 9.8.2010 Re: Wizards Stadium Project Update – Week of 9.6.2010 Area 3 – Underground plumbing installation is ongoing at the lower dock area. Area 4 – Structural Steel Erection Sequence 3-3 has been set to column line 39. Area 2 – CMU wall installation has started at Stage.

Upload: kansas-city-wizards

Post on 26-Jun-2015

137 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction Update 09-8-2010

Building the Future

Current Activities this Week:

Underground Utilities:

Area 3 - Deep underground Plumbing continues.

on the east side of France Family Drive. Installation of

the gas service has commenced.

Foundations:

Area 4 Field Level – Upper Field wall forms are being

installed.

Concrete Flatwork:

Area 2 Concourse – Concrete placement for slab at

South Concession Buildings is complete to column line

15.

Structural Steel Erection:

Area 2 – Main Canopy Truss Erection are set to Column

Line 6. Area 4 – Structural Steel in Sequence 3-3 is

erected to column line 39.

MEP Rough-in:

Area 3 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite and Press Levels

are ongoing. Plumbing rough-in is ongoing on Suite and

Press Levels. Fire Protection rough-in is ongoing on

Suite and Press Levels. Electrical rough-in is ongoing on

Suite and Press Levels.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels are ongoing. Exterior metal stud framing

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 9.8.2010

Re: Wizards Stadium Project

Update – Week of

9.6.2010

Area 3 – Underground plumbing installation

is ongoing at the lower dock area.

Area 4 – Structural Steel Erection Sequence

3-3 has been set to column line 39.

Area 2 – CMU wall installation has started at

Stage.

Page 2: Construction Update 09-8-2010

Building the Future

and sheathing installation is ongoing at Field, Suite, and

Press Levels.

Masonry:

Area 1 Field Level – Masonry wall installation is ongoing

in Areas E, F, G and H.

Area 1, 2 Concourse Level – Masonry wall installation at

Main Concourse Buildings are underway.

Curtainwall:

Area 1 – Curtainwall framing installation will continue

at West Elevation. Installation of Curtainwall glass is

ongoing.

Projected Activities occurring next Week:

Underground Utilities:

Deep Plumbing installation will continue in Area 3.

Foundations:

Area 4 Field Level – Foundation wall installation for Main

Stair will begin.

Concrete Flatwork:

Area 3 Field Level – Concrete placement for Slab-on

Grade at upper dock area will begin. Prep work for slab-

on-grade for lower dock area will begin.

Area 3 and 4 Field Level – Installation of on-grade seating

risers and intermediate stairs will continue.

Structural Steel Erection:

Area 2 – Canopy truss installation at East side of Stadium

will continue.

MEP Rough-in:

MEP Rough-in at Suite and Press Levels will continue.

Ductwork installation on Press Level will continue. Fire

Sprinkler installation will continue on Suite and Press Levels.

Field Level Area 3 – Formwork of Main Stair

support walls are being set.

Area 1 – Filled and polished CMU Block walls

at the Stair 4 and Restrooms.

Area 3 – Canopy Truss erection is complete

in Sequence 2-2 (installation of Truss to 6

Line shown).

Page 3: Construction Update 09-8-2010

Building the Future

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels will continue. Exterior Framing and

sheathing installation will continue.

Curtainwall:

Area 1 – Curtain Framing and Glass installation will

continue.

Area 1 – Installation of curtainwall framing

and Glass at West Building is ongoing.

Area 1 – Shot of the west building showing

the progress of the canopy decking on

trusses.

Page 4: Construction Update 09-8-2010

Building the Future

Additional Photos:

Suite Level Area 1 – Shot looking through

the glass at Suite Level Club.

Area 1 – Shot of Suite fronts from roof of

Stadium Suite.

Area 1 – Curtainwall framing installation at

south face of Club Areas.

Concourse Level Area 1 – Masonry

installation continues on Concourse

Buildings.

Field Level Area 3 – Installation of cast-in-

place risers continue on east side.

Field Level Area 3 – Upper dock slab edge

formwork is installed.