life - 10/21/09 - lsc-cyfair new construction update

13
New Facilities/Construct ion Update Lone Star College - CyFair

Upload: lsc-cyfair-library-life-workshops

Post on 13-Jun-2015

460 views

Category:

Education


3 download

TRANSCRIPT

Page 1: LIFE - 10/21/09 - LSC-CyFair New Construction Update

New Facilities/Constructio

nUpdate

Lone Star College - CyFair

Page 2: LIFE - 10/21/09 - LSC-CyFair New Construction Update

TIMELINE

• Bond Referendum Approved – May, 2008• Programming/Planning Phase – Oct., 2008

– Feb., 2009• Design Phase – Feb., 2009 – Feb., 2010• Construction Phase – Feb., 2010 – July, 2011• First Use – Fall Semester, 2011

Page 3: LIFE - 10/21/09 - LSC-CyFair New Construction Update

New Buildings/Renovations

• Academic /Student Services Building– To be located west of current LRNC Building– Description• 138,937 SF• 44 Classrooms• 10 Computer Labs• Offices – 3 Faculty Suites, 1 Dean Suite, 1 CE Suite• Student Services – Approx. 38,000 SF with Areas for

Advising, Counseling, Registration, Assessment, Financial Aid, and Payment Services

Page 4: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Academic/Student Svcs Building

Page 5: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Science Building

• To be located east of current HSC building• Description– 52,809 SF– 7 Science Labs– 4 Computer Labs– 15 Classrooms– Offices – 1 Faculty Suite

Page 6: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Science Building

Page 7: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Student Activity Area Renovation

• Renovation of current student services area• Description– 18,000 SF– Zones – Student Government Offices, Staff

Offices, Recreational/Game Area, TV Area, Meeting Rooms

Page 8: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Student Activity Area Renovation

Page 9: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Student Activity Area Renovation

Page 10: LIFE - 10/21/09 - LSC-CyFair New Construction Update

New Center

• Full service, 2nd offsite center• Description– Location – Clay Road/Fry Road Area– 83,918 SF– 14 Classrooms– 8 Computer Labs– 4 Workforce Training Labs– Offices – 2 Faculty Suites– 600 Parking Spaces

Page 11: LIFE - 10/21/09 - LSC-CyFair New Construction Update

New Center

Page 12: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Additional Parking/Infrastructure

• Description– 1,200 New Parking Spaces– New Road– Campus Core/Landscaping• Green Space• Community Garden

Page 13: LIFE - 10/21/09 - LSC-CyFair New Construction Update

Long Range Master Plan