construction project status report alderman library …€¦ · capital construction &...
TRANSCRIPT
FACILITIES MANAGEMENT J anuary 31 , 2020 Capi t a l Con st ru ct ion & Renovat ions Repor t No. 01
CONSTRUCTION PROJECT STATUS REPORT Alderman Library Renewal
160 McCormick Road
Architect: HBRA Architects, Chicago Construction Manager: Skanska USA Building, Inc, Durham
Current Status:
Current Activities Metal shelving being removed and recycled, 50% complete New and Old Stacks abatement start, 5% complete Site fencing, signage, and mark Newcomb Road, 70% complete
Near Future Activities Set construction trailer Install gates Start site utilities
Package 1 (Demo, Site, Abate) NTP January 23, 2020 Alderman Library closes for two years May 9, 2020 Full construction activities start June 8, 2020 Partial library reopens Fall Semester 2022 Construction complete December 2022 Percent complete now 0.5%
FM CC&R Project Team Please feel free to contact any of our team with questions or comments. Kit Meyer 434-531-7094 * Charles Durrer 434-962-4084 * Jesse Kidd 434-987-2170 * Henry Hull 434-270-1574
[email protected] [email protected] [email protected] [email protected]
1. Historic photo showing the 4th
floor reference room in 1939,the year that Alderman Libraryopened.
2. 2019 photo showing the currentcondition of the 4th floorreference room.
3. Rendering of the same roomwith sprinklers, code upgraddes,and original features restored.
Consider clicking on the icons above to follow the project on Twitter or Instagram for up to date construction photos.