concreting works
TRANSCRIPT
-
8/17/2019 Concreting Works
1/42
Quality Control
for
Concrete Works
-
8/17/2019 Concreting Works
2/42
Contents
1. What is Quality
2. Importance of Quality
3. Stages of Quality Control in Concrete Works
a) Pre Pour Stage
b) During Pour Stage
c) Post Pour Stage
4. Responsibilities
-
8/17/2019 Concreting Works
3/42
What Is Quality
What is Quality
The term “QUALITY” has been defined as the totality
of features and characteristics of a product or services
that bear on its ability to satisfy stated or implied
needs.
-
8/17/2019 Concreting Works
4/42
What Is Quality
What is Quality Assurance
All those planned and systematic actions necessary to
provide adequate confidence that a product or
service will satisfy given requirements for quality.
It usually requires a continuous evaluation of factors
that affect the adequacy of the design or specificationfor intended applications, verifications and audits of
production, installation and inspection operations and
adequate documentation.
-
8/17/2019 Concreting Works
5/42
What Is Quality
What is Quality Control
The operational techniques and activities that are
used to fulfill requirements for quality.
These Operational techniques are defined in quality
assurance stage
-
8/17/2019 Concreting Works
6/42
Importance of Quality
Why do we need Quality in Construction
The most essential aspects in any construction are to
achieve-
o Strength
o Serviceability &
o Durability
-
8/17/2019 Concreting Works
7/42
Importance of Quality
Why do we need Quality in Construction
So to attain these aspects of construction we should
follow some set of norms as prescribed through
specifications, standards, codes of practice, standard
construction practice etc…
To avoid any delay or reworks which requires Moneyand Time which are very vital for a contractor
-
8/17/2019 Concreting Works
8/42
Importance of Quality
Why do we need Quality in Construction
Structures can stand with good quality construction
even though there is marginal deficiency in design
But
Good design cannot prevent failure of structures if
the construction quality is poor
-
8/17/2019 Concreting Works
9/42
Stages of Quality Control in Concrete Works
Stages of Quality Control in Concrete Works
a) Pre Pour Stage
b) During Pour Stage
c) Post Pour Stage
-
8/17/2019 Concreting Works
10/42
Pre Pour Stage
Pre Pour Stage
To eliminate any undesired results after concreting
following norms are to be followed before starting
any concreting…
-
8/17/2019 Concreting Works
11/42
Pre Pour Stage
Pre Pour Stage
Ensure all approvals for construction, IFC drawings, Safety
Norms, Work Method Statements are in place before starting
any activity at site.
-
8/17/2019 Concreting Works
12/42
Pre Pour Stage
Pre Pour Stage
Before starting any new
activity all concerned persons
should be made familiar with
the sequences of activities to
complete the work in safe &
proper way with optimumutilization of resources by the
way of toolbox talks.
-
8/17/2019 Concreting Works
13/42
Pre Pour Stage
Pre Pour Stage
Ensure all prerequisites like termite control, Screed concrete
waterproofing works are completes and signed off from
consultant to proceed further stage of work.
-
8/17/2019 Concreting Works
14/42
Stages of Quality Control in Concrete Works
Coordinate Making
Mark coordinates, grid
lines, opening and
element dimensions,
on the screed concrete
before starting fixing
of rebars as per IFC.
-
8/17/2019 Concreting Works
15/42
Pre Pour Stage
Rebar Works
Ensure rebars are fixed
as per Bar Bending
Schedule or shop
drawing with proper
cover, extra bars as per
general reinforcementdrawings,
-
8/17/2019 Concreting Works
16/42
Pre Pour Stage
-
8/17/2019 Concreting Works
17/42
Pre Pour Stage
Rebar Works
Use proper supporting
system to support
vertical rebars in place
Proper platforms shall
be used for fixing of reinforcement
-
8/17/2019 Concreting Works
18/42
Pre Pour Stage
Formwork
Formwork shall be
fabricated as per
approved formwork
details with all
accessories fixed in
position as permanufacturer
recommendations
-
8/17/2019 Concreting Works
19/42
Pre Pour Stage
Formwork
-
8/17/2019 Concreting Works
20/42
Pre Pour Stage
Formwork
Apply uniformly approved
Form releasing agent toshutter before fixing in
position
-
8/17/2019 Concreting Works
21/42
Pre Pour Stage
Formwork
Tie rods must be provided exactly in same number and
position as per manufacture recommendations
Cones and sleeves used in tie rod are be sealed perfectly with
masking taps as this is most vulnerable for leakage.
-
8/17/2019 Concreting Works
22/42
Pre Pour Stage
Formwork
-
8/17/2019 Concreting Works
23/42
Pre Pour Stage
Formwork
All Joints are to be
properly sealed with foamsheet to prevent any gout
loss
-
8/17/2019 Concreting Works
24/42
Pre Pour Stage
Formwork
Adequate support shall
be provided to supportthe formwork in position
and avoid bulging
-
8/17/2019 Concreting Works
25/42
Pre Pour Stage
Formwork
After completion of
shuttering in all respectsformwork should be
checked for alignment
plumb, dimension, cover
and inserts if any.
-
8/17/2019 Concreting Works
26/42
Pre Pour Stage
Formwork
Proper scaffoldings and
platforms shall beprovided to place the
concrete, so that no
workers will use the form
work as platform forconcreting
-
8/17/2019 Concreting Works
27/42
Pre Pour Stage
Formwork
Construction activities are to be inspected by QC Engineer
during execution and suggest for any corrections
Before starting concreting activates works are to be cleared by
MEP and approving authority
-
8/17/2019 Concreting Works
28/42
During Pour Stage
Concreting Activities
Clean the area ready for
concrete prior to concreteby air jet and ensure area
is clean and dry before
concrete
-
8/17/2019 Concreting Works
29/42
During Pour Stage
Concreting Activities
o Ensure adequate equipment like viberator trowels screeds
etc., are available before starting concrete activities .o Only trained Forman and works should be engaged for
concrete operations.
o Sufficient number of carpenters must be available for
checking and tightening the tie rods.o Ensure adequate curing facilities are available before
starting concrete.
-
8/17/2019 Concreting Works
30/42
-
8/17/2019 Concreting Works
31/42
During Pour Stage
Concreting Activities
-
8/17/2019 Concreting Works
32/42
During Pour Stage
Concreting Activities
o Ensure concrete is done from height of 1.5 m. grater height may
lead to honeycomb and segregation.o Concrete must be done in layers in not more than 600mm in
height.
o Either sides of the opening shall be equally filled and vibrated to
prevent dislocation of formwork at openings.
o Correct concrete slump must be ensured to prevent
honeycombing and segregation.
o excessive vibration will lead to bleeding of concrete and disturb
the stability of form work to greater extent.
-
8/17/2019 Concreting Works
33/42
During Pour Stage
Concreting Activities
-
8/17/2019 Concreting Works
34/42
During Pour Stage
Concreting Activities
-
8/17/2019 Concreting Works
35/42
During Pour Stage
Concreting Activities
o The carpenters must be slightly hammering the forms with rubber
mallets during concrete to obtain a smooth surface.o The concrete pour rate must not exceed the formwork design
criteria
o Any addition of water in concrete transit mixer for workability
should be strictly restrained. Such act shall lead to segregation of
concrete and result in excessive honeycombs
o For the areas where reinforcement congestion is encountered it is
recommended to use self-compacting concrete rather than
vibrating the normal concrete excessively
-
8/17/2019 Concreting Works
36/42
Post Pour Stage
Post Pour Stage
o Check plumb for vertical elements and adjust if necessary
while concrete is still green.o Curing must commence immediately using water/ approved
curing compound.
o Any minor deformities / honey-combings observed must be
immediately repaired as per approved repair methodologyand with approved repair material .
-
8/17/2019 Concreting Works
37/42
Post Pour Stage
Post Pour Stage
Ensure shutter are
properly cleaned oiledsoon after stripping for
further use
-
8/17/2019 Concreting Works
38/42
Post Pour Stage
Post Pour Stage
Coordinates must be
checked and as built mustbe prepared to confirm
there is no deviation
-
8/17/2019 Concreting Works
39/42
Responsibilities
QA/QC Engineer
o Check work under execution from time to time for any
corrective measures that may be required to avoid reworks.
o Rise NCR in the event of any deviations.
o Provide Tool Box Talks on all new activities to all concernedpersons to make them familiar with the sequences of
activities to complete the work in safe & proper way with
optimum utilization of resources.
-
8/17/2019 Concreting Works
40/42
Responsibilities
Construction Manager
o Arrange material and man power for execution of works without
any hindranceo Provide toolbox talks to all concerned persons to make them
familiar with the sequences of activities to complete the work in
safe & proper way with optimum utilization of resources.
o Address all comments made by QC Engineer in preliminary
inspection prior to consultants inspection.o shall be thorough in all the IFC Drawings, shop drawings, Method
statement and normal construction practices etc.,
-
8/17/2019 Concreting Works
41/42
Responsibilities
Project Manager
o Take corrective action immediately after receipt of internal
NCR.
o NCRs should be addressed / closed by all concerned within 3
days.
o In addition, preventive measures / Lesson learnt to be
implemented to avoid the recurrence.
-
8/17/2019 Concreting Works
42/42
THANK YOU