concreting works

Upload: cdnaveen

Post on 06-Jul-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/17/2019 Concreting Works

    1/42

    Quality Control

    for

    Concrete Works

  • 8/17/2019 Concreting Works

    2/42

    Contents

    1. What is Quality

    2. Importance of Quality

    3. Stages of Quality Control in Concrete Works

    a) Pre Pour Stage

    b) During Pour Stage

    c) Post Pour Stage

    4. Responsibilities

  • 8/17/2019 Concreting Works

    3/42

    What Is Quality

    What is Quality

    The term  “QUALITY” has been defined as the totality

    of features and characteristics of a product or services

    that bear on its ability to satisfy stated or implied

    needs.

  • 8/17/2019 Concreting Works

    4/42

    What Is Quality

    What is Quality Assurance

    All those planned and systematic actions necessary to

    provide adequate confidence that a product or

    service will satisfy given requirements for quality.

    It usually requires a continuous evaluation of factors

    that affect the adequacy of the design or specificationfor intended applications, verifications and audits of 

    production, installation and inspection operations and

    adequate documentation.

  • 8/17/2019 Concreting Works

    5/42

    What Is Quality

    What is Quality Control

    The operational techniques and activities that are

    used to fulfill requirements for quality.

    These Operational techniques are defined in quality

    assurance stage

  • 8/17/2019 Concreting Works

    6/42

    Importance of Quality

    Why do we need Quality in Construction

    The most essential aspects in any construction are to

    achieve-

    o   Strength

    o   Serviceability &

    o   Durability

  • 8/17/2019 Concreting Works

    7/42

    Importance of Quality

    Why do we need Quality in Construction

    So to attain these aspects of construction we should

    follow some set of norms as prescribed through

    specifications, standards, codes of practice, standard

    construction practice etc…

    To avoid any delay or reworks which requires Moneyand Time which are very vital for a contractor

  • 8/17/2019 Concreting Works

    8/42

    Importance of Quality

    Why do we need Quality in Construction

    Structures can stand with good quality construction

    even though there is marginal deficiency in design

    But

    Good design cannot prevent failure of structures if 

    the construction quality is poor

  • 8/17/2019 Concreting Works

    9/42

    Stages of Quality Control in Concrete Works

    Stages of Quality Control in Concrete Works

    a) Pre Pour Stage

    b) During Pour Stage

    c) Post Pour Stage

  • 8/17/2019 Concreting Works

    10/42

    Pre Pour Stage

    Pre Pour Stage

    To eliminate any undesired results after concreting

    following norms are to be followed before starting

    any concreting…

  • 8/17/2019 Concreting Works

    11/42

    Pre Pour Stage

    Pre Pour Stage

    Ensure all approvals for construction, IFC drawings, Safety

    Norms, Work Method Statements are in place before starting

    any activity at site.

  • 8/17/2019 Concreting Works

    12/42

    Pre Pour Stage

    Pre Pour Stage

    Before starting any new

    activity all concerned persons

    should be made familiar with

    the sequences of activities to

    complete the work in safe &

    proper way with optimumutilization of resources by the

    way of toolbox talks.

  • 8/17/2019 Concreting Works

    13/42

    Pre Pour Stage

    Pre Pour Stage

    Ensure all prerequisites like termite control, Screed concrete

    waterproofing works are completes and signed off from

    consultant to proceed further stage of work.

  • 8/17/2019 Concreting Works

    14/42

    Stages of Quality Control in Concrete Works

    Coordinate Making

    Mark coordinates, grid

    lines, opening and

    element dimensions,

    on the screed concrete

    before starting fixing

    of rebars as per IFC.

  • 8/17/2019 Concreting Works

    15/42

    Pre Pour Stage

    Rebar Works

    Ensure rebars are fixed

    as per Bar Bending

    Schedule or shop

    drawing with proper

    cover, extra bars as per

    general reinforcementdrawings,

  • 8/17/2019 Concreting Works

    16/42

    Pre Pour Stage

  • 8/17/2019 Concreting Works

    17/42

    Pre Pour Stage

    Rebar Works

    Use proper supporting

    system to support

    vertical rebars in place

    Proper platforms shall

    be used for fixing of reinforcement

  • 8/17/2019 Concreting Works

    18/42

    Pre Pour Stage

    Formwork

    Formwork shall be

    fabricated as per

    approved formwork

    details with all

    accessories fixed in

    position as permanufacturer

    recommendations

  • 8/17/2019 Concreting Works

    19/42

    Pre Pour Stage

    Formwork

  • 8/17/2019 Concreting Works

    20/42

    Pre Pour Stage

    Formwork

    Apply uniformly approved

    Form releasing agent toshutter before fixing in

    position

  • 8/17/2019 Concreting Works

    21/42

    Pre Pour Stage

    Formwork

    Tie rods must be provided exactly in same number and

    position as per manufacture recommendations

    Cones and sleeves used in tie rod are be sealed perfectly with

    masking taps as this is most vulnerable for leakage.

  • 8/17/2019 Concreting Works

    22/42

    Pre Pour Stage

    Formwork

  • 8/17/2019 Concreting Works

    23/42

    Pre Pour Stage

    Formwork

    All Joints are to be

    properly sealed with foamsheet to prevent any gout

    loss

  • 8/17/2019 Concreting Works

    24/42

    Pre Pour Stage

    Formwork

    Adequate support shall

    be provided to supportthe formwork in position

    and avoid bulging

  • 8/17/2019 Concreting Works

    25/42

    Pre Pour Stage

    Formwork

    After completion of 

    shuttering in all respectsformwork should be

    checked for alignment

    plumb, dimension, cover

    and inserts if any.

  • 8/17/2019 Concreting Works

    26/42

    Pre Pour Stage

    Formwork

    Proper scaffoldings and

    platforms shall beprovided to place the

    concrete, so that no

    workers will use the form

    work as platform forconcreting

  • 8/17/2019 Concreting Works

    27/42

    Pre Pour Stage

    Formwork

    Construction activities are to be inspected by QC Engineer

    during execution and suggest for any corrections

    Before starting concreting activates works are to be cleared by

    MEP and approving authority

  • 8/17/2019 Concreting Works

    28/42

    During Pour Stage

    Concreting Activities

    Clean the area ready for

    concrete prior to concreteby air jet and ensure area

    is clean and dry before

    concrete

  • 8/17/2019 Concreting Works

    29/42

    During Pour Stage

    Concreting Activities

    o   Ensure adequate equipment like viberator trowels screeds

    etc., are available before starting concrete activities .o   Only trained Forman and works should be engaged for

    concrete operations.

    o   Sufficient number of carpenters must be available for

    checking and tightening the tie rods.o   Ensure adequate curing facilities are available before

    starting concrete.

  • 8/17/2019 Concreting Works

    30/42

  • 8/17/2019 Concreting Works

    31/42

    During Pour Stage

    Concreting Activities

  • 8/17/2019 Concreting Works

    32/42

    During Pour Stage

    Concreting Activities

    o   Ensure concrete is done from height of 1.5 m. grater height may

    lead to honeycomb and segregation.o  Concrete must be done in layers in not more than 600mm in

    height.

    o   Either sides of the opening shall be equally filled and vibrated to

    prevent dislocation of formwork at openings.

    o   Correct concrete slump must be ensured to prevent

    honeycombing and segregation.

    o   excessive vibration will lead to bleeding of concrete and disturb

    the stability of form work to greater extent.

  • 8/17/2019 Concreting Works

    33/42

    During Pour Stage

    Concreting Activities

  • 8/17/2019 Concreting Works

    34/42

    During Pour Stage

    Concreting Activities

  • 8/17/2019 Concreting Works

    35/42

    During Pour Stage

    Concreting Activities

    o   The carpenters must be slightly hammering the forms with rubber

    mallets during concrete to obtain a smooth surface.o  The concrete pour rate must not exceed the formwork design

    criteria

    o  Any addition of water in concrete transit mixer for workability

    should be strictly restrained. Such act shall lead to segregation of 

    concrete and result in excessive honeycombs

    o   For the areas where reinforcement congestion is encountered it is

    recommended to use self-compacting concrete rather than

    vibrating the normal concrete excessively

  • 8/17/2019 Concreting Works

    36/42

    Post Pour Stage

    Post Pour Stage

    o  Check plumb for vertical elements and adjust if necessary

    while concrete is still green.o   Curing must commence immediately using water/ approved

    curing compound.

    o  Any minor deformities / honey-combings observed must be

    immediately repaired as per approved repair methodologyand with approved repair material .

  • 8/17/2019 Concreting Works

    37/42

    Post Pour Stage

    Post Pour Stage

    Ensure shutter are

    properly cleaned oiledsoon after stripping for

    further use

  • 8/17/2019 Concreting Works

    38/42

    Post Pour Stage

    Post Pour Stage

    Coordinates must be

    checked and as built mustbe prepared to confirm

    there is no deviation

  • 8/17/2019 Concreting Works

    39/42

    Responsibilities

    QA/QC Engineer

    o   Check work under execution from time to time for any

    corrective measures that may be required to avoid reworks.

    o   Rise NCR in the event of any deviations.

    o  Provide Tool Box Talks on all new activities to all concernedpersons to make them familiar with the sequences of 

    activities to complete the work in safe & proper way with

    optimum utilization of resources.

  • 8/17/2019 Concreting Works

    40/42

    Responsibilities

    Construction Manager

    o   Arrange material and man power for execution of works without

    any hindranceo   Provide toolbox talks to all concerned persons to make them

    familiar with the sequences of activities to complete the work in

    safe & proper way with optimum utilization of resources.

    o   Address all comments made by QC Engineer in preliminary

    inspection prior to consultants inspection.o   shall be thorough in all the IFC Drawings, shop drawings, Method

    statement and normal construction practices etc.,

  • 8/17/2019 Concreting Works

    41/42

    Responsibilities

    Project Manager

    o  Take corrective action immediately after receipt of internal

    NCR.

    o   NCRs should be addressed / closed by all concerned within 3

    days.

    o   In addition, preventive measures / Lesson learnt to be

    implemented to avoid the recurrence.

  • 8/17/2019 Concreting Works

    42/42

    THANK YOU