Columbia County Road Department. Work Performed By County Road Crews. Ditching. Road Grading. Bridge Repair. Culvert Replacement. Herbicide Application. Chip Seal. 39 Miles in 2012. Excavation. Clear Debris From Landslides and Floods. We Move Snow. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/1.jpg)
Columbia County Road Department
![Page 2: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/2.jpg)
Ditching
Road Grading
Work Performed By County Road Crews
![Page 3: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/3.jpg)
Bridge Repair
Culvert Replacement
![Page 4: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/4.jpg)
Herbicide Application
![Page 5: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/5.jpg)
Chip Seal
39 Miles in 2012
![Page 6: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/6.jpg)
Excavation
![Page 7: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/7.jpg)
Clear Debris From Landslides and
Floods
![Page 8: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/8.jpg)
We Move Snow
and apply sand and anti-ice chemicals
![Page 9: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/9.jpg)
Storm Damage Removal
![Page 10: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/10.jpg)
Earthquake Preparation and
Recovery
![Page 11: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/11.jpg)
Other Tasks Performed By The Road Department
• Signs and Striping
• Roadside Vegetation
• Pothole Repair
• Paving
• Equipment Repair
• Building Repair
• Regulation and Permitting
![Page 12: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/12.jpg)
Columbia County Road Department Personnel & Mileage• EMPLOYEES: Road Maintenance 13 (includes supervisors)
Mechanics 2 Signs 1
Office 5Total 21 (25.5 in 2011)
– COUNTY ROAD MILES: Paved Gravel Total Employees Miles
/Emp– Clatskanie District 79 55 135 3
45– Rainier District 111 43 153 4
38– St. Helens District 147 32 179 4
45*– Vernonia District 52 34 85 2
42
– Total 389 164 553 If all the Columbia County Roads were placed end to end they would reach from St. Helens to Reno NV.
* St. Helens crew performs all centerline striping and herbicide application for all districts
![Page 13: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/13.jpg)
2012 Revenues
78%
12%
1%
1%
8% Motor Vehicle FeesDepletion FeesO&C Timber PermitsFederal STP
$3,278,527
$314,381
$493,248
Total Revenue: $4,125,962
$27,843
$37,352
![Page 14: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/14.jpg)
2010-2011 Revenue Per Mile
Higher Revenue Per Mile than Columbia County
Lower Revenue Per Mile than Columbia County
![Page 15: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/15.jpg)
Expense CostPersonnel Salary (59%) $1,233,845 $2,097,412
Med Insurance (18%) $384,861PERS (15%) $312,155SS, W/C, Unemployment (8%) $166,551
Rock $150,000Asphalt $300,000Paint (for striping) $130,000Culvert, Herbicide, Anti-Ice, Signs, Supplies $105,000Fuel $220,000Equipment, Parts, Supplies & Repairs $225,000Utilities, Insurance, Admin, Other $388,000Bridges (Fishhawk, JP West & Pebble Cr Rds) $383,000*
Total $3,998,412
FY 2014 County Road Department Budget
* STP Fund Exchange through ODOT
![Page 16: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/16.jpg)
Recent Road Projects
![Page 17: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/17.jpg)
Canaan Rd Guard Rail
Before
After
Total Cost: $494,000
Grant: $345,000
![Page 18: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/18.jpg)
Nicolai Rd Overlay 2011
Total Cost: $500,000
4.6 Miles
![Page 19: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/19.jpg)
Brinn Rd, Cox Cr
Four Watershed Council Culvert Replacements
Cater Rd, Alder Cr
Cedar Cr Rd, Cedar Cr
Scappoose Vernonia Rd, Elk Cr
Cost: $73,000
![Page 20: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/20.jpg)
Scappoose Vernonia Road At Milepost 8
.
Repaired in 2011
Total Cost: $465,000
Grant: $390,000
![Page 21: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/21.jpg)
Nick Thomas Road Landslide
Repair and Construction To Start: June 2013
![Page 22: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/22.jpg)
Marshland – Midland Road Recycled Asphalt Resurfacing
5000 CY of Asphalt Grindings used on Midland District Rd
Before
After
![Page 23: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/23.jpg)
Eddings Road Culvert
Before
After
![Page 24: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/24.jpg)
Scappoose – Vernonia Road Landslide / Heaving
Walker Road Landslide
![Page 25: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/25.jpg)
Other Bridge Replacement Projects:
• JP West - 2014 - $1,425,000
• Coon Creek - 2014 - $2,915,000
• Pebble Creek - 2016 - $2,693,000
County Bridge Inventory:
93 bridges
Total Cost: $921,000
Grant: $820,000
Total Cost: $1,624,000
Grant: $1,477,000
Hudson Park Bridge
Fishhawk Bridge
![Page 26: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/26.jpg)
Very Poor
Poor
Fair
Good
Very Good
Preventive Maintenance
Corrective Maintenance
Heavy Resurfacing
Reconstruction
$50 K
$120 K
$200 K
$360 K
10 Yrs 20 Yrs
Pavement Life Cycle
![Page 27: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/27.jpg)
Very Good
Typical Time
Maintenance Strategies
Heavy Resurfacing
Good
Fair
Poor
Very Poor $200,000 /
RM$200,000 / RM
Heavy Resurfacing
Total Spent on Preventative Maintenance: $150,000 /RM
Total Spent on Heavy Resurfacing: $400,000 / RM
30 Yrs
15 Yrs
![Page 28: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/28.jpg)
Ilmari Road Haven Acres Road
Mayger Road
Poor Roads
![Page 29: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/29.jpg)
Tide Creek Road
Lentz Road Conyers Creek Road
More Poor Roads
![Page 30: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/30.jpg)
Apiary Culvert Replacement
![Page 31: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/31.jpg)
Apiary Culvert Replacement
Today
Poor Roads, Poor Funding,
But we will work safe, hard, and effective to perform good work …
![Page 32: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/32.jpg)
… and with a smile!
![Page 33: Columbia County Road Department](https://reader036.vdocuments.us/reader036/viewer/2022062502/56814acd550346895db7e559/html5/thumbnails/33.jpg)
Have a Great Day!