collaboration mtg cotober 11, 2000 installation status opening remarks overview, logistics recent...
TRANSCRIPT
DD
Collaboration MtgCotober 11, 2000
Installation Status
• Opening Remarks• Overview, logistics• Recent events, status• Outlook, concerns• Conclusions
Jon KotcherCollaboration Meeting
October 11, 2000
DD
Collaboration MtgCotober 11, 2000
Opening Remarks
Installation/detector evolving very nicely Huge progress on many fronts
Detectors delivered/mounted Critical electrical & mechanical infrastructure
installed – necessary ingredients Cabling of all flavors (delicate, tricky) Electronics (deliveries will remain problem) Commissioning! (J. Yu)
Focus of hardware upgrade almost completely at DAB (SMT finishing up)
Tight organization, working well together We are all indebted to excellent support
staff Buy them a cigar, cognac sometime…
Much left to do in time allotted Some of it detailed work that can only go so
quickly without unacceptable amount of risk Not without concerns for March 1 startup
Will discuss later in talk
Two major “innovations” have opened up our ability to progress rapidly:
Split silicon into two halves Put large pieces in place on final installation
“runways” as early as possible EF irons on platform, EMC trusses brought
down to pit (Awaited delivery of CFT)
DD
Collaboration MtgCotober 11, 2000
Since NIU Workshop
Fiber Tracker installed Thu/Fri, June 29-30 Transport from Lab 3, light-tighting in Hi
Bay, insertion into bore, transfer to final mounts
Went very smoothly Used 2 days of the 2 wks we’d allotted
Surveyed into position CFT well-centered on solenoid, axially and
transversely Solenoid ~ 5/8” south
– Critical area, need clearance for CFT/CPS/CFT waveguides
– Sophisticated “putty test” in inter-cryostat gap demonstrated ample space – quite definitive
Kudos to D0 Mechanical Group, CFT Group Completion, installation represents major
technical achievement Starting gun for motion of large pieces back
into position… ECS on center beam Tues, July 11
Surveyed, repositioned, resurveyed, … Positioning constraints much tighter for Run 2
(beam pipe, silicon) Some outstanding issues remain
Cryogenic hookup, recabling of ECS, beryllium beam pipe placed in CFT Barrel 1
Bubble wrap, PVC, foam, purge
DD
Collaboration MtgCotober 11, 2000
Since NIU Workshop
After ECS, platform moved west, end irons picked up, returned 8/4 (one week – faster than anticipated)
Trusses brought down immediately thereafter, completed 8/15
VLPC cryostats installed 8/7, commissioned 8/17
Working very reliably, without incident Copper ground straps installed for electronic
noise Handful of production VLPC cassettes installed
to do waveguide checkout Data looks great – another important milestone
Waveguide installation ran into some snags Spatial constraints btwn calorimeters at outer
radius not properly accounted for 4:1 model made of entire face, incl silicon
cable runs Waveguide running on south face completed
this week A necessary prerequisite for SMT-S installation Actually will be ahead of schedule
Detailed modeling demonstrated need for more room for waveguides/silicon cables & services
Two inner H-disks will be moved 1.75” away from interaction point
Waveguide checkout continues, much progress Using kludged stereo boards for front end
DD
Collaboration MtgCotober 11, 2000
Since NIU Workshop
All Forward Muon detectors complete (Sep) Congratulations Dmitri, et al.
Forward Muon A-layer pixels and MDTs mounted
Manipulation, alignment of large pieces – manpower, effort
Mounting of full A-layer major accomplishment Has typically required iteration – a worry for
completion of full system Final articulating drawbridges not yet in place
C-layer north MDTs installed, being surveyed into position
Lead time for turnaround of survey information can be painful
C-layer north pixel plane assembled on shield wall
Quite impressive (go see it) Being surveyed, then “hung” into place on truss
after rear C-layer MDTs positioned Expect north truss ready to roll in to Collision
Hall mid Oct, south truss mid Nov Truss installation to Collision Hall begins Nov 13
Accelerator shutdown, warm up, low retraction
System is progressing, but engineering is proving to be a significant bottleneck
4.5 months ain’t much time…
DD
Collaboration MtgCotober 11, 2000
Since NIU Workshop
Calorimeter electronics arriving Almost 2 full quadrants of upgraded
electronics available Vendors an issue, as always
Purity of liquid argon in dewar 0.4 ppm test cell, stand-alone test cryostat measurements being taken now Ready to be used to fill cryostats
Thanks to G. Sajot & Co.! Considering filling prior to roll in
Purity monitoring & thermometry (C. Zeitnitz, Mainz), HV, electronics
Manpower, amount of activity an issue Will be discussed in Yu’s commissioning mtg
this week Beam loss monitors, radiation sensors, Run
1 luminosity counters installed in Collision Hall (NIKHEF, Brown, others)
Readout, feedback to accelerator Silicon is doing very well
Cabling of SMT-S finishing at SiDet within next two weeks
Expect SMT-S installed early November, SMT-N around Xmas
Noise, error rates on 70k channels at 10% test looks quite good
Talks by Zdrazil, Lehner on Friday
DD
Collaboration MtgCotober 11, 2000
Outlook, Concerns
Hardware: Both SMT half-barrels should be in before roll in
Won’t be necessary to do in Collision Hall B-layer pixels are in jeopardy
Design of mounting hardware not quite complete If late, will likely require roll out to complete
(crane) Would be a blow (detectors complete) - pushing
very hard Alignment, positioning accuracy of detector
elements far more stringent for Run 2 Beryllium beam pipe + bellows, silicon,
calorimeters… Difficult problem - much thought, survey
Amount of work in limited space, time Arrival of electronics for tracking & other
systems is very, very late Interface cards for silicon: start arriving mid-
Nov Adapter cards: partials Nov? Power supplies for CFT AFE: Feb 12 (partials?) 8-chip AFE boards for CFT: end Dec (RH), mid-
Jan (LH) 3-4 in hand til then, no partials 12-chip AFE (stereo, preshowers): Spring
Completion of CAL BLS motherboards: mid-Feb Level 2 trigger commissioned: 25 April
Alpha boards – smoke hasn’t settled here… Vendors a canonical problem – much work
focusing on expediting these orders, but… Robust economy is not helping us
DD
Collaboration MtgCotober 11, 2000
Outlook, Concerns
Impossible to overstate delicacy of silicon hookup
Final connection of low mass cable must be made one and only one time
Full checkout upstream of adapter card prior to hookup of detector
Detectors damaged, fried with little effort – has been proven in the field by other exp’ts
Electronics will be trickling in Dressing of inner cables very delicate,
convoluted Properly functioning interlocks an integral part
of process (complex system) Extreme care essential here Parallel activities a worry
Locked gate at intercryostat gap! Beginnings of commissioning team in place,
needs coalescing Si hookup will take a while – no corners can be
cut Need access to intercryostat gap, cathedral
Time allotted for detector commissioning time prior to roll in has all but disappeared
Replaced by electronics installation & hookup: Being synched to accelerator downtimes for
electronics installation & hookup in a system of this complexity will severely hamper our readiness for acquiring physics-quality data
Detector, front end, DAQ, online, trigger experts will be absolutely crucial
DD
Collaboration MtgCotober 11, 2000
Conclusions
D0 is doing extremely well, an excellent year for the hardware portion of upgrade
Si, CFT, Muon, Cal, infrastructure, online, commissioning
Systems are coming up, behaving as hoped in most cases
Serious, dedicated young people have been, and continue to be, instrumental in getting us there
Much remaining to do, activity in hall escalating organically – OK for moment, but approaching saturation
Spatial/temporal constraints may mean some things cannot get done prior to roll in
Pressure rapidly mounting Danger now is breaking something,
hurting somebody Taking appropriate care more important
than speed!
DD
Collaboration MtgCotober 11, 2000
Data Taking Position
Clamshells closed, shielding mid-piece extended, EF & calorimeters closed
DD
Collaboration MtgCotober 11, 2000
Calorimeter Access
Retraction of shielding mid-piece & EF travel allow access to region between calorimeters
FPS, ICD, LUM, SMT installation & cabling CFT cabling on face of CC Collision Hall access – servicing, repairs, etc.
EF travel only 42/47” for Run 2