    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SR

    Soil investigation

    The contractor shall implemented of exploratory drilling and Notemechanical test in all types of soil with on site testing and theissuance of the final report which contain the test results andrecommendations of the foundation work.

    01 Research and treatment for cavities

    Implementation through a perforating exploratory(cavity probing) In 1 M3

    all types of rock to determined the horizontal and vertical elongation

    of cavities, the contractor will be responsible for treatment all

    cavities By injection and treatment for all cavities and voids of rock

    with all necessary work accordance with the technical

    specifications and instructions of the Supervising engineer

    SITE DEVELOPMENT

    Earthworks, concrete works, water proofing, moisture Note

    protection for foundations works are measured in BOQ AP06

    The bidder is advised to visit the site before quoting the rates in

    order to get himself familiarized with the present site conditions

    Site clearance and demolitions

    02 Demolish and clear away existing structures, pavings, electrical 1 Item

    lighting, pavements or upstands, cut and plug or reroute existing

    service lines or utilities inside property line, clear site of rubbish orany impediments, loose top soil and as deemed necessary, for the

    total site cluster number 5 (CL05) area, approximately (23230m2),

    subject to engineer approval and as coordinated with public

    pension agency as shown on drawing CL05- XC-01

    To Collection SR

    RATEITEM D E S C R I P T I O N QTY UNIT

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    1 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    2/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    SITE GRADING

    Bulk excavate over site on unclassified ground including all hard Noteand rock layers to reduced levels generally in cutting profiles the

    work shall include clear away to approved disposals.

    All additional excavation required for temporary works and spaces, Note

    shoring, dewatering, removal of surplus excavated materials,

    support, temporary spoil heaps and general compaction

    EXCAVATION AND EARTHWORK

    Necessary moving or transportation about the site excavation

    material including handling to temporary stockpile or ultimate

    disposal off site is to be included in the unit rate of excavation

    SITE PREPARATION AND GRADING

    01 Excavation oversite on unclassified ground including all hard and 50 M3

    rock layers (if any) to reduced levels generally in cutting profiles

    and forming depressions, falls and the like and clear away to

    approved disposal tip.

    02 Fill oversite with approved imported fill material according to site 11000 M3

    soil report recommendation including compaction in making up

    levels to required formations, embankments, contouring and the

    like as per drawings and spec.

    Note

    Work on proposed structural built-up areas from part of the Work

    pertaining to respective building or structure as measured

    elsewhere.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    2 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    3/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    PAVING AND SURFACING

    01 Supply and install precast concrete shotblasted pavers (beige 3438 M2

    color) size 400x400x60mm thk.with photocatalytic titanium doxide

    coating including 100mm thick cast-in-place concrete slab with

    A193-WWF mesh reinforcement, 20mm thick cement mortar

    setting bed, moisture barrier on compacted subgrade, 3mm water

    proofing membrane on R.C. slab as per detail no A1 on drawing

    CL05-XL301 to suit required locations as shown on drawing

    CL05-XL101

    02 Supply and install precast concrete shotblasted pavers (beige, & 64 M2

    brown color) size 400x400x60mm thk.with photocatalytic titanium

    doxide coating including 100mm thick cast-in-place concrete slab

    with A193-WWF mesh reinforcement, 20mm thick cement mortarsetting bed, polyethylene moisture barrier, compacted subgrade,

    3mm water proofing membrane on R.C. slab as per detail no. A5

    on drawing CL05-XL301 to suit required locations as shown on

    drawin CL02-XL101

    03 Supply and install precast concrete shotblasted pavers (light grey 1749 M2

    & grey color) size 400x400x60mm thk.with photocatalytic titanium

    doxide coating including 100mm thick cast-in-place concrete slab

    with A193-WWF mesh reinforcement, 20mm thick cement mortar

    setting bed, polyethylene moisture barrier, compacted subgrade,

    3mm water proofing membrane on R.C. slab as per detail no. A6

    on drawing CL05-XL301 to suit required locations as shown on

    drawing CL05-XL101

    04 Supply and install precast concrete shotblasted pavers (beige & 649 M2

    light beige color) size 400x400x60mm thk w./grey color granite

    band size 200x200x30mm thk including 100mm thick cast-in-place

    concrete slab with A193-WWF mesh reinforcement, 20mm thick

    cement mortar setting bed, polyethylene moisture barrier,

    compacted subgrade, 3mm water proofing membrane on R.C. slab

    as per detail no. B3 on drawing CL05-XL301 to suit required

    locations as shown on drawing CL05-XL101

    05 Supply and install polished granite paving dark &light colors,size 380 M2

    400x400x30mm thk w.\ granite band dark color, size200x200x30mm including 100mm thick cast-in-place concrete slab

    with A193-WWF mesh reinforcement, 20mm thick cement mortar

    setting bed, polyethylene moisture barrier, compacted subgrade,

    3mm water proofing membrane as per detail no. C2

    on drawing CL05-XL301 to suit required locations as shown on

    drawing CL05-XL101

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    3 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    4/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    PAVING AND SURFACING

    01 Supply and install concrete screed with epoxy coat finish including 12690 M2

    100mm/50mm thick cast-in-place concrete slab with A193-WWF

    reinforcement mesh, polyethylene moisture barrier, compacted sub

    grade, 3mm water proofing membrane on R.C. slab as per detail

    no. D on drawing CL05-XL301 to suit required locations as shown

    on drawing CL05-XL101

    02 Supply and install 50mm thk rubber pavement green, blue , brown 120 M2

    & red color including adhesive mixture,100mm thick cast-in-place

    concrete slab with A193-WWF mesh reinforcement smooth finish,

    polyethylene moisture barrier, compacted subgrade, 3mm water

    proofing membrane on R.C. slab as per detail no. E4 on drawing

    CL05-XL301 to suit required locations as shown on drawingCL05-XL101

    03 Supply and install 80mm thick ( beige & grey) color, interlocking 1507 M2

    concrete pavers including 20mm thik cement ,mortar setting bed,

    compacted sand leveling course , compacted aggregate base

    course 150mm thick, cast in place concrete foundation, concrete

    edger compacted subgrade complete as per detail F8 on drawing

    CL05-XL301 to suit required locations as shown on drawing

    CL05-XL101

    04 Supply and install cast in place concrete paving with A193-WWF 22 M2

    mesh reinforcement, smooth finish light grey color, 100mm thick

    w.\ brick edge band size 200x200x60mm thick including 20mm

    thick cement mortar setting bed, polyethylene moisture barrier,

    compacted subgrade, 3mm water proofing membrane on R.C. slab

    as per detail no. G7 on drawing CL05-XL301 to suit required

    locations as shown on drawing CL05-XL101

    EARTH MOUNT

    05 Supply and formation of 500-1500 mm height earth mount including

    compacted sub base layer, 100 mmm thick layer of sand and

    gravel mix, and all required to complete and finish te work as

    shown on drawing CL05- XL101, and as per detail no. 5 on drawing

    CL05- XL302 and sections details 166 M2

    (Softscape and planting soil mix are measured elsewhere)(area

    measured on plan)

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    4 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    5/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    CURBS AND EDGING

    01 Supply and install precast concrete road curb, size 300X500X150 2728 Mmm with exposed aggregate finish including bedding, haunching,

    cast in place concrete base and concrete grout behind curb, 20mm

    thick cement mortar setting bed, on R.C. slab as per detail no.1 on

    drawing CL05-XL302 to suit required locations as shown on

    drawing CL05-XL101

    02 Supply and install precast concrete mowing edge, size 28 M

    200X100X65 mm including concrete base, 20mm thick cement

    mortar setting bed, cast in place concrete base on R.C. slab, as

    per detail no. 2 on drawing CL05-XL302 to suit required locations

    as shown on drawing CL05-XL101

    SUNDRIES

    TENSILE STRUCTURE

    03 Supply and install tensile staructure comprising columns, tent

    fabric, foundation, earthwork, and all required to compleet and fix

    the work as shown on drawing CL05- XL101 and as per detail no. 3

    on drawing CL05- XL302, and section details and as per

    manufacturer's recommendations and subject to engineer's

    approoval to cover an area of 80 m2 . Contractor shall submitt shop

    drawings for approval before supply 1 No.

    Wooden Shade Structure

    04 Supply and install wooden shade staructure comprising 200200mm

    artificial wooden post, 100200 mm wooden beams , foundation,

    earthwork, and all required to compleet and fix the work as per

    deatail 6 on drawing XL302 and manufacturer's recommendations

    and subject to engineer's approoval to cover an area of 90 m2 . 1 No.

    Contractor shall submitt shop drawings for approval before supply

    Wooden Bench

    05 Supply and install wooden bench comprising concrete walls,reinforced concrete slab with A 193 W.W.F reinforcement mesh

    smooth finished including footings, waterproofing membrane, joint

    filler, 50x75 mm interior wooden rails, including earthworks,

    insulation, finishing, fixing, and all required to complete the work

    as per detail no.4 on drawing CL5- XL302 30 M2

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    5 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    6/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    Manufacturer's standard outdoor sings, letters and plaques

    including fixings, finishes, accessories complete as per

    details on drawing CL05-XL601,602 and as per specifications

    01 Ref. type 1 ( RESIDENTIAL SIGN ) 6 No.

    02 Ref. type 2 ( DIRECTIONAL SIGN ) 4 No.

    03 Ref. type 3 ( CENTRAL PLAZZA SIGN ) 1 No.

    04 Ref. type 4 ( ADVERTISING PANEL ) 2 No.

    Manufacturer's standard outdoor sings, letters and plaques

    including fixings, finishes, accessories complete as perdetails on drawing CL05-XC-05, CL05-XC-06 and as per

    specifications

    INFORMATIVE SIGNS

    05 Ref. type I-1 ( PARKING ) 3 No.

    06 Ref. type I-2 ( ENTRY ) 6 No.

    REGULATORY SIGNS

    07 Ref. type R2-1 (GIVE WAY ) 9 No.

    08 Ref. type R5-1 ( ENTRY PROHIBTED ) 11 No.

    09 Ref. type R 8-1 ( NO LEFT TURN ) 2 No.

    10 Ref. type R 17-6 (MANDATORY MOVEMENT - L ) 1 No.

    WARNING SIGNS

    11 Ref. type W11-1 ( PEDESTRAIN CROSSING ) 17 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    6 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    7/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    ROAD SIGNAGE & PAVEMENTMARKING

    Thermoplastic paint for traffic marking on drive way atbasement/ground floor and ramps floor as per

    Manufacturer's standard as shown on details on drawing

    CL05-XC-06, to suit required locations as shown on drawing

    CL02-XC-05, as per specification and as per engineer's

    instructions

    pavement marking

    01 Straight arrows 42 No.

    02 Straight & curved arrows 5 No.

    03 Curved arrows 11 No.

    04 Handicapped marking on floor 3 No.

    05 Parking lane marking 2170 M

    06 White stop line 70 M

    07 Pedestrain crossing 122 M

    08 Lane marking 910 M

    09 White edge line 810 M

    10 Dotted ( give way line ) 1010 M

    11 Speed control hump including cut & removal of existing wearing 25 M

    (0.05m) course & add a new course, tack coat and 0.10m of

    bituminous wearing course, ref. 10 detail G

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    7 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    8/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    LANDSCAPING

    Trees including pit excavation, stakes and ties, soilplanting mix, mulching, filter membrane and drainage

    layer all as details and planting schedule as per detail

    P1 on drawing CL05-XL-401

    01 T/Af 16 No.

    02 T/Fm 32 No.

    03 T/Po 2 No.

    Shrubs including planting, site excavation as required, soilplanting mix, mulching, filter membrane, screed sloped to

    drain and drainage layer all as per details and planting

    schedule as per detail P3 on drawing CL05-XL-401

    04 S/Hs 107 No.

    05 S/Mc 78 No.

    06 S/Pav 18 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    8 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    9/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    LANDSCAPING

    Ground cover including planting, site excavation asrequired, soil planting mix, mulching, filter membrane,

    screed sloped to drain and drainage layer all as per details

    and planting schedule as per detail P2, on drawing

    CL05-XL-401

    01 G/As 1509 No.

    02 G/Ggp 1725 No.

    03 G/Gr (Y) 493 No.

    04 G/Cm (W) 565 No.

    Lawn planting, including soil planting mix, filter membrane

    and drainage layer, screed sloped to drain all as per details

    and planting schedule as per detail P3 on drawing

    CL05-XL-401

    05 L/Cd 487 M2

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    9 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    10/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    PLUMBING INSTALLATION

    WASTE AND DRAINAGE INSTALLATION

    Supply, install and testing pipework, UPVC schedule 40, the

    work shall include but not limited to fittings, supports, cast

    iron pipes on roof for vent with caps, installation, all

    associate works and all materials and equipments required

    to complete and finish the work according to drawings,

    specification and code of practices

    01 100 mm dia. 60 M

    02 150 mm dia. 315 M

    03 200 mm dia. 90 M

    Construction work for briks inspection chamber, the work

    shall include bit not limited to earth work, plain concrete

    for foundation BED, concrete channel at chamber DED with

    standard cast iron manhole frame and double cover and all

    materials and equipments required to complete and finish

    the work according to specifications, drawings and code of

    practice

    04 Inspection chamber, ref. (IC) 600x600mm 4 No

    05 Inspection chamber, ref. (STIC) 600x600mm 6 No

    WASTE AND DRAINAGE INSTALLATION

    Supply, installation and test drainage pipe work UPVC

    schedule 80 the work shall include but not limited to fittings,

    supports hangers, excavation, backfilling, cast iron pipes on

    roof for vent with caps and all materials and equipment

    required to complete and finish the work according to

    specifiactions, drawings and code of practice

    06 100 mm dia 50 M

    Construction work for briks inspection chamber, the work shall

    include bit not limited to earth work, plain concrete for

    foundation BED, concrete channel at chamber DED with

    standard cast iron manhole frame and double cover, UPVCpipework schedule 40 to nearest main sewer manhole and all

    materials and equipments required to complete and finish the

    work according to specifications, drawings and code of practice

    07 Slow down chamber 5 No

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    10 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    11/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    PLUMBING INSTALLATION

    Reinforced concrete under ground water tank and pumproom with required capacity proprietary cast iron manhole

    covers and frames, including (concrete work & earthwork,

    water proofing) internal lining access ladders, pipework

    submersible pump, ventilating fans with exhaust and fresh

    air pipework, valves, vent pipes and truck fill pipework as

    detailed on drawings

    01 Fire Water tank 1 No.

    MANHOLE AND COVERS

    Supply , install, testing and commissioning precast

    concrete sewer manholes with standard traffic (heavy duty)

    type cast iron manhole covers and frames, access ladders,concrete channel at manhole bed, foundation bed, drop

    pipe to manhole where required, all associated earthworks,

    damp proofing, and all materals, equipments required to

    complete and finish. the work according to specifications

    section 02605, 02730, drawings and code of practices

    02 Sewer manhole, ref. (MH) 6 No.

    03 Sewer manhole, ref. (STMH) 3 No.

    Fire WATER INSTALLATION

    Supply, install and testing pipework, UPVC Schedule 80 forfire water the work shall include but not limited to

    fittings, supports, all associate works and all materials and

    equipments required to complete and finish the work

    according to drawings, specification and code of practices

    04 100 mm dia. 105 M

    Supply, installation and test horizontal split case centrifugal

    fire pump, including piping network and valving within pump

    chamber,complete with all controllers, accessories for

    automatic operateion and all associate workks as per code

    standard and as scheduled on drawings and specification

    05 Ref. FP1 CAP 75 KW electrically driven 1 No

    06 Ref. FP2 CAP 75 KW fuel diesel driven 1 No

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    11 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    12/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    FIRE WATER UTILITIES

    Supply, installation and test Electrically driven peripheralturbine Jockey pump, including piping network and valving

    within pump chamber, complete with all controllers,

    accessories for automatic operateion and all associate

    workks as per code standard and as scheduled on drawings

    and specification

    01 Ref. JP CAP 5 KW 1 No

    IRRIGATION WATER INSTALLATION

    Supply, install and testing pipework, UPVC Schedule 80 for

    Irrigataion water the work shall include but not limited to

    fittings, supports, all associate works and all materials andequipments required to complete and finish the work

    according to drawings, specification and code of practices

    02 20 mm dia. 33 M

    03 25 mm dia. 110 M

    04 32 mm dia. 30 M

    05 50 mm dia. 295 M

    Accessories

    06 Supply and installation irrigation controller as detailed on drwings 1 No.

    and as per specifications

    07 Supply and install bubbler for shrubs, ground cover and 770 No.

    succulents

    08 Supply and installation bubbler for trees 135 No.

    09 Supply and installation spray lawn sprinkler 16 No.

    10 Gate valve W/valve box 25 mm dia., 1 No.

    11 Gate valve W/valve box 32 mm dia., 1 No.

    12 Gate valve W/valve box 50 mm dia., 6 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    12 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    13/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    Supply and installation remote control valve assembly

    including piping complete with valve box, Y-strainer,

    accessories and all associated works as detail on drawingand as per specifications section 02810

    01 Ref. RCV 20 mm dia. 1 No.

    02 Ref. RCV 25 mm dia. 1 No.

    03 Ref. RCV 32 mm dia. 1 No.

    04 Ref. RCV 50mm dia. 6 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    13 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    14/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    SITE DEVELOPMENT

    Collection

    Sheet -1

    Sheet -2

    Sheet -3

    Sheet -4

    Sheet -5

    Sheet -6

    Sheet -7

    Sheet -8

    Sheet -9

    Sheet -10

    Sheet -11

    Sheet -12

    Sheet -13

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    14 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    15/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 2 - SITE WORK

    SITE GRADING

    All additional excavation required for temporary works and

    spaces, shoring, dewatering, removal of surplus excavated

    materials, support, temporary spoil heaps and general Note

    compaction

    EXCAVATION AND EARTHWORK

    Necessary moving or transportation about the site excavation Note

    material including handling to temporary stockpile or ultimate

    disposal off site is to be included in the unit rate of excavation

    Excavation in natural land consisting of solid rock

    formation, cracked rocks, bolders and natural contoured

    soil, temporary earthwork supports, dewatering ( if any ) as

    per specifications sections 02200

    01 Excavation for foundations commencing from existing grade level 73752 M

    Backfilling

    02 Approved selected imported fill material including compaction in 2300 M

    making up levels around and over foundations, beds and the like as

    per spec. sections 02200

    03 Approved fill material selected from excavated material including M price only

    compaction as per specification section 02200

    Soil treatment application for termite control

    04 To subgrades of slabs and along periphery of building The work 19170 M

    shall include all materials and equipments required to complete

    and finish the work according to specifications and code of

    practice

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    15 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    16/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 2 - SITE WORK

    TRAFFIC MARKING DIMENSION

    Thermoplastic paint for traffic marking on parking pavement

    as detail 11 shown on drawing CL-GA-901 and specification

    01 Straight arrows 78 No.

    02 Turning arrows 1 No.

    03 Parking lane marking 1465 M

    04 Handicapped marking on floor 19 No.

    05NO ENTRY (text)

    3 No.

    06 EXIT (text) 3 No.

    07 Lane numbers 142 No

    To Collection SR

    Collection

    Sheet - 15

    Sheet - 16

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    16 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    17/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 3 - CONCRETE

    CONCRETE WORK

    CONCRETE TYPES

    Include in Unit Rates for concrete of the following types and

    locations:

    20 Mpa

    a) Blinding concrete

    b) Catch basins and side walks Note

    40 Mpa

    a) Footings

    b) Columns and R.C. walls

    c) Floor and roof slabs, beams, girders, stairs

    d) Concrete topping or structural screed

    e) Slab on grade

    f) water tanks

    Water stops including junction accessories are not measured

    separately The cost of water stop items are to be included in the

    unit rates of the related concrete items

    To Collection

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    17 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    18/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 3 - CONCRETE

    Plain insitu concrete, 20 Mpa, cement type Vas per specifications section 03300

    01 Screed, 50mm thick 1057 M

    02 Blinding beds, 100mm thick 2113 M

    Supply and placing Insitu reinforced concrete, 40 Mpa

    cement type V including formwork and steel reinforcements

    conforming to ASTMA615and A185 and all requiments to

    finish the work according to drawings as per specifications

    sections 03100, 03200 & 03300 , and code of practice in:

    03 Raft foundation various thickening including depression areas, 14300 M

    sump pits and elevators pits and electrical cables trench

    04 Retaining walls 855 M

    05 Reinforced concrete for tanks 521 M3

    To Collection

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    18 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    19/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 3 - CONCRETE

    CONCRETE WORK

    Supply and placing of Insitu reinforced concrete, 40 Mpa

    type I cement including formwork and steel reinforcements

    conforming to ASTM A615 and A185 and all requirements to

    finish the work according to the drawings,as per

    specifications sections 03100, 03200 & 03300,and code of

    practice

    01 Columns 477 M

    02 Shear wall 424 M

    03 Beams 71 M

    04 Suspended flat slabs, 300mm thickening including drop panel 2718 M

    05 Suspended flat slabs, 350mm thickening including drop panel 1531 M

    06 Suspended flat slabs, 380mm thickening including drop panel 2565 M

    07 Ramps 70 M

    08 Stairs including landings 84 M

    PRECAST CONCRETE

    Precast concrete wheel stopper including dowels, grouting

    and accessories for complete installation as per detail 21 on

    drawing CL-GA-901 and specification

    09 Precast concrete wheel stopper including fixings 375 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    19 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    20/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 3 - CONCRETE

    CONCRETE WORK

    Sundries

    01 Allow for reinforced concrete equipment pads including upstand 17 M

    surrounds and anti-vibration accessories as required

    02 150mm thick raised slabs, Handicapped`s ramps and curbs to suit 645 M

    required areas as per detail 10,14, 20 on drawing CL-GA-901

    03 Reinforced concrete electrical cable trench including all associated 48 M

    works

    To Collection SR

    Collection

    Sheet - 17

    Sheet - 18

    Sheet - 19

    Sheet - 20

    To Bill Summary

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    20 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    21/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 4 - MASONRY

    UNIT MASONRY

    Supply and fix concrete masonry blocks in courses with

    cement lime mortar including concrete lintels over

    openings , horizontal and vertical reinforcement, fixings,

    fillers, sealants and grout to complete the work according

    to specifications and drawings

    01 15 mm thick wall, one hour fire rated 42 M

    02 200 mm thick wall 37 M

    03 200 mm thick wall, one hour fire rated 308 M

    04 200 mm thick wall, two hours fire rated 487 M

    05 300 mm thick wall, one hour fire rated 21 M

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    21 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    22/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 5 - METALS

    Expansion joint

    Supply and install expansion joint cover including

    extruded aluminum assembles, fillets, accessories, fixing

    and sealants as per drawing CL-GA-902 and according to

    specifications

    01 Floor to floor cover as per detail no. 1a 2300 M

    02 Wall to wall cover as per detail no. 1b 1450 M

    03 Wall to wall cover as per detail no. 1e 1705 M

    04 Floor to wall cover as per detail no. 1d 750 M

    05 Ceiling to ceiling cover as per detail no. 1j 1200 M

    06 Wall to ceiling cover as per detail no. 1h 400 M

    Steel cover as per details on drawings

    07 To suit electrical cable trench 68 M2

    08 To suit sump pits at basement 7 No

    Supply and install 30mm depth panted galvanized cast iron

    gratings including 40x40mm steel angle, medium gauge

    galvanized gutter slope to drain and all required for fixing

    and finisheng as per detail no.9 on drawing CL-GA-901 and

    specificatons

    09 To suit required locations 24 M

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    22 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    23/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 7 - THERMAL AND MOISTURE PROTECTION

    Water proofing and moisture protection as per specificationsection 07100

    01 Membrane waterproofing as per specifications to suit base slab and 30800 M2

    retainig walls

    02 Protection board to suit base slab and retainig walls 2380 M2

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    23 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    24/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 8-DOORS AND WINDOWS

    DOOR SETS

    Supply and install all doors to suit masonry openings and Note

    approved samples including fixings, decorations, frames,

    architrave, hardwares and saddles and all required to complete

    and finish the work as detailed on drawing CL-GA-801 and

    according to specifications and code of practice

    TYPE B : 44mm thick painted hollow metal insulated

    door including door grill (where required)

    01 Type B1, single leaf door, size 900x2150mm and 45 min. fire rated 7 No.

    02 Type B6, double leaves door, leaf size 950x2150mm and 45 min. fire 6 No.

    rated

    . .

    motorized adjustable louvers panel working upon signal from

    fire alarm system for generator .

    03 Type C1, double leaves door, leaf size 950x2400mm and 45 min. fire 7 No.

    rated

    04 Type C2, double leaves door, leaf size 1050x2400mm and 45 min. 1 No.

    fire rated

    WINDOWS

    24 mm thick double tempered glazed sliding window tinted

    outside clear inside , on powder coated aluminum frame

    including all hardware, fixtures, packings, sealants, weather

    strippings and the like as described drawing CL-GA-801 to suit

    opening and as per specification

    05 Ref. W02 3 No

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    24 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    25/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 9 - FINISHES

    INTERNAL FINISHES

    Flooring including respective types of bounding materials,

    concrete screed sub-floor of required thickness, (if any)

    accessories for complete installations as per ID drawing

    and specification

    01 Epoxy paint on cement screed. , ref. EC 368 M

    02 Anti carbonation protection epoxy coating for pavement. , ref. AEC 4302 M

    03 8mm thk. heavy duty multi component epoxy screed with 352 M

    polyurethane base on concrete screed for car ramps,supported withlinear metal strip for non sliding. , ref.HES

    04 Multi component epoxy coating on concrete screed for drive way & 8105 Mturns. , ref. MEC

    Finishings : walls including metal angle beads and lathing at

    junctions of differing backgrounds

    05 Cement plaster to suit walls 7630 M

    06 Paint on cement plaster ,ref. W01 7630 M

    Finishings : ceilings

    07 Cement plaster to suit ceiling 15950 M

    08 Paint on cement plaster, ref.C01 15950 M

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    25 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    26/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 9 - FINISHES

    EXTERNAL FINISHES

    Finishing : walls including metal angle beads and lathing at

    junctions of differing backgrounds

    01 Cement plaster to suit external surface 66 M2

    02 External Paint on cement plaster to suit external surface 66 M2

    To Collection SR

    Collection

    Sheet - 25

    Sheet - 26

    To Bill Summary

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    26 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    27/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 10 -SPECIALTIES

    CORNER & COLUMN GUARD

    Corner guards install at 600 high from finish floor heavy duty

    rubber guard bumper, including all associated works, as per

    detail 18 shown on drawing CL-GA-901 and as specification

    01 To suit column location as required 63 No

    ALUMINUM LOUVERS SCREEN

    Supply and install fixed anodized aluminum sand trap louvers

    panels on anodized aluminum frames including finishes and all

    associated works to complete and fix the works as per detailson drawing CL-GA-802 and specification

    02 Ref. L03, size 3200x2500mm to suit required locations 2 No

    03 Ref. L06, size 2300x2500mm to suit required locations 2 No

    04 Ref. L07, size 700x450mm to suit required locations 2 No

    05 Ref. L08, size 700x400mm to suit required locations 6 No

    06 Ref. L09, size 2500x5000mm to suit required locations 1 No

    07 Ref. L10, size 1500x1500mm to suit required locations 3 No

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    27 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    28/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 10 -SPECIALTIES

    SIGNAGE

    Manufacturer's standard indoor signs, letters and plaques

    including fixings, finishes, accessories complete as per

    interior design drawings CL05-i901 to CL05-i907 and all

    required materials and equipments to complete and finish

    the works according to specifications, drawings and code of

    practice

    01 Ref. type S01 18 No

    02 Ref. type S02 4 No

    03 Ref. type S09 20 No

    04 Ref. type S10 30 No

    05 Ref. type S11 21 No

    06 Ref. type S12 17 No

    07 Ref. type S13 3 No

    To Collection SR

    Collection

    Sheet - 27

    Sheet - 28

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    28 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    29/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 14 - CONVEYING SYSTEMS

    AUTOMATED WASTE COLLECTION SYSTEM

    Supply and provide all required to construct, test and operate

    automated waste collection system, consisting of the

    following items:-

    01 Discharge valve room with basement floor including all required 14 No.

    works as detailed on drawing no. STM - ITCCP2 - TD - 008.

    Contractor shall perform all required coordination with other trade to

    ensure proper installation and operation of the complete system to

    transport waste from tower chute to pipe networks as shown on

    drawings STM - ITCCP2 - TD - 001 to 007 and 015, 016 andaccording to manufacturer's standards and specifications

    02 Discharge valve room without basement floor including required 3 No.

    earthworks, concrete works for the vacuum room masonry for the

    vacuum room and electromechanical works and all required works

    as detailed on drawing no. STM - ITCCP2 - TD - 009. Contractor

    shall perform all required coordination with other trades to ensure

    proper installation and operation of the complete system to

    transport waste from tower chute to pipenetworks as shown on

    drawings STM - ITCCP2 - TD - 001 to 007 and 015, 016 and

    according to manufacturer's standards and specifications

    PIPE WORK

    Supply and installation of Automated waste collection system

    piping. Item shall include the earth works, insulation,

    ,concentric reducer, puddle flanges ,inspection covers and all

    required materials and equipments to complete the transport

    pipe line from DV rooms , outdoor load stations and full

    vacuum load stations to waste plant

    03 508mm under/above ground transport pipe 1070 M

    RC MANHOLE

    Supply and install cast insitu or precast reinforced concrete

    manhole ,the item shall include excavation, backfill

    insulation ,inspection cover steel rungs and all required tocomplete the work.

    04 RC manhole to suit required location in sitesas shown on drawings 29 No.

    STM - ITCCP2 - TD 001 to 016

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    29 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    30/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    PLUMBING INSTALLATIONS

    WASTE AND DRAINAGE INSTALLATION

    Supply, installation and test drainage pipe work UPVC

    schedule 40 the work shall include but not limited to fittings,

    supports hangers, excavation, backfilling, cast iron pipes on

    roof for vent with caps and all materials and equipment

    required to complete and finish the work according to

    specifiactions, drawings and code of practice

    01 32 mm dia 150 M

    02 50 mm dia 210 M

    03 100 mm dia 490 M

    04 150 mm dia 940 M

    Accessories

    05 Area drain 150mm dia., ref. AD 21 No.

    06 Floor drain, 50 mm dia., ref. (FD) 22 No.

    07 Parking drain, 150mm dia., ref. PD 57 No.

    08 Cleanout, 75 mm dia., ref. (CO) 36 No.

    09 Cleanout, 100 mm dia., ref. (CO) 138 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    30 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    31/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    PLUMBING INSTALLATIONS

    WASTE AND DRAINAGE INSTALLATION

    Accessories

    01 Floor cleanout 100mm dia., ref. (FCO) 41 No.

    02 Floor cleanout 150mm dia., ref. (FCO) 22 No.

    03 Gully trap, ref. GT 16 No.

    04 Trench drain outlet, 100mm dia., ref. TDO 3 No.

    Reinforced concrete gray water tank with required capacityand proprietary medium duty cast iron manhole cover and

    frame, including sump pit, submersible pumps, internal

    lining, access ladder vent pipework within tank as detailed

    on drawing (Concrete work, earthwork & water proofing

    measured elsewhere)

    05 Gray water tank 10 No

    Packaged type variable speed discharge pressure system

    Gray water lift pumps, including piping and valves network

    within pump chamber, complete with all controllers,

    accessories for automatic operation as scheduled on

    drawing as per spec. section 15453

    06 Gray water lift pumps CAP. 5 KW 5 Set

    07 Gray water lift pumps CAP. 6 KW 5 Set

    Reinforced concrete sump pit including internal lining,

    proprietary galvanized steel manhole cover and frame,

    guide bar, lifting chain and all associated works, valves

    pipework within sump pit chamber as detailed on drawings

    (concrete work & earthwork, waterproofing measured

    elsewhere)

    08 Sump pit 7 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    31 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    32/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    PLUMBING INSTALLATIONS

    WASTE AND DRAINAGE INSTALLATION

    Submersible pumps (one duty and one stand-by) including

    associated valves, pipework, valves controllers and

    accessories within sump pit chamber as described on

    drawings (sump pit measured separately)

    01 Ref. SP1 capacity 1.5 HP 5 Set

    02 Ref. SP2 capacity 2 HP 2 Set

    Allow for the design, supply and installation of packaged

    type waste water treatment plant complete including filter,chemical feeders, air blowers controls, wirings, piping and

    all as associated works as per specifications section 02736

    and scheduled on drawing

    03 Packaged water treatment unit. Cap. 58 m3/day 9 No.

    POTABLE WATER INSTALLATION

    Supply, installation and test pipework, plypropylene

    for potable water the work shall include but not limited

    to installation, fittings, insulation for hot pipework,

    valves, supports and all materials and equipment

    required to complete and finish the work according tospecifications, drawings and code of practice

    04 20 mm dia. 835 M

    05 25 mm dia. 205 M

    06 50 mm dia. 685 M

    07 63 mm dia. 165 M

    08 100 mm dia. 485 M

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    32 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    33/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    PLUMBING INSTALLATIONS

    NON-POTABLE WATER INSTALLATION

    Supply, installation and test pipework, plypropylene

    for non-potable water the work shall include but not limited

    to installation, fittings, insulation for hot pipework,

    valves, supports and all materials and equipment

    required to complete and finish the work according to

    specifications, drawings and code of practice

    01 50 mm dia. 1585 M

    02 63 mm dia. 80 M

    03 75 mm dia. 610 M

    04 100 mm dia. 505 M

    Accessories

    05 Water meter assembly 63mm dia., 14 No.

    06 Isolating valve, 50 mm dia, ref. (IV) 33 No.

    07 Isolating valve, 75 mm dia, ref. (IV) 28 No.

    08 Isolating valve, 100 mm dia, ref. (IV) 1 No.

    09 IV & CV assembly 100 mm dia., 7 No.

    10 Hose bib 20mm dia., ref. (HB) 51 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    33 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    34/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    PLUMBING INSTALLATIONS

    Packaged type duplex unit discharge pressure system

    potable water lift pumps, (one duty & one stand by)

    including piping and valves network within pump chamber,

    complete with all controllers, accessories for automatic

    operation as scheduled on drawing and specification

    section 15453

    01 Potable water pump CAP. 7.17 KW 6 Set

    02 Circulating potable water pump CAP. 0.5 HP 6 Set

    Reinforced concrete under ground water tank and pump

    room with required capacity and proprietary cast ironmanhole covers and frames, including internal lining

    access ladders, pipework submersible pump, ventilating

    fans with exhaust and fresh air pipework, valves, vent pipes

    and truck fill pipework as detailed on drawings (concrete

    work & earthwork, water proofing measured elsewhere)

    03 Potable Water tank 6 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    34 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    35/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    FIRE WATER UTILITIES

    Supply, installation and test Pipework, UPVC class 5

    including fittings, trenching, back fill supports system and

    all associate works as per code standard

    01 25 mm dia. 3155 M

    02 32 mm dia. 405 M

    03 40 mm dia. 745 M

    04 50 mm dia. 405 M

    05 100 mm dia. 1725 M

    06 150 mm dia. 795 M

    07 200 mm dia. 60 M

    Accessories

    08 Pendent sprinkler head 126 No

    09 Upright sprinkler head 1239 No

    10 Side wall sprinkler head 14 No

    11 100mm Fire departement valve , ref. FDV 31 No

    12 Floor control valve assembly 100mm dia., ref. FCVA 3 No

    13 Floor control valve assembly 150mm dia., ref. FCVA 7 No

    14 Fire department connection, 2 way fire department inlet

    connection type with gate and check valve 100mm dia. 2 No

    15 Fire department connection, 2 way fire department inlet

    connection type with gate and check valve 150mm dia. 3 No

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    35 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    36/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    FIRE WATER UTILITIES

    Supply, install, testing and commissioning proprietary

    integrated fire hose reel and fire extinguisher cabinet the

    work shall include but not limited to fire extinguisher, hose

    reel nozzle, fixings, isolating valve 40 mm dia., trims and

    all associate works and all materials and equipments

    required to complete and finish the work according to

    drawings, specification and code of practices

    01 Ref. FHC 18 No

    Supply, install, testing and commissioning portable

    multipurpose fire extinguisher the work shall include butnot limited to fixing to wall, all associate works and all

    materials and equipments required to complete and finish

    the work according to drawings, specification and code of

    practices

    02 Ref. PFE 3 No

    03 Ref. CO2 33 No

    CO2 system

    Supply, install and test CO2 cylinders including pipe work,

    black steel seamless for CO2 fittings, supports valves,

    regulators, sleeves, as shown on drawings and as per

    specification

    04 CO2 cylinders CAP 45 KG 38 No.

    05 Control panel 14 No.

    06 Remote manual release 14 No.

    07 Abort switch 14 No.

    08 Alarm bell 14 No.

    09 4-port nozzle 14 No.

    10 Ioization detector 14 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    36 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    37/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15 - MECHANICAL

    PLUMBING INSTALLATION

    DIESEL FUEL STORAGE TANK INSTALLATION

    Allow for underground fiberglass diesel fuel storage tank

    with required capacity including concrete anti-flotation

    pad, heavy duty traffic type manhole ring and cover,

    pipework, valves duplex diesel fuel transfer pumps, steel

    ladder, pea gravel bed, earthworks, fixings and accessories

    all as detailed on drawings

    01 Proprietary tank units CAP. 3800 Lit. 3 No.

    To Collection SR

    Collection

    Sheet -29

    Sheet -30

    Sheet -31

    Sheet -32

    Sheet -33

    Sheet -34

    Sheet -35

    Sheet -36

    Sheet -37

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    37 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    38/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15B - MECHANICAL

    HVAC INSTALLATIONS

    CHILLED WATER SYSTEM

    Supply, install and test black steel pipework including

    fittings thermal insulation, flexible connections and

    accessories as per required drawings and specification

    sections15050 to 15140 ,15510

    01 15 mm dia. 265 M

    02 20 mm dia. 70 M

    03 25 mm dia. 20 M

    04 32 mm dia. 200 M

    05 100 mm dia. 810 M

    06 150 mm dia. 505 M

    07 200 mm dia. 270 M

    08 250 mm dia. 120 M

    09 350 mm dia. 55 M

    10 400 mm dia. 465 M

    11 450 mm dia. 15 M

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    38 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    39/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15B - MECHANICAL

    HVAC INSTALLATIONS

    CHILLED WATER SYSTEM

    Supply and install valve / BTU meter

    Butterfly valve

    01 Ref. MBFV 400 mm dia., 1 No.

    Isolating valve

    02 32mm dia., 34 No.

    Check valve

    03 32mm dia., 17 No.

    BTU meter

    04 32mm dia., 17 No.

    Supply and install heat exchanger including valves and

    short length piping as detailed on drawings and as per

    specifications

    05 Ref. HEX-01 to 05, 1960 KW capacity 5 No.

    Supply, install, test and commission, variable speed chilled

    water centrifugal inline pumps unit including valves, flexible

    connections, Y-striners, mounting and fixing to pads

    (measured separately) as detailed on drawing and

    specifications

    06 Ref. CWP-01 to 05, 52.0 L/S capacity 45 m TDH 5 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    39 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    40/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15B - MECHANICAL

    HVAC INSTALLATIONS

    CHILLED WATER SYSTEM

    Supply, install and commission, expansion tank as detailed

    on drawings and specifications

    01 Ref. ET, 1200 liter capacity 1 No.

    Supply, install and commission, air separator tank as

    detailed on drawings and specifications

    02 Ref. AS 1 No.

    Supply, install, test and commission, Fan coil units ducted

    type including control valves, pressure & temperature,

    gauge, Y-strainer mounting and fixing as per drawings and

    specifications section 15781

    03 Ref. FCU-02, 17.1 KW cooling capacity 2 No.

    04 Ref. FCU-03, 3.1 KW cooling capacity 13 No.

    05 Ref. FCU-04, 4.3 KW cooling capacity 13 No.

    06 Ref. FCU-05, 5.3 KW cooling capacity 4 No.

    Supply, install, test and commission DX-ducted split unit

    including control, pipes and fixing as per drawing and

    specifications

    07 Ref. RAC-01, 3.51 KW nominal coollling capacity 51 No.

    Supply, install, test and commission, DX-ducted split unit

    including control, pipes and fixing as per drawings and

    specifications section 15781

    08 Ref. FCU-01/ACCU-01 , 4 KW capacity 3 No.

    Supply, install, test and commission automatic chemical

    dosing unit as detailed on drawings and specifications

    09 Ref. ACDU 1 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    40 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    41/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15B - MECHANICAL

    HVAC INSTALLATIONS

    Supply, install, test and commission, Ventilating fans as

    details on drawings and specifications, section 15860

    01 Ref. PEF- 01, 13500/22500 LPS capacity with exh. Duct and 6 No.

    CAP.

    02 Ref. EF- 01, 85 LPS capacity 3 No.

    03 Ref. EF- 02, 60 LPS capacity 3 No.

    04 Ref. EF- 03, 1600 LPS capacity 3 No.

    05 Ref. EF- 04, 160 LPS capacity 3 No.

    06 Ref. EF- 05, 105 LPS capacity 3 No.

    07 Ref. EF- 06, 50 LPS capacity 18 No.

    08 Ref. BIF-01, 3600 LPS capacity 24 No.

    Supply, install, test and commission, Supply air round

    ceiling diffusers with opposed blade volume damper

    including frame trims & insulated plenum box as detailedon drawing and specification, section 15860

    09 Ref. SD1 26 No.

    10 Ref. SD2 28 No.

    11 Ref. SD3 616 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    41 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    42/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15B - MECHANICAL

    HVAC INSTALLATIONS

    Supply, install, test and commission, supply air register as

    detailed on drawings and specification

    01 Ref. SR 1 / RR1 8 No.

    Supply, install, test and commission, Return round louver

    face ceiling diffusers as detailed on drawing and

    specification

    02 Ref. RD1 26 No.

    03 Ref. RD2 28 No.

    04 Ref. RD3 6 No.

    Supply, install, test and commission, door grill as detalied

    and specificaitons

    05 Ref. DG1 18 No.

    06 Ref. DG3 2 No.

    Supply, install and test motorized door louver as detailedon drawing and specification

    7 No.07 size 950 x 2200 mm

    Supply and install Galvanized steel sheet rectangular

    ductwork, including supports and volume damper , and bill

    mouth opening as per drawings and specification

    08 Various gauges 985 Kg

    Supply and install Duct insulation

    09 Thermal semi-rigid insulation to rectangular ductwork 250 M

    Supply, install and test generator exhaust ductwork with

    canvass connection

    10 To suit generator room 3 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    42 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    43/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 15B - MECHANICAL

    HVAC INSTALLATIONS

    Supply, install, test and commission, of electric works and

    motor control centers MCC C/W weather proof, magnetic

    starters, cabinets including power cables, wiring and

    conduits and cable trays from the MCC to HVAC equipment,

    interlocks, earthing ...etc, all materials and equipments

    required to complete and finish the work according to

    drawings, specifications and code of practices

    01 Ref. MCC- CWP 1 No.

    To Collection SR

    Collection

    Sheet - 38

    Sheet - 39

    Sheet - 40

    Sheet - 41

    Sheet - 42

    Sheet - 43

    To Bill Summary SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    43 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    44/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    MEDIUM VOLTAGE INSTALLATION

    MVSWGR (medium voltage switchgear)

    Supply , install , testing and commissioning 13.8 KV, 3 phase,

    60 Hz,SF6 MVSWGR with 3 cells (1 inputs +2 outputs)

    including all associated works to complete installation as per

    drawings and specifications. The contractor shall prepare

    sketches and details for approval from SEC and shall make

    arrangement and required coordination with supervising

    engineer to complete the work

    01 M.V Switchgear unit ref (MVSWGR/CL-5) 1 No

    RING MAIN UNIT

    Only installation, testing and commissioning for 13.8 KV, 3

    phase, 60 Hz SF6 ring main unit including all associated

    works for complete installation as per drawings and

    specifications and required coordination (supply will be by

    client)

    02 Ring main unit RMU1,2,3.4 4 No

    MEDIUM AND LOW VOLTAGE DISTRIBUTION

    Supply installation, testing and commissioning of the

    following equipment including all accessories and

    necessary works required for installation as shown on the

    drawings E-701,E201 and as described in specifications

    section 16461,16124and and by making arrangiement with

    supervising engineer to achieve the work to the best

    possible and specifications

    03 Dry type transformers , 1000 KVA, 13.8 KV ,400/230V , 3PH, 3 No.60HZ, ref (TR 1,2,4-CL5)

    04 Dry type transformers, 1600 KVA, 13.8 KV ,400/230V , 3PH, 60HZ, 1 No.ref (TR 3-CL5)

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    44 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    45/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    MEDIUM VOLTAGE INSTALLATION

    Supply , install and test medium voltage copper Cables 15KV/

    XLPE/STA/PVC, between medium voltage equipments as

    shown on drawings and coordination with other disciplines

    shall be conducted during work execution as per technical

    specifications, drawings and by making arrangement with

    supervising engineer to achieve the work to the best possible

    and specifications

    01 Medium voltage cable comprising 3 core 70 mm CU / XLPE /STA/ 20 M

    PVC, cables route from RMU up to transformers

    02 Medium voltage cable comprising 3 core 300 mm CU / XLPE /STA/ 485 M

    PVC, cables

    Smart Metering System

    Supply, installation , testing and commissioning of Smart

    Metering System comprising of M-bus master controller

    complete with soft ware and bus IP router, including digital

    electrical KWH meters, 1 pair twisted cable # 22 AWG type

    to TCP/IP net work and all associated works required as

    shown on drawing E-501--E520 and as described inspecifications section 16211

    To suit Building Smart Metering System with multi -electronic

    meter (MEM) and main bus and IP router as required to form a Note

    complete and fully operative system to link all project buildings

    with the existing data center at phase 1

    03 Electronic KWH meters 17 No

    04 M-bus master controller complete with software 17 No

    05 M-bus IP router 17 No

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    45 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    46/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    MAIN AND SUB-MAIN POWER

    Supply and install an Emergency Power Generating Sets

    including Generator Control Panel (GCP). In addition to

    circuit breakers, pads, supports, controls and daily diesel

    fuel storage tank, including all necessary equipment,

    accessories and associated works, as shown on drawings

    E-701,E201 as described in specifications section 16231,

    and by making arrangiement with supervising engineer to

    achieve the work to the best possible and specifications

    01 Ref. (G1,G3) 550 KVA, 3 phase 4 wire ,400/230V , 60 Hz. 2 No.

    02 Ref. (G2) 600 KVA, 3 phase 4 wire ,400/230V , 60 Hz. 1 No.

    supply , install, testing and commissioning multicore copper

    cable ( XLPE/PVC -1000/600V) in cable tray or cable trench

    (measured elsewhere) including junction boxes, connection

    for feeders and various power loads as shown on drawings

    E-701 and as per specification section 16126 and by makingarrangement with supervising engineer to achieve the workto the best possible specifications

    03 (4 C-10 mm ) + 10 mm G/ cable tray 115 M

    04 (4 C-16 mm ) + 16 mm G /cable trench 20 M

    05 (4 C-25 mm ) + 16 mm G/ cable tray 345 M

    06 4 C-35 mm + 16mm G/ cable tray 200 M

    07 4 C-50 mm + 25mm G/ cable tray&cable trench 665 M

    08 4 C-70 mm + 35mm G/ cable tray 60 M

    09 4 C-95 mm + 50mm G/ cable tray&cable trench 265 M

    10 4 C-185 mm + 95 mm G/ cable tray&cable trench320

    M

    11 4 C-240 mm + 120 mm G/ cable tray&cable trench 785 M

    12 2(4C-150mm2) + 150 mm G/ cable tray 875 M

    13 2(4C-240mm2)/ cable trench 15 M

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    46 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    47/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    supply , install, testing and commissioning multicore coppercable ( XLPE/PVC -1000/600V) in cable tray or cable trench

    (measured elsewhere) including junction boxes, connection

    for feeders and various power loads as shown on drawings

    E-701 and as per specification section 16126 and by makingarrangement with supervising engineer to achieve the workto the best possible specifications

    01 3(4X1C-630mm2)/ cable trench 35 MThe length of cables including the cluster-5 cables and cables in Notethe first floor for AP03 & AP04 & AP06 according to No. for each

    AP in site

    Supply , install , power distribution heavy duty galvanizedsteel cable trays with cover including fixings, supports and all

    accessories as shown on drawingsE201--E220 and

    coordination & integration with other systems shall be

    conducted during work execution as per technical

    specifications section 16050 and by making arrangement with

    supervising engineer to achieve the work to the best possible

    specifications

    02 Cable tray 200 mm width 152 M

    03 Cable tray 200 mm width for emergency cables 540 M

    04 Cable tray 300 mm width 222 M

    05 Cable tray 400 mm width 263 M

    05 Cable tray 400 mm width for emergency cables 50 M

    06 Cable tray 400 mm width double layers 50 M

    07 Cable tray 600 mm width 29 M

    08 Cable tray 600 mm width double layers 25 M

    09 Cable tray 800 mm width 30 M

    10 Cable tray 1000 mm width 37 M

    11 Covered cable tray 300 mm width for optical fiber cables and 1955 M

    primary and secondary networks.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    47 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    48/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    MAIN AND SUB-MAIN POWER

    supply and install reinforced concrete Man / Holes connected

    via duct banks, complete with man / hand hole bolted type

    metal cover, drain pipe outlet, including trenching and

    backfilling for duct banks, conduits for M.V cables in duct

    banks, tapes, all as required to suit locations as shown on

    drawings drawings E201--E220and as all accessories and

    coordination & integration with other systems shall be

    conducted during work execution as per technical

    specificationssection 16180 and by making arrangement with

    supervising engineer to achieve the work to the best

    possible specifications

    01 Power Man Holes (180018001800 )Ref. MH for power including 4 No

    UPVC conduit

    02 Power Hand Hole (900900900 ) Ref. HH including UPVC conduit 7 No

    03 Comm, Hand Hole (600600600 ) Ref. CHH including UPVC conduit 5 No

    Site work

    04 Power Man Hole Ref. PHH for power including UPVC conduit 4 No

    05 Power Hand Hole (900900900 ) Ref. HH including UPVC conduit 3 No

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    48 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    49/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    MAIN AND SUB-MAIN POWER

    Supply , install , testing and commissioning of panel boards

    including grounding, circuit breakers, grounding, fixings,

    markers and , other functional units and all associated works

    as required and shown on drawings E 701,E704 , E201--E220

    and coordination & integration with other systems shall be

    conducted during work execution as per technical

    specificationssection 16442,16410,16415 and by makingarrangement with supervising engineer to achieve the workto the best possible specifications

    01 Ref. MDP-P1 1 No.

    02 Ref. MDP-P2 1 No.

    03 Ref. MDP-P3 1 No.

    04 Ref. MDP-P4 1 No.

    05 Ref. EMDP-P1 1 No.

    06 Ref. EMDP-P2 1 No.

    07 Ref. EMDP-P3 1 No.

    08 Ref. DP31 12 No.

    09 Ref. DP32 12 No.

    10 Ref. DP41 2 No.

    11 Ref. DP42 2 No.

    12 Ref. DP61 3 No.

    13 Ref. DP62 3 No.

    14Ref. DPSB1

    1 No.

    15 Ref. DPSB2 1 No.

    16 Ref. EDPS3 12 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    49 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    50/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    MAIN AND SUB-MAIN POWER

    Supply , install , testing and commissioning of panel boards

    including grounding, circuit breakers, grounding, fixings,

    markers and , other functional units and all associated works

    as required and shown on drawings E 701,E704 , E201--E220

    and coordination & integration with other systems shall be

    conducted during work execution as per technical

    specificationssection 16442,16410,16415 and by makingarrangement with supervising engineer to achieve the workto the best possible specifications

    01 Ref. EDPSB1 1 No.

    02 Ref. EDPSB2 with interlock and ATS built in 1 No.

    03 Ref. EPMSB1A 1 No.

    04 Ref. EPMSB2B 1 No.

    05 Ref. EPMSB2A with interlock and ATS built in 1 No.

    06 Ref. EPMSB2B 1 No.

    07 Ref. EDPSB3A 1 No.

    09 Ref. EPSB1 1 No.

    10 Ref. EPSB2 1 No.

    11 Ref. EPSC 12 No.

    12 Ref. EPSC1 2 No.

    13 Ref. EPSE 3 No.

    14 Ref. PPSB1 1 No.

    15Ref. PPSB2

    1 No.

    16 Ref. PPSC 12 No.

    17 Ref. PPSC1 2 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    50 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    51/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    MAIN AND SUB-MAIN POWER

    Supply , install , testing and commissioning of panel

    boards including grounding, circuit breakers, grounding,

    fixings, markers and , other functional units and all

    associated works as required and shown on drawings E

    701,E704 , E201--E220 and coordination & integration with

    other systems shall be conducted during work execution as

    per technical specificationssection 16442,16410,16415 andby making arrangement with supervising engineer toachieve the work to the best possible specifications

    01 Ref. PPSE 3 No.

    02 Ref. SLP1A 1 No.

    03 Ref. SLPE 6 No.

    Pump room

    04 Ref. EPP (IP 54 ) 1 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    51 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    52/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    POWER INSTALLATION

    The contractor is to insure that all power outlets mounted in Notewet areas and all service outlets for kitchens, bathrooms,laundry and water heaters are to be protected by centralground fault circuit interrupter (GFCI)

    Supply , install, testing and commissioning of power and

    sockets accessories including all necessary boxes,

    faces(according to the engineer approvement ) comprising

    cables, conduits, fittings, connections, from the outlets to

    Panelboards feeder associated works as required to suit the

    locations shown on drawings E201--E220 Coordination with

    other disciplines shall be conducted during work executionas per technical specifications, section 16050and by making

    arrangiement with supervising engineer to achieve the work

    to the best possible specifications

    01 Junction box ceiling mounted 34 No.

    02 Junction box, wall mounted 77 No.

    03 Disconnect switch,non-fused and with pilot light16A, 1P, 230V 14 No.,weatherproof for waste collection equipment

    04 Above false ceiling disconnect 20A, 1P, 230V for FCU-03.04,05 33 No.

    05 Disconnect switch,non-fusedand with pilot light 20A, 1P, 230V 10 No.,weatherproof for SP-01,02,03,04,05,06&fuel pumps

    06 Disconnect switch,non-fused and with pilot light 20A, 1P, 230V 57 No.

    for BD3,4,6&FDB1,2,FD3G,FD4G,FD6G&FACP&A/P switcher

    07 Disconnect switch, fused and with pilot light 20A, 1P, 230V 54 No., for RAC& RAC-01&FCU-02

    08 Disconnect switch, non-fused and with pilot light 20A, 3P, 380V 16 No.,weatherproof for gray& potabole pumps

    09 Above false ceiling disconnect 20A, 3P, 400V for BIF-01 24 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    52 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    53/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    POWER INSTALLATION

    Supply , install, testing and commissioning of power and

    sockets accessories including all necessary boxes,

    faces(according to the engineer approvement ) comprising

    cables, conduits, fittings, connections, from the outlets to

    Panelboards feeder associated works as required to suit the

    locations shown on drawings E201--E220 Coordination with

    other disciplines shall be conducted during work execution

    as per technical specifications, section 16050and by making

    arrangiement with supervising engineer to achieve the work

    to the best possible specifications

    01 Disconnect switch, fused and with pilot light ,32A, 1P, 230V 4 No.

    for FCU-01

    02 Disconnect switch, non-fused and with pilot light ,50A, 3P,400V 6 No.

    for PEF-01

    03 Disconnect switch, non-fused and with pilot light ,500A, 3P,400V 1 No.

    weatherproof for jocky pump, MCC-CWP

    04 Circuit breaker 200A for fire alarm panel (magnetic trip only) 1 No.

    05 Motor switch with built -in over load protection (tumbler switch) 32 No

    06 For exhust fan outlet 34 No.

    07 Single socket outlet, 10A, 230V, grounding type 256 No

    08 Single socket outlet, 13A, 230V, grounding type, weatherproof 102 No

    09 Single socket outlet, 16A, 230V, grounding type, EF 34 No

    10 Single socket outlet, 16A, 230V, grounding type, EF 34 No

    11 Duplex socket outlet, 16A, 230V, grounding type 8 No

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    53 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    54/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    POWER INSTALLATION

    Supply , install, testing and commissioning of power and

    sockets accessories including all necessary boxes,

    faces(according to the engineer approvement ) comprising

    cables, conduits, fittings, connections, from the outlets to

    Panelboards feeder associated works as required to suit the

    locations shown on drawings E201--E220 Coordination with

    other disciplines shall be conducted during work execution

    as per technical specifications, section 16050and by making

    arrangiement with supervising engineer to achieve the work

    to the best possible specifications

    01 Single pole one-way ,one gang switch (13A) 108 No.

    02 Single pole one-way ,two gang switch (13A) 20 No.

    03 Push button switch 55 No.

    Site work

    04 Junction box ,floor mounted for site 2 No.

    Pump rooms

    05 Junction box ceiling mounted 1 No.

    06 Disconnect switch, non-fused and with pilot light 20A, 1P,230V 1 No.

    weatherproof for sub. pump

    07 Disconnect switch, non-fused ,200A, 3P,400V, weatherproof for 1 No.

    fire& jockey pump,

    08Motor switch with built-in over load protection (tumbler switch), 1 No

    weatherproof

    09 Single socket outlet, 13A, 230V, grounding type, weatherproof 1 No

    10 Single pole one-way ,one gang switch (13A), weatherproof 1 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    54 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    55/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    LIGHTING INSTALLATION

    Supply, install , testing and commissioning of lighting

    fixture outlets and including conduits, wires and all boxes

    belong to Lighting Panelboards and associated works as

    required to suit the locations shown on drawings E101--E120

    .Coordination with other disciplines shall be conducted

    during work execution as per technical specifications,

    section 16050 and by making arrangiement with supervising

    engineer to achieve the work to the best possible

    specifications

    01 Lighting fixer outlet 1588 No.

    Pump room

    02 Lighting fixer outlet 4 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    55 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    56/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    LIGHTING INSTALLATION

    Supply ,install, testing and commissioning of lighting

    fixture (furnishe with lamp and electronic blast, accessories

    and internal wires) mounting accessories.(according to the

    engineer approval ) associated works as required to suit the

    locations shown on drawings E101--E120 ,GE-E01,GE-E01 and

    Coordination with other disciplines shall be conducted

    during work execution as per technical specifications,

    section 16500 and by making arrangiement with supervising

    engineer to achieve the work to the best possible

    specifications

    01 Type EX ( wall mounted, single sided) 71 No.

    02 Type EX ( ceiling mounted, single sided) 47 No.

    03 Type F1 522 No.

    04 Type F1E 142 No.

    05 Type F2 308 No.

    06 Type F2E 96 No.

    07 Type F7E 130 No.

    08 Type F8E 112 No.

    09 Type NE 20 No.

    10 Type WL3 55 No.

    11 Type WL4 8 No.

    12 Type WL4E 41 No.

    13 Type FT1 flixible tube LED cove light 998 M.

    Pump room

    14 Type F1E 4 No.

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    56 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    57/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    GROUNDING SYSTEM

    Supply, installation , test and commissioning of a grounding

    system comprising bare copper conductor to bond the

    building's distribution boards and HVAC equipments to the

    main ear thing grid of the building. Including necessary

    earthwork, buried galvanized steel foundations strips

    surrounding the building phosphor bronze test joints &

    triangular counter poise and all associated works to suit

    grounding resistivity required as shown on drawings

    E301--E310 and as described in specifications16452,16453

    by making arrangiement with supervising engineer to

    achieve the work to the best possible specifications

    01 Complete building grounding system network to suit ground 1 Item

    resistivity as shown on drawings and specification

    02 To suit grounding system for low current system equipment as 1 Item

    shown on drawings and specification

    03 To suit grounding system for Pump room as shown on drawings 1 Item

    and specification

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    57 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    58/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATEITEM D E S C R I P T I O N QTY UNIT

    DIVISION 16 - ELECTRICAL

    TELECOMMUNICATION SYSTEM

    Supply, installation, testing and commissioning of

    telecommunication system commporising of server,

    Building distributor with core switch,floor distribution,

    data/telephone outlets including cable / wires and conduits

    as shown on drawings E- 501--E520 ,E801and as described

    in specification section 16715,16720 and by making

    arrangiement with supervising engineer to achieve the

    work to the best possible specifications

    To suit system network equipped with:

    01 Building distributor ,ref ( BD3,BD4,BD6) contains main optical 3 No

    data patch panel (F.O.P.P)

    02 Floor distribution includes( fiber optical patch panel F.O.P.P ,

    data switch CAT6 a 1 36 RJ 45 ports and UTP P.P CAT6 a 1

    36 ports and blank ),ref FDB1 with UPS 1.5 KVA and 1 No

    connected with power supply

    03 Floor distribution includes( fiber optical patch panel F.O.P.P ,

    data switch CAT6 a 1 48 RJ 45 ports and UTP P.P CAT6 a 1 No.

    1248 ports and blank ),ref FDB2 with and connected with

    power supply

    04 Floor distribution includes( fiber optical patch panel F.O.P.P , 17

    data switch CAT6 a 1 24 RJ 45 ports and UTP P.P CAT6 a 2 No.

    24 ports and blank ),ref FD3G,FD4G ,FD6G with and

    connected with power supply

    05 Wall mounted telecommunication outlet 1 port (1data ) , ref. (T0) 27 No.

    06 Ceiling mounted telecommunication outlet 1 port (1data ) , 77 No.

    ref. (T0)

    07 Wall mounted telecommunication outlet 1 port for intercome 17 No.

    system

    08 Wall mounted telecommunication outlet 1 port (1 Tel ) 38 No.

    at 1500 mm A.F.F.L , ref. (T01)

    To Collection SR

    Project No. J10-13300

    ZUHAIR FAYEZ PARTNERSHIP

    58 / 67

    REVISED PAGE

    Date: MAY 2012

  • 7/28/2019 CL05 (MAY 2012)

    59/67

    PROJECT: Infrastructure buildings of the residential complex (phase 2)

    of ITCC complex - RIYADH

    REVISED BOQ FOR PARKING CLUSTERS (CL05)

    AMOUNT

    SRRATE