chle update
DESCRIPTION
CHLE Update. STP October Team Lead Meeting 11/29/2012 Janet Leavitt, Ph.D. Overview. T2 LBLOCA Results Bench Top Experiments NRC Call. Corrosion/precipitation scenario. T2 LBLOCA. Objective Determine the mass of aluminum corrosion - PowerPoint PPT PresentationTRANSCRIPT
1
CHLE UpdateSTP October Team Lead Meeting
11/29/2012Janet Leavitt, Ph.D.
2
Overview
• T2 LBLOCA Results
• Bench Top Experiments
• NRC Call
Corrosion/precipitation scenario
4
T2 LBLOCA• Objective
– Determine the mass of aluminum corrosion– Evaluate possible effects of key corrosion and dissolution materials on head
loss• Conditions
– 15” Temperature profile– 6.5 hr spray– Standard Chemistry
• Boric Acid, LiOH, TSP, HCL, HNO3
– Multiple Materials• Submerged zinc granules determined from 371 lbs of paint chips• Vapor and submerged STP aluminum scaffolding (90%/10%)• Submerged Fiber glass – columns and tank (41%/59%)• Submerged concrete
5
T2 LBLOCA Preliminary Results
• SEM– Membranes
– Scale
– Coupons
• ICP Analysis of Scale• XRD• XPS
• Temperature Profile• Approach Velocity• Differential Pressure• pH• Turbidity• Select metal
concentrations
6
Temperature Profile
7
Velocity
8
Temperature Corrected Dp
9
pH
10
Turbidity
11
Measured Aluminum
12
Measured Calcium
13
Measured Silicon
14
Measured Zinc
CHLE Tank
CHLE Head Loss Columns
Debris beds in head loss columnsBlender bed vs. NEI bed
18
Vapor Space Materials
Pre-test Post-test
19
Submerged Materials
• Pre-test
Pre-test Post-test
20
Inside the Mesh
21
Submerged MaterialPre-test
Post-test
22
Scale
23
ICET Test 2
24
Post-test Tank Solution
25
SEM of Scale
Element Atomic %O 56.3P 18.6
Zn 25.1
26
Digested Scale ICP-OES Results
Metal mg/Kg %Aluminum 180 0.04
Calcium 1000 0.21
Silicon 100 0.02
Zinc 480,000 99.73
27
XRD of Scale
• Crystalline• Mixture
– Main phase – Zn3(PO4)2●4H2O (Hopeite)– Trace phase – CaAl2Si7O18 ● 6H2O (Heulandite)
28
Scale on Submerged Al
• Preliminary SEM results – Similar to constituents of MBLOCA scale
• Aluminum and oxygen• Aluminum, phosphorous, and oxygen• Exception; trace amounts of zinc detected
– Possibly more scale
MBLOCA LBLOCA
29
Awaiting….
• Post-test analysis of bed• XPS Results
– Another confirmation of scale constituents– Provides stoichiometric formula
30
Post-test beds
31
SEM
Element Element % Atomic %O 7.3 24.2Zn 92.7 75.8
32
Zinc Material
33
SEM
Element Atomic %O 73.7P 11.4
Ca 3.9Zn 10.9
Element Atomic %O 56.3P 18.6
Zn 25.1
ScaleCaptured Particle
34
SEM
Element Atomic % O 88. 7 Al 7.1 Si 4.2
35
SEM
36
T2 Observations• Visible chemical product were detected • Measured aluminum concentrations are ~1/3 of that detected in T1• The filtered concentrations of zinc, aluminum and calcium maybe
lower than the total concentration• Membrane filters appears to capture more debris as compared to
T1• Turbidity has decreased to the lowest levels observed during the
testing series• NEI beds in C2 and C3 measure head loss due to solution
constituents • Chemical products may mainly be a zinc phosphate with trace
amounts of aluminum and/or calcium products
37
Bench Top Experiments• Batch Corrosion test
– Three temperatures (85, 60, 35 oC)– Three solution pH values (6.0, 7.2, 7.7)– Two time frames (24 hours and 30 days)– Aluminum only, aluminum and silicon, zinc only
• Batch Dissolution/leaching test– Fiberglass dissolution in the presence of soluble aluminum
• Three temperatures, pH values and two time frames– Concrete leaching test for UNM and Southern concrete samples
• Path forward– Test plan will be re-visited after evaluation of current test result– More bench test for corrosion focused on zinc and aluminum materials– Another integrated tank test with blender bed
38
NRC Call• Kerry to discuss UNM position • UNM’s position is supported by four test• Basis for Conclusion
– The release of corroded aluminum into solution is much less than predicted
– Precipitation in the bulk solution is not likely to have occurred– If precipitates were to form, they would be unlikely to cause a
significant increase in head loss• Conclusion
– Chemical precipitates are expected to have no effect on the ECCS strainers at the STP plant for all LOCAs smaller than a 6-inch break
• Likely valid for breaks up to 15 inches
39
Questions?
Series 100: Leaching (concrete, debris)Series 200: Al corrosion T> 85 C
Lab Tests
Series 2000 -3000: Corrosion TestMax 30 day and initial release , variability
Series 4000: Precipitation testIdentification, characterization, variability
30 Day Tank Tests
Test 3: SBLOCA
Test 2: LBLOCA
Test 1 : Shake down
Test 4: MBLOCA
Short Term Tank Test
Test 1: Bed thickness to particulate Ratio 1
Test 2: Bed thickness to particulate Ratio 2
Test 2: Bed thickness to particulate Ratio 3
CASA
Thermodynamic Modeling
Precipitate calculator
Head Loss Calculator
Streamline CFD CalculationNE View
Slide 41
Velocity Magnitude and Unit Vector CFD Calculation
NE View
Slide 42