checked,8834,project reveiw meet formats - november

Upload: rohitsingh

Post on 05-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    1/30

    Master Job Data Sheet

    Sl.

    No.

    Description

    1 Contract Commencement Date

    2 Original Contract Period (in months)

    3 Contractual completion date (As Extended)

    4 Expected Completion Date

    5 Original Contract Value ( in Rs Cr )

    6 Gross Value of work as per latest CE Oct'10 ( in Rs Cr )

    7 JTD Work Done till 31/03/2010 ( in Rs Cr )

    8 Revised Target Turnover for FY 10-11 ( in Rs Cr )

    9 Actual YTM Oct'10 ( in Rs Cr )

    10 Asking Rate (Nov'10 Mar'11)( in Rs Cr )

    Page 1

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    2/30

    Master Job Data Sheet

    Remarks

    1st January 2010

    22 Months

    30th Octomber 2010

    30th Octomber 2010

    32

    32

    0.63

    17.68

    4.322.6

    Page 2

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    3/30

    Phy Prg

    Sl.

    No

    Activity Unit Original Scope Revised Scope

    1 Excavation Cum 16000 16000

    2 Raft Foundation Cum 8354 8354

    3 RCC Shell Cum 11896 11896

    4

    5

    6

    7

    8

    9

    10

    Physical Progress

    Page 1

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    4/30

    Phy Prg

    Cumulative

    Achieved

    Balance Remarks

    16000

    8354

    232 11664

    Page 2

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    5/30

    Financial Prg

    Sl.

    No

    Activity Unit Original Target

    Current Year

    Revised Target

    Current Year

    1 RCC of Shell Cum 9.75 9.75

    2 Flue Can Fabrication MT 2.29 2.29

    3 Plat form Fabrication MT 2.46 2.46

    4

    5

    6

    7

    8

    9

    10

    Financial Progress

    Page 3

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    6/30

    Financial Prg

    YTM Balance

    0.21 9.54

    2.29

    2.46

    Page 4

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    7/30

    Financial Progress Billing

    Month Revised Budget

    (Monthly)

    Revised Budget

    (Cumulative)

    Actual Achieved

    (Monthly)

    Apr'10 0.64 0.64May'10 0.64 1.28 0.16

    Jun'10 0.64 1.92 1.5

    Jul'10 0.64 2.56 1.51

    Aug'10 0.64 3.2 0.21

    Sep'10 3.2Oct'10 2.05 5.25

    Nov'10 2.25 7.5

    Dec'10 2.37 9.87Jan'11 2.57 12.44

    Feb'11 2.67 15.11

    Mar'11 2.57 17.68

    Total 17.68 17.68 3.38

    Page 5

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    8/30

    Financial Progress Billing

    Amount in Rs Crs

    Actual Achieved

    (Cumulative)

    % Cumulative Remarks

    0.16 12.50%

    1.66 86.46%

    3.17 123.83%

    3.38 105.63%

    3.38 105.63%3.38 64.38%

    3.38 45.07%

    3.38 34.25%3.38 27.17%

    3.38 22.37%

    3.38 19.12%

    3.38 19.12%

    Page 6

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    9/30

    Financial Progress Billing

    0.00

    Page 7

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    10/30

    FP-Billing

    Dec'10 Jan'11

    1 Raft Foundation 3.18

    2 RCC of Shell 0.21 2 2.25 1.75

    3 Plat form Fabrication

    4 Flue Can Fabrication 0.76

    56

    7

    8

    9

    10

    3.39 2 2.25 2.51Total

    Sl.

    No

    Top 10 Items YTM Oct'10

    Actual

    Nov'10

    Likely

    Proje

    Page 8

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    11/30

    FP-Billing

    Amount in Rs Crs

    Feb'11 Mar'11

    3.18

    1.75 1.75 9.71

    1.25 1.26 2.51

    0.76 0.76 2.28

    3.76 3.77 17.68

    FY 10-11tions

    Page 9

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    12/30

    Con Est

    Sl.

    No

    Description

    1 Work Done (Undisputed)

    a Turnover 32 32b Escalation

    c Extra items / Variations / others

    A Total (a + b + c ) 32 32

    2 Cost

    I Blue Sheet Expenditure 15.9 50% 15.9

    II Yellow Sheet Expenditure 6.98 22% 6.98

    B Sub total (BS+YS) ( I + II ) 22.88 72% 22.88

    III Plant Hire (Internal) 1.93 6% 1.93

    IV H.O. Overheads 0.74 2% 0.74

    V H. O. Finance Cost

    VI Contingencies 0.25 1% 0.25

    C Sub total (HO Cost) 2.92 9% 2.92

    D Total Cost ( B + C ) 25.8 81% 25.8

    3 Contribution @ Site Level (A B) 9.12 29% 9.12

    4 Profit @ H. O. Level (A D) 6.2 19% 6.2

    1st CE Previous CE

    Page 10

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    13/30

    Con Est

    Amount in Rs Crs

    32

    32

    50% 15.9 50%

    22% 6.98 22%

    72% 22.88 72%

    6% 1.93 6%

    2% 0.74 2%

    1% 0.25 1%

    9% 2.92 9%

    81% 25.8 81%

    29% 9.12 29%

    19% 6.2 19%

    Mar'10 Latest CE Oct'10

    Page 11

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    14/30

    CE

    Sl.

    No

    Description

    1 Work Done (Undisputed)

    a Turnover 32 4.32b Escalation

    c Extra items / Variations / others

    A Total (a + b + c ) 32 4.32

    2 Cost

    I Blue Sheet Expenditure 15.9 50% 2.76 64%

    II Yellow Sheet Expenditure 6.98 22% 0.93 22%

    B Sub total (BS+YS) ( I + II ) 22.88 72% 3.69 85%

    III Plant Hire (Internal) 1.93 6% 0.08 2%

    IV H.O. Overheads 0.74 2% 0.03 1%

    V H. O. Finance Cost

    VI Contingencies 0.25 1%

    C Sub total (HO Cost) 2.92 9% 0.11 3%

    D Total Cost ( B + C ) 25.8 81% 3.8 88%

    3 Contribution @ Site Level (A B) 9.12 29% 0.63 15%

    4 Profit @ H.O.Level (A D) 6.2 19% 0.52 12%

    Latest CE Oct'10 JTD Sept'10

    Page 12

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    15/30

    CE

    Amount in Rs Crs

    3.69

    27.68 3.69 13.99 17.68

    13.14 47% 2.31 63% 2.99 21% 5.3

    6.05 22% 1.56 42% 0.52 4% 2.08

    19.19 69% 3.87 105% 3.51 25%

    1.85 7% 0.07 2% 0.84 6%

    0.71 3% 0.03 1% 0.32 2%

    0.25 1%

    2.81 10% 0.09 3% 1.17 8%

    22 79% 3.96 107% 4.68 33%

    8.49 31% -0.18 -5% 10.48 75%

    5.68 21% -0.2739583 -7% 9.3127094 67%

    Balance YTM Sept'10 Balance for the

    year (10-11)

    Page 13

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    16/30

    CashFlow

    Amt in Rs Crs.

    Description Receipts Recoupment Net Inflow

    Actual

    April'10 to Sept'10 4.68 3.7 0.98

    Oct'10

    Total 4.68 3.7 0.98

    Projected

    Nov'10 1.2 -1.2

    Dec'10 1.68 1.38 0.3

    Jan'11 3.57 2.22 1.35Feb'11 2.03 2.33 -0.3

    March'11 2.26 2.5 -0.24

    Total 9.54 9.63 -0.09

    Total for Year 10-11 14.22 13.33 0.89

    Page 14

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    17/30

    Inflow

    Am

    Sl.

    No.

    Description Receipts Recoupment

    1 JTD as on 31st March 2010.

    2 YTM as on 30th

    September 2010. 4.323 JTD as on 30th September 2010 4.68 4.32

    4 Projected Oct'10 To March'11 9.72 10.44

    5 Expected JTD (31st March 2011) 9.72 10.44

    5.4

    Page 15

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    18/30

    Inflow

    ount in Rs Crs

    Net Inflow

    4.320.36

    -0.72

    -0.72

    Page 16

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    19/30

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    20/30

    Work Cap

    A

    31st

    March

    2010

    30th

    Sept 2010 31st

    Oct 2010

    1 Receivables 4.68 0.08

    2 Liability 0.58 1.69 2.45

    3 Stock 0.27 1.85 1.92

    -0.31 4.84 -0.45

    Sl.

    No

    Description As on

    Net Working Capital

    Page 18

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    21/30

    Work Cap

    ount in Rs Crs

    Projected 31st

    March 2011

    9.72

    10.44

    -0.72

    Page 19

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    22/30

    Plant & Equipment

    A

    Owned

    1 Total no of Plants at Site 84

    2 Value of Plant at site (Purchase Price / Gross Block)

    3 Energy Consumption

    a POL 0.02

    b Energy Consumption

    Total 0.02

    4 Cost of Spares in H1 (April'10 to Sept'10) 0.08

    5 Cost of Repairs in H1 (April'10 to Sept'10) 0.02

    0.02

    6 Hire Charges in H1 (April'10 Sept'10)

    (Internal)

    Sl.

    No

    Description Plant & E

    Page 20

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    23/30

    Plant & Equipment

    ount in Rs Crs

    Hired

    5

    (External)

    uipment

    Page 21

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    24/30

    Milestone

    Start Date End Date Start Date

    1 Milestone - I2 Milestone II

    3 Milestone III

    Sl.

    No

    Description Planned Achi

    Page 22

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    25/30

    Milestone

    End Date Remarks

    eved Progress %

    Page 23

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    26/30

    Right of Way

    Both way One way

    12

    3

    4

    5

    Sl.

    No

    Chainage Clearance received Remarks

    Page 24

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    27/30

    PNM Performance

    Productivity

    Norms

    Unit Achieved

    Productivity

    1

    Batching Plant Schwing

    StetterConcrete Cum 20.14 cum/hrs

    2 Concrete Pump (Bp-350E) Concrete Cum 4.55 cum/hrs

    3

    Sl.

    No

    Plant Description Perfor

    Page 25

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    28/30

    PNM Performance

    Fuel

    Consumption

    Weightage Remarks

    ance

    Page 26

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    29/30

    HR

    ASl.

    No

    Category Head Count Nos

    (As on 31/10/10)

    H1 Cost

    (April'10 to

    Sept'10)

    Oct'10 Cost

    1 H O Staff 22 0.75

    2 LMR 71 2368127 549073

    3 DMR

    4 PRW Workers 175 1737174 448650

    Remarks :

    Page 27

  • 8/2/2019 Checked,8834,Project Reveiw Meet Formats - November

    30/30

    HR

    ount in Rs CrsExpected Cost

    (April'10 to

    March'11)