checked,8834,project reveiw meet formats - november
TRANSCRIPT
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
1/30
Master Job Data Sheet
Sl.
No.
Description
1 Contract Commencement Date
2 Original Contract Period (in months)
3 Contractual completion date (As Extended)
4 Expected Completion Date
5 Original Contract Value ( in Rs Cr )
6 Gross Value of work as per latest CE Oct'10 ( in Rs Cr )
7 JTD Work Done till 31/03/2010 ( in Rs Cr )
8 Revised Target Turnover for FY 10-11 ( in Rs Cr )
9 Actual YTM Oct'10 ( in Rs Cr )
10 Asking Rate (Nov'10 Mar'11)( in Rs Cr )
Page 1
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
2/30
Master Job Data Sheet
Remarks
1st January 2010
22 Months
30th Octomber 2010
30th Octomber 2010
32
32
0.63
17.68
4.322.6
Page 2
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
3/30
Phy Prg
Sl.
No
Activity Unit Original Scope Revised Scope
1 Excavation Cum 16000 16000
2 Raft Foundation Cum 8354 8354
3 RCC Shell Cum 11896 11896
4
5
6
7
8
9
10
Physical Progress
Page 1
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
4/30
Phy Prg
Cumulative
Achieved
Balance Remarks
16000
8354
232 11664
Page 2
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
5/30
Financial Prg
Sl.
No
Activity Unit Original Target
Current Year
Revised Target
Current Year
1 RCC of Shell Cum 9.75 9.75
2 Flue Can Fabrication MT 2.29 2.29
3 Plat form Fabrication MT 2.46 2.46
4
5
6
7
8
9
10
Financial Progress
Page 3
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
6/30
Financial Prg
YTM Balance
0.21 9.54
2.29
2.46
Page 4
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
7/30
Financial Progress Billing
Month Revised Budget
(Monthly)
Revised Budget
(Cumulative)
Actual Achieved
(Monthly)
Apr'10 0.64 0.64May'10 0.64 1.28 0.16
Jun'10 0.64 1.92 1.5
Jul'10 0.64 2.56 1.51
Aug'10 0.64 3.2 0.21
Sep'10 3.2Oct'10 2.05 5.25
Nov'10 2.25 7.5
Dec'10 2.37 9.87Jan'11 2.57 12.44
Feb'11 2.67 15.11
Mar'11 2.57 17.68
Total 17.68 17.68 3.38
Page 5
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
8/30
Financial Progress Billing
Amount in Rs Crs
Actual Achieved
(Cumulative)
% Cumulative Remarks
0.16 12.50%
1.66 86.46%
3.17 123.83%
3.38 105.63%
3.38 105.63%3.38 64.38%
3.38 45.07%
3.38 34.25%3.38 27.17%
3.38 22.37%
3.38 19.12%
3.38 19.12%
Page 6
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
9/30
Financial Progress Billing
0.00
Page 7
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
10/30
FP-Billing
Dec'10 Jan'11
1 Raft Foundation 3.18
2 RCC of Shell 0.21 2 2.25 1.75
3 Plat form Fabrication
4 Flue Can Fabrication 0.76
56
7
8
9
10
3.39 2 2.25 2.51Total
Sl.
No
Top 10 Items YTM Oct'10
Actual
Nov'10
Likely
Proje
Page 8
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
11/30
FP-Billing
Amount in Rs Crs
Feb'11 Mar'11
3.18
1.75 1.75 9.71
1.25 1.26 2.51
0.76 0.76 2.28
3.76 3.77 17.68
FY 10-11tions
Page 9
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
12/30
Con Est
Sl.
No
Description
1 Work Done (Undisputed)
a Turnover 32 32b Escalation
c Extra items / Variations / others
A Total (a + b + c ) 32 32
2 Cost
I Blue Sheet Expenditure 15.9 50% 15.9
II Yellow Sheet Expenditure 6.98 22% 6.98
B Sub total (BS+YS) ( I + II ) 22.88 72% 22.88
III Plant Hire (Internal) 1.93 6% 1.93
IV H.O. Overheads 0.74 2% 0.74
V H. O. Finance Cost
VI Contingencies 0.25 1% 0.25
C Sub total (HO Cost) 2.92 9% 2.92
D Total Cost ( B + C ) 25.8 81% 25.8
3 Contribution @ Site Level (A B) 9.12 29% 9.12
4 Profit @ H. O. Level (A D) 6.2 19% 6.2
1st CE Previous CE
Page 10
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
13/30
Con Est
Amount in Rs Crs
32
32
50% 15.9 50%
22% 6.98 22%
72% 22.88 72%
6% 1.93 6%
2% 0.74 2%
1% 0.25 1%
9% 2.92 9%
81% 25.8 81%
29% 9.12 29%
19% 6.2 19%
Mar'10 Latest CE Oct'10
Page 11
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
14/30
CE
Sl.
No
Description
1 Work Done (Undisputed)
a Turnover 32 4.32b Escalation
c Extra items / Variations / others
A Total (a + b + c ) 32 4.32
2 Cost
I Blue Sheet Expenditure 15.9 50% 2.76 64%
II Yellow Sheet Expenditure 6.98 22% 0.93 22%
B Sub total (BS+YS) ( I + II ) 22.88 72% 3.69 85%
III Plant Hire (Internal) 1.93 6% 0.08 2%
IV H.O. Overheads 0.74 2% 0.03 1%
V H. O. Finance Cost
VI Contingencies 0.25 1%
C Sub total (HO Cost) 2.92 9% 0.11 3%
D Total Cost ( B + C ) 25.8 81% 3.8 88%
3 Contribution @ Site Level (A B) 9.12 29% 0.63 15%
4 Profit @ H.O.Level (A D) 6.2 19% 0.52 12%
Latest CE Oct'10 JTD Sept'10
Page 12
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
15/30
CE
Amount in Rs Crs
3.69
27.68 3.69 13.99 17.68
13.14 47% 2.31 63% 2.99 21% 5.3
6.05 22% 1.56 42% 0.52 4% 2.08
19.19 69% 3.87 105% 3.51 25%
1.85 7% 0.07 2% 0.84 6%
0.71 3% 0.03 1% 0.32 2%
0.25 1%
2.81 10% 0.09 3% 1.17 8%
22 79% 3.96 107% 4.68 33%
8.49 31% -0.18 -5% 10.48 75%
5.68 21% -0.2739583 -7% 9.3127094 67%
Balance YTM Sept'10 Balance for the
year (10-11)
Page 13
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
16/30
CashFlow
Amt in Rs Crs.
Description Receipts Recoupment Net Inflow
Actual
April'10 to Sept'10 4.68 3.7 0.98
Oct'10
Total 4.68 3.7 0.98
Projected
Nov'10 1.2 -1.2
Dec'10 1.68 1.38 0.3
Jan'11 3.57 2.22 1.35Feb'11 2.03 2.33 -0.3
March'11 2.26 2.5 -0.24
Total 9.54 9.63 -0.09
Total for Year 10-11 14.22 13.33 0.89
Page 14
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
17/30
Inflow
Am
Sl.
No.
Description Receipts Recoupment
1 JTD as on 31st March 2010.
2 YTM as on 30th
September 2010. 4.323 JTD as on 30th September 2010 4.68 4.32
4 Projected Oct'10 To March'11 9.72 10.44
5 Expected JTD (31st March 2011) 9.72 10.44
5.4
Page 15
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
18/30
Inflow
ount in Rs Crs
Net Inflow
4.320.36
-0.72
-0.72
Page 16
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
19/30
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
20/30
Work Cap
A
31st
March
2010
30th
Sept 2010 31st
Oct 2010
1 Receivables 4.68 0.08
2 Liability 0.58 1.69 2.45
3 Stock 0.27 1.85 1.92
-0.31 4.84 -0.45
Sl.
No
Description As on
Net Working Capital
Page 18
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
21/30
Work Cap
ount in Rs Crs
Projected 31st
March 2011
9.72
10.44
-0.72
Page 19
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
22/30
Plant & Equipment
A
Owned
1 Total no of Plants at Site 84
2 Value of Plant at site (Purchase Price / Gross Block)
3 Energy Consumption
a POL 0.02
b Energy Consumption
Total 0.02
4 Cost of Spares in H1 (April'10 to Sept'10) 0.08
5 Cost of Repairs in H1 (April'10 to Sept'10) 0.02
0.02
6 Hire Charges in H1 (April'10 Sept'10)
(Internal)
Sl.
No
Description Plant & E
Page 20
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
23/30
Plant & Equipment
ount in Rs Crs
Hired
5
(External)
uipment
Page 21
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
24/30
Milestone
Start Date End Date Start Date
1 Milestone - I2 Milestone II
3 Milestone III
Sl.
No
Description Planned Achi
Page 22
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
25/30
Milestone
End Date Remarks
eved Progress %
Page 23
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
26/30
Right of Way
Both way One way
12
3
4
5
Sl.
No
Chainage Clearance received Remarks
Page 24
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
27/30
PNM Performance
Productivity
Norms
Unit Achieved
Productivity
1
Batching Plant Schwing
StetterConcrete Cum 20.14 cum/hrs
2 Concrete Pump (Bp-350E) Concrete Cum 4.55 cum/hrs
3
Sl.
No
Plant Description Perfor
Page 25
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
28/30
PNM Performance
Fuel
Consumption
Weightage Remarks
ance
Page 26
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
29/30
HR
ASl.
No
Category Head Count Nos
(As on 31/10/10)
H1 Cost
(April'10 to
Sept'10)
Oct'10 Cost
1 H O Staff 22 0.75
2 LMR 71 2368127 549073
3 DMR
4 PRW Workers 175 1737174 448650
Remarks :
Page 27
-
8/2/2019 Checked,8834,Project Reveiw Meet Formats - November
30/30
HR
ount in Rs CrsExpected Cost
(April'10 to
March'11)