reveiw on 27.09.07 at site

Upload: mukul-bain

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Reveiw on 27.09.07 at Site

    1/22

    ECC Division

    Welcome to our Honourable

    HEAD - IP&U Sectorand

    HEAD-M&M BU

    At BSL Site

  • 7/30/2019 Reveiw on 27.09.07 at Site

    2/22

    ECC Division

    Civil, Structural, Equipment & Piping Works at

    Bhushan Steel Limited, Angul

    Project Review

    Consultant: MECON, Ranchi

    On 28thSeptember2007

  • 7/30/2019 Reveiw on 27.09.07 at Site

    3/22

    Salient Features of the Project

    Cement, Steel, Equipments & Pipes including the Coarse & FineAggregates are free issue materials by Client.

    Description CUMS 6534 CUMS 6538RCV (L) 14015 12209Cont Start 28th Oct' 06 14th Feb' 07Act Start 07th Jan' 07 15th Feb' 07Cont Comp 27th Nov' 08 13th Mar' 09Exp Comp 27th Nov' 08 13th Mar' 09Cont Duration 25 Months 25 MonthsInv as on Sep'07 (L)

    3379.02 545.76

    % Comp w.r.t. Inv 24.11% 4.47%

  • 7/30/2019 Reveiw on 27.09.07 at Site

    4/22

    Major Scope of Works & Values

    Equipmet,

    5250 L Structura,

    6929 L

    Civil,

    8105L

    Slipform,

    340 LPiping,

    5600 L

    Civil Structural Equipmet Piping Slipform

    Concrete Cum 300000Structural MT 40000Equipment MT 35000Piping MT 3000Slip form Sqm 18658

    Civil, Structural, Equipment

    & Piping Works for

    SMS II

    Slab CasterHot Strip Mill

    Water Complex

    Civil Works for Coke Oven

    Total:

    26224 L

  • 7/30/2019 Reveiw on 27.09.07 at Site

    5/22

    Completion Status as on Sep07

    Com leted Balance

    30%

    STATUS OF STRUCTURAL WORK

    Completed Balance

    20%

    80%

    Equipment & Piping Work Yet to

    Start.

  • 7/30/2019 Reveiw on 27.09.07 at Site

    6/22

    Civil Works

  • 7/30/2019 Reveiw on 27.09.07 at Site

    7/22

    Concrete Status at a Glance on 26th Sep 2007

    Civil WorksUOM

    SMS - II

    HSM

    Water

    Comp

    Coke

    Oven Total

    Estimated Quantity Cum 70000 118000 85000 55000 328000

    Drawing Released Cum 62402 67407 42932 44950 217691

    Front Available Cum 51357 59107 27732 15850 154046

    Ach as on 26.09.07 Cum 50721 41107 24997 8426 125251

    % ofAchievement

    72% 35% 29% 15% 38%

    Balance

    QuantityCum 19279 76893 60003 46574 202749

  • 7/30/2019 Reveiw on 27.09.07 at Site

    8/22

    Area wise Status of Progress for SMS & CASTER

    Description UOM Scope Comp%

    CompTarget Date Remarks

    Building Clmn Fdn Nos 187 140 75% 30-Nov-07 J Row front NA

    Slab Caster Area Cum 8800 7035 80% 31-Jan-08Drg. Yet to recd.

    For roof slab

    CONARC Area Cum 5000 4941 99% 30-Sep-07

    Transformer Room(33mtr high 05 slab)

    Cum 1000 496 49.6% 31-May-08Hold due to CG

    erection.

    Torpedo Relading Cum 4550 2350 52% 31-Dec-07

    Flume Tunnel Cum 1000 300 30% 31-Jan-08 Front yet to recd

    Cable Tunnel Cum 4094 2944 72% 30-Nov-07 Front yet to recd

  • 7/30/2019 Reveiw on 27.09.07 at Site

    9/22

    Area wise Status of Progress for SMS & CASTER

    Description UOM Scope Comp%

    Comp

    Target

    DateRemarks

    Water Tunnel Cum 13400 1238 9% 28-Feb-08140mtr. Front recd

    O/F 806mtr.

    Scale Pit - Water

    System

    Cum 3500 0% 31-May-08Front yet to

    receive.

    Water Complex Cum 28000 24248 87% 31-Mar-08

    LT Sub Station Cum 1730 391 22% 31-Mar-08Front-02 bldg

    (+14.00mtr 03 slab)

    MRSS Cum 1660 31-May-0822mtr. Front recd

    O/F 100mtr

    Fume Extraction

    System

    Cum 5000 31-May-08Front yet to

    receive

  • 7/30/2019 Reveiw on 27.09.07 at Site

    10/22

    Area wise Status of Progress for HSM -

    Area Description UOM Scope Comp% of

    Comp

    Comp.

    TargetRemarks

    Raft Cum 27900 24377 87%31-Oct-07 34grid to 37grid drg.

    & front Yet to recd.

    Wall & Column Cum 13900 1027 7% 31-Jan-0834grid to 37grid drg.

    & front Yet to recd.

    Slab Cum 12600 28-Feb-088th grid to 37th grid

    drg. Yet to recd.

    Bldg. Clmn. Fdn

    except mill bayCum 9000 300 3% 28-Feb-08 Front yet to recd.

    ECR & Motor Room Cum 7500 31-Apr-o8ECR 2 & 3 drg & front

    yet to recd.

    Re-Heating Furnace Cum 31-Apr-o8Drg. & Front yet to

    recd.

    Down Coiler Cum31-May-08 Drg. & Front yet to

    recd.

    Water Com Cum 40000 31-May-08 Drg. & Front yet to

    recd.

  • 7/30/2019 Reveiw on 27.09.07 at Site

    11/22

    Structural

    Works

  • 7/30/2019 Reveiw on 27.09.07 at Site

    12/22

    Structural Status at a Glance on 26th Sep 2007

    AreaEst.

    Qty

    Drg

    Issued

    Match

    Steel

    Fab

    Comp

    WIP

    Fab

    Erec

    Comp

    SMS &

    Caster

    Building17000 16452 12100 7558 1786 1962

    HSM

    Building10000 3934 528 165 278

    WC & Others 3100 1918 710 495 546

    Tech Str inclFES & Ducts

    9900 6099 1237 120 49

    Total 40000 28403 14575 8338 2659 1962

  • 7/30/2019 Reveiw on 27.09.07 at Site

    13/22

    Structural Building Features:

    SMS & Caster BuildingMaximum Height of Column: 62.00 Mtr

    Maximum Weight of Column (Single Lift): 64.00 MT

    Maximum Weight of Crane Girder (Single Lift): 181.0 MT

    All the columns in ABCD Row to be erected in 02 Lifts

    HSM Building

    Maximum Height of Column: 26.00 Mtr

    Maximum Weight of Column (Single Lift): 28.00 MT

    Maximum Weight of Crane Girder (Single Lift): 14.00 MT

    Technological Structure including FES & Stack to be

    fabricated at site (Approx9900 MT)

  • 7/30/2019 Reveiw on 27.09.07 at Site

    14/22

    Progress Status of SMS II Building Column

    Sl.No

    Description Uom Qty Remarks

    A Total No. of Column Nos. 145

    BColumn fabrication

    Comp.Nos. 106

    C Column Erection Comp Nos. 49

    Balance

    erection front

    to be released

  • 7/30/2019 Reveiw on 27.09.07 at Site

    15/22

    Civil Completion : 15th Oct 2007

    Strl Completion : 31st Dec 2007

    EOT Erection from : 01st Nov 2007

    Eqpt Erection from: 01st Dec 2007

    Civil Completion : 31st Oct 2007

    Strl Completion : 28th Feb 2008

    Eqpt Erection from: 01st Jan 2008

    Civil Completion : 31st Dec 2007

    Strl Completion : 30th Apr 2008

    Eqpt Erection from: 01st Mar 2008

    Civil Completion : 31st Oct 2007

    Strl Completion : 31st Jan 2008

    EOT Erection from : 01st Dec 2007

    Eqpt Erection from : 01st Jan 2008

    Civil Completion : 31st Jan 2007

    Strl Completion : 30th Apr 2008

    Eqpt Erection from : 01st Feb 2008

  • 7/30/2019 Reveiw on 27.09.07 at Site

    16/22

    +62.00mtr

  • 7/30/2019 Reveiw on 27.09.07 at Site

    17/22

    Equipment

    & PipingWorks

  • 7/30/2019 Reveiw on 27.09.07 at Site

    18/22

    Equipment Break Up:Sl No Description UOM Appx. Wt Start Date Finish date Duration

    1 SMS II Days

    1.1 Conarc MT 2306 01-Dec-07 31-May-08 182

    1.2 Caster MT 1906 01-Dec-07 30-Jun-08 212

    1.3 LRF MT 331 02-Jan-08 31-May-08 150

    1.4 HMDS MT 96 01-Mar-08 30-Jun-08 121

    1.5 RH degasser MT 300 01-Mar-08 30-Jun-08 1211.6 EOT MT 3500 01-Nov-07 15-Apr-08 166

    1.7 FES MT 5579 01-Dec-07 15-Jun-08 197

    Sub Total MT 14018 01-Nov-07 30-Jun-08 242

    2 HSM MT

    2.1 Mill Eqpt. MT 17940 02-Jan-08 30-Jun-08 180

    2.2 EOT MT 1500 01-Dec-07 15-Apr-08 136

    2.3 Other MT 1542 01-Feb-08 30-Jun-08 150

    Sub Total MT 20982 01-Dec-07 30-Jun-08 212

    Total 35000 01-Nov-07 30-Jun-08 242

  • 7/30/2019 Reveiw on 27.09.07 at Site

    19/22

    Major Equipment in SMS & Caster

    1. Electric Arc Furnace (CONARC)02 Nos

    2. Ladle Furnace02 Nos3. Ferro Alloys Storage, Additive & Storage System

    4. Hot Metal De-Sulphurizing System with Storage Silo

    5. Ladle Transfer Cars & Ladle Pre Heating System

    6. Ladle Turret for Caster

    7. Oscillating Mould, Segments & Tundish with Car

    8. EOT for SMS & Caster13 Nos

    9. Control Rooms & Hydraulic Rooms

    10.Torpedo Cars

    11.Complete Hydraulic & Utility System

  • 7/30/2019 Reveiw on 27.09.07 at Site

    20/22

    Major Equipment in HSM

    1. Reheating Furnace : 02 + 01 Nos

    2. De-scaler : 01 No

    3. Roughing Mills : 02 + 01 Nos

    4. Finishing Mills : 06 + 01 Nos5. Down Coiler : 02 + 01 Nos

    6. EOT : 09 Nos

    7. Complete Hydraulic & Utility System

  • 7/30/2019 Reveiw on 27.09.07 at Site

    21/22

    1. Civil Works

    Balance Drawing and Work front to be released for HSM,

    SMSII, water complex & Coke oven area

    2. Structural Works

    Balance drawing, matching steel, area for additional

    fabrication yard

    Backfilling to be completed for balance erection works.

    Un-interrupted power supply.3. Equipment & Piping Works

    Detail drawing and packing list. List of equipments with weight.

    Erection manual

    Area for piping fabrication.

    Inputs Required from BSL:

  • 7/30/2019 Reveiw on 27.09.07 at Site

    22/22

    THANKYOU!!!