chapter 1 1.0 introductionenvironmentclearance.nic.in/writereaddata/eia/...sri. raavi surya prakash...
TRANSCRIPT
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 1
CHAPTER –1
1.0 INTRODUCTION
1.1 PURPOSE OF THE REPORT:
Sri. Ravi Surya Prakash Babu is proposes to construct a Residential Complex
with a plot area of about 8,606.89 Sq.mts. The total built up area is 55,126.67
Sq.mts with 313 flats, a club house and parking area at Sy. No: 978 & 979,
Kukatpally Village, Balanagar Mandal, Ranga Reddy District of Telangana.
The proposed site comes under Residential Zone as per the Master Plan of
HMDA vide GO. MS NO. 288, MA Dated 03.04.2008. Copy of certificate from
HMDA confirming this area as residential Zone is enclosed at Annexure I
As the total area proposed to be developed <1,50,000 Square Meters, as
per the EIA Notification dated 14th September 2006, the proposed project
activity falls under Building & Construction projects 8(a) Category B (B2),
which necessities to obtain Environmental Clearance from State Level
Environmental Authority, Telangana. As currently SEIAA in Telangana is not in
place, we are submitting the proposal along with Form-1, Form-1A and
Environmental Management Plan for MOEF clearance at Delhi
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT:
The project is promoted by Sri. Ravi Surya Prakash Babu,1-8-
460/11,Chikkadpally, Hyderabad – 20, Telangana who is into real estate
business for the last 20 years.
1.3 PROJECT COST:
The estimated cost for the proposed project will be 76.32 Crore.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 2
1.4 SALIENT FEATURES OF THE PROJECT:
The salient features of the project are given below
TABLE 1.1 – SALIENT FEATURES OF THE PROJECT
Total Plot Area 8,606.89 Sq.mts/10,285 Syds
Land Scaping & Greenbelt
Area
Land Scape :874.31Sq.mts
Green belt: 325.5 Sq.mts
No.of Blocks with Built-up area
Blocks No. of
Floors
No. of
Flats
Area
(Sq.mts)
Block-I
G+12
Floors
313
38659.94
Club
House (
Located
in
Ground
& 1st
floor of
main
block)
- - 1194.64
Total 313 39,854.58
Parking Facilities
Parking area Area
(Sq.mts)
Cellar parking area 5,034.72
1st Sub cellar parking
area
5,034.72
2nd sub cellar parking
area
5,202.65
Total 15,272.09
Height of the building 39.21 mts
Nearest Fire station Sanath Nagar – 4 Kms
Water requirement & Source 150 KLD of fresh water from HMWS&SB
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 3
Power requirement & Source
230 KVA, APCPDCL
Backup Power 1 x 100 KVA & 1 x 150 KVA DG sets
Solid waste &
mode of disposal
313 kgs/day - waste will be sent to GHMC
300 Kgs/month STP sludge used as manure
Hazardous waste &
mode of disposal
Used batteries – 2 no’s/Year
Waste Oil from D.G. Sets – 80 Liters/Year
Transformer oil – 40 Liters/Year will send to
APPCB Authorized recyclers/
re-processors
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 4
CHAPTER – 2
2.0 PROJECT DESCRIPTION
2.1 LOCATION DETAILS:
Sri. Ravi Surya Prakash Babu is proposes to construct a Residential Complex
with a plot area of about 8,606.89 Sqmts. The total built up area is 55,126.67
Sq.mts. The proposed site is at Sy.No:978 & 979, Kukatpally Village,
Balanagar Mandal, Ranga Reddy District of Telangana.
Features of the site:
The area comes under residential zone as per the Master Plan of HMDA GO
MS NO. 288, MA dated 03.04.2008. Copy of the certificate confirming the
same is enclosed at Annexure I
The site is about 3.8 km from Mosapet – Kukkatpally Road (NH 9) and 0.28
KM from JNTU to Hi-Tech City Road. The geographical co-ordinates of
Residential complex are between 170 27’ 50.8” & 170 27’ 53.8” N latitude and
78 023’40.2” & 78 023’45.6” E longitude. Mean Elevation above MSL is varying
558.5 Meters
i.Accessibility & Existing Road network
The nearest major road is Hitech City to Atapur Road at a distance of 0.28
km from the proposed Residential complex. Outer Ring Road is at about 4
KM from the site and NH9 is at about 3.80 kms from the site. The access to
the project site is through the link road goes to Kukatpally Housing Board
Road at a distance of 1km.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 5
ii.Topography & Surrouding features of the site
The Land is plain area with elevation difference of about 5 metes. Following
are the surrounding features of the proposed site
South Direction - Raiway track of South Central Railway ( 22.38 Meters from
Railway Boundary)
North Direction - Existing 80 Feet Road (200‘sanctioned road under
expansion) abutting the site. Metro water line of HMW&SB is beyond this
road
Eastern Direction - Vacant house sites
Western Direction - Vacant land and Housing complex of weaker section
under Rajiv Griha Kalpa Scheme. A 33/11 KVA Substation is on the North
Western corner of the site
Topo sheet of the area is given at Figure 2.1. Base map of the Area is given
at Figure 2.2 and photographs of the site are given at Figure 2.3 respectively
iii. Water Bodies & other features of the site and 10 KM radius
The major surface water bodies within the 10 kms radius are Hussain Sagar
Lake at about 9.5 KM in the downstream of the site in the South Eastern
Direction, , Durgam Cheruvu is at about 3.4 KM in the Southern direction of
the site. Maisamma Cheruvu is at about 1 KM from the site on North- Eastern
direction and Kaminoni Cheruvu is at about 0.71 KM from the site on North
Eastern direction
Kothaguda RF is at about 5 KM from the proposed site in the Western
direction and Gajularamaram RF is at about 9.5 KM in the North Eastern
direction of the site
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 6
Golkonda Fort is at about 9.25 KM from the proposed site and Kutub Shahi
Tombs are at 7.74 KM in the South –Eastern direction
Kasu Brahmananda Reddy National Part is at about 5 KM from the site
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 7
FIGURE NO: 2.1 – TOPO SHEET OF THE AREA – 10 KM RADIUS
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 8
Figure 2.2 Base Map of the Area
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 9
Figure 2.3 Site photographs
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 10
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 11
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 12
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 13
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 14
TABLE 2.1: SALIENT FEATURES OF PROJECT SITE
Vil lage
Mandal
Distr ict
Kukatpally
Balanagar
Ranga Reddy
Longitude 170 27’ 53.8” N
Lati tude 780 23’ 43.1 ” E
Ambient Temperature Minimum 130 C
Maximum 430C
Humidity 55 – 65 %
Rainfal l 800 – 1100 mm per Annum
Cl imate Tropical & Semi-Arid
Type of soil Hard Morum soil with outcraps
Distance from Urban area Within the urban area, Moosapet
is at 3.8 KM,
Distance from nearest Air Port Shamshabad Airport – 45 kms
Begumpet Airport - 10 kms
Distance from nearest vi l lage Part of Kukatpally Vil lage
Distance from nearest
surface water source
Kamunoni Cheruvu – 0.71 kms
upstream
Reserve Forest Kottaguda RF – 3.43 kms
Any historical monuments
within 10 KM radius
Golkonda Fort –9.25 kms
Kutumshahi Tombs – 7.74 kms
Any ecologically sensitive
areas within 10 KM radius
Kasu Bhramananda Reddy
National Park - 5 kms
Topography Plain and land locked
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 15
2.2 SITE AREA & BUILT-UP AREA:
It is proposed to develop in single block with 313 flats, in an area of 2.05
acres of land. Following is the overall area statement of the site
Table 2.2
Overall Area statement of the Area
S.No Land use Area in Square Meters
1 Total Plot area 8606.89
2 Area affected for road
widening
1615.84
3 Net Area available for
development
6991.05
Table 2.3
Development Plan of the plot
S.NO Land Use Area in square meters
1 Residential block( Plinth
Area)
3198.12
2 Set Back area 2394.08
3 Other utilities
(water storage, STP,
Transformers etc.)
360.11
5 Land scape & Green
belt
1037.74
Total area 6990.05
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 16
2.2.1 Built Up Area:
Following is built up area of the proposed blocks
It is proposed to construct a residential complex with one Block with 313
residential flats (184 Nos 2 BHK and 129 Nos 3 BHK flats) and the club house
details are provided in Table 2.4
TABLE 2.4 – NUMBER OF FLOORS AND AREA
S. No Block Details No. of Floors No .of Flats Area (Sq.Mts)
Block - I Floor
1 Ground Floor 19 & club
House
3,198.12
2 1st floor 19 & club
House
3,198.12
3 2nd floor 25 3226.37
4 3rd floor 25 3226.37
5 4th floor 25 3226.37
6 5th floor 25 3226.37
7 6th floor 25 3226.37
8 7th floor 25 3226.37
9 8th floor 25 3226.37
10 9th floor 25 3226.37
11 10th floor 25 3226.37
12 11th floor 25 3226.37
13 12th floor 25 3226.37
14 Club House G +1 - 1194.64
Total 313 39,854.58
As per the GO. MS No 245 dated 30.06.2012 of Government of AP, if the
development area is less than 5 acres then there is no need to provide EWS
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 17
flats but shall pay the shelter fee @ Rs. 750/ Square Meter. Copy of GO MS
NO 45 is enclosed at Annexure II
2.3 PARKING AREA:
The total area allocated for parking is 15,272.09 Sq.Mts, which can
accommodate 390 four wheelers and 450 two wheelers. The total parking
area is being proposed in the proposed project is given below:
TABLE 2.5 – PARKING SPACE PROVISION
SNo. Parking Facility Area
1 Cellar parking Area 5,034.72
2 1st sub-cellar parking area 5,034.72
3 2nd Sub-cellar area 5,202.65
Total 15,272.09
The conceptual Plan of the project is given at Annexure III
2.4 ROAD NETWORK:
The nearest major road is Hitech City to Alapur Road at a distance of 0.28
km from the Residential complex. Outer Ring Road is at about 4 KM from
the site and NH9 is at about 3.80 kms from the site. The access to the
project site is through the link road goes to Kukatpally Housing Board Road
at a distance of 1km. Fig 2.4 gives road net works and connecting point of
road to the site
2.5 WATER REQUIREMENT:
As per National Building Code,2005 (NBC), water requirement for
occupants is 135 litres/day/ person and for visitors the requirement is 15
litres/day/person. The total population likely to be accommodated would
be around 1400 people. Another 10 people would be there like security
and other support staff. Thus total water requirement for inmates is
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 18
estimated at 190 KLD. Quantity estimated for guests and visitors is
estimated at another 5 KLD. Considering washings of floors and other
requirement, a total requirement is estimated at 200 KLD. Out of this, it is
estimated that 50 KLD of water would be required for toilet flushing’s and
rest for other uses. Also it is estimated that about 50 KLD of water is required
for landscaping and plantation purposes. Thus total water requirement
would be 250 KLD
It is proposed to source water from HMWS&SB and the treated waste water
would be recycled for toilet flashings and green belt. Any additional
treated waste is there, same will be connected to municipal sewer
The total sewage water generated is 170 KLD. It is proposed to treat the
sewage in STP of capacity of 180 KLD. The treated waste water is used for
Flushing & gardening (100 KLD). Rest of the 170 KLD of treated water would
be send to municipal sewer. Thus the total fresh water requirement during
occupational stage is would be 150 KLD as detailed below
TABLE 2.6 – WATER REQUIREMENT
S.No Stream Quantity
(KLD)
Fresh/
Recycled
Waste
water
generated
in KLD
Method of
treatment
1 Domestic Water 150 Fresh 120 STP
2 Toilet Flushing
water
50 Recycled 50 STP
3 Gardening 50 Recycled - -
Total 250 170
2.6 POWER REQUIREMENT:
The power requirement for the proposed project is estimated as 230 KVA
which will be sourced from the APTRANSCO
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 19
2.7 BACK-UP POWER DETAILS:
IT is proposed to provide emergency power back up for lifts, water
pumping and common area lighting with two DG sets of 1x 100 KVA and 1
x 150 KVA capacities.
2.8 FUEL REQUIREMENT:
The fuel requirement for 1 x 100 KVA and 1 x 150 KVA DG sets is 100 Liters.
The fuel used in DG sets is High Speed Diesel (HSD).
2.9 MAN POWER REQUIREMENT:
The maximum man power required for the development of proposed
project during construction phase is 50 persons. And during occupational
phase it would be around 10 people
2.10 ROADS & STREET LIGHTS:
As it is single block residential complex and parking area is provided in
cellars, direct paved road from gate to cellar areas would be provided.
Setbacks of minimum 7 meters al round the block is left for free movement
of fire tender as per the A.P. Fire services directorate guidelines
2.11 STORM WATER DRAINS:
All along the block of the housing complex, storm water drains would be
provided to collect water during rains. They would adequately sized to
prevent over flooding of the site. Storm water collection sump is proposed
before discharging to municipal sewers.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 20
2.12 ENVIRONMENTAL INFRASTRUCTURE:
a). Waste Water Generation & Management:
Total quantity of wastewater generation is likely to be 170 KLD. The
generated waste water is collected and treated in in-house Sewage
Treatment Plant of 180 KLD capacity. Out of the total treated water, 100
KLD is used for Gardening & Flushing and rest would be discharged to
municipal sewers. The water balance details are presented below.
TABLE 2.7 - WATER BALANCE
Input Requirement Quantity Out put Quantity
Domestic 150 Domestic Waste Water 120
Flushing 50 Flushing waste water 50
Gardening 50 Losses and uses 80
Total 250 Total 250
The waste water generated from process i.e 170 KLD which will be treated
in S.T.P. The available recycled water after treatment @ 100 KLD will be
used for Gardening & Flushing and the rest will be disposed to sewer
system. It should therefore be concluded there is no significant impact on
surface water quality & hydrology of the area. The proposed rainwater
harvesting scheme stabilizes the groundwater table in the area.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 21
FIGURE 2.4: WATER BALANCE DIAGRAM
b). Sewage Treatment Plant (STP):
A sewage treatment plant of 180 KLD capacity based on Fluidized Aerobic
Bio-Reactor (FAB) technology is proposed to treat 170 KLD of sewage
water generated in the proposed project .After treatment the water will be
used for Gardening & Flushing.
The design of the STP shall be based on the parameters given in below
table.
70 KLD to
Public Sewer
Daily Fresh Water
150 KLD Domestic Demand
150 KLD
Waste
Water –
170 KLD
STP
Recycled Water
100 KLD
Flushing Demand –
50 KLD
Greenbelt –
50 KLD
120 KLD
50K LD
STP Treated Water – 100 KLD
Daily water demand: 150 KLD + 100 KLD = 250 KLD
Fresh water – 150 KLD and recycled water – 100 KLD
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 22
TABLE 2.8 - DESIGN PARAMETERS OF SEWAGE TREATMENT PLANT
Parameter Unit
Quantity KLD 180
pH -- 6.5-8.5
Oi l & Grease Mg/l 20
TSS Mg/l 200
BOD Mg/l 350 mg/l it
COD Mg/l 500 mg/l it
Sewage Treatment Process Description:
SEWAGE treatment plant is designed to treat 180 cum of Sewage per day.
This Sewage shall be generated across the 3 shifts. The proposed scheme is
depicted in the figure attached below.
Primary treatment: The Sewage is collected and led via drain to the
treatment plant site. In the drains, screens shall be provided for retaining
coarse matter. The screens are manual type and are to be cleaned at
regular intervals. Two stages of screens are provided i.e. coarse screen
followed by fine screens. The Sewage is then taken to grit chamber for
removal of grit. Following removal of grit, the Sewage is taken to an
equalization tank for attenuation of variation in waste flow rate and
characteristics. It is proposed to have equalization tank with holding
capacity of 6 hours DT. For mixing, and to avoid solids from settling, air shall
be bubbled in the equalization tank through a grid placed at the base of
the tank. The equalized Sewage is pumped at a uniform and constant rate
for further treatment.
Secondary treatment: Sewage from the primary stage treatment is
subjected to bio-chemical oxidation in aeration tank. An attached growth
fluidized bed aerobic system working as an extended aeration system is
proposed. Air for aeration is supplemented by means of blowers
connected to air diffusers. For immobilizing the microbes, high surface area
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 23
to volume ratio synthetic media shall be provided in the aeration tank. This
system has the following advantages:
a) Smaller foot print area
b) Ease in operation and maintenance
c) Operator skills required are minimal
d) System less susceptible to upset conditions (shock loading, power
failure etc.)
e) Lower energy requirements
f) No clogging or chocking of the media.
Following bio-chemical oxidation, the Sewage from the aeration tank is
taken to a tube-deck (secondary settling tank) for solid-liquid separation.
The sludge collected in the hopper bottom of the settling tank is
periodically withdrawn to sludge sump tank. Overflow from the settling
tank is subjected to tertiary treatment. Overflow from the secondary
settling tank is taken to chemical oxidation tank for chemically oxidizing
the residual contaminants. Chlorine shall be added for chemical oxidation.
For adequate contact time a chlorine contact chamber with 30 minutes
detention time and mixing arrangement is proposed.
Tertiary treatment: The Sewage from chlorine contact chamber is then
collected in a sump and pumped to a pressure sand filter for removal of
particulate matter. The Sewage is then taken through an activated carbon
column for removal of trace organics and pollutants (chlorine, color, trace
organics etc.).
Sludge Treatment: Sludge from the settling tank shall be transferred to
sludge sump tank. By using filter press feed pumps we transfer the sludge
from sludge sump tank to filter press. The water from the filter press is
recycled into the equalization tank.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 24
FIGURE – 2.5– PROPOSED SCHEME OF TREATMENT
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 25
c). Solid & Hazardous Waste Details:
Domestic garbage is anticipated from the residential complex. Total solid
waste estimated @ 1 Kg/day per house hold. Thus total garbage
anticipated from the complex will be 313 kg/day which is proposed to be
disposed to municipal solid waste disposal facility of MCH through local
municipal authorities. About 300 Kgs/month of solid waste anticipated from
sewage treatment plant and same will be used as manure.
The hazardous waste generated will primarily be waste lube oil from
maintenance of DG sets of about 80 liters per annum and 40 liters per
annum of transformer oil from transformers. This waste oils will be collected
in barrels and disposed off through parties authorized by APPCB / CPCB.
2 no’s of per annum of used batteries will be disposed of by a buy-back
arrangement with the battery supplier.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 26
CHAPTER – 3
3.0 BASELINE ENVIRONMENT
3.1 BASELINE SCENARIO
In order to assess the current environmental setting and likely impact of the
project on the surroundings, baseline study is carried out by M/s. Pridhvi
Envirotech (P) Limited. Ground water, ambient air, noise and soil samples
were collected and analyzed. The results are presented in the following
sections.
3.2 MICROMETEOROLOGY
Hot steppe type climate prevails over Hyderabad. The mean daily
temperature varies from 300C to 430C from April to June and from 200C to
240C in the months of December and January. The climate is pleasant from
November to February. The summer months of April and May are
uncomfortable due to oppressive heat. The period from July to September
is warm, humid and uncomfortable.
More than 75 per cent of the rainfall is received during the south-west
monsoon season, i.e., from June to September, July being the month when
it rains. September is the month, when there are rains. The south-west
monsoon sets in by 2nd week of June. Its advent is sudden and the rainfall
increases from less than 5 per cent (of the annual) in May to 15 per cent in
June.
Humidity in the morning is high exceeding 80 per cent from July to
September. In the dry months of March, April and May, humidity is
generally low with an average of 25 to 30 per cent and decreases to 20
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 27
per cent at individual stations. June to October is the period when more
than half of the sky is covered with clouds, while only about 2/8 of the sky is
clouded from January to March. Half of the days in July and August have
overcast skies. About 10 to 13 days in the months of January, February and
March, the skies are free from clouds, clear weather.
The ambient temperature ranges between 17oC to 35oC with average
temperature being 25oC. The relative humidity ranges from 28 to 65% with
average humidity being about 45%.
3.3 AIR QUALITY:
The ambient air quality in the study area was measured at project site and
analysed for PM2.5, PM10, SO2, and NOx. The air quality at main entrance of
the site is presented below.
TABLE 3.1 - AMBIENT AIR QUALITY
S.No. Parameters Units
Values NAAQ
Standards
1
Particulate Matter (PM10)
µg/m3
52
100
2
Particulate Matter (PM2.5)
µg/m3
26
60
3
Sulphur Dioxide (SO2)
µg/m3
7.1
80
4 Oxides of Nitrogen (NOx) µg/m3
18.7 80
3.4 NOISE QUALITY:
The Noise levels in the study area at project site measured for one day and
the results are given below.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 28
TABLE 3.2 - NOISE LEVEL MONITORING
S. No Name of Location Values Units
1 Near Entrance Gate 65.3 (day)
52.1 ( Night)
dB(A)
*All values in dB (A)
3.5 WATER QUALITY:
Ground water quality at project site is measured and the test report is
presented below.
TABLE 3.3 – GROUND WATER ANALYSIS REPORT
SNO. PARAMETER
PERMISSIBLE
LIMITS DESIRABLE LIMITS
Permissible
limits in
absence of
alternative
source
1 Color (Hazen units) <5.0 5 max 25 max
2 Odour
Un
Objectionable UnObjectionable ---
3 Turbidity (NTU) 0.2 05 max 10 max
4 pH 6.92 6.50 - 8.50
5 E.C (micromhos/cm) 958 -- --
6 Total dissolved solids 605 500 max 2000 max
7
Phenolpthalene
alkalinity
as CaCo3 Nil -- --
8
Methylorange
alkalinity
as CaCo3 396 -- --
9
Total alkalinity as
CaCo3 396 200 max 600 max
10
Total hardness as
CaCo3 262 300 max 600 max
11 Calcium as Ca 71 75 max 200 max
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 29
12 Magnesium as Mg 20.54 30 max 100 max
13 Sodium as Na 92 -- --
14 Potassium as K 13.29 -- --
15 Copper as Cu 0.14 0.05 max 1.50 max
16 Iron as Fe 0.27 0.3 max 1.0 max
17 Manganese as Mn <0.04 -- --
18 Chlorides as Cl 136 250 max 1000 max
19 Sulphates as SO4 92 200 max 400 max
20 Nitrates as NO3 10.6 45 max 100 max
21 Fluorides as F 0.945 1.0 max 1.5 max
3.6 SOIL QUALITY:
The soil condition and bearing capacity were tested for analysis and the
report is presented below.
TABLE 3.4 – SOIL SAMPLE ANALYSIS REPORT
S.NO PARAMETERS RESULT
1. pH (1.5 Soil water extract) 8.47
2. E.C (1.5 Soil water extract) 173
3. Available Nitrogen 69.25
4. Available Phosphorous as P2O5 14.64
5. Available potassium as K2O 9.54
6. Sodium as Na 21.42
7. Calcium as Ca 52.10
8. Magnesium as Mg 13.20
9. Chloride as Cl 49.60
10. Organic Carbon 0.58
11. Texture Sandy Loam
12. a) Sand % 51.20
13. b) Silt % 39.50
14. c) Clay % 9.30
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 30
CHAPTER – 4
4.0 POLLUTION SOURCES - CHARACTERISTICS,
QUANTIFICATION AND PREDICTION
4.1 POLLUTION SOURCES
Pollutants generated due to project activities during both the construction
and operation phase are solid, liquid and gaseous in nature. Also the
generation of pollution could be continuous, periodic or accidental.
Sources of pollutants and their characteristics during the construction and
operation phase are given below in Table 4.1.
TABLE 4.1: POLLUTANT SOURCES AND CHARACTERISTICS
S.
No
Activity/Area Pollutant Pollutant
Characteristics
Frequency
CONSTRUCTION PHASE
1. Ground working
and leveling
Air emissions –
PM, NOx,
SO2, CO
Dust from
construction
activities and
excavation.
Particulate
matter, NOx
and CO from
vehicle exhaust
Temporary
during
construction
phase only- bulk
of the emissions
are expected
from ground
working and
leveling
activities.
Earth / solid
waste
Solid waste from
construction
activity and
excavation.
Periodic.
Noise Noise
generated from
construction
equipment and
Temporary
during initial
construction
phase
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 31
S.
No
Activity/Area Pollutant Pollutant
Characteristics
Frequency
Machinery
2. Labour Camps Sewage Sewage
generated from
temporary labor
camps on site
Temporary –
during the initial
construction
phase
Solid Waste Solid Waste
generated from
temporary
labour camps
on site
Temporary –
during
the initial
construction
phase
OPERATION PHASE
1. Vehicular
movement
Air emissions
and noise
Vehicle exhaust
emissions
Continuous /
Periodic
2. Diesel power
generators
Air emissions SO2, NOx, SPM,
CO from
fuel burning
Periodic, only
during
power failure
Noise Noise due to
running of
equipment
Periodic
Waste Used Oil
Generation
Periodic, during
oil changes
3. Residential Wastewater Wastewater
containing
food matter
Continuous /
Periodic
Domestic
Solid waste
Garbage /
Food waste
Continuous
4. Raw water
treatment
Wastewater Backwash
water discharge
Continuous
Solid waste Sludge from
coagulation
process
Continuous
5. S.T.P Solid waste Settled and
stabilized
sludge
Continuous
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 32
S.
No
Activity/Area Pollutant Pollutant
Characteristics
Frequency
Treated water Treated sewage
water used for
Greenbelt
Continuous
6. Diesel Storage Solid waste Settled sludge
during tank
cleaning
Occasional
Oil Oil spillage –
Accidental
large spills due
to pipe rupture
Oil Spillage -
Small quantities
due to small
pipe leaks
Accidental /
Only due
to poor
housekeeping
7. Maintenance /
housekeeping
Wastewater Floor washing Continuous
Solid waste Used
equipment
parts and
garden wastes
Continuous
8. Vehicle Parking
Area
Oil Spills Minor oil leaks in
parking lot
Continuous –
small Quantities
9. Storm water
drains
Wastewater Contamination
discharge from
site – Mainly
suspended
solids
During rainy
season
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 33
4.2 AIR EMISSION SOURCES
Air emissions have no boundaries and can migrate between areas
depending upon the wind direction and speed.
4.2.1 Predicted Air Emissions from the site
CONSTRUCTION PHASE
During the construction phase, PM is expected to be the main pollutant
associated with on-site roads (paved and unpaved), stockpiles and
material handling. In this case, pollution emission sources shall be
distributed throughout the project site and shall fall under the category of
area source. The land acquired is fairly flat, so extensive formation work is
not expected during this phase. It is assumed that most of the excavated
material shall be used within the project, with minimal cut and fill material
to come from outside the site.
Due to the confined nature of heavy construction activity during this
limited period, tailpipe emissions from construction equipment are
assumed to be essentially negligible.
OPERATIONAL PHASE
During the operational phase, the diesel generator sets to be operated for
back-up power supply are the major source of air pollution. From this point
source, the following pollutants are expected;
PM, SO2, NOx and CO
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 34
Diesel Generator Set Fuel Combustion - Point Source
To serve as a emergency power back-up, two diesel generators of 1 x 100
KVA & 1 x 150 KVA connected to individual stacks shall be installed. The
diesel generator sets are operated only during power failure thus
conserving fuel and reducing the pollution.
As a worst-case scenario, emissions were predicted assuming an operation
time of 24 hours. The emissions from the diesel generators are provided in
the following table:
TABLE 4.2 – DIESEL GENERATOR SET EMISSIONS
Capacity
of DG Set
No. of
DG Sets
Stack
Height
(m)
Diamete
r of
Stack
(m)
Temp. of
exhaust
gases (0C)
Exit
velocity
(m/sec)
Pollutant
Emission rate (g/sec)
SPM SO2 NOx
100 KVA
&
150 KVA
2 5 mts
above
DG
room
0.4 450 12.5 0.02 0.03 0.12
4.3 NOISE EMISSIONS SOURCES
The assessment of the impacts of noise on the surrounding community
depends upon:
Characteristics of noise source (instantaneous, intermittent, or
continuous in nature, with the latter contributing the least to noise
pollution);
Time of day at which noise occurs; and
Location of noise source with respect to noise sensitive receptor.
CONSTRUCTION PHASE
The description of construction activity as detailed in Section 4.2.1 (with
regards to spatial phasing and type of sources) is also pertinent to the
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 35
noise emissions emitted in the construction phase. Sources of noise
emissions are expected from various types of construction equipment.
General noise levels generated from the operation of equipment and
machinery are provided in Table 4.3 below:
TABLE 4.3: NOISE LEVELS GENERATED FROM CONSTRUCTION EQUIPMENT
Name of the source Noise Level at 16 m (50
ft)from Source in dB (A)
Noise Level at 1 m from
Source (calculated)in dB(A)
Air Compressor 87 111
Back Hoe/Loader 81 105
Concrete Mixer Truck 85 109
Concrete Pumper 70 94
Concrete Vibrators 77 101
Cranes - mobile 81 105
Dump Truck 83 107
Generator Not Considered 75 (CPCB)
Hammering 86 110
Jackhammer 88 112
Pile Driver 100 124
Radial Arm Saw 80 104
Source:www.gvrd.bc.ca/education/pdf04/ColumbiaWorkshop1-ConstructionNoise.pdf
The MoEF has not yet prescribed noise emission specifications for
construction equipment. However, the limited information available is
provided in Table 4.4.
TABLE 4.4 – NOISE LIMITS FOR APPLIANCES AND CONSTRUCTION EQUIPMENT
AT MANUFACTURING STAGE
Equipment Noise Limit dB (A)
Window Air Conditioner(1ton -1.5 tons) 68
Air Coolers 60
Diesel Generators 85-90
Compactors (rollers), Front Loaders,
Concrete Mixers, Cranes(movable),
Vibrators, and Saws
75
Source: http://dpcc.delhigovt.nic.in/pdf/Pollution_Control_Law.pdf
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 36
OPERATIONAL PHASE
During the operational phase, the diesel power generators will be the
major source of noise.
Diesel Generator Sets
Noise Limit for Generator sets run with Diesel
Noise limit for diesel generator sets (upto 1000 KVA) manufactured on or
after the 1st January, 2005.
The maximum permissible sound pressure level for new diesel generator
(DG) sets with rated capacity upto 1000 KVA, manufactured on or after
the 1st January, 2005 shall be 75 dB(A) at 1 meter from the enclosure
surface.
Noise control for diesel generator will be as follows:-
Noise from DG set shall be controlled by providing an acoustic enclosure
or by treating the room acoustically, at the users end.
The acoustic enclosure or acoustic treatment of the room shall be
designed for minimum 25 dB (A) insertion loss or for meeting the ambient
noise standards, whichever is on the higher side ( if the actual ambient
noise is on the higher side, it may not be possible to check the
performance of acoustic enclosure/ acoustic treatment. Under such
circumstances the performance may be checked for noise reduction upto
actual ambient noise level, preferably, in the night time).The measurement
for Insertion Loss may be done at different points at 0.5 m from the acoustic
enclosure/ room. The DG set shall be provided with proper exhaust muffler
with insertion loss of minimum 25 dB (A).These limits shall be regulated by
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 37
the State Pollution Control Boards and the State Pollution Control
Committees.
Source: www.cpcb.nic.in
4.4 WATER AND WASTEWATER MANAGEMENT
4.4.1 WATER REQUIREMENTS
Water requirement during the construction phase will be met from water
tankers. The required water during the operational phase will be sourced
from HMWS&SB. However, in the event of non availability of water or for
any excess requirement of water during the operational phase, the
proponents are proposing backup with the aid of rainwater collection in
the reservoirs which will be duly treated, water recycling and water tankers
(in case of water supply failure). It is also emphasized that at any stage of
the project, groundwater reserves would not be exploited for the water
requirement. The water requirements during various phases of the project
are discussed below:
A) CONSTRUCTION PHASE
The project implementation would involve various construction activities.
The following section summarizes the water requirement, its sources and
management of wastewater.
Site development:
Development of site for the proposed development involves excavation,
leveling of the ground surface and stock piling. However as the project site
is flat with no vegetation cover, the leveling activities would result in very
less water usage. Water requirement for any use at this stage would be
provided from water tankers. Similarly, the generation of domestic
wastewater can be managed on site.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 38
Construction of building infrastructure:
The construction of building infrastructure that includes residential and
other units, Offices, restaurants and multiplex would require water and may
generate waste water too. Water demand during construction phase
would be for:
Construction activities.
Domestic use.
Construction phase may last for a period of approximately two years in
order to complete the earthwork, foundation lying, superstructure
development, service provision and finishing. The water requirement is
being met from the water tankers.
B) OPERATIONAL PHASE
Daily Water Requirement and Sources:
It has been mentioned before that the domestic water requirements will
be met from the HMWS&SB Water supply scheme. The water requirement
for Flushing, Gardening, Landscaping and other purposes would be met
from duly treated recycled water. However, in case of failure of HMWS&SB,
water requirements are planned to be met partly by ground water &
through private tankers. Rain water will be recharged to the ground to
augment the water table in the area. Water tankers will be used only in
case of any emergency or failure of water supply by HMWS&SB or
insufficiency of the water reservoir.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 39
Water conservation:
Water conservation is an important part of sustainable living and in order to
optimize the water requirement in the project, the developers would
incorporate the component of water conservation by means of rainwater
harvesting and water recycling using fixtures which are low flow and water
efficient models such as 3 litre capacity WC flushing system, sensor
operated urinals and taps to minimize the wastage of water along with
employee education and awareness programme and selective use of dry
type urinals. As per the approved plans from GHMC, various mitigative
measures shall be proposed to further minimize the impacts.
Storm Water Management & Rain Water Harvesting Structures
It is proposed to channelizing the storm water by constructing water drains
leading to the storm water sump. In order to minimize the surface runoff
loss, groundwater recharging through groundwater recharge pits at the
project site has been planned. Appropriate design considerations have
been taken while designing the recharge pits.
Calculating Runoff for Water Harvesting
Calculating runoff is an important step in designing your water harvesting
system. You should determine both your water supply and your water
demand. Use this worksheet to determine your rainwater supply.
Catchment Area: the area in which rain directly falls (i.e. a roof, a
driveway, or a landscape). The area is the same regardless of slope; you
can also think of the area as seen from a birds-eye view or as the horizontal
surface space occupied.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 40
Runoff Coefficient: the average percentage of rainfall that will run off a
particular surface (i.e. a metal roof has a runoff coefficient of 0.95 or 95%
runoff). The runoff coefficient will vary depending on the composition of
the surface and the rainfall intensity.
Annual Rainfall: the average amount of rainfall over one year period for
your location.
TABLE-4.5: ESTIMATE OF RAIN WATER HARVESTING
S.No. Particulars Plot Area
(Net
area)
Roof area
Landscape
& Set back
1 Catchment Area (Sq.Mts) 6900.05 4445 5994.93
2 Runoff Coefficient 0.6 0.8 0.3
3 Average annual Rainfall
(Mts)
0.8 0.8 0.8
4 Rain water collection per
annum(cum)
3312 2844.8 1438.78
Total Rain water potential after the project implementation is
=2844.8+1438.78= 4283.58 Cum/per annum
Without project:
= Catchment Area X Runoff Coefficient X Annual Rain Fall
= 6900.05 X 0.60 X 0.8
= 3312 Cum/per annum
With project (Roof Area):
= Catchment Area X Runoff Coefficient X Annual Rain Fall
= +4445X 0.80 X 0.8
= 2844.8 Cum/per annum
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 41
With project (set backs, Landscape & green belt):
= Catchment Area X Runoff Coefficient X Annual Rain Fall
= 5994.93 X 0.30 X 0.8
= 1438.78 Cum/per annum
The total annual rainwater harvesting potential of the project site is 4283.58
Cum/per annum. The rainwater is proposed to be channelized for
groundwater recharging through the Harvesting pits. 18 no’s of Rain Water
Harvesting pits are provided at four corners of the site.
FIGURE-4.1: RAIN WATER HARVESTING STRUCTURE
Size 1.5 X 1.5 X 2.0
4.4.2 WASTEWATER QUANTIFICATION AND CHARACTERISTICS
The wastewater generation during construction and operational phase is
described below:
A) CONSTRUCTION PHASE
Waste water generation during construction period shall be from
construction labours and construction activities. Wastewater generation
due to construction activities would be very less. Since the project lies in an
urban stretch, preference would be given to the employment of labours
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 42
local to the area. This would result in settlement of less labour colonies in
the project site and hence less wastewater generation from the transit
labour settlements. Wastewater generation from labour colonies shall not
exceed 2 KLD.
B) OPERATIONAL PHASE
During this phase, it has been assumed that 80 % of the water supplied will
be discharged as wastewater (Source: Manual on sewerage and sewage
treatment, published by Government of India). Hence approximately 140
m3 per day of domestic effluent would be generated.
Wastewater generated is expected to have characteristics and pollution
load as shown in Table 4.6.
TABLE 4.6: EXPECTED WASTEWATER CHARACTERISTICS AND POLLUTION LOAD
Parameter Unit Concentration
Quantity KLD 170
pH -- 6.5-8.5
Oi l & Grease Mg/l 20
TSS Mg/l 200
BOD Mg/l 350 mg/l it
COD Mg/l 500 mg/l it
The wastewater with the foresaid characteristics can neither be
discharged into inland surface water nor reused. Suitable treatment would
be given to the wastewater so as to meet CPCB requirements depending
upon the end use. It is proposed to install a sewage treatment plant of
capacity 180 KLD, to recover the recycled water of quality suitable for use
in flushing and gardening. A sewage treatment plant of 180 KLD capacity
based on Fluidized Aerobic Bio-Reactor (FAB) technology is proposed to
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 43
treat 170 KLD of sewage water generated in the proposed project .After
treatment the water will be used for Flushing & Gardening.
The treated wastewater shall meet the standard required for discharge on
land for horticulture. Table 4.7 gives the comparison of the standards that
would be met by the treated wastewater and quality norms prescribed for
discharge on land by irrigation.
TABLE - 4.7: DISCHARGE NORMS FOR WASTE WATER
Parameters Quality Norms
Discharge On
land for
irrigation
Quality Norms
for Discharge
in inland
surface water
Treated standard
For proposed
project
pH 5.5 to 9.0 5.5-9.0 6.5 to 7.5
Biological Oxygen
Demand
(BOD3 at 27°C)
mg/l
100 30 < 15
Chemical Oxygen
Demand (COD)
mg/l
- 250 < 100
Suspended Solids 200 100 <30
Oil and Grease 10 10 < 10
4.5 SOLID AND OTHER WASTES
Waste quantification and characterization exercise is being carried out to
estimate the quantum and type of waste that would be generated by
different activities due to proposed project during construction and
operation phase. The estimated quantity and quality of waste would serve
as a baseline for designing collection, transportation, treatment and
disposal options for solid waste generated due to proposed project.
4.5.1 WASTE SOURCES AND QUANTIFICATION
Description of solid and other wastes generated from the site during
construction and operation phases of the project is given in Table 4.8.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 44
TABLE 4.8: SOLID AND OTHER WASTES GENERATED
S.
No.
Activity/Area Waste
Generated
Waste Characteristics Frequency of
generation
CONSTRUCTION PHASE
1. Earth Working
and
Construction
Construction
Wastes
Earth, Stones,
concrete,
bricks, lumber etc.
Larger quantities
will be
generated in
construction
phase.
2. Labour camps Domestic
wastes
Mainly bio-
degradable
wastes including food
wastes.
Temporary –
during
construction
phase.
OPERATIONAL PHASE
1. Residential
areas
Domestic
waste
Biodegradable
wastes (food
waste) and non-
biodegradable
wastes (paper,
plastics etc.)
Daily
3. Set back area sweepings dust, leaves etc. Daily
3. Utilities
including
Power
generation
Waste from
oil
Waste oil Only during oil
changes – six
monthly.
4. Sewage
Treatment
Plant
STP Sludge Stabilized sludge – to
be used as manure
for the landscaping.
Every week –
after sludge
drying
operation.
Waste quantification has been done based on the activities proposed in
the project master plan. The waste generation for each activity has been
estimated based on National and International standards applicable in
similar setting. The following section gives the details of the type of waste
generated by different activity, waste generation factors and assumptions
used for estimating waste generation.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 45
Waste quantification and characterization exercise is being carried out to
estimate the quantum and type of waste that would be generated by
different activities due to the proposed project activity during the
construction and operation phase.
4.5.2 WASTE QUANTIFICATION
A) CONSTRUCTION PHASE
Construction activities create solid wastes that need to be disposed. Such
wastes include sand, concrete, gravel, stone, bricks, plastic, paper, wood,
metal and glass. According to a report prepared by the Technology
Information, Forecasting, and Assessment Council (TIFAC), estimated waste
generation during construction and demolition operations is 60 kg/m2 and
500 kg/m2 respectively (TIFAC, 2001). This waste after sorting can be used
for backfilling in the basement and for leveling purposes.
B) OPERATIONAL PHASE
Waste quantification has been carried out based on the activities
proposed in the project master plan. Waste generation factors for each
activity are as per the National and International standards applicable in
similar setting. Following section outlines details of the type of waste
generated by different activities.
Residential waste: Domestic garbage is anticipated from the residential
complex. Total solid waste estimated @ 1 Kg/day per house hold. Thus total
garbage anticipated from the complex will be 313 kg/day which is
proposed to be disposed to municipal solid waste disposal facility of MCH
through local municipal authorities. About 300 Kgs/month of solid waste
anticipated from sewage treatment plant and same will be used as
manure.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 46
Garden and open spaces: Waste from open spaces and garden comprise
of horticultural waste that will be generated by periodical lawn mowing
and trimming of trees. Horticulture waste generated is based on the
experience in other projects with similar setting. Assumed waste generation
factor for horticulture waste is 15 kg/acre / day or .0037 kg/ sq m /day.
Table 4.9 gives detail of the estimated waste generation
TABLE 4.9: ESTIMATED WASTE GENERATION FROM DIFFERENT ACTIVITIES
Facilities
Provided
Waste generation
norms per unit
No. Of
units/Area
Total Waste
Generated
(Kg /day)
Residential area 1.0 kg/day 313 flats 313
Garden &
Open space
15 kg/Acre/day or
0.0037kg/sq m/day
5994.93 22.18
Total Waste Generated (kg/day)
4.5.3 WASTE CHARACTERIZATION
Waste characterization for the proposed project has been carried out on
the basis of waste characterization studies in similar settings. The following
section details the estimated waste generation for proposed project during
construction and operation phases.
A) CONSTRUCTION PHASE
During the construction phase, a considerable quantum (90%) of waste
generated at the project site would be inert waste, which largely
comprising of clay, sand, gravel, untreated wood (natural wood, no paint),
brick, concrete, concrete block, asphalt, pipes, conduits and light steel
material. A major portion of this waste will be used for backfilling the
basement and other leveling purposes.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 47
Table 4.10 gives an estimate of the average composition of waste that
shall be generated from the onsite construction activities.
TABLE 4.10: WASTE COMPOSITION – CONSTRUCTION PHASE
S. No Constituents Percentage Composition
1. Soil, Sand and Gravel 34.99
2. Brick and Masonry 29.95
3. Concrete 24.98
4. Metal 4.97
5. Bitumen 2.04
6. Wood 2.04
7. Other 1.02
Total 100
Source: Derived from TIFAC Report “Utilization of Waste from Construction Industry”, 2001
B) OPERATIONAL PHASE
Waste generated during operational phase can be broadly subdivided
into following.
a) Biodegradable
b) Recyclable
c) Non recyclable(Inert)
Table 4.11 shows the estimated composition of waste generated in
proposed project during operation phase.
TABLE 4.11: ESTIMATED WASTE COMPOSITION
S. No Characteristics of Waste Units Percentage
Composition
Physical Characteristics
1. Paper and paper board % 40
2. Glass /ceramics % 5
3. Metals % 3
4. Plastics % 11
5. Rubber and Leather % 1
6. Textile % 2
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 48
7. Wood % 1
8. Food waste % 18
9. Others (Garden and
Inert)
% 19
Total 100
4.6 OTHER STRESSORS LEADING TO ENVIRONMENTAL IMPACTS
Change in Landscape of the site: The landscape of the area will change
with the coming up of proposed project. The large vista, interconnected
lawns and open green areas will change the aesthetics of the local area.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 49
CHAPTER –5
5.0 IMPACT ASSESSMENT & MITIGATION MEASURES
5.1 IMPACT ASSESSMENT:
The potential impacts on the surrounding environment in the 10km radial
distance of proposed project site along with the mitigation measures
during construction and operational stages are summarized in Table 5.1
and Table 5.2.
The construction phase is for a period of 24 months. Considering this to be
a relatively short period, all construction impacts can be considered to be
short term and temporary.
As for the operational phase, the project proponent shall ensure that
impacts are minimized and are within applicable/ specified limits by
APPCB & CPCB by providing relevant pollution control equipment and/ or
mitigation measures discussed in the following tables.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 50
TABLE – 5.1 - CONSTRUCTION PHASE - POTENTIAL IMPACTS AND MITIGATION MEASURES
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
1. Water resources Minor negative &
temporary
impact on
surface & ground
water resources.
Water requirement
of 50 - 70 KLD for
construction
activities
Judicious use of water;
minimization of water
consumption by use of high-
pressure hoses for dust
suppression
Water requirement
will be sourced from
the outside water
tanker.
2. Surface water
quality
No impact Erosion and run-off
due to excavation/
construction
activities, especially
in monsoon season;
Discharge of waste
water, construction
as well as domestic.
Avoiding excavation in
monsoon season; providing
appropriate measures for
erosion and sediment
control; providing adequate
sanitation facilities for
workers at site; avoiding
discharge of untreated
wastewater in the area.
-
3. Ground water
quality
No impact Construction
activities
Storage area for fuels, paints,
thinners, etc. to be such so
as to avoid chances of
spillage. No discharge to
ground water body.
-
4. Air quality Temporary
negative impact
Construction
equipment;
Carrying out construction
activity in temporary
-
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 51
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
operation of DG sets
for construction
power requirement;
vehicular traffic;
excavation;
concreting; etc.
enclosures, where feasible;
water sprinkling for dust
suppression; regular
maintenance of
construction equipment &
vehicles; use of fuel of
proper quality; use of state-
of-the-art construction
equipment & methods
5. Noise Medium
negative &
temporary
Various construction
activities; material
and vehicular
movement
Use of low noise generating
state-of-the-art construction
equipment and construction
techniques; providing
personnel protective
equipment to workers;
providing temporary
enclosure for DG set and
other construction activities,
where feasible; avoiding
construction work in the
night time
-
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 52
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
6. Land
(i) Land use/
requirement
No impact The total plot area is
8,606.89 Sq. m.
No land conversion is
required as land is a vacant
plot and is designated for
Residential complex by
municipal corporation.
Site Premises is
designated as
Residential area
(ii) Solid wastes &
land pollution
Temporary minor
negative impact
Construction
material handling;
construction wastes
handling and
disposal
Maintaining proper inventory
control for reduced waste
generation; substitution of
hazardous raw materials by
non-hazardous materials,
where feasible; providing
proper facility for storage
and handling of fuel oils;
disposal of spent oils,
classified as hazardous
waste by sale to authorized
third party; proper handling
and disposal of construction
wastes; Contractor’s to
assume full responsibility for
clearing off construction
-
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 53
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
wastes
(iii) Geology &
Seismicity
No impact Construction of the
Residential complex
No heavy structure planned
as part of the project
All civil structures shall
be constructed as
per earthquake zone
classification
7. Ecology Minor positive
impact
Construction activity
causing impact on
existing ecosystem
on-site and top soil;
cutting of existing
vegetation, if
required;
No trees on the site shall be
cut.
In fact green belt will be
developed all along the
building boundary, roadside
and lane divider.
water sprinkling during dust
generation activities; erosion
and sediment control; noise
and fugitive dust control;
restricting construction
activity during night time
No ecologically
sensitive area such as
forest/ agricultural
land will be used for
the project. Presently,
the site has no trees.
3085 Sq. m to be
developed as
greenbelt.
8. Socio-economic
(i) Population and
literacy rate
Minor negative
and temporary
Increase in
population due to
possible temporary
settling of
construction workers
Employing local people to
the maximum extent possible
About 50 construction
workers are expected
to be employed
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 54
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
from outside the
study area for the
project
(ii) Employment Minor positive &
temporary
impact
Availability of
construction jobs
Employing local people to
the maximum extent possible
About 50
construction workers
are expected to be
employed
(ii) Amenities such
as education,
medical, water
supply,
sanitation, etc.
No impact Needs of
construction
workers;
Employing local people to
the extent possible for
construction work; making
adequate provision through
the contractors to handle
water, sanitary, medical and
fuel requirement of
construction workers to
ensure that the existing
infrastructure is not strained
-
(iv) Transportation Temporary
negative impact
Increased traffic
load due to
transportation of
construction
materials and
workers
Ensuring that traffic is well
regulated. Use of non-peak
hours for material
transportation
-
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 55
TABLE – 5.2 - OPERATIONAL PHASE – POTENTIAL IMPACTS AND MITIGATION MEASURES
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
1. Water
resources
Minor negative
impact on surface
water resources
Moderate
negative impact
on ground water
resources due to
consumption.
Minor positive
impact due to
recharge by
rainwater
harvesting.
Total water
requirement for the
proposed project is
250 KLD.
(Fresh water 150 KLD
&
S.T.P recycle100 KLD)
Recycle water will be used
Flushing and Gardening
The fresh water will
be sourced from
HMWS&SB.
2. Surface water
quality
No impact Discharge of sewage
and waste water
from utilities
Recycle water will be used
Flushing and Gardening
-
3. Ground water
quality
No impact Discharge of sewage
and waste water
from utilities
No discharge of
wastewater to ground
water body; use of treated
sewage water for Flushing,
Rainwater from the
rain water
harvesting will be
used to recharge
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 56
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
Gardening ground water.
4. Air quality Minor negative
impact (for SO2,
NOX and HC
emissions)
Fuel combustion in
DG sets
All emissions will be well
within the specified
emissions standards;
stack height = building
height +5 mts. for safe
dispersal of pollutants;
HSD with 0.25% sulfur
content in DG sets; periodic
maintenance of DG sets for
reduced emissions
All emissions well
within the specified
limits
5. Noise Minor negative
impact
Noise generating
rotating/ moving
equipment
Proper equipment selection;
mandatory acoustic
enclosure for DG sets;
regular maintenance of
noise generating
equipment; providing
personnel protective
equipment to persons
working in noisy areas;
suitable design and
location of utility block;
-
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 57
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
development of suitable
green belt and landscaping
6. Land environment
(i) Land use /
requirement
No impact Requirement of land
for the proposed
project
6991.05 Sq.m of area
available for development
Once the project is
operational, no
additional land will
be required.
(ii) Solid wastes &
land pollution
Minor negative
impact
Handling and
disposal of
hazardous and solid
wastes
Segregation of wet and dry
garbage – disposal of dry
garbage through off-site
recycling or to municipal
waste collection system
and wet waste to
composting at site; disposal
of waste lube oils by sale to
authorized third party; buy-
back arrangement for
waste lead acid batteries
Though no solid/
hazardous waste
will be disposed off
on land, chances
of inadvertent
occasional spillage
on land cannot be
ruled out
(iii) Geology &
Seismicity
No impact Improper building
design not adhering
to specified codes;
improper building
Regular maintenance of
the structures to withstand
natural phenomena;
carrying out the structural
-
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 58
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
maintenance integrity testing
9. Ecology No impact Emissions and
discharges from
project operations;
noise generation;
improper disposal of
wastes
All emissions and discharges
including noise will be within
specified standards; all
solid/ hazardous waste will
be disposed off in
environmentally sound
manner
-
10. Socio-economic factors
(i) Population and
literacy rate
No impact Increase in
population due to
settlement of
personnel and their
families from
outside the study
area for the
proposed project
Employing personnel from
within the study area to the
extent possible, subject to
availability of skilled
manpower requisite to the
job requirement
About 10 personnel
would get direct
employment from
the project
(ii) Employment Medium positive
impact
Direct employment
of personnel for
proposed project.
Employing personnel from
within the study area to the
extent possible, subject to
availability of skilled
manpower requisite to the
job requirement
Approximately 10
persons Direct
employment and
20 persons indirect
employment are
expected to be
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 59
S.
No.
Environmental
components
Potential impacts Source of impacts Mitigation measures Remarks
employed for the
project
(ii) Amenities such
as education,
medical, water
supply,
sanitation, etc.
No impact Requirement of
various facilities for
the children of
personnel
employed from
outside the study
area
Employing personnel from
within the study area to the
extent possible, subject to
availability of skilled
manpower requisite to the
job requirement
Various amenities in
the study area are
adequate.
(iv) Transportation Medium negative
impact
Burden on the
existing road
infrastructure due
to the increased
traffic from the
proposed project
Ensuring that vehicular
movement is controlled
during peak traffic hours;
providing bus services from
the office to the nearest
railway station; encouraging
car-pools for office
employees
-
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 60
CHAPTER – 6
6.0 ENVIRONMENTAL MANAGEMENT PLAN
6.0 INTRODUCTION:
The Environmental Management Plan (EMP) is a site specific plan developed
to ensure that the project is implemented in an environmental sustainable
manner where all contractors and subcontractors, including consultants,
understand the potential environmental risks arising from the proposed
project and take appropriate actions to properly manage that risk. EMP also
ensures the project implementation is carried out in accordance with the
design by taking appropriate mitigative actions to reduce adverse
environmental impacts during its life cycle.
The plan outlines existing and potential problems that may adversely impact
the environment and recommends corrective measures where required. Also,
the plan outlines roles and responsibility of the key personnel and contractors
who are charged with the responsibility to manage the site.
The EMP is generally:
Prepared in accordance with rules and requirements of the MOEF and the
Telangana Pollution Control Board;
To ensure that the component of facility are operated in accordance with
the design;
Process that confirms proper operation through supervision and
monitoring;
System that addresses public inconvenience during construction and
operation of the facility; and
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 61
Plan that ensure remedial measures are implemented immediately.
The key benefits of the EMP are that it provides the organization with means
of managing its environmental performance thereby allowing it to contribute
to improved environmental quality. The other benefits include cost control as
improved relations to the stakeholders.
EMP includes four major elements;
Commitment & Policy: Project proponents will strive to provide and
implement the EMP that incorporates all issues related to air, land and
water for the project.
Planning: This includes identification of environmental impacts, legal
requirements and setting environmental objectives.
Implementation: This comprises of resources available to the developers,
accountability of contractors, training of operational staff associated with
environmental control facilities and documentation of measures to be
taken.
Measurement & Evaluation: This includes monitoring, corrective actions,
and record keeping.
It is suggested that as part of the EMP, a Monitoring Team should be formed
by the project proponent comprising of the site in-charge, project planning
group representative and project implementation team representative. This
committee’s role would be to ensure proper, operation and management of
the EMP including the regulatory compliance.
6.1 ENVIRONMENTAL MANAGEMENT PLAN
An Environmental Management Plan (EMP) will be required to mitigate the
adverse environmental impacts during construction and operation phase of
the project and these are as below:
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 62
6.1.1 EMP FOR AIR ENVIRONMENT
A) CONSTRUCTION PHASE
To mitigate the impact of PM (dust) during the construction phase of the
proposed project, the following measures are recommended for
implementation:
a dust control plan; and
Procedural changes to construction activities.
TABLE 6.1: DUST CONTROL PLAN
S.No Fugitive Dust
Source Category
Dust Control Actions
1. Earth-moving - For any earth moving which is more than
30m from all property lines, conduct
watering as necessary to prevent visible
dust emissions from exceeding 100m in
length in any direction.
2. Disturbed surface areas
(except completed
grading areas)
- Apply dust suppression in a sufficient
quantity and frequency to maintain a
stabilized surface;
- Areas, which cannot be stabilized, as
evidenced by wind driven dust, must
have an application of water at least
twice per day to at least 80 percent of
the unstabilized area.
Disturbed surface areas
(completed grading
areas)
- Apply water to at least 80 percent of all
inactive accessible disturbed surface
areas on a daily basis when there is
evidence of wind driven fugitive dust.
3. Inactive disturbed surface
areas
- Apply dust suppressants in sufficient
quantity and frequency to maintain a
stabilized surface.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 63
4. Unpaved roads -Water all roads used for any vehicular
traffic at least twice per day of active
operations; OR
- Water all roads used for any vehicular
traffic once daily and restrict vehicle
speed to 30 kmph.
5. Open storage piles - Apply water to at least 80 percent of the
surface areas of all open storage piles on
a daily basis when there is evidence of
wind driven fugitive dust.
6. Track-out control -Downwash of trucks (especially tyres)
prior to departure from site.
The most cost-effective dust suppressant is water, because a source of water
tends to be readily available on a construction site. Water can be applied
using water trucks, handheld sprays and automatic sprinkler systems.
Furthermore, incoming loads could be covered to avoid loss of material in
transport, especially if material is transported off-site.
Procedural Changes to Construction Activities
Material Production - The transport of materials such as concrete and asphalt
to construction sites generate significant amounts of road dust, especially for
sites that are relatively far from material manufacturers. Setting up temporary
portable concrete plants and/or asphalt plants at construction sites can
eliminate haulage of materials.
Emission Control for Equipment- Control equipment such as particle filters can
be used to reduce diesel particulate matter emissions.
Idling Time Reduction - Construction equipment is commonly left idling while
the operators are on break or waiting for the completion of another task.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 64
Emissions from idling equipment tend to be high, since catalytic converters
cool down, thus reducing the efficiency of hydrocarbon and carbon
monoxide oxidation. Existing idling control technologies, which automatically
shut the engine off after a preset time can reduce emissions, without
intervention from the operators.
Improved Maintenance - Recognizing that significant emission reductions
can be achieved through regular equipment maintenance, contractors will
be asked to provide maintenance records for their fleet as part of the
contract bid and at regular intervals throughout the life of the contract. A
monetary incentive/disincentive provision will be established to encourage
contractors to comply with regular maintenance requirements.
Reduction of On-site Construction Time - Rapid on-site construction would
reduce the duration of traffic interference and therefore, reduce emissions
from traffic delay. Off-site fabrication of structural components can also
enhance the quality of work, as the production takes place in controlled
settings and external factors such as weather and traffic do not interfere.
B) OPERATION PHASE
To mitigate the impact of pollutants from diesel generator sets during the
operational phase of the site the following measures are recommended for
implementation:
Diesel generator set emission control measures; and
Greenbelt development.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 65
Diesel Generator Set Emission Control Measures
The most important pollutant requiring further control is NOx, as the impact of
SO2 emission is minimal because of the use of low (~0.05%) Sulphur in diesel as
fuel.
The following mitigation measures are proposed for NOx reduction:
add-on emission control technologies; and
NOx retarder
Among the above-mentioned options, inherent low NOx emissions
technologies (i.e. a temperature retarder) and better dilution through higher
stack are preferred cost effective mitigation measures. The add-on emission
control technologies are not considered as it leads to pollution transfer to
another media and shall require further mitigative measures.
Greenbelt Development
Increasing vegetation in the form of greenbelt is one of the preferred
methods to mitigate air pollution. Plants serve as a sink for pollutants, reduce
the flow of dust and reduce noise pollution.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 66
TABLE 6.2 SPECIES TO BE USED TO REDUCE AIR POLLUTION IN GREENBELT DEVELOPMENT
General Pollution
Abatement
Air Pollution Attenuation Dust Absorbers
Teak
Shisham
Palash
Neem
Amaltas
Kachnar
Subabul
Mohua
Aam
Karanj
Imli
Baheda
Harda
Saj
Jamun
Ficus glomerata (Guler)
Terminalia tomentosa
(Asan)
Acacaia auriculiformis
(Babul)
Polyalthia
longifolia(Debdaru)
Ficus benghalensis
(Banyan)
Mangifera indica (Aam)
Nerium odorata (Kaner)
Azadiarchta indica
(Neem)
Melia
azaderach(Mahaneem)
Butea
monosperma(Palash)
Cassia fistula (Amaltas)
Bauhinia
variegata(Kachnar)
Terminalia arjuna (Arjun)
6.1.2 EMP FOR NOISE ENVIRONMENT
A) CONSTRUCTION PHASE
To mitigate the impact of noise from construction equipment during the
construction phase of the site the following measures are recommended for
implementation:
Noise Shields - Construction equipment producing the most amount of noise
should be fitted with noise shields. This shield is a physical barrier (composed
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 67
of brick and mud, with a non reflective internal plastering), approximately 3
meters in height, which will provide adequate noise attenuation.
Time of Operation - Noisy construction equipment should not be permitted
during night hours.
Job Rotation and Hearing Protection - Workers employed in high noise areas
will be rotated. Earplugs/muffs, or other hearing protective wear will be
provided to those working very close to the noise generating machinery.
B) OPERATION PHASE
To mitigate the impact of noise from diesel generator sets during the
operational phase the following measures are recommended for
implementation:
Noise emissions control technologies; and
Greenbelt development.
Noise Emissions Control Technologies: All the diesel generators will be housed
in a suitable acoustic enclosure so that noise levels at a distance of one
meter do not exceed 75 dB(A) at 75% load (as per CPCB norms). The diesel
generator set housing will be equipped with walls and ceilings lined with glass
wool to acoustically treat the noise levels. This acoustic insulation shall be
designed to meet the mandatory standards based on a 25 dB(A) insertion
loss.
Greenbelt Development: The following species can be used in a greenbelt to
serve as noise breakers:
Tectona grandis (Teak);
Butea monosperma (Palash);
Leucana leucocephala (Subabual);
Mangifera indica (Aam); and
Dalbergia Sissoo (Shisham).
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 68
6.1.3 EMP FOR WATER ENVIRONMENT
A) CONSTRUCTION PHASE
To prevent degradation and maintain the quality of the water source,
adequate control measures have been proposed to check the surface run-
off, as well as uncontrolled flow of water into any water body. Following
management measures are suggested to protect the water quality during
the construction phase.
Avoid excavation during monsoon season.
No discharge of treated wastewater to soil and ground water body.
Waste water channels from the site would be connected to septic tank
during construction to prevent wastewater from entering the water
bodies.
To prevent surface and ground water contamination by oil/grease,
leak proof containers should be used for storage and transportation of
oil/grease. The floors of oil/grease handling area should be kept
effectively impervious. Any wash off from the oil/grease handling area
or workshop shall be drained through impervious drains, Clarifiers or
oil/water separators shall be constructed and effluent should be
treated appropriately before releasing it.
Construction activities generate disturbed soil, concrete fines, fertilizer,
oils and other wastes. On-site collection and settling of storm water,
prohibition of equipment wash downs, and prevention of soil loss and
toxic releases from the construction site are necessary to minimize
water pollution.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 69
All stacking and loading areas should be provided with proper garland
drains equipped with baffles to prevent run off from the site to enter
any water body.
B) OPERATION PHASE
In the operation phase of the project, water conservation and development
measures need to be taken including all possible potential for conservation of
water, reuse, rainwater collection in reservoirs, and recycling of waste water.
These could be in the form of the following:
Water source Development
Minimizing water consumption
Promoting reuse of water after treatment and development of closed
loop systems for different water streams.
Water Source Development
Water source development shall be practiced by installation of scientifically
designed artificial water recharging structures. The objective is to develop the
water sources of the region, such that sustainable water supply to the
proposed project is maintained. Following methods normally do artificial
recharge;
Area Treatment
Spreading Methods
Open Well and Shafts
Drilled wells and Bore Holes
The suitability of a particular method is based on hydro-geological condition,
quality of source and proposed use of recharge water. In the proposed
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 70
project, groundwater recharge pits are planned for groundwater recharging.
It is envisaged that recharging to ground water will improve the water quality
in the area, as the rainwater is fresh and without any pollution. It is planned to
effectively harvest water by rainwater harvesting mechanism.
Minimizing Water Consumption
Water consumption will be minimized by implementing water efficient fixtures
such as 3 litres WC flushing cistern and taps to minimize the wastage of water
together with other water conservation measures. Furthermore, to ensure
ongoing water conservation, an employee education and awareness
programme will be introduced for the employee of the mall. Dry type urinals
will also be used selectively. Following section discusses the specific
measures, which shall be implemented;
Residential Usage:
Use of water efficient plumbing fixtures (ultra flow toilets and urinals,).
Water efficient plumbing fixtures use less water with no marked
reduction in quality and service. To install water less W.C. flushing
cistern helps in conserving water.
Leak detection and repair techniques
Sweep with a broom and pan where possible, rather than hose down
for external areas;
Awareness campaign to disseminate knowledge on strategies and
technologies that can be used for water conservation
New employees will be issued a standard water information packet.
The information should include water conservation plans, water
conservation methods being adopted in the complex and a list of
essential and non-essential water uses.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 71
Office Manager will periodically remind the staff of water conservation
efforts and notify staff of recurring problems with compliance or any
changes in policy. As new conservation efforts are implemented, the
manager will communicate these changes to the employees.
Proper methods of water use will be placed in the toilets and other
areas of water consumption.
Horticulture:
Drip irrigation system shall be used for the lawns and other green area.
Drip irrigation can save between 15-40% of the water use, compared
with other watering techniques.
Plants with similar water requirements shall be grouped on common
zones to match precipitation heads and emitters.
Use of low-volume, low-angle sprinklers for lawn areas.
Select controllers with adjustable watering schedules and moisture
sensors to account for seasonal variations, and calibrate them during
commissioning.
Selecting a drought resistant grass, and using lawn chemicals and
fertilizer sparingly also reduces watering needs.
Place 3 to 5 in. of mulch on planting beds to minimize evaporation.
Promoting Reuse of Water after Treatment and Development of Closed Loop
Systems
To promote reuse of Water after Treatment and development of closed loop
system for water, segregation of two schemes namely (i) Wastewater
Treatment scheme; and (ii) Storm water management scheme have been
suggested.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 72
Harvested storm water as discussed in earlier section, shall be utilized for
artificial recharge of ground water sources as well as to augment the project
water requirements. Recycled wastewater shall be reused on site for flushing,
and gardening.
It is estimated that reusing wastewater will save approximately 30 to 35 % of
portable water per day in the shopping mall. Following section details the
wastewater treatment scheme suggested for the project.
6.1.4 EMP FOR LAND ENVIRONMENT
A) CONSTRUCTION PHASE
Waste generated from construction activity includes construction debris,
biomass from land clearing activities (if any), waste from the labour camp,
and. other waste. The following section discusses management of each type
of waste. Besides management of topsoil is an important area for which
management measures are required.
Construction Debris
Construction debris is bulky and heavy and re-utilization and recycling is an
important strategy for management of such waste. As concrete and masonry
constitute the majority of waste generated, recycling of this waste by
conversion to aggregate can offer benefits of reduced landfill space and
reduced extraction of raw material for new construction activity. This is
particularly applicable to shopping mall project as the construction is to be
completed in a phased manner.
Recycled aggregate will be used for filler application, and as a sub-base for
internal road construction. Mixed debris with high gypsum, plaster, shall not
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 73
be used as fill, as they are highly susceptible to contamination, and will be
given to recyclers.
Construction contractors shall remove metal scrap from structural steel,
piping, concrete reinforcement and sheet metal work from the site. A
significant portion of wood scrap can be reused on site. Recyclable wastes
such as plastics, glass fiber insulation, roofing etc shall be sold to recyclers.
Solid and Other waste
Construction sites are sources of many toxic substances, such as paints,
solvents, wood preservatives, pesticides, adhesives and sealants. Such wastes
generated during construction phase shall be stored in sealed containers,
labeled, and disposed of as required by the Hazardous Wastes Management,
Handling and Transboundary Movement Amendment Rules (MoEF, 2009).
Some management practices to be developed are;
Herbicides and pesticide will not be over applied (small-scale
applications) and not applied prior to rain;
Paintbrushes and equipment for water and oil based paints shall be
cleaned within a contained area and shall not be allowed to
contaminate site soils, watercourses, or drainage systems.
Adequate storage facilities for such waste shall be provided and the
waste collection containers conveniently located. A separate
designation to earmark such waste will be made so that the waste
storage areas are away from storm drains or watercourses.
Clearly label all such waste containers with the waste being stored and
the date of generation.
Educate employees and subcontractors on waste storage and
disposal procedures.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 74
Soil Management
Measures, which would be followed to prevent soil erosion and
contamination include - Maximize use of organic fertilizer for landscaping
and green belt development.
To prevent soil contamination by oil/grease, leak proof containers
should be used for storage and transportation of oil/grease and wash
off from the oil/grease handling area shall be drained through
impervious drains and treated appropriately before disposal.
Vegetation of bare areas after the project.
Working in a small area at a point of time (phase wise construction).
Construction of erosion prevention troughs/berms.
B) OPERATIONAL PHASE
The philosophy of solid waste management at the shopping mall will be to
encourage the four R’s of waste i.e. waste reduction, reuse, recycling, and
recovery (materials & energy). This will reduce in lesser reliance on land filling.
Regular public awareness meetings will be conducted to involve the
occupants and the employees to ensure proper segregation, storage and
collection of waste as per the Municipal Solid Waste (Management and
Handling) Rules 2000.
The Environmental Management Plan for the solid waste focuses on the
Segregation, Storage at source and Collection of the waste management
system.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 75
Segregation and storage at source
Segregation of waste at source should be made mandatory for the complex.
Segregation or sorting waste at its source should be practiced in order to
encourage reuse/recycling. With segregation at source recyclables do not
lose their commercial value due to cross contamination.
Waste generated at the complex should be segregated as: bio degradable,
inert cum mixed waste, recyclables and waste from changing oil. The entire
waste stream from the complex should be stored and collected separately.
Collection
The Recyclables from the shopping mall would be given to the waste
itinerant buyers or rag pickers, whereas segregated bio-degradable waste
and inert cum mixed waste shall be sent to the nearest landfill site for
processing and final disposal. Wastes, such as spent oils, paint residues etc.
from the site would be collected separately & would be properly disposed
off.
6.1.5 EMP FOR BIOLOGICAL ENVIRONMENT
Construction activities change the natural environment. But it also creates a
built environment for the surrounding. The project requires the
implementation of following choices exclusively or in combination.
A) CONSTRUCTION PHASE
Restriction of construction activities to defined project areas, which are
ecologically less sensitive.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 76
Restrictions on location of labour camps and offices for project staff
near the project area to avoid human induced secondary additional
impacts on the flora and fauna species.
Cutting, uprooting, coppicing of trees or small trees present in and
around the project site for cooking, burning or heating purposes by the
laborers will be prohibited and suitable alternatives for this purpose will
be found.
Along the major construction work the peripheral greenbelt should be
developed, so that; it will grow to become a full-fledged green cover
by the time the construction is over.
B) OPERATION PHASE
Enhancement of current ecology at the proposed project site will entail the
following measures:
Plantation & landscaping
Green Belt Development
Park & avenue plantation
The section below summarizes the techniques to be applied to achieve the
above objective.
Plantation & landscaping
Selection of the plant species will be based on their adaptability to the
existing geographical conditions and the vegetation composition of the
forest type of the region.
During the development of the green belt within the project area, it has to be
emphasized that those native plant species should be planted which are
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 77
having good ornamental values and fast growing with excellent canopy
cover.
Selection of plant species for Green belt development
The selection of plant species for the development depends on various
factors such as climate, elevation and soil. The list of plant species, which can
be suitably planted, and having significant importance are provided in Table
6.3. The plants should exhibit the following desirable characteristic in order to
be selected for plantation.
i. The species should be fast growing and providing optimum
penetrability.
ii. The species should be wind-firm and deep rooted.
iii. The species should form a dense canopy.
iv. As far as possible, the species should be indigenous and locally
available
v. Species tolerance to air pollutants like SPM, SO2 and NOx should be
preferred.
vi. The species should be permeable to help create air turbulence and
mixing within the belt.
vii. There should be no large gaps for the air to spill through.
viii. Trees with high foliage density, leaves with larger leaf area and hairy on
both the surfaces.
ix. Ability to withstand conditions like inundation and drought.
x. Soil improving plants (Nitrogen fixing, rapidly decomposable leaf litter).
xi. Attractive appearance with good flowering and fruit bearing.
xii. Bird and insect attracting tree species.
xiii. Sustainable green cover with minimal maintenance
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 78
TABLE 6.3: SUGGESTED TREES FOR GREEN BELT DEVELOPMENT
SNo. Scientific Name Standard Name Time when
flowering –
fruiting occurs
1 Tamarindus indica Imli March-April
2 Syzygium cumini Jamun June-July
3 Spathodea campanulata Rugtoora(African tulip) February-May
4 Peltophorum
pterocarpum
Copper pod/
Yellow flame tree
December-May
5 Mangifera indica Mango April-July
6 Leucaena leucocephala Subabul February-May
7 Emblica officinalis Amla January
8 Cassia fistula maltas March-June
9 Azadirachta indica Neem June-July
10 Anthocephalus cadamba Kadamb August- October
Landscaping and Avenue Plantation
Parks or gardens maintained for recreational and ornamental purposes will
not only improve the current ecology of the proposed site but also aesthetic
value in the area. The plan for plantation in parks and avenues is given
below.
Parks/Gardens
Ornamental trees with spreading branches, shade giving with colorful
flowers for people to relax.
Suitable patches of lawns, rocketry with cactus and other small
flowering xerophytic plants.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 79
TABLE 6.4: ORNAMENTAL TREES
SNO. ORNAMENTAL TREES
1 Alstonia scholaris
2 Saraca asoca
3 Ailanthus excelsa
4 Peltophorum pterocarpum
5 Callistemon citrinus
6 Acalypha hispida
7 Caesalpinia pulcherrima
8 Calliandra haematocephala
9 Cestrum nocturnum
10 Erythrina indica
11 Plumeria acuminata
12 Polyalthia longifolia
13 Polyalthia pendula
14 Putranjiva roxburghii
15 Tabernaemontana divaricata
Avenue plantation
Trees with colonial canopy with attractive flowering
Trees with branching at 10 feet and above
Trees with medium spreading branches to avoid obstruction to the
traffic
Fruit trees to be avoided because children may obstruct traffic and
general movement of public.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 80
6.1.6 EMP FOR SOCIO-ECONOMIC ENVIRONMENT
The Social management plan has been designed to take proactive steps
and adopt best practices, which are sensitive to the socio-cultural setting of
the region. The Social Management Plan for the proposed project will focus
on the following components
Income Generation Opportunity during Construction and Operation phase
Proposed project would provide employment opportunity during construction
and operation phase. There would also be a wider economic impact in terms
of generating opportunities for secondary occupation within and around the
complex. The main principles considered for employment and income
generation opportunities are out lined below:
Employment strategy would prefer employment of local people.
General recruitment procedures will be transparent, public, open to all
and recruitment should be publicized in advance.
There will be no discrimination on basis of gender, caste or other
factors.
Improved Working Environment for Employees
Proposed project would provide safe and improved working conditions for
the workers employed at the facility during construction and operation
phase. The complex will provide a new experience in working and recreation.
Following measures should be taken to improve the working environment of
the area.
Less use of chemicals and biological agents with hazard potential
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 81
Developing a proper interface between the work and the human
resource through a system of skill improvement
Measures to reduce the incidence of work related injuries, fatalities and
diseases
Maintenance and beautifications of the Complex and the surrounding
roads.
Providing a system of incentives to employers and employees to achieve
higher health and safety standards
Opportunities would be provided to the emerging and established artist to
showcase their work
Handicraft and indigenous crafts from different states would be promoted
by providing a platform for display and trade.
MITIGATIVE MEASURES
Transport and road safety: Since the project involves the movement of
vehicles and machineries in the area, the health and safety of pedestrians
and residents accessing the communities is an issue of concern. Considering
this, the project proponents shall mitigate the impact by drawing traffic
management plans, so that any mishap due to traffic thenceforth can be
avoided.
Besides having an implication on their safety, the increase in traffic would
create congestion, cause potential delays and inconvenience for
pedestrians. Taking this into concern, following aspects should be kept in
mind:
Proper precautionary signage shall be installed.
Training to the drivers
Installation of adequate speed breakers at correct locations.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 82
Conclusion
Thus overall, it’s evident that the project aims at maximizing the project
benefits to the people around the site, the region and the state in general. As
discussed in the study, appropriate measures would be taken to mitigate
negative impacts on the residents. The benefits along with mitigation
measures to tackle any adverse impact on the socio-economic conditions
should aim at creating most conducive situation for the project to operate
and maximize benefits of the socio-economic status of the society and
residents existing around the project site.
6.1.7 EMP FOR ENERGY CONSERVATION
Energy conservation program will be implemented through measures taken
both on energy demand and supply as given in Figure 6.1
FIGURE 6.1: FLOW DIAGRAM FOR ENERGY CONSERVATION
Energy conservation will be one of the focuses during the Residential
Complex planning and operation stages. The conservation efforts would
consist of the following:
Supply Demand Energy
Conservation
Use energy –efficient DG Sets
Exploring the possibilities of
introducing renewable energy
Reduce Consumption
Use energy –efficient
appliances
Create guest awareness
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 83
Energy Saving Practices
Purchase of energy efficient appliances
Constant monitoring of energy consumption and defining targets for
energy conservation
Adjusting the settings and illumination levels to ensure minimum energy
used for desired comfort levels
Installing programmable on/off timers and sensors for low occupancy
areas
Use of compact fluorescent lamps and low voltage lighting.
Sunscreen films on windows to reduce heating inside the buildings
Behavioral change on consumption
Training staff on methods of energy conservation and to be vigilant to
such opportunities.
6.2 Fire Protection and handling system:
As a part of fire protection and handling system, the following facilities are
proposed
3 Fire sumps with water capacity of 75,000 Liters
Fire Hose reels in each floor
Portable fire extinguishers in each floor and near electrical installations
Smoke detectors and automatic sprinkler system in vulnerable areas
Fire Jockey pump, Electrical main pump & Standby diesel pump
Emergency lamps in each floor and on stair cases
Smoke exhausters will be provided in basement and cellars
List of fire protection measures proposed to be installed in housing complex
are given in the Table 6.5
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 84
Table 6.5
Floor wise fire fighting systems proposed
S.
No.
Floors Exting
-
uisher
s
Hos
e
Ree
l
Down
Comer
with
hose
box
MCP Autom
atic
sprinkl
ers
Under
Ground
sumps
Fire
sump
s
Terrace
sumps
1 Basem
ent-1
53 04
04
04 434 01 03 NA
2 Basem
ent-2
50 04 04 420 NA NA NA
3 Basem
ent-3
50 04 04 420 NA NA NA
4 Groun
d Floor
16 04 04 NA NA NA NA
5 1st
Floor
16 04 04 NA NA NA NA
6 2nd
Floor
16 04 04 NA NA NA NA
7 3rd
Floor
16 04 04 NA NA NA NA
8 4th
Floor
16 04 04 NA NA NA NA
9 5th
Floor
16 04 04 NA NA NA NA
10 6th
Floor
16 04 04 NA NA NA NA
11 7th
Floor
16 04 04 NA NA NA NA
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 85
12 8th
Floor
16 04 04 NA NA NA NA
13 9th
Floor
16 04 04 NA NA NA NA
14 10th
Floor
16 04 04 NA NA NA NA
15 11th
Floor
16 04 04 NA NA NA NA
16 12th
Floor
16 04 04 NA NA NA NA
17 Terrac
e
-- -- -- -- -- -- -- 01
Total 361 64 04 64 1274 01 03 01
Summary of facilities are given below
S.No. Item Required as per Table 23 of
Part-IV of NBC of India 2005
1 Fire Extinguishers as per IS :
2190
361 Nos.
2 Hose Reel system 64 Nos.
3 Wetriser with hose box 04 Nos.
4 Automatic sprinklers system 1274 Nos.
5 Manually operated electric
fire alarm system
64 Nos.
6 Underground static water
storage tank
75,000 liters
7 Terrace Tank 10,000 liters
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 86
8 FIRE PUMPS 1 No. Elec. Pump of 1620 LPM
1 No. Diesel pump of 1620
LPM
1 No. Jockey pump of 180
LPM
Also 7 meter set back is left al round the building for free movement of fire
tender. Stairs are designed as per National Building code norms for high rise
building. Adequate signage and warnings will be provided on fire safety and
availability of fire fighting systems in the building. Ensures all electrical
installations and wiring will be complied with Indian Electricity Act and Rules
and National Building code norms. Adequate earth pits would be installed
and maintained for earthing of equipment
6.3 ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN
Apart from having an Environmental Management Plan, it is necessary to
have a permanent staff charged with the task of ensuring its effective
implementation of mitigation measures and to conduct environmental
monitoring. The major duties and responsibilities of the person – in - charge
shall be as given below:
To implement the environmental management plan,
To assure regulatory compliance with all relevant rules and regulations,
To ensure regular operation and maintenance of pollution control
devices,
To minimize environmental impacts of operations by strict adherence
to the EMP.
To initiate environmental monitoring as per approved schedule.
Review and interpretation of monitored results and corrective
measures in case monitored results are above the specified limit.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 87
Maintain documentation of good environmental practices and
applicable environmental laws as ready reference.
Maintain environmental related records.
Coordination with regulatory agencies, external consultants, monitoring
laboratories.
Maintain of log of public inconvenience and the action taken
6.2.1 ENVIRONMENTALMONITORING
The purpose of environmental monitoring is to evaluate the effectiveness of
implementation of Environmental Management Plan (EMP) by periodically
monitoring the important environmental parameters within the impact area,
so that any adverse affects are detected and timely action can be taken.
The following areas will be monitored regularly;
1) Raw water quality of HMWS&SB water supply, Bore well water and
tanker water (whenever used) will be monitored regularly to ensure
suitability for drinking or other domestic usage.
2) The treated water quality shall also be checked on a regular basis
particularly at the points of actual use.
3) Water consumption in various areas and for different users will be
measured on a regular basis. Water measurement devices will be
included in the design itself so that representative water consumption
data can be obtained and measures of control instituted.
4) Raw and Treated Sewage will be monitored for general parameters like
pH, SS, COD, BOD and Oil & Grease. Also, residual chlorine and
coliforms will also be monitored for treated effluent.
5) Ambient air quality within the project area will be monitored quarterly
in a year for Pm2.5, PM10, SO2, NOx & CO.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 88
6) Stack emissions with respect to PM, SOx, and NOx level will be regularly
monitored from all stacks. The DG stack emissions especially are
regulated as per G.S.R- 489(E) dated July 9th, 2002 and compliance to
these or APPCB standards if any, will be ensured.
7) Noise levels will be checked at regular interval near service block with
DG sets, boilers, compressors and HVAC system, near STP and other
noise generating areas.
8) Quantity of solid waste generation will also be measured for the
different types of solid waste.
9) Quantity of hazardous wastes generated (waste lube and transformer
oil) shall be measured on a regular basis and records of disposal
maintained as per the Hazardous Waste (Management & Handling
Rules, 2003).
10) Numbers of used lead-acid batteries disposed off to authorised
vendors/ dealers will be monitored and requisite records maintained.
6.2.2 AWARENESS AND TRAINING
Training and human resource development is an important link to achieve
sustainable operation of the facility and environmental management.
For successful functioning of the project, relevant EMP’s should be
communicated to the following groups of people:
Employees
Employees must be made aware of the importance of waste segregation
and storage, water and energy conservation. This awareness can be
provided through leaflets and periodic in house meetings. They should be
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 89
informed of their responsibilities for successful operation of various
environmental management schemes inside the premises.
Site Staff
Relevant personnel at site must be trained for the following:
Collection, Segregation and Storage of the solid and waste generated
during oil change.
Operation and maintenance of Sewage Treatment Plant and
reclamation system
Requirements of the Emergency Response Plan in case of an
emergency.
Techniques for waste minimization, water conservation and energy
conservation
Applicable environmental, health and safety regulations and
compliance requirements for the same.
Functioning of the Environmental Management System including
environmental monitoring, reporting and documentation needs.
6.2.3 RECORD KEEPING AND REPORTING
Record keeping and reporting of performance is an important management
tool for ensuring sustainable operation of the proposed project. Records
should be maintained for regulatory, monitoring and operational issues.
Typical record keeping requirements for the project site is summarized in
Table – 6.6: RECORD KEEPING REQUIREMENTS
Parameter Particulars
Solid Waste Handling
and Disposal
Daily quantity of waste generated and sent for
disposal
Sewage Treatment Daily quantity of raw and treated sewage
Quantity and point of usage of treated
wastewater
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 90
Treated wastewater quality
Regulatory Licenses
(Environmental)
Environmental Permits / Consents from APPCB /
MOEF
Copy of Waste manifests as per requirement
Monitoring and
Survey
Records of all monitoring carried out as per the
finalized Monitoring protocol.
Other Log book of compliance
Employee environmental, health and safety
records
Equipment inspection and calibration records,
where applicable
Vehicle maintenance and inspection records
6.2.4 ENVIRONMENTAL AUDITS AND CORRECTIVE ACTION PLANS
To assess whether the implemented EMP is adequate, the project
Management Committee will conduct periodic environmental audits. These
audits will be followed by Corrective Action Plans (CAP) to correct various
issues identified during the audits.
6.2.5 BUDGET FOR EMP:
The details of activities and expenses to be incurred on EMP are presented
below.
TABLE 6.7 – BUDGET FOR EMP
S. No Component Amount Rs Lakhs
1 Dust Suppression 5.0
2 STP 40.0
3 Acoustic enclosures to
DG sets
10.0
4 Green Belt Development 10.0
5 Rainwater Harvesting 10.0
Total 75.0
Recurring Expenditure 5.0
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 91
The recurring expenditure includes maintenance of green area & landscape,
monitoring of environmental attributes and maintenance & operation of STP
and rain water harvesting system.
The budget for the components of EMP will be a part of project cost while the
recurring expenditure will be met from the maintenance charges collected
from residents on monthly basis.
6.2.6 ENVIRONMENTAL MANAGEMENT CELL
At least one permanent employee (Environmental Officer) with adequate
educational and professional qualification and experience to discharge
responsibilities related to environmental management including statutory
compliance, pollution prevention/ waste minimization, environment
monitoring, preventive maintenance of pollution control equipment, green
belt development and maintenance will be employed by the project
proponent. The Environmental Officer will be responsible for all issues related
to environmental management at proposed project and will report directly
to the management.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 92
CHAPTER–7
7.0 BENEFITS OF THE PROJECT
The project would benefit the project area in many aspects as detailed
below:
The project would provide residential apartments at affordable costs.
The project also ensures healthy and comfortable living environment. The
improvements in the physical infrastructure of the project result in the
development of Residential and service activities in the surroundings.
The implementation of project contributes to improvements in the social
infrastructure like roads, housing, water supply, electrical power, drainage,
educational institutions and hospitals etc., in the locality.
The project would create employment potential for skilled, semi-skilled and
unskilled labor both during construction and operational phases of the
project to local population.
Also for imparting any specialized skills to them to be eligible for such
employment in the project on a long term basis i.e., during operational and
maintenance stages of the project.
Residential Complex Sri. Raavi Surya Prakash Babu, Sy.No 978 & 979,Kukatpally(v), Balanagar(M),Rangareddy(D), Telangana.
Pridhvi Envirotech (P) Ltd,Hyderabad. Page 93
CHAPTER– 8
8.0 CONCLUSION
The proposed project is aimed at developing residential facilities. The
proposed site is away from city traffic and located in serene environment
which will give comfort to guests. Adequate care is taken to protect,
preserve and improve the environment around the site. About 3805.11 Sq.mts
of the area earmarked for development of greenery. It is proposed to take
water from HMWS&SB so that project need not draw ground water. Further
rain water harvesting structures proposed to enhance the ground water of
area. The waste water is proposed to be treated in ecologically friendly
treatment methodology and re-use back.
As the site is well connected with existing road net work and outer ring road
no additional impact will be there on existing roads. Enough parking place is
proposed to be developed for vehicles within the complex.
Thus the project is environmentally viable and sustainable.