hpgcl centre/presentation...boiler light-up. 01-aug-09. ... tg on barring gear. 16-sept-09....

53
HPGCL HARYANA POWER GENERATION CORPORATION LIMITED 01 May 2009

Upload: lamdiep

Post on 19-Mar-2018

216 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

HARYANA POWER GENERATION CORPORATION LIMITED

01 May 2009

Page 2: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Presentation

before

State Advisory Committee

on

HPGCL’s Tariff Application for FY 2009-10

Page 3: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLPRESENT INSTALLED CAPACITY OF HPGCL IN THE STATE

Sr.No

Name of Power Station Capacity (MW) &Unit No.

Date of commissioning

AGENERATIONCAPACITY OF1324.4 MWHAS BEENADDED INTHE STATEAFTERCREATIONOF HPGCLWHICH IS ANINCREASEOF MORETHAN 150%.

Unit-2 of FTPShas beenphased outw.e.f. 08.09.08

1 Faridabad Thermal PowerStation 110 MW (2x55 MW)

55 MW Unit-1 55 MW Unit-3

22.11.7401.04.81

2 Panipat Thermal PowerStation, Panipat 1360 MW(4x110 MW+2x210+2X250MW MW).

110 MW Unit-1110 MW Unit-2110 MW Unit-3110 MW Unit-4210 MW Unit-5210 MW Unit-6250 MW Unit-7250 MW Unit-8

01.11.7927.03.8001.11.8511.01.8728.03.8931.03.0129.12.0408.04.05

3 Deen Bandhu Chhotu RamThermal Power Project 600MW (2x300 MW)

300 MW Unit-1300 MW Unit-2

14.04.0824.06.08

4 WYC Hydro Electric Station,Yamuna Nagar 62.7 MW(6x8+2X7.2 MW+0.3 MW)

2x8 MW PH-A2x8 MW PH-B2x8 MW PH-C

2x7.2 MW PH-D

19861987

1988-892004

Total Installed Capacity 2132.7 MW

Page 4: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLCAPACITY ADDITION - POST REFORMS

• BEFORE UNBUNDLING, THE INSTALLEDGENERATION CAPACITY IN THE STATE WAS863 MW.

• A GENERATION CAPACITY OF 1324.4 MW HASBEEN ADDED IN THE STATE AFTER CREATIONOF HPGCL WHICH IS AN INCREASE OF MORETHAN 150%.

Page 5: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL GENERATION CAPACITY OF HPGCL BY 2009-10

Present GenerationCapacity (MW)

Generation Capacity by2009-10 (MW)

Increase

2132.7 3332.7 56 %

Page 6: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

IMPROVEMENT IN PERFORMANCE OF HPGCL SINCE ITS CREATION

Particulars 1998-99 2008-09 Achievements

InstalledCapacity (MW)

863.30 2132.70 An addition of around 150%.

Generation (MUs) 3784 13519 An increase by 250 % achieved with increase in generation capacity of

only 150%.PLF (%) 49.24 75.01 An increase of around 52 %.

AuxiliaryConsumption(%)

12.04 9.66 A reduction of 20 % resulting into lower cost of generation. Lowest

since formation of HPGCL.CoalConsumption(Gms/kwh)

838 712 A reduction of more than 15% resulting into lower cost of generation and reduced emissions. Lowest since

formation of HPGCL.Oil Consumption(ml/kwh)

12.70 2.87 A reduction of 77% resulting into lower cost of generation.

Page 7: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

HPGCL Performance since 1998-99

Page 8: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

PERFORMANCE OF HPGCL AS A WHOLE FROM FY 1998-1999 TO 2008-09

Particulars

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

InstalledCapacity(MW)

863.3 863.3 863.3 1073.3 1073.3 1073.3 1587.7 1587.7 1587.7 2187.7 2132.7

GrossGeneration(MUs)

3784 4051 3792 5161 6212 6998 6915 9181 10780 10845 13519

PLF (%) 49.24 53.24 49.73 60.80 66.44 74.91 69.46 67.00 78.78 78.94 75.01

AuxiliaryConsumption (%)

12.04 11.70 11.80 11.11 10.56 10.47 11.04 10.08 9.80 9.93 9.66

CoalConsumption(Gms/kwh)

838 803 816 789 770 764 784 741 721 735 712

OilConsumption (ml/kwh)

12.70 6.38 5.97 3.29 3.43 3.35 3.97 3.74 1.85 1.66 2.87

TransitLoss ofCoal (Up toDec)

6.58 6.48 4.19 4.23 4.79 3.06 6.00 2.87

Page 9: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL INSTALLED CAPACITY (MW) OF HPGCL FROM FY 1998-1999 TO 2008-09

863.3 863.3 863.3

1,073.31,073.3 1,073.3

1,587.7

1,587.71,587.7

2,187.72,132.7

0.0

500.0

1,000.0

1,500.0

2,000.0

2,500.0

MW

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09 YEARS

Installed Capacity

Page 10: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

PLANT LOAD FACTOR (PLF) OF HPGCL FROM FY 1998-1999 TO 2008-09

49.24

53.24

49.73

60.8066.44

74.91

69.4667.00

78.78 78.9475.01

0

10

20

30

40

50

60

70

80

% A

GE

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

YEARS

PLF

*

Page 11: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

PLANT LOAD FACTOR (PLF) OF HPGCL FROM FY 1998-1999 TO 2008-09

49.2453.24

49.73

60.8066.44

74.9169.46 67.00

78.78 78.9480.9

0

10

20

30

40

50

60

70

80

90

% A

GE

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

YEARS

PLF

* Excluding PTPS Unit-1 and DCRTPP

*

Page 12: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLAUXILIARY CONSUMPTION OF HPGCL FROM FY 1998-1999 TO 2008-09

12.0411.70 11.80

11.11

10.56 10.4711.04

10.089.80

9.939.66

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

% A

GE

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

YEARS

AUXILIARY CONSUMPTION

Page 13: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL COAL CONSUMPTION OF HPGCL FROM FY 1998-1999 TO 2008-09

712

735721

741

784

764770

789

816803

838

640

660

680

700

720

740

760

780

800

820

840

860

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

YEARS

GM

S/K

WH

COAL CONSUMPTION

Page 14: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

OIL CONSUMPTION OF HPGCL FROM FY 1998-1999 TO 2008-09

12.7

6.38 5.97

3.293.43 3.35

3.97 3.74

1.85 1.66

2.87

0

2

4

6

8

10

12

14

(ML

/KW

H)

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

YEARS

O IL CO NSUMPTIO N

Page 15: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

OIL CONSUMPTION OF HPGCL FROM FY 1998-1999 TO 2008-09 (excluding DCRTPP)

12.7

6.385.97

3.293.43 3.35

3.97 3.74

1.85 1.66 1.8

0

2

4

6

8

10

12

14

(ML

/KW

H)

98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

YEARS

OIL CONSUMPTION

Page 16: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

CAPACITY ADDITION DURING THE 11TH

FIVE YEAR PLAN

Page 17: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

POWER SCENARIO

CAPACITY ADDITION PROGRAMME OF HARYANA

• In the 17th Electric Power Survey carried out by the CentralElectricity Authority (CEA), New Delhi, peak demand of 6839 MWhas been projected for Haryana during the year 2011-12.

• However, on the basis of actual load growth pattern, Haryana hasmade liberal projections of 15% per annum increase in growth ofpeak demand which is expected to reach 7335 MW during 2008-09 and 11155 MW by the year 2011-12.

• Haryana has accordingly embarked on an aggressive programmefor capacity addition to the tune of 5000 MW during the 11th Planperiod.

Page 18: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLCAPACITY ADDITION SCENARIO DURING 11TH PLAN PERIOD

AND BEYOND

Sources of installed capacity 2008-09 2009-10 2010-11 2011-12 2012-13State Owned Projects 1532.7 1532.7 1422.7 1422.7 1422.7Central Sector Share 1628 1628 1628 1628 1628Shared Projects - BBMB & IP 937.5 937.5 937.5 937.5 937.5DCRTPP Yamuna Nagar 600 600 600 600 600Hisar TPS (600X2) Mega Plant Status 1080 1080 1080 1080

Jhajjar Case- II 1320 MW 594 1188Aravali STPS,Jhajjar (500*3){Haryana:Delhi - 50:50} 750 750 750

Additional availability through PPA with IPPs/CPSU 97.5 655 983 2651 6028

Yamuna Nagar Extention 300Faridabad Gas 432Total Available Capacity (MW) 4795.7 6433.2 7401.2 9663.2 13634.2Projected Demand with 15% growth (MW) 7335 8435 9700 11155 12828

Page 19: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

7335

8435

9700

11155 12828

4795

64337401

9663

13634

3000400050006000700080009000

100001100012000130001400015000

2008-09 2009-10 2010-11 2011-12 2012-13

Year

Demand with 15% GrowthProposed Capacity

Year 2008-09 2009-10 2010-11 2011-12 2012-13

Demand with 15% Growth 7335 8435 9700 11155 12828Proposed Capacity 4795 6433 7401 9663 13634

DEMAND, PROPOSED CAPACITY & AVAILABLE

CAPACITY GROWTH (MW)

Page 20: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

GENERATION CAPACITY ADDITION PROJECTS IN PIPELINE

Page 21: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLGENERATION CAPACITY ADDITION PROGRAMME

IN THE STATE DURING 11th PLAN (2007-12)

Sr. No.

Name of Project Capacity in MW

Commissioning Schedule

1. Deenbandhu Chhotu Ram Thermal Power Station, Yamuna Nagar.

2x300 MW = 600 MW

Commissioned on 14.04.08 & 24.06.08.

2. Rajiv Gandhi Thermal Power Project, Hisar

2x600 MW = 1200 MW

Unit-I : Dec. 2009Unit-II : March 2010

3. Indira Gandhi Super Thermal Power Project, Jhajjar (JV between NTPC, Delhi & Haryana)

3x500 MW(Haryana’s Share 750 MW)

Unit-I : Apr 2010Unit-II : July 2010Unit-III : Oct 2010

4. Jhajjar Thermal Power Project (Case-2)

2x660 MW =1320 MW

Unit-I : Dec. 2011Unit-II : May 2012

Page 22: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL 2X300 MW DEENBANDHU CHHOTU RAM THERMAL POWER PROJECT, YAMUNA NAGAR

INSTALLED CAPACITY : 2X300 MW

TOTAL ESTIMATED COST : Rs. 2400 CRORE

TOTAL LAND : 1107 ACRES.

EPC CONTRACTOR : RELIANCE ENERGY LTD.

EPC COST : Rs. 3.49 CRORE/MW

COAL LINKAGE : 2.77 MTPA FROM CCL.COMMISSIONED ON : UNIT-I : 14.04.2008

UNIT-II : 24.06.2008POWER AVAILABILITY : AROUND 144 LAC UNITS

PER DAY WHEN OPERATING AT RATED CAPACITY.

PROJECT HIGHLIGHTS :

Page 23: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Unique features of the Project:

First successful inception of Chinese Technologyin Indian Power Sector

First Project in the Country where BTG equipmentwas supplied by M/s Shanghai Electric Corp.China.

Very low per MW EPC cost - Rs. 3.49 Crore per MW.

2 x 300 MW DEENBANDHU CHHOTU RAM THERMAL POWER PROJECT, YAMUNA NAGAR

Page 24: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

A. PROJECT FINANCING:

Debt Equity ratio: 20% State Govt. equity and 80% loan. Loan of Rs. 1920.00 crore from M/s PFC.

B. TARIFF: First year tariff : Rs. 2.70 Levelized tariff for 25 years : Rs. 3.08 Levelized tariff for 30 years : Rs. 3.15

2 x 300 MW DEENBANDHU CHHOTU RAM THERMAL POWER PROJECT, YAMUNA NAGAR

Page 25: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL2 x 600 MW RAJIV GANDHI

THERMAL POWER PLANT, KHEDAR, HISAR

PROJECT HIGHLIGHTS :

INSTALLED CAPACITY : 2X600 MW

TOTAL ESTIMATED COST : Rs. 4297 CRORE

STATUS OF CLEARANCES : ALL CLEARANCES AVAILABLE

COAL LINKAGE : 5.83 MILLION TONNE PER ANNUM FROMMAHANADI COALFIELDS LTD (MCL)

ORISSA

WATER AVAILABILITY : 50 CUSECS ALLOCATED FROM BARWALA BRANCH OF BHAKRA CANAL

COMMISSIONING : UNIT-I : 28.12.2009 (35 Months)*SCHEDULE UNIT-II : 28.03.2010 (38 Months)*

POWER AVAILABILITY : 288 LAC UNITS PER DAY

BEST EFFORT SCHEDULE : Unit-I : 28.11.2009 (34 Months)Unit-II : 28.01.2010 (36 Months)

PROGRESS : Around 70 % overall progress achieved.

Page 26: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Unique features of the Project:

First Mega Power Project in the Northern Region. 600 MW – Largest single Unit capacity in the Northern

Region. Lowest per MW cost in the Country - Rs. 3.14 Crore per MW. Most aggressive commissioning schedule of 35 and 38

months. Best effort schedule of 34 and 36 months being targeted.

2 x 600 MW RAJIV GANDHI THERMAL POWER PLANT, KHEDAR, HISAR

Page 27: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

A. PROJECT FINANCING:

Debt Equity ratio: 20% State Govt. equity and 80% loan. Loan of Rs. 1453.00 crore from M/s PFC.

Rs. 1536.03 crore from M/s RECRs. 500.00 crore from NCR Planning Board.

B. TARIFF: First year tariff : Rs. 2.80 Levelized tariff for 25 years : Rs. 3.54 Levelized tariff for 30 years : Rs. 3.65

2 x 600 MW RAJIV GANDHI THERMAL POWER PLANT, KHEDAR, HISAR

Page 28: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL2 x 600 MW RAJIV GANDHI

THERMAL POWER PLANT, KHEDAR, HISAR

SL Milestones Unit-1 Date/Schedule

Unit-2 Date/Schedule

1 Piling Commencement 19-May-07 22-Jul-07

2 Boiler Erection - Start 04 Dec 07 31-Dec-07

3 Boiler Drum Lifting 10-Sep-08 06-Nov-08

4 TG Erection – Start 24-Nov-08 22-Dec-08

5 Boiler Hydro-Test 28-Feb-09 28-June-09

6 Turbine Box Up 15-Jul-09 15-Oct-09

7 Boiler Light-Up 01-Aug-09 01-Nov-09

8 TG on barring Gear 16-Sept-09 16-Dec-09

9 Synchronization 28-Sept-09 28-Dec-09

10 Provisional Taking Over 28-Dec-09 28-March-10

MILESTONES

Page 29: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Highlights of Progress

• The construction work of the project is going on at full swing.• Overall 70 percent of the work has already been completed.• In engineering and procurement a progress of 85 percent and

78 percent, respectively, has been achieved.• The major milestone of boiler drum lifting of Unit-2 was achieved

on Nov. 06, 2008 , 22 days ahead of schedule.• The project has achieved a record by completing the hydraulic

test of the boiler of Unit -1 in 24 months and 29 days which isthe fastest hydraulic test in India.

• The hydraulic test of Unit-2 boiler was also completed on18.04.09 , about four months ahead of original schedule.

• An overall expenditure of Rs. 1916.69 crore has so far beenincurred on the project which is more than 50 percent of thetotal Engineering, Procurement and Construction cost of Rs.3775.42 Crores.

2 x 600 MW RAJIV GANDHI THERMAL POWER PLANT, KHEDAR, HISAR

Page 30: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL3X500 MW ARAVALI SUPER THERMAL POWER PROJECT,

JHAJJAR1500 MW coal based Power Plant being executed at Jhajjar by Aravali Power Company Pvt. Ltd., a joint venture of Haryana with NTPC and NCT of Delhi.Haryana’s Share 750 MW (Generation from the project is scheduled to

commence during 2010-11).Total estimated cost Rs 7892.42 crore

a) Land Requirement 2231 acre

b) Water availability 75 cusecs from Jawahar Lal Nehru canal.

c) NOC from Haryana State Pollution Control Board (HSPCB)

Received in August, 2007.

d) MoE&F clearance Received on 08.08.07.

e) Coal linkage Coal linkage of 6.94 Million Tonne Per Annumallocated from Mahanadi Coalfields Ltd. by Ministryof Coal, Govt. of India.

Equity contribution NTPC-50%, Haryana-25%, Delhi-25%.

Date of LOI 06.07.07 (boiler), 14.07.07 (turbine)

Power Availability 180 Lac Units Per day for Haryana.

Page 31: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL DCRTPP YAMUNA NAGAR – UNIT-3

Capacity 250-300 MW

Estimated cost of the project 1345 crore

Debt Equity ratio 80:20

The expert Appraisal Committee of MoE&F , Govt. of India in its meeting held on 11 February 2009 has approved the Terms of Reference (ToR) for setting up of 3rd Unit.

Page 32: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Procurement of power through Case-1 & Case-2 tariff based competitive bidding

Page 33: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLPROCUREMENT OF POWER : CASE-1 & CASE 2

TARIFF BASED COMPETITIVE BIDDING

Tariff Policy of Ministry of Power( 06.01.2006 ):All future procurement of power on long term basis by distributionlicensees through tariff based competitive bidding

HPGCL assessed future requirement upto 2012-13 and after takingapproval of HERC decided to procure power for a period of 25years as under:

1. 2000 MW under case-1 (land, fuel or other details notspecified).

2. 90% power from a Thermal Project to be developed at Jhajjarof capacity 1320 MW under Case-2.

Page 34: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

PROCUREMENT OF POWER THROUGH CASE-1 TARIFF BASED COMPETITIVE BIDDING

Initiation: May 2006 ; Request for Qualification ( RFQ)Conclusion: July 2008 by selecting three bidders by theEvaluation Committee headed by the Chief Secretary:

Bidder Levelised Tariff ( Rs. Per Unit)

Quantum of Power ( MW)

Lanco Kondapalli Pvt Ltd 2.355 389

PTC from GMR Project 2.86 300

Adani Power Limited 2.94 1424

PPA signed with PTC and Adani on 07.08.2008

Lanco did not come forward to sign PPA. BG of Rs. 11.67crore encashed. Petition filed with HERC for adjudicationand for issuing directions to Lanco for signing of PPA

Page 35: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLPOWER PROCUREMENT THROUGH TARIFF

BASED COMPETITIVE BIDDING UNDER CASE-2

19 bidders submitted their bids after Request forQualification (RFQ).

Evaluation Committee headed by the Chief Secretaryapproved qualification of 11 bidders for submitting thefinancial bids on 22 May 07.

Financial bids submitted by three bidders opened on 17March 2008.

Bid submitted by M/s CLP Power India Pvt Limited,Mumbai found most competitive

Letter of Intent (LOI) issued on M/s CLP Power IndiaPrivate Limited, Mumbai on 23.07.2008.

Page 36: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

SPV Jhajjar Power Limited (JPL) incorporated assubsidiary company of HPGCL for easy transfer ofLand, Water, Fuel and Environmental Clearance to thesuccessful bidder.

The Power Purchase Agreement (PPA) signedbetween the Haryana Distribution Companies and M/sJPL on 07 August 08.

“Jhajjar Power Limited” taken over by M/s CLP

CLP Power india Ltd is committed to commission firstunit of 660 MW in December 2011 and the second unitof 660 MW in May 2012.

Page 37: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

FUTURE GENERATION PROJECTS / INITIATIVES BEING PLANNED IN THE STATE

1050 MW Gas based Project at Faridabad by phasing out oldFaridabad Thermal Power Station.

300 MW capacity Thermal Unit at Yamuna Nagar as anextension of 2x300 MW DCRTPP, Yamuna Nagar.

2800 MW (4x700 MW) Nuclear Power Plant near Fatehabad –Site stands identified by Nuclear Power Corporation of India.

Coal block at Mara-to-Mahan in MP with estimated coalreserves of 956 Million Tonnes allocated jointly to HPGCLand Delhi Govt. Required steps being taken for developmentof coal block.

Page 38: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

11TH FIVE YEAR PLAN INVESTMENTS OF HARYANA POWER SECTOR

Amount (Rs. Crores)

Generation 11367.01

Transmission 7643.00

Distribution 6514.32

Grand Total (Generation + Transmission + Distribution) 25524.33

Govt. of Haryana will provide equity support of Rs. 4942 crores

Page 39: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLCHALLENGES BEFORE HPGCL

INCREASING PLF FROM PRESENT 78-80% TO 90% ON A SUSTAINED BASIS IN THENEXT TWO YEARS

ISO 9000 AND 1SO 14000 CERTIFICATION FOR OUR POWER PLANTS.

IT ENABLEMENT OF ALL PROCESSES AND SYSTEMS AT PLANTS AND OFFICES.

CAPACITY ADDITION OF 200 -300 MW EVERY YEAR TO KEEP UP WITH THE DEMAND.

DEDICATED COAL SOURCES FOR ENERGY SECURITY.

PITHEAD POWER PLANT NEAR ALLOCATED COAL BLOCK-POWER DEDICATED FORHARYANA.

TO DEVELOP ALTERNATE SOURCES OF GENERATION-GAS, HYDRO THROUGH JVETC.

EXPEDITING THE NUCLEAR POWER PLANT AT FATEHABAD, IN VIEW OF THE INDO-USNUCLEAR DEAL.

DEVELOPMENT OF A SYSTEM FOR SELLING SURPLUS POWER TO OTHER STATES.

FULFILLING CORPORATE SOCIAL RESPONSIBILITY IN THE AREAS AROUNDPROJECTS AND CONTRIBUTE TOWARDS NATION BUILDING.

Page 40: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

2x600 MW RAJIV GANDHI THERMAL POWER

PROJECT KHEDAR, HISAR

Page 41: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL An overall view

Page 42: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL Another overall view

Page 43: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Mara-to-Mahan Coal Block in Madhya Pradesh

Page 44: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL MARA-TO-MAHAN COAL BLOCK IN MADHYA PRADESH

Mara-to-Mahan Coal Block allocated jointly toGovernment of Delhi and HPGCL in August 2006.

Estimated reserves are 950 Million Tonnes and cansupport about 6000 MW power generation.

Provisional Geological Report (GR) obtained from M/SCentral Mine planning & Design Institute Ltd (CMPDI),Ranchi on 29.11.2007

Letter of Intent (LOI) issued to M/s Mineral ExplorationCorpn Limited (MECL) Nagpur on 26.02.2008 for priorityexploration of Coal block under Phase-1 (10 Sq Km)

Joint Venture Agreement (JVA) between HPGCL andGovt. of NCT Delhi (through Indraprastha PowerGeneration Company Ltd, N.Delhi) signed on 05.12.08.

Page 45: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Joint Venture Company (JVC) of HPGCL and IPGCLincorporated in the name of “Yamuna Coal Company PrivateLimited” (YCCPL) with head office at Faridabad on 15January 2009.

Case forwarded on 13.02.09 by MP Govt to Ministry of Coal for issuing prospecting licence

Forest Deptt. (MP) on 17.02.09 conveyed approval forconducting topographical survey

Forest Deptt. (MP) on 03.03.09 forwarded the case to theMinistry of Forest/ GoI for according clearance for drilling inthe area.

The work of topographical survey shall be done by MECLNagpur as part of the scope of work under the aforesaidLOI.

Firm/ Detailed work order to be issued to M/s MECLalongwith advance payment of Rs. 1.14 Cr is underfinalization.

Page 46: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Setting up of Nuclear Power Plant in the State of Haryana

Page 47: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLSETTING UP OF NUCLEAR POWER PLANT IN

THE STATE OF HARYANA

In 1984 Haryana offered a couple of sites in Yamunanagarand Hisar for location of an Atomic Power Plant to theDepartment of Atomic Energy.

The proposed site in village Kumharia (in DistrictFatehabad) found suitable as per the preliminaryinvestigation.

Detailed investigations carried out in the year 2001 by theSite Selection Committee of NPCIL

The site was assessed for a potential of 2800 MW (4x700MW units).

Haryana Irrigation Deptt confirmed availability of total of 320cusecs of water for 2800 MW plant, in January 2006.

The Site Selection Committee in June 2007 againinvestigated the site for setting up 2X700 MW Nuclear PowerPlant in the first stage.

NPCIL has recommended this site besides three others

Page 48: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL

Phasing out of Faridabad Thermal Power Station

Page 49: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL OLD AND OBSOLETE UNITS

•The three Coal based Thermal Units at FTPS, Faridabad weresupplied and commissioned by M/s. BHEL, in November 1974, March1976 & April 1981.

•These Units were originally rated for 60 MW Capacity each and weresubsequently de-rated to 55 MW by the Central Electricity Authority(CEA) on 11 January 90 on account of technical constraints which still

exist.

•The Units are based on obsolete technology and have already out-lived their useful life as the designed working life of a thermal Unit isnormally considered as 25 years.

•These Units are designed for coal inputs with very high calorific value(5500 Kcal/kg) and low Ash content (i.e. 22%). Coal with theseparameters is not being supplied by the coal companies since lastmany years.

Page 50: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL The major constraints are :

• Very high cost of generation• Poor coal quality. • Poor quality of raw water.• Problems in ash disposal. • Non availability of standby auxiliaries.• Location of the plant in the heart of the city with a

Municipal road passing through.• Major Safety Hazard.• Environmental issues.

Page 51: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL PHASING OUT

During August 2005 the Government of Haryanaaccorded administrative approval for:

Phasing out the existing coal based 3x55 MW FTPS inthe next 5-6 years.

Setting up of 1050 MW (3x350 MW) Gas basedCombined Cycle Power Plant at Nawada Koh nearBadkhal during the 11th Plan.

Page 52: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCLUNIT-2 RETIRED

• Though, the performance of all the Units has gonedown during the last 3-4 years, the deterioration inperformance of Unit-2 was very rapid due torepeated failures of boiler tubes on the one sideand turbine blade failure on the other side.

• The Board of Directors of HPGCL in its 66th

meeting held on 15.10.08 approved the phasingout of Unit -2 of FTPS.

• Government & CEA approval for phasing out units1 & 3 by March 2010.

Page 53: HPGCL Centre/Presentation...Boiler Light-Up. 01-Aug-09. ... TG on barring Gear. 16-Sept-09. 16-Dec-09. 9. Synchronization . 28-Sept-09. 28-Dec-09. 10. ... • The hydraulic test of

HPGCL