options report sept 09 - 28 sept, 2009.pdf

Upload: soleb

Post on 14-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    1/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    1

    EXECUTIVE SUMMARY

    By letter ref. xxxx, dated xxxxxx, the Consultant was instructed by the Client to commence

    the dual design services for the section of Kampala Gayaza Zirobwe road project from

    Ch 0+000 to Ch 1+300, i.e. from the Mulago/Bombo road Roundabout to the Gayaza

    road/Kampala Northern Bypass Roundabout, pending formal signature of the relevantAddendum no. xxxxx still under preparation..

    Having mobilised the proposed staff for this assignment and commenced services as

    instructed by the Client, the Consultant has to date executed the following activities:

    1.1 Identification, survey and mapping of all existing roads accessing the proposed dualcarriageway section.

    1.2 Review of the existing traffic data.

    1.3 Study of the current traffic flow patterns and vehicle parking characteristics and

    development of traffic flow management options.

    1.4 Identification, survey and mapping of existing road drainage facilities

    1.5 Identification, survey and mapping of all building structures and visible/overheadutility services within and adjacent to 15m from the existing road centreline.

    1.6 Liaison with utility companies and identification of all underground utility serviceslikely to be affected by the proposed works.

    1.7 Analysis of the feasible options

    1.8 Presentation of the best evaluated two dual design options

    1.9 Recommendation of the preferred dual design option

    In respect of Activity 1.1 above, it is evident from the information obtained that most of

    the existing access roads are minor earth/gravel access roads that are not engineered apart

    from Mawanda road access at approximately Ch 0+757 RHS.

    In respect of Activity 1.2 above, based on a review of the available 2007 traffic data, the

    projected design year (2020) traffic is 26,205 PCUs/day and according to

    recommendations by the Uganda Road Design Manual (Road Safety Revision, of July

    2004), this level of traffic justifies provision of a dual carriageway in order to meet the

    desired level of service standards for category A & B roads in a flat terrain typical of theproject area.

    In respect of Activity 1.3 above, traffic surveys conducted by the Consultant during this

    assignment have confirmed the following:

    The access roads are mainly used by private cars, taxis and commuter matatus asby-passes during the peak-hour traffic congestion periods as opposed to being used

    by residents to access their homes.

    There is a significant level of parking traffic around the Kalerwe area; these beingmainly commuter taxis/matatus dropping and picking up passengers, private cars

    for shoppers and trucks loading and offloading merchandise and that this parking

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    2/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    2

    traffic significantly reduce the available travelled way for the through traffic

    resulting in traffic congestion.

    In respect of Activity 1.4 above, all existing drainage facilities have been surveyed and

    included on drawings in appendix 1.

    In respect of Activity 1.5 above, building structures and visible utility services within 15m

    from the existing road centreline and adjacent to that 30m corridor, have been surveyed

    and included on the existing services drawings in appendix 1.

    In respect of Activity 1.6 above, the Consultant has liaised with the respective services

    bodies and identified existing underground services likely to be affected by the proposed

    works. These services indicated on drawings in appendix 1 are for National Water and

    Sewerage Corporation, Uganda Telecom and UMEME. No services were identified for the

    remaining utility companies.

    In respect of Activity 1.7, the feasible options analysed during this study relate to thetraffic flow / management options, access to the various frontage businesses and markets,

    surface water drainage outline options and geometric lay out options.

    In respect of Activity 1.8, the Consultants options are summarised below:

    Option 1

    Traffic flow onto and along the proposed dual carriageway section

    This option requires that no right turns are allowed for traffic joining the proposed dual

    carriageway section. Consequently, all motorised traffic joining the proposed dual

    carriageway would have to follow the general traffic flow direction of the proposed dual

    carriageway until the next roundabout where it would turn to join the intended

    carriageway.

    Surface water drainage layout

    This option requires that side drains generally drain surface water towards Gayaza side as

    the proposed dual carriageway vertical profile generally falls in that direction.

    Dual carriageway geometric layout; including all frontage business service accesses

    This option provides that 3.25m wide lanes are used with a 1.2m wide central raised island

    (0.2m above the adjacent finished road levels), service roads at selected locations on the

    right hand side (in front of the market area) and on the left hand side on the approaches to

    the Kalerwe market area. 1.5 m wide raised sidewalks are also proposed on both the LHS

    and RHS with accesses to main business premises.

    Option 2

    Traffic flow onto and along the proposed dual carriageway section

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    3/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    3

    Option 2 provides that since Mawanda road is a major access road, traffic joining the

    proposed dual carriageway section from Mawanda road be allowed to make a right turn

    and the junction be designed as a partly Channelised T-intersection. Traffic from the rest of

    the access roads is prohibited from making any right turn.

    Surface water drainage layout

    In terms of surface water drainage, this option provides that surface water runoff in the side

    drains travels the minimum distance possible before discharging into the nearest cross

    culvert and into the discharge channels. This therefore requires that in some instances, the

    invert levels for the side drains will be adjusted to force water to flow backwards (towards

    Km 0+000).

    Dual carriageway geometric layout; including all frontage business service accesses

    Like option 1, option 2 also provides that 3.25m wide lanes are used with 1.2m wide

    central raised island (0.2m above the adjacent finished road levels), service roads atselected locations on the right hand side (in front of the market area) and 3.25m wide lay-

    bys, 50m long, on the left hand side at selected locations, where significant vehicle parking

    traffic is anticipated. 1.5 m wide raised sidewalks are also proposed on both the LHS and

    RHS with accesses to main business premises.

    The Recommended Dual Design Option

    Bearing in mind that the underlying reason for the proposed dualling of this first 1.3km of

    Gayaza road (through the Kalerwe market area) is the severe traffic congestion at this

    location and keeping in mind that draining surface water backwards against the general

    longitudinal slope of the road may present undesirably deep side drains, it is the

    Consultants opinion that option 1, described in section 4.1 above be adopted and carried to

    the detailed engineering design stage.

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    4/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    4

    1.0 Introduction

    1.1 Project Background

    The upgrading works of Kampala-Gayaza-Zirobwe road commenced on 31 March

    2008 under World Bank funding. However, while the proposed upgrading workswill go a long way in improving traffic movement in the north of Kampala, serious

    concerns have persisted relating the chronic traffic congestion on the first 1.3km of

    this road (i.e. between the Gayaza/Mulago/Bombo road roundabout and the Gayaza

    road/Kampala Northern Bypass Roundabout. The traffic flow constriction on this

    section of the road has frequently been attributed to the several side road accesses

    to Gayaza road which are commonly used as bypasses by commuter taxi drivers;

    resulting into traffic flow constrictions at several locations along this road stretch,

    as well as the availability of 2 road side markets in this area with all the trucks

    offloading their goods by the road side and causing further traffic flow constraints.

    In addition, the rampant poor driver behaviour in this country may also have asignificant compounding effect of this traffic flow problem.

    It is therefore perfectly understandable that with the eminent opening of the

    Kampala Northern Bypass to public traffic and the likely increase in the traffic

    levels on the northern part of the City, more traffic flow problems are envisaged

    and therefore the need for a major intervention to alleviate this problem is certainly

    timely and justified.

    It is on the background of the above that by letter ref. xxxxxx, dated xxxxx, the

    Client requested Norconsult to submit a proposal for the dual design of the first

    1.3km of Gayaza road.

    Having accepted the Consultants proposal for the dual design, by letter ref.

    xxxxxx, dated xxxxxx, Norconsult was instructed to commence the dual design

    services pending formal signature of the relevant Addendum no. xxxxx still under

    preparation.

    1.2 Key Project Milestones

    Milestone Date

    Submission of the proposal for the proposed dual design xxxxxxxUNRAs instruction to commence the dual design xxxxxxx

    Scheduled date of submission of the draft options report xxxxxxx

    Scheduled date of receipt of the Clients comments on

    the draft options report

    xxxxxxx

    Scheduled date for submission of the final options report xxxxxxx

    Scheduled date for submission of the drat final design

    report

    xxxxxxx

    Scheduled date for submission of the final design report xxxxxxx

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    5/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    5

    2.0 Activities executed by the Consultant to date

    2.1 Identification, survey and mapping of all existing roads accessing theproposed dual carriageway section.

    Bearing in mind that traffic flow along the proposed dual carriagewaysection is significantly affected by side roads access traffic, the consultant

    has already captured all existing motorable side road accesses to the

    proposed dual carriageway section. These accesses are indicated on the Plan

    and Profile drawings in the appendices.

    2.2 Review of the existing traffic data.

    Through the Client, the Consultant had previously obtained traffic survey

    data from the 2007 traffic counts on the National Road Network project.

    The 12hr manual classified traffic count data was taken over a period of

    6days (7am to 6pm), commencing on Friday, 9th March 2007 and ending onWednesday, 14

    thMarch, 2007. A night expansion factor of 1.2 (evident

    from the data collected from the Client) was used to convert the 12hr traffic

    counts into Average Daily Traffic (ADT) values. The review and analysis of

    the data involved the following:

    Analysis of the hourly motorised 6-day total traffic flows in bothdirections (see Template 1 & 2)

    Analysis of the weekday average hourly traffic flows for each trafficclass for each direction and for both directions (see Template 3)

    Weekend average hourly traffic flows for each traffic class in bothdirections (see Template 4)

    Determination of the 6-day average daily traffic flows in PCUs for eachtraffic class and for each direction (see Template 5)

    Analysis of the peak hour traffic flows (see Template 6).

    From templates 1 & 2 below, it is clear that there are two traffic peak flow

    periods everyday; with the morning traffic peaking at around 8am and the

    evening traffic peaking after 6pm. The exact peak flow time for the evening

    traffic could not be established from the available traffic data as the traffic

    counts were conducted up to 6pm. However, observations by the consultant

    have suggested that the evening peaking hour occurs at about 8pm. The twotraffic flow peaking periods correspond with the periods when the majority

    of the working people are going for work in the morning and when they arereturning home from work in the evening.

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    6/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    6

    Template 1: Hourly motorised 6-day total traffic flows in both directions

    Time 7 8 9 10 11 12 13 14 15 16 17 18 Total

    Hourly 6-

    day totals

    (Motorized)

    8597 9661 8258 7296 7204 6782 6964 5834 5453 6885 7559 8126 88619

    Equivalent

    %age9.7% 10.9% 9.3% 8.2% 8.1% 7.7% 7.9% 6.6% 6.2% 7.8% 8.5% 9.2% 100%

    Template 2: 6-day average hourly motorised traffic variation

    Variation of Combined Motorised Traffic with Time of

    the Day

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    0 5 10 15 20

    Time of the Day

    CombinedMotorisedTraffic

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    7/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    7

    From template 3 below, its also apparent that different vehicle categories have different

    peaking periods during weekdays; with the passenger vehicles (saloon cars, taxis, minibuses

    matatus and motorcycles) peaking from 8 to 9am; during which most of the people employed

    in the informal sectors such as markets, shops, etc are going for work. On the other hand, the

    peaking period for the goods vehicles such as the light, medium, large and articulated trucks

    is between 11am and 2pm; corresponding to the period when most the goods are beingdelivered to the various business outfits around Kalerwe area.

    Template 3: Weekday average hourly traffic flows for each traffic class for each

    direction and for both directionsHour (Starting at:) 7 8 9 10 11 12 13 14 15 16 17 18 TOTAL

    DIRECTION A: ToGayazaMotorised

    SALOON CARS andTAXIS 48 77 121 81 91 118 129 125 129 130 180 194 1420LIGHT GOODS VANS,

    PICKUP and 4WD 36 51 94 69 76 90 92 88 104 92 104 112 1007Small Bus: MINIBUSESand MATATUS 188 207 193 147 153 126 179 104 135 151 182 203 1968Medium Bus: COASTERS 3 2 1 1 2 4 2 2 2 1 4 3 26BUSES 0 1 0 1 0 0 1 2 3 1 1 1 9Light Single Unit Truck:DYNAS and TRACTORs 7 7 11 14 18 15 22 11 14 12 15 19 164Medium-Single UnitTrucks:- 7 4 11 10 10 13 14 7 11 11 11 9 115Large -Single Unit Trucks:-Lories, Fusos 3 4 7 8 7 9 9 3 6 5 6 5 72TRUCK TRAILER ANDSEMI TRAILER 0 0 1 1 1 3 2 0 1 1 1 1 11MOTORCYCLES 307 416 270 235 207 211 233 121 122 191 225 266 2805

    Total 599 769 708 567 565 588 682 462 525 593 728 812 7596

    Non-motorised

    BICYCLES 303 385 295 179 174 151 122 118 128 161 259 300 2572CARTS 3 5 3 5 2 3 3 2 3 2 3 5 39

    Total 305 390 298 183 177 154 125 120 130 163 262 305 2611

    DIRECTION B: ToKampalaMotorised

    SALOON CARS andTAXIS 256 211 154 131 113 114 98 103 79 112 120 103 1592LIGHT GOODS VANS,

    PICKUP and 4WD 107 125 94 79 93 83 74 71 60 94 81 71 1029Small Bus: MINIBUSESand MATATUS 253 265 180 155 132 111 131 89 107 139 178 205 1945Medium Bus: COASTERS 6 9 2 1 1 0 0 2 0 1 2 0 22BUSES 0 1 0 0 0 1 0 0 0 0 0 1 3Light Single Unit Truck:DYNAS and Tractors 14 17 17 13 11 13 15 8 7 5 6 6 131Medium-Single UnitTrucks:- 10 10 10 10 10 7 9 9 12 6 6 8 104Large -Single Unit Trucks:-Lories, Fusos 4 10 7 6 10 8 4 6 6 5 2 4 72TRUCK TRAILER ANDSEMI TRAILER 0 2 1 2 2 3 2 0 2 1 1 1 16MOTORCYCLES 405 353 201 164 186 142 120 117 105 141 148 195 2277

    Total 1055 1002 664 559 556 481 453 405 377 503 542 593 7190

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    8/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    8

    Non-motorised

    BICYCLES 441 286 134 133 121 95 65 60 73 139 139 178 1863CARTS 12 12 4 1 1 0 0 0 0 1 1 1 32

    Total 453 298 138 134 122 95 66 60 73 140 140 179 1895

    BOTH DIRECTIONS(A+B)

    TypeMotorised excl. M-bikes 941 1003 901 727 728 717 781 628 675 763 897 944 9704Motorised incl. M-bikes 1654 1772 1372 1126 1121 1069 1135 866 902 1096 1270 1406 14786Non-motorised 758 688 435 317 298 249 190 180 203 303 402 484 4506

    During weekends, template 4 suggests that although there are generally two peaking traffic

    flow periods (during the morning and the evening periods), peaking periods for the

    passenger traffic during weekends shifts from 8am (during weekdays) to 9am during the

    weekend. Again this is no surprise since most people are more relaxed about travelling to

    work on weekends than during weekdays. Another important observation is that the traffic

    flow for the weekend is lower than that for the weekday for the minibuses, matatus,

    medium buses, large buses, heavy trucks, truck trailers and motorcycles; with the weekdaytraffic for medium buses being as high as 74% more than for the weekend traffic and even

    higher (192% more) for the truck trailers and semi trailers.

    However, an important trend to note is that the hourly traffic flow variation over weekdays

    is a lot more pronounced than during the weekend.

    Template 4: Weekend average hourly traffic flows for each traffic class in both

    directions

    Hour (Startingat:) 7

    am

    8

    am

    9

    am

    10am

    11am

    12pm

    1

    pm

    2

    pm

    3

    pm

    4

    pm

    5

    pm

    6

    pm

    TO

    TAL

    BOTHDIRECTIONS(A+B)

    Motorised

    SALOON CARSand TAXIS 123 246 368 348 356 329 343 340 269 363 363 350 3796LIGHT GOODSVANS, PICKUPand 4WD 68 141 193 199 189 179 207 186 169 206 213 198 2146Small Bus:

    MINIBUSES andMATATUS 339 538 437 386 175 247 420 80 279 224 248 368 3741Medium Bus:COASTERS 1.5 2.5 5.5 4 0.5 2 3.5 0.5 1.5 0.5 3 2.5 27.5BUSES 0 0 0 0 1 0 1 1.5 1.5 2.5 0.5 0.5 8.5Light Single UnitTruck: DYNAS andTRACTORs 20.5 24 24 29.5 27 31 22 25.5 23.5 32 29 20.5 308.5Medium-SingleUnit Trucks:- 15 26 18.5 19 30.5 24.5 14 15 12 16.5 17.5 14.5 223Large -Single UnitTrucks:- Lories,Fusos 6 6 10 12.5 19 14.5 9.5 6.5 7 6.5 7 2.5 107

    TRUCK TRAILERAND SEMI 1 1 0 0.5 0 1.5 0.5 1 0.5 0.5 1.5 1 9

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    9/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    9

    TRAILERMOTORCYCLES 418 515 392 401 357 343 297 277 225 315 272 261 4071

    Total 992 1499 1447 1399 1155 1172 1317 932 987 1166 1154 1219 14436

    Non-motorised

    BICYCLES 373 443 345 327 241 190 188 207 224 260 249 320 3365

    CARTS 3 12 9 5.5 2.5 4.5 4 0.5 1 2.5 8.5 0.5 53.5Total 376 455 354 333 244 194 192 208 225 262 258 321 3418

    Further analysis of the traffic flow data has been conducted by converting the 12hr. count

    traffic into the equivalent passenger car units (PCUs) using PCU factors proposed in the

    Kenya Road Design Manual, Part 1 published in 1979. The 12hr PCU values for each

    traffic class were expanded into 24hr. PCU values using the Clients accepted 1.2 night

    expansion factor. The resulting equivalent PCU values per traffic category are given in

    template 5 below; indicating that the total PCUs per day has been estimated at 20,473 for

    the year 2007.

    Having assumed that the traffic growth rate would remain constant at about 2.8% per yearover the next 10 years after opening the road to traffic (i.e. up to the design year), andassuming that the 2007 traffic would be maintained throughout the construction period up

    to 2010 when the road is expected to be commissioned after construction, the 2007 PCU

    values, have been used to estimate the design year (2020) traffic (projected at 26,205

    PCUs) using relationship given below.

    DT =Tc + Tc x (r) x n

    Where DT =Design year traffic in PCUs

    Tc = 2007 traffic in PCUs.

    r = Average traffic growth rate per year estimated at 2.8%

    n = 10 years (i.e. the time to elapse from the scheduled year of completion of works to the

    design year)

    It is therefore evident that based on the 2007 traffic count data availed to the Consultant

    and the recommendations of the Uganda Road Design Manual of July, 2004, which inter

    alia states The level-of-service standards for Category A and B roads in flat terrain can

    only be met by building a dual carriageway road once the design year volume exceeds

    about 13000 pcu/day, it technically justifiable that the first 1.3km of Gayaza road be

    upgraded to dual carriageway standard.

    Template 6 gives a detailed analysis of the peak hour traffic flows for each traffic class.

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    10/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    10

    Template 5: Determination of the 6-day average daily traffic flows in PCUs for

    each traffic class and for each directionDIRECTION A

    Vehicle No. per day

    PCU

    Factors

    PCUs per

    day

    PCUs per day &

    NightSALOON CARS and TAXIS 1579 1 1579 1894.4LIGHT GOODS VANS, PICKUP and4WD 1035 1 1035 1242.2

    Small Bus: MINIBUSES and MATATUS 1987 1 1987 2384.4

    Medium Bus: COASTERS 23 2 45 54

    BUSES 8 2 17 20Light Single Unit Truck: DYNAS andTractors 164 2.5 409 491

    Medium-Single Unit Trucks:- 120 2.5 300 360Large -Single Unit Trucks:- Lories,Fusos 70 2.5 174 208.5

    TRUCK TRAILER AND SEMI TRAILER 8 3.5 29 34.3

    MOTORCYCLES 2618 1 2618 3142

    BICYCLES 2422 0.5 1211 1453.3

    Total 10034 9403 11284

    DIRECTION B

    Vehicle No. per dayPCUFactors

    PCUs perday

    PCUs per day &Night

    SALOON CARS and TAXIS 1695 1 1695 2034LIGHT GOODS VANS, PICKUP and4WD 1037 1 1037 1244

    Small Bus: MINIBUSES and MATATUS 1969 1 1969 2363Medium Bus: COASTERS 19 2 37 44

    BUSES 3 2 6 7Light Single Unit Truck: DYNAS andTractors 136 2.5 339 407

    Medium-Single Unit Trucks:- 101 2.5 251 302Large -Single Unit Trucks:- Lories,Fusos 62 2.5 155 186

    TRUCK TRAILER AND SEMI TRAILER 12 3.5 43 52

    MOTORCYCLES 2126 1 2126 2551

    BICYCLES 1656 0.5 828 994

    Total 8815 7658 9189

    Total PCUs per day in both directions 20,473

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    11/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    11

    Template 6: Analysis of the peak hour traffic flowsHour (Startingat:) 7 8 9 10 11 12 13 14 15 16 17 18 AVERAGE

    DIRECTIONA+B

    Motorised

    SALOON CARSand TAXIS 214 267 321 280 280 280 285 284 238 302 331 324 284LIGHT GOODSVANS, PICKUPand 4WD 105 158 190 173 179 176 186 173 166 196 199 190 174Small Bus:MINIBUSES andMATATUS 390 505 405 344 230 242 365 136 261 257 304 388 319Medium Bus:COASTERS 5 7 4 3 2 3 3 2 2 1 4 3 3

    BUSES 0 1 0 0 1 1 1 2 2 2 1 1 1Light Single UnitTruck: DYNAS andTRACTORs 21 24 26 28 28 30 29 22 22 25 25 23 25Medium-SingleUnit Trucks:- 16 20 19 19 25 22 18 15 17 16 17 16 18Large -SingleUnit Trucks:-Lories, Fusos 7 10 12 13 18 16 11 8 10 8 8 6 10TRUCKTRAILER ANDSEMI TRAILER 1 2 1 2 2 4 2 1 2 1 2 1 1MOTORCYCLES 565 642 431 400 375 348 325 257 226 324 322 361 381

    Total 1323 1635 1409 1262 1138 1120 1226 899 944 1131 1212 1312 1218

    Non-motorised

    BICYCLES 558 557 387 319 268 217 188 192 212 280 323 399 325CARTS 9 15 8 6 3 4 3 1 2 2 6 3 5

    Total 567 572 394 325 271 221 191 194 214 282 330 402 330

    Vehicle Category

    PeakHrlytraffic(A)

    Avg DailyPerCategory(B) (A/B)*100

    SALOON CARS and TAXIS 331 284 117

    LIGHT GOODS VANS, PICKUP and 4WD 199 174 114Small Bus: MINIBUSES and MATATUS 505 319 158

    Medium Bus: COASTERS 7 3 223

    BUSES 2 1 229

    Light Single Unit Truck: DYNAS and Tractors 30 25 119

    Medium-Single Unit Trucks:- 25 18 136

    Large -Single Unit Trucks:- Lories, Fusos 18 10 172

    TRUCK TRAILER AND SEMI TRAILER 4 1 272

    MOTORCYCLES 642 381 168

    BICYCLES 558 325 172

    CARTS 15 5 289

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    12/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    12

    2.3 Study of the current traffic flow patterns and vehicle parking characteristicsand development of traffic flow management options.

    As noted in Section 1, the observed traffic flow congestion on the proposed

    dual carriageway section has been attributed to the several side road

    accesses to Gayaza road which are commonly used as bypasses bycommuter taxi drivers; resulting into traffic flow constrictions at several

    locations along this road stretch, as well as the availability of 2 road side

    markets in this area with all the trucks offloading their goods by the road

    side and causing further traffic flow constraints.

    Under this task therefore, the Consultant organised a 2-day, 16hr. traffic

    flow study (16th

    & 17th

    , September 2009) at 6 different locations along the

    proposed dual carriageway section. The table 2.1 below gives the locations

    of the traffic surveys and nature of the data collected. The detailed analysis

    of the traffic survey data obtained is presented in template 7 below.

    Table 2.1: Details of the current traffic flow patterns investigated

    SNo. Location (Ch) Key parameter

    surveyed

    Details of data

    collected

    1 0+310 RHS Traffic flow to &

    from access road

    Manual classified

    junction traffic flows

    2 0+625 RHS Traffic flow to &

    from access road

    Manual classified

    junction traffic flows

    3 0+635 LHS Traffic flow to &

    from access road

    Manual classified

    junction traffic flows

    4 0+757 RHS Traffic flow to &from access road Manual classifiedjunction traffic flows

    5 0+800 Traffic flows along

    Gayaza Road

    Manual Classified

    traffic flows through

    the Kalerwe area.

    6 1+137 RHS Traffic flow to &

    from access road

    Manual classified

    junction traffic flows

    To assess the vehicle parking requirements, roadside parking surveys were

    also conducted concurrently with the above traffic surveys. These surveys

    covered a section from Mawanda Road (Ch 0+757) to Ch. 1+200 and were

    aimed at collecting vehicle parking data such as vehicle type, duration ofparking, purpose of parking as well as the perceived adequacy/inadequacy

    of the parking (i.e. in the opinion of the parking surveyor, has the driver

    parked properly or not).

    Analysis of the roadside parking survey data obtained indicates that while

    commuter taxis constituted the biggest component of the parking vehicles

    (41.9%), the average parking duration for the taxi commuters (matatus) was

    only 11minutes compared with the 58minutes of parking for trucks (which

    constitute only 12.3% of the parking traffic. Private cars, pajeros and

    pickups also posted significant parking durations ranging from 19minutes to

    24minutes. Again this data seems consistent with the logic that trucks spenda comparably longer duration offloading agricultural produce and other

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    13/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    13

    merchandise than commuter taxis (matatus), which only stop for

    considerably shorter durations to pick up and drop off passengers.

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    14/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    Template 7: Analysis of the current access roads traffic survey data

    Traffic to access road at 0+635LHS

    Time

    6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    SALOON CARS and TAXIS 4 22 21 20 16 12 14 12 14

    LIGHT GOODS VANS, PICKUP and 4WD 8 15 25 24 24 26 26 17 21

    Small Bus: MINIBUSES and MATATUS 1 4 3 4 3 6 3 2 3

    Medium Bus: COASTERS 0 1 1 0 0 0 1 1 0

    BUSES 0 0 0 0 0 0 0 0 0

    Light Single Unit Truck: DYNAS and Tractors 2 4 9 3 5 3 2 1 3 Medium to Large -Single Unit Trucks:- Lories,Fusos 1 2 3 4 3 4 3 3 4

    TRUCK TRAILER AND SEMI TRAILER 0 0 0 0 0 0 0 0 0

    MOTORCYCLES 27 86 91 71 67 48 74 56 70

    BICYCLES 2 30 30 27 21 18 26 17 25

    CARTS 0 2 5 4 3 1 0 1 1

    Total 44 164 187 155 141 117 147 107 138

    Traffic from access road at 0+635LHS

    Time 6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    SALOON CARS and TAXIS 6 41 34 12 13 15 19 14 17 17

    LIGHT GOODS VANS, PICKUP and 4WD 11 48 36 22 18 26 30 22 31 29

    Small Bus: MINIBUSES and MATATUS 4 9 7 3 6 4 2 4 11 3

    Medium Bus: COASTERS 1 2 2 0 0 1 1 1 0 1

    BUSES 0 1 0 0 0 0 0 0 0 0

    Light Single Unit Truck: DYNAS and Tractors 4 4 5 5 5 6 4 5 3 3

    Large -Single Unit Trucks:- Lories, Fusos 2 4 5 4 4 6 5 4 1 4

    TRUCK TRAILER AND SEMI TRAILER 0 0 1 0 0 0 0 0 0 0

    MOTORCYCLES 32 103 86 72 54 60 73 52 64 59

    BICYCLES 7 15 22 14 17 12 18 7 15 17

    CARTS 0 1 1 7 2 1 1 0 1 1

    Total 65 226 197 137 118 129 151 108 141 133 1

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    15/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    Traffic to access road at 0+310RHS

    Time

    7-8am

    8-9am

    9-10am

    10-11am

    11-12am

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    16-17pm

    17-18pm

    18-19pm

    SALOON CARS and TAXIS 1 2 7 8 4 7 9 6 4 9 11 5

    LIGHT GOODS VANS, PICKUP and 4WD 2 4 4 5 7 9 8 4 7 8 8 8

    Small Bus: MINIBUSES and MATATUS 0 1 1 2 2 2 1 1 2 1 1 3

    Medium Bus: COASTERS 0 1 0 1 0 0 1 0 0 0 0 0

    BUSES 0 0 0 0 0 0 0 0 0 0 0 0

    Light Single Unit Truck: DYNAS and Tractors 0 0 1 1 0 0 1 1 1 0 0 1

    Medium-Single Unit Trucks:- 1 7 1 0 1 1 0 1 1 1 0 1

    Large -Single Unit Trucks:- Lories, Fusos 0 1 0 0 0 0 0 2 0 0 0 0

    TRUCK TRAILER AND SEMI TRAILER 5 6 21 16 14 15 9 13 11 9 9 15

    MOTORCYCLES 8 8 6 6 3 6 8 8 7 6 6 4

    BICYCLES 1 2 3 2 4 2 3 1 2 6 1 2

    CARTS 0 0 0 0 0 1 0 0 0 0 1 0

    Total 17 30 43 40 34 41 37 35 32 39 35 38

    Traffic from access road at 0+310RHS

    Time

    7-8am

    8-9am

    9-10am

    10-11am

    11-12am

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    16-17pm

    17-18pm

    18-19pm

    SALOON CARS and TAXIS 5 11 9 6 6 5 6 3 10 9 7 10

    LIGHT GOODS VANS, PICKUP and 4WD 7 7 1 5 7 3 6 6 5 7 3 9

    Small Bus: MINIBUSES and MATATUS 2 1 1 3 1 1 1 1 2 1 1 3

    Medium Bus: COASTERS 0 0 0 0 0 0 1 0 0 0 0 0

    BUSES 0 0 0 0 0 0 0 0 0 0 0 0

    Light Single Unit Truck: DYNAS and Tractors 0 0 1 0 0 1 0 0 0 0 0 0

    Medium-Single Unit Trucks:- 0 0 0 0 0 1 1 0 1 0 0 0 Large -Single Unit Trucks:- Lories, Fusos 0 0 1 0 1 1 1 0 1 1 0 0

    TRUCK TRAILER AND SEMI TRAILER 0 0 0 0 0 0 0 0 0 0 0 0

    MOTORCYCLES 8 8 6 6 3 6 8 8 7 6 6 4

    BICYCLES 1 7 3 0 1 1 1 0 2

    CARTS 1 0 1 0 0 0 0 0 0

    Total 23 32 20 19 17 17 22 18 26 23 16 25

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    16/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    Traffic to access road at 0+625RHS

    Time

    6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    16-17pm

    17-18pm

    18-19pm

    SALOON CARS and TAXIS 3 13 11 8 14 5 7 7 10 7 5 14 18

    LIGHT GOODS VANS, PICKUP and 4WD 1 2 8 7 7 9 2 5 6 9 6 8 12

    Small Bus: MINIBUSES and MATATUS 2 5 4 1 1 1 0 1 1 1 1 0 2

    Medium Bus: COASTERS 0 0 1 0 0 0 0 0 0 1 0 0 0

    BUSES 0 0 1 0 0 0 0 0 0 0 0 0 0 Light Single Unit Truck: DYNAS andTractors 0 0 1 1 2 0 1 9 2 0 0 2 2

    Large -Single Unit Trucks:- Lories, Fusos 1 1 1 1 1 2 1 0 0 1 0 1 1

    TRUCK TRAILER AND SEMI TRAILER 0 0 0 1 0 1 1 1 0 0 0 0 0

    MOTORCYCLES 18 38 41 41 26 29 26 27 25 26 29 43 36

    BICYCLES 4 8 15 14 6 7 4 3 4 8 4 7 4

    CARTS 0 4 10 3 1 1 0 0 1 0 0 0 0

    Total 28 69 90 75 57 54 41 52 48 52 44 73 74

    Traffic from access road at 0+625RHS

    Time

    6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    16-17pm

    17-18pm

    18-19pm

    SALOON CARS and TAXIS 3 10 12 13 7 10 9 6 7 8 10 17 22

    LIGHT GOODS VANS, PICKUP and 4WD 1 6 8 7 4 7 4 6 7 7 7 14 15

    Small Bus: MINIBUSES and MATATUS 1 1 1 0 1 1 2 0 2 1 0 10 45

    Medium Bus: COASTERS 0 1 0 1 0 0 0 0 0 0 0 0 1

    BUSES 0 0 0 0 0 0 0 0 0 0 0 0 1 Light Single Unit Truck: DYNAS andTractors 1 1 1 1 1 2 1 2 1 1 0 1 3

    Large -Single Unit Trucks:- Lories, Fusos 1 0 1 1 1 1 0 0 1 0 0 0 0

    TRUCK TRAILER AND SEMI TRAILER 0 0 0 0 0 0 0 0 0 0 1 0 0

    MOTORCYCLES 10 14 10 13 17 13 16 17 10 11 12 12 18

    BICYCLES 3 1 2 2 2 4 1 2 4 1 2 1 2

    CARTS 0 0 0 0 0 0 0 0 0 0 0 0 0

    Total 18 32 33 36 32 37 33 32 29 27 30 53 104

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    17/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    Traffic to access road at 0+757RHS (Mawanda Road)

    Time

    6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    SALOON CARS and TAXIS 56 36 55 36 34 37 35 30 37 13

    LIGHT GOODS VANS, PICKUP and 4WD 34 23 37 30 44 38 40 33 34 23

    Small Bus: MINIBUSES and MATATUS 12 0 2 2 1 13 5 8 14 4

    Medium Bus: COASTERS 1 1 0 1 1 1 0 1 1 0

    BUSES 0 0 0 0 0 0 3 0 0 0

    Light Single Unit Truck: DYNAS and Tractors 9 4 9 7 10 11 10 7 10 6

    Large -Single Unit Trucks:- Lories, Fusos 2 2 11 2 13 5 11 10 15 4

    TRUCK TRAILER AND SEMI TRAILER 1 8 0 2 7 2 3 1 0 0

    MOTORCYCLES 71 47 86 46 80 42 64 51 37 26

    BICYCLES 21 7 10 5 12 10 1 12 7 1

    CARTS 0 5 2 1 0 0 0 0 0 0

    Total 205 131 211 130 199 155 170 151 154 74

    Traffic from access road at 0+757RHS (Mawanda Road)

    Time

    6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    1 6 1 7

    SALOON CARS and TAXIS 114 148 146 50 51 57 92 72 56 44 10

    LIGHT GOODS VANS, PICKUP and 4WD 25 9 10 5 10 33 33 33 5 5 4

    Small Bus: MINIBUSES and MATATUS 78 41 46 6 1 14 9 3 2 0 4

    Medium Bus: COASTERS 3 0 0 1 0 0 0 0 0 0

    BUSES 1 0 0 0 0 0 1 2 0 0

    Light Single Unit Truck: DYNAS and Tractors 4 5 2 9 10 24 27 9 13 6 1

    Large -Single Unit Trucks:- Lories, Fusos 9 4 4 6 6 4 30 8 2 5 TRUCK TRAILER AND SEMI TRAILER 0 0 3 0 0 0 1 0 2 4

    MOTORCYCLES 40 26 31 26 46 52 139 67 24 37 9

    BICYCLES 8 1 2 0 0 11 3 2 0 0

    CARTS 1 2 0 0 0 0 0 0 0 0

    Total 281 236 243 101 123 195 333 194 102 100 30

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    18/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    Traffic to access road at 1+137RHS (Through market)

    Time

    6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    16-17pm

    17-18pm

    SALOON CARS and TAXIS 0 0 0 0 0 1 0 1 0 0 0 1

    LIGHT GOODS VANS, PICKUP and 4WD 0 0 0 0 0 0 1 1 0 0 1 1

    Small Bus: MINIBUSES and MATATUS 0 0 0 0 0 0 0 0 0 0 0 0

    Medium Bus: COASTERS 0 0 0 0 0 0 0 0 0 0 0 0

    BUSES 0 0 0 0 0 0 0 0 0 0 0 0

    Light Single Unit Truck: DYNAS and Tractors 0 0 1 0 0 0 0 0 0 0 0 0

    Large -Single Unit Trucks:- Lories, Fusos 0 0 0 0 0 0 0 1 0 0 0 1

    TRUCK TRAILER AND SEMI TRAILER 0 0 0 0 0 0 0 0 0 0 0 0

    MOTORCYCLES 28 35 32 19 25 18 11 8 7 9 14 15

    BICYCLES 25 19 24 21 19 15 13 10 7 7 9 12

    CARTS 21 34 32 17 13 10 1 3 1 3 2 4

    Total 74 87 88 57 56 44 26 23 15 19 26 33

    Traffic to access road at 1+137RHS (Through market)

    Time

    6-7am

    7-8am

    8-9am

    9-10am

    10-11am

    11-12pm

    12-13pm

    13-14pm

    14-15pm

    15-16pm

    16-17pm

    17-18pm

    SALOON CARS and TAXIS 0 0 0 0 0 1 1 2 2 1 4 24

    LIGHT GOODS VANS, PICKUP and 4WD 1 0 0 0 3 0 0 1 2 1 3 14

    Small Bus: MINIBUSES and MATATUS 1 0 0 0 0 0 0 0 0 1 3 8

    Medium Bus: COASTERS 0 0 0 0 0 0 0 0 0 0 0 1

    BUSES 0 0 0 0 0 0 0 0 0 0 0 0

    Light Single Unit Truck: DYNAS and TRACTORs 1 0 1 0 0 0 0 0 0 0 0 1

    Large -Single Unit Trucks:- Lories, Fusos 0 1 0 0 0 0 0 0 1 0 1 1 TRUCK TRAILER AND SEMI TRAILER 0 0 0 0 0 0 0 0 0 0 0 0

    MOTORCYCLES 17 30 40 22 19 12 19 10 4 8 10 21

    BICYCLES 18 22 26 18 24 19 7 8 3 4 5 11

    CARTS 21 23 22 11 8 3 1 0 1 0 2 3

    Total 57 75 88 51 53 35 26 20 12 14 26 81

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    19/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    19

    Template 8: Analysis of the roadside parking survey data

    Vehiclecategory

    No. documented insurvey

    %age of totalAverage duration of

    parking (min)

    Taxis 246 41.9 11

    Cars 205 34.9 19

    Trucks 72 12.3 58Pickups 52 8.9 24

    Pajero 9 1.5 22

    Mini Buses 3 0.5 17

    Total 587 100

    2.4 Identification, survey and mapping of existing road drainage facilities

    The proposed dual carriageway section of Gayaza road being in a low-lying flat

    area, surface water drainage is likely to be a major design problem. In order toassess the existing surface drainage facilities, the consultant has identified,

    surveyed and mapped all existing road drainage facilities along the proposed dual

    carriageway section. The details captured at this stage include the following:

    The location of all drainage channels crossing the existing road (in terms oftheir X, Y and Z coordinates)

    The existing cross drainage culverts, including their location, sizes, condition,inlet and outlet invert levels as well as invert levels of the immediate inlet and

    outlet channels draining into and out of the culverts respectively.

    Location, type and condition of the existing side drainage channels along theexisting road; including their invert levels.

    This information has been included on drawings in appendix 1. Notable from

    information obtained from this activity is the following:

    The existing side drains clearly fall within the limits of the proposed dualcarriageway pavement and will inevitably have to be shifted outwards.

    Given the flat low-lying terrain of the proposed dual carriageway section, itsvirtually impossible to drain most of the surface water into the main drainage

    channel near Ch 1+300. It may therefore be preferable to drain most of the

    surface water into the identified 8 no. intermediate drainage channels identifiedalong this section.

    Most of the existing cross drainage culverts are 900mm dia size culverts in asilted condition and therefore it is likely that these will need replacement

    2.5 Identification, survey and mapping of all building structures and visible/overheadutility services within and adjacent to 15m from the existing road centreline.

    Item 6(c) of the Clients letter of request for proposal requires that the dual

    carriageway options to be proposed by the Consultant should fit within the 30m

    corridor currently being expropriated. In view of this, under this task, the

    Consultant has pickup the locations (x and y coordinates) of all building structuresas well as visible/overhead utility services within the 30m corridor (i.e. 15 m on

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    20/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    20

    either side of the existing road centerline). Results from this activity indicate no

    major building structures shall be affected by the proposed dual carriageway works.

    However, from the drawings of the existing buildings (refer to the appendices),

    some minor roadside temporary shop buildings are affected between the access

    road to the Kampala Northern Bypass foot bridge (approx Ch 1+000 LHS) and Ch

    1+137 (access road into Kalerwe Market on RHS). Another minor building is also

    affected at Ch 1+175 RHS.

    2.6 Liaison with utility companies and identification of all underground utility serviceslikely to be affected by the proposed works.

    In addition to the visible/overhead utility services identified and mapped above, the

    Consultant has to date held meetings with NWSC (existing services identified and

    included on the existing services drawings), UTL (existing services identified and

    included on the existing services drawings), UMEME (existing services identified

    and included on the existing services drawings). Zain and MTN did confirm their

    services were not affected by the proposed works. The Identified existing servicesare also indicated on the drawings in appendix 1. This information shall also be

    used later in determining the space requirements for the relocation of these

    services.

    3.0 Analysis of the feasible options

    3.1 Traffic Flow Options

    3.1.1 Options for traffic flow from / to all access roads connecting to theproposed dual carriageway section.

    From the traffic survey results in section 2.3, it is evident that the various side road

    accesses to the proposed Gayaza road dual carriageway section are mainly used as

    bypasses during peak hour flow traffic congestion periods by especially saloon

    cars, taxis, light goods vans, pickups, 4WD vehicles and Minibuses/Matatus. This

    is evident from the access roads traffic survey data presented in section 2.3;

    indicating a significant increase in the above traffic flows into access roads near the

    sections where the traffic congestion usually starts in the evening (approx 300

    400m from the Roundabout at Ch 0+000) and an equally significant increase in the

    traffic flows from the access roads towards the end of the proposed dual

    carriageway section (presumably where the traffic flow congestion is considered to

    be easing). To streamline the traffic flow along the proposed dual carriageway, it istherefore essential that either very limited (for only a major access like Mawanda

    road Ch 0+757 RHS) or absolutely no right turns should be permitted for traffic

    joining the proposed dual carriageway. In view of this, the proposed traffic flow

    options for traffic moving onto, along and off the proposed dual carriageway is as

    indicated on drawings in appendices 2 and 3.

    3.1.2 Options for traffic accessing the various frontage businesses and markets

    Having analysed the vehicle parking characteristics (section 2.3 of this report), the

    following is evident about the traffic congestion at the Kalerwe market area:

    There is no dedicated parking facilities (lay-bys) for the commutertaxis, around Kalerwe area yet many shoppers embark and

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    21/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    21

    disembark at this location. This has resulted into inappropriate

    parking habits by the commuter taxi drivers; resulting into

    obstruction of through traffic by the commuter taxis and more traffic

    congestion.

    There are no dedicated parking facilities (lay-bys) for the trucks

    delivering merchandise at the Kalerwe market area; resulting inlight, medium and heavy trucks parking by the roadside for extended

    long hours during offloading of agricultural produce and other

    merchandise. This further reduces on the available carriageway

    width for the through traffic and results in inevitable traffic

    congestion.

    The 2 no. markets at Kalerwe area attract a significant number ofpeople delivering fresh food stuffs to the market vendors and buyers

    of the food stuffs. Indeed a significant portion of the vehicles parked

    at Kalerwe area are private cars belonging to people buying things

    from the markets. This has also compounded the traffic flowproblem, resulting into serious traffic congestion at the Kalerwe

    market area.

    In view of the above observations, decongesting the traffic at the proposed dual

    carriageway section will inevitably involve provision of dedicated facilities for

    accessing the various frontage businesses and markets at Kalerwe and the following

    options have been considered:

    1. Provision of service roads at selected locations (as indicated on drawingsno. KG/PP/TD101, KG/PP/TD1-02, KG/PP/TD2-01 & KG/PP/TD2-02 in

    appendices 4 & 5), to provide access to markets or other frontage

    businesses (where adequate space is considered available). This option is

    considered to be suitable where it is considered necessary to remove parked

    trucks delivering merchandise, from the carriageway and increase the

    capacity of the road for the through traffic.

    2. Provision of lay-bys for parking of commuter taxis and other small cars.Details of these are also given on drawings no. KG/PP/TD101,

    KG/PP/TD1-02, KG/PP/TD2-01 & KG/PP/TD2-02 in appendices 4 & 5).

    3. Provision of access roads to the market area where deemed appropriate.Details of these are given on drawings no. KG/PP/TD101, KG/PP/TD1-

    02, KG/PP/TD2-01 & KG/PP/TD2-02 in appendices 4 & 5).

    3.1.3 Options for pedestrian sidewalks and crossings

    The proposed dual carriageway area has got a significant level of pedestrian traffic

    activity; being a heavily built up area. The Uganda Road Geometric Design Manual

    (2005), Section 7.15.2, recommends that raised, kerbed footways (sidewalks)

    should be provided in the larger built-up areas. Having carefully examined the

    existing situation along the proposed dual carriageway section, the locations

    proposed for the provision of the sidewalks is indicated on the typical cross

    sections in appendix 6.

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    22/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    22

    3.2 Drainage layout options

    3.2.1 Median drainage option

    Given that the proposed dual carriageway road is located in a low-lying area to the

    left of the Mulago/Kyebando hills, the major catchment area for the surface water

    anticipated onto the proposed dual carriageway is coming from the higher grounds

    on the RHS of the proposed dual carriageway. In view of this, it would be

    technically unwise to locate the surface water drainage channel in the median area

    as this would allow all the storm water onto the RHS carriageway, with its

    attendant problems of storm water becoming a nuisance to road users and possible

    undermining of the pavement structural integrity.

    Secondly, with a median drain, there would be no temporary refuge for pedestrians

    crossing the dual carriageway; increasing the risk of injury to pedestrians.

    In view of the above concerns, the option of the median drain has been ruled out ofconsideration.

    3.2.2 Side drainage option

    In view of the above observed short-comings of median drains, the preferred

    surface water drainage option is the side drains. Because of the flat low-lying

    nature of the terrain for the proposed dual carriageway and the urban nature of the

    proposed road section, the key principles to be considered in the design of these

    drains are as follows:

    There should be sufficient discharge points and culverts to ensure that the drainnever gets very deep

    In built-up/urban areas channel drains deeper than 250 mm should be coveredfor the safety and convenience of both pedestrians and vehicles

    The drains should terminate or discharge in a satisfactory manner without riskof causing erosion or other problems

    The drain should be capable of being cleaned and maintained easily.

    With the above considerations taken into account, the 2 considered surface water

    drainage system lay-outs are presented in appendices 2 & 3.

    3.3 Dual carriageway geometric layout options

    3.3.1 Typical cross section options

    A review of the design report by M/S Phoenix Engineering and Research Ltd

    clearly defines the proposed dual carriageway section as an urban road section,

    with a design speed of 50kph. Indeed the 2005 Ministry of Works, Housing and

    Communications Road Design Manual (Table 4-3) also specifies a design speed of

    50kph for urban and peri-urban dual carriageway roads; the recommended Right of

    Way from table 4-3 is 40m (i.e. more than the 30m corridor available for this

    project).

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    23/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    23

    In view of this severe land access problem and given the urban environment of the

    proposed dual carriageway section, recourse has been made to the July, 2004 Road

    Safety Revision of the Road Design Manual (prepared by TRL Ltd), section 4.3.2,

    cross section class T2, which, for a design speed of 50kph, allows for the lane

    widths to be reduced up to 3.0m each and the median island to be as narrow as

    1.2m. For the proposed dual carriageway however, the Consultant proposes lane

    widths of 3.25m each.

    The typical cross sections for the following scenarios are given in appendix 6:

    Scenario 1 Sidewalks on both LHS & RHS

    Scenario 2 Sidewalk on LHS & RHS plus service road to frontage

    businesses on LHS

    Scenario 3 Sidewalk on LHS & RHS plus service road to frontage

    Businesses on RHS

    Scenario 4 Section with lay-bys on LHS plus service road on RHSScenario 5 Section with lay-bys on RHS plus service road on LHS

    3.3.2 Access roads junction layout options

    Given the minor nature of most of the access roads junctions, it is considered that

    these junctions be designed as unchannelised T-intersections with the proposed

    dual carriageway traffic having the priority over the side road traffic, probably with

    the exception of the Mawanda road junction which may be suitable for part -

    channelisation

    4.0 Presentation of the best evaluated two dual design options

    4.1 Option 1

    4.1.1 Traffic flow onto and along the proposed dual carriageway section

    This option requires that no right turns are allowed for traffic joining the proposed

    dual carriageway section. Consequently, all motorised traffic joining the proposed

    dual carriageway would have to follow the general traffic flow direction of the

    proposed dual carriageway until the next roundabout where it would turn to join the

    intended carriageway. Drawings no. KG/PP/TD1-01 & KG/PP/TD1-02 illustrate

    this option.

    4.1.2 Surface water drainage layout

    This option requires that side drains generally drain surface water towards Gayaza

    side as the proposed dual carriageway vertical profile generally falls in that

    direction. However, as previously noted, the following additional considerations are

    also characteristic of this option:

    Sufficient discharge points and culverts are to be provided to ensure that thedrain never gets very deep

    Channel drains deeper than 250 mm shall be covered for the safety andconvenience of both pedestrians and vehicles

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    24/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    24

    The drains are to terminate or discharge in a satisfactory manner without therisk of causing erosion or other problems

    The drains should be capable of being cleaned and maintained easily.

    Drawings no. KG/PP/DR01-1 & KG/PP/DR1-02 present the general layout of the

    proposed drainage system.

    4.1.3 Dual carriageway geometric layout; including all frontage business serviceaccesses

    This option provides that 3.25m wide lanes are used with a 1.2m wide central

    raised island (0.2m above the adjacent finished road levels), service roads at

    selected locations on the right hand side (in front of the market area) and on the left

    hand side on the approaches to the Kalerwe market area. 1.5 m wide raised

    sidewalks are also proposed on both the LHS and RHS with accesses to main

    business premises. Typical drawings for this option are included in the appendices.

    4.2 Option 2

    4.2.1 Traffic flow onto and along the proposed dual carriageway section

    Option 2 provides that since Mawanda road is a major access road, traffic joining

    the proposed dual carriageway section from Mawanda road be allowed to make a

    right turn and the junction be designed as a partly Channelised T-intersection.

    Traffic from the rest of the access roads is prohibited from making any right turn.

    Drawings no. KG/PP/TD2-01& KG/PP/TD2-02 illustrate this option.

    4.2.2 Surface water drainage layout

    In terms of surface water drainage, this option provides that surface water runoff in

    the side drains travels the minimum distance possible before discharging into the

    nearest cross culvert and into the discharge channels. This therefore requires that in

    some instances, the invert levels for the side drains will be adjusted to force water

    to flow backwards (towards Km 0+000). However, as previously noted, the

    following additional considerations are also typical of this option:

    Sufficient discharge points and culverts are to be provided to ensure that the

    drain never gets very deep

    Channel drains deeper than 250 mm shall be covered for the safety andconvenience of both pedestrians and vehicles

    The drains are to terminate or discharge in a satisfactory manner without therisk of causing erosion or other problems

    The drains should be capable of being cleaned and maintained easily.

    4.2.3 Dual carriageway geometric layout; including all frontage business servicelanes

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    25/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    25

    Like option 1, option 2 also provides that 3.25m wide lanes are used with 1.2m

    wide central raised island (0.2m above the adjacent finished road levels), service

    roads at selected locations on the right hand side (in front of the market area) and

    3.25m wide lay-bys, 50m long, on the left hand side at selected locations, where

    significant vehicle parking traffic is anticipated. 1.5 m wide raised sidewalks are

    also proposed on both the LHS and RHS with accesses to main business premises.

    Typical drawings for this option are presented in the appendices.

    5.0 The recommended dual design option

    Bearing in mind that the underlying reason for the proposed dualling of this first 1.3km of

    Gayaza road (through the Kalerwe market area) is the severe traffic congestion at this

    location and keeping in mind that draining surface water backwards against the general

    longitudinal slope of the road may present undesirably deep side drains, it is the

    Consultants opinion that option 1, described in section 4.1 above be adopted and carried to

    the detailed engineering design stage.

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    26/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    26

    APPENDICES

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    27/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    27

    APPENDIX 1:PLAN & PROFILE DRAWINGS INDICATING

    EXISTING BUILDINGS AND UTILITY

    SERVICES

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    28/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    28

    APPENDIX 2:OPTION 1 DRAINAGE OUTLINE DRAWINGS

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    29/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    29

    APPENDIX 3:OPTION 2 DRAINAGE OUTLINE DRAWINGS

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    30/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    30

    APPENDIX 4:OPTION 1 GEOMETRIC LAY-OUT AND

    TRAFFIC FLOW DRAWINGS

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    31/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    ____________________________________________________________________________________

    Norconsult International AS

    Service Contract No. RDP/HW/CS014, Addendum No. xxxxxxxxxxxxxxxxxx, September 2009

    31

    APPENDIX 5:OPTION 2 GEOMETRIC LAY-OUT AND

    TRAFFIC FLOW DRAWINGS

  • 7/30/2019 Options Report Sept 09 - 28 Sept, 2009.pdf

    32/32

    Dual Standard Design of Gayaza Road section from Ch 0+000 to Ch 1+300 Draft Options Report

    APPENDIX 6:TYPICAL CROSS SECTIONS FOR 5

    DIFFERENT SCENARIOS