![Page 1: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/1.jpg)
1 [Type the document title]
Capital Works
Monthly Review
October 2018
![Page 2: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/2.jpg)
Page 2
Capital Works Monthly Review > September 2018
OVERVIEW .......................................................................................................................... 3
SAFETY .............................................................................................................................. 4
1.1. Incidents and Injuries ................................................................................................. 4 1.2. Lost time Injuries & Days Lost ................................................................................... 5
CAPITAL PROJECT UPDATES ................................................................................... 6
2.1. Capital Summary Report ........................................................................................... 6 2.2. Financial Performance ............................................................................................... 6 2.3. Capital Projects Status .............................................................................................. 8 2.4. Key Contracts Approved for October ......................................................................... 9
MAJOR PROJECT UPDATES..................................................................................... 10
3.1 Renewable Energy - Small Scale Solar Installation ................................................. 10 3.2 Mackay Regional Sports Precinct ............................................................................ 12
ROADS & TRANSPORT PROJECT UPDATES ...................................................... 14
4.1 Camilleris Road Causeway Reconstruction ............................................................. 14 4.2 Bakers Creek Ferris Gully Ch 3350-4200 Landscaping Works ................................ 16
WATER & SEWERAGE PROJECT UPDATES ........................................................ 18
5.1 60080-rwi-New Eton Bore ........................................................................................ 18 5.2 Sewer Renewals - Replacement: Mackay and Sarina ............................................. 20 5.3 Mirani STP Effluent Storage Expansion ................................................................... 21
![Page 3: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/3.jpg)
Page 3
Capital Works Monthly Review > September 2018
OVERVIEW
This report is for Capital Works Department activities during the month of October 2018. Significant items
in this period include:
• The safety of our staff, contractors and the public continue to be our top priority. In September we
recorded five incidents, two relating to vehicle damage and three first aid events. The leadership
team is investigating this increase in Human Factor incidents. Complacency leading up to the end of
year break is a known trend and to try and mitigate this the team is engaging with the supervisors
and crews at their toolbox talks to reinforce the importance of safety and gather ideas for
improvement. The initiative shown by line management to address the spike in incidents
demonstrates the emphasis the team puts on driving a safety-first culture.
• For the month of October $12M of work was completed. YTD expenditure is $40.0M against a YTD
forecast of $42.6M representing a 94% completion rate. The main driver for the underspend relates
to the procurement of plant ($0.64M), a two-week delay to the resurfacing program $0.45M and
Milton St/Boundary Rd $0.40M. The current underspend is recoverable and there are currently no
known risks to the program.
• There are several projects hitting key milestones this month. These include:
o Commencement of the Queens Park Development design, consultancy for the Water Front
Masterplan and the construction of the Paget workshop expansion;
o On ground completion of 2 out 3 bitumen resurfacing contracts representing approximately
$2M of bitumen sealing which will providing protection for pavement for the upcoming wet
season;
o Substantial completion of the Mirani STP Effluent Storage Expansion project;
o Installation of the synthetic running tracked has commenced at the Sports precinct and will be
completed by mid-December; and
o Resolution of supply issues for the Schmidtkes road culvert upgrade allowing for completion
of the installation of the culverts. The road will be open to traffic WE 9/11/18.
Stewart Furness Director Capital Works
![Page 4: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/4.jpg)
Page 4
Capital Works Monthly Review > September 2018
SAFETY
1.1. Incidents and Injuries
The incident statistic details a summary of the Capital Works safety incident performance. Capital Works
aspires to achieve zero harm with a stretch target of zero injuries
October 2018 Summary:
No. of
Incidents Mechanism of injury Injury Type
2 Vehicle Incident Asset Damage
1 Being hit by falling objects First Aid
1 Muscular stress First Aid
1 Hitting objects with part of
the body First Aid
![Page 5: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/5.jpg)
Page 5
Capital Works Monthly Review > September 2018
1.2. Lost time Injuries & Days Lost
Capital Works aspires to achieve zero Lost Time Injuries by improving safety performance by developing
a proactive safety culture and implementing best practice safety management across all business areas
October 2018 Summary:
Two (2) asset damage incidents were reported during October 2018:
• An unlatched door on a van opened, striking a parked non-MRC vehicle.
• The rear part of a trailer hitting a gate post as a vehicle was exiting a MRC compound.
Three (3) Contractor related incidents were reported in October:
• A contractor who was stripping formwork was hit on their head by an unsecured piece of timber
(approximately 50mm size) which fell 1.2 metres; first air treatment only was required.
• A contractor who was performing a manual task felt a sharp pain in their back.
• A contractor hit their finger when hammering survey pegs.
Each incident was investigated, an appropriate corrective measure implemented to reduce future risks. For
the 2018/2019 year to date, there have been no Lost Time Injuries.
![Page 6: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/6.jpg)
Page 6
Capital Works Monthly Review > September 2018
CAPITAL PROJECT UPDATES
2.1. Capital Summary Report
As we move through a new financial year, the delivery of the 2018/19 capital program remains a significant
focus of Council. The following capital information provides a financial summary of the status of delivery
against our baselined budget position. The original budget was adopted by Council in July. This was
amended in August to take into account carryovers and other adjustments. The September budget review
noted further adjustments to the capital program including $5.7M deferred to next financial year. Overall
the budget decreased by $2.5M.
The 2018/19 capital works program is made up of a total of 428 projects with a current approved budget of
$142.5M. Delivery for the capital program is on track with 94% of the forecast YTD spend being incurred.
2.2. Financial Performance
The table below summarises the year to date financial summary for the 2018/19 Capital program.
Department
Original Budget (inc
Carryover) Approved Budget Current Forecast YTD Forecast YTD Actuals
% Spent of
YTD
Forecast
% Spent of
Approved
Budget
Major Projects 51,812,995 49,815,851 48,300,131 18,083,253 17,681,307 97.78% 35%
Waste 410,653 694,653 436,958 250,383 253,493 101.24% 36%
Water 12,320,613 13,133,237 13,909,025 3,033,473 2,784,570 91.79% 21%
Sewerage 15,967,464 16,948,464 15,678,810 3,430,797 3,413,532 99.50% 20%
Corporate Revenues and Expenses 2,000,000 2,000,000 2,000,000 0 0 0.00% 0%
Works For Queensland Round 2 Funding Project 7,126,380 6,957,380 6,249,645 2,903,012 2,690,056 92.66% 39%
NDRRA 9,339,749 10,399,867 9,431,117 1,312,417 811,286 61.82% 8%
Transport and Infrastructure Projects 47,090,654 42,505,687 41,299,380 13,577,263 12,388,918 91.25% 29%
Total 146,068,508$ 142,455,138$ 137,305,066$ 42,590,599$ 40,023,161$ 93.97% 28.10%
Capital Expenditure 137,309,142 132,892,678 128,366,735 41,387,599 39,212,990 94.75% 29.51%
Operational Expenditure 8,759,366 9,562,461 8,938,331 1,203,001 810,171 67.35% 8.47%
Capital Projects Expenditure 2018/19October 2018
![Page 7: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/7.jpg)
Page 7
Capital Works Monthly Review > September 2018
The ~$5M variance between the approved budget and the forecast is made up of the following:
• Deferral of $1.2M expenditure to next FY for Camilleri District Skate Park that is forecast to not be
fully delivered this FY.
• New projects and scope changes of $1.2M for projects adjusted as part of the September Quarterly
Review where the forecast needs to be adjusted accordingly. (Major Contributors –, Fourways
Drainage, Endpoint Device Replacements, PTAIP Bus Shelter works, Eton Bore Upgrade).
• Forecasting of the advance design header $1.3M will be included in November following a Council
briefing on identified 19/20 projects.
• Potential savings of $0.8M from projects under construction or due for construction. The actualisation
of these savings will be dependent on the extent of contingency utilised during delivery and will be
more refined as delivery of the program continues.
Capital Expenditure Forecast 2018/19
As at 31 October 2018, $40M of work has been completed against a YTD forecast of $42.5M.
The main variances between actuals and forecast for October are identified in the below table.
![Page 8: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/8.jpg)
Page 8
Capital Works Monthly Review > September 2018
Improvement initiatives / focus areas
The focus for the month of October has been on reviewing and updating the full year schedule of works.
An initial baseline was established in July and this has been updated as part of the September review
process. The July baseline was developed on the information available at the time and for a number of
projects, this has now been refined which has allowed the works schedule to be updated.
As part of the reporting for Project Manager slippages from this amended September baseline will be
reviewed and mitigation measure put in place where required.
Interviews have occurred for the Design Manager position and an appointment is expected in November.
2.3. Capital Projects Status
The above graph shows the status of capital projects as at the end of October 2018. Please note the
completed projects can include projects commenced in prior years which were finalised in July and includes
projects with carryover expenditure. The following list identifies the projects marked complete in October.
Sugar Bowl Skate Precinct, Public Toilets 2019 $242,024
Park Shelter Roof Replacement - Grasstree Esplanade Park 2019 $70,626
Sugar Bowl Skate Precinct 2018 $2,240,282
Blacks Beach Park 2018 $199,124
Bakers One - CQU 2016 $3,209,892
Sarina Beach Mountneys Bus Set down 2017 $275,867
Anzac Pde Shared Path 2018 $69,169
Lamberts Beach - Fencing -2017 NDRRA Eve FLDMAR17 $30,534
W4Q2 - Drain lining - Celeber Drive W4Q2 $156,821
Burgess St, North Mackay - Culvert Replacement 2018 $50,745
Blacks Beach Rd, Eimeo - Pavement Improvement 2018 $699,388
Rocky Creek Bridge Replacement 2015 $1,540,068
Dome Building Rental Tenancies - AC Refrigeration 2019AMD $48,278
Mirani Depot - Refurbishment & Upgrade 2012 $1,131,965
Morley St Shared Path 2018 $62,214
![Page 9: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/9.jpg)
Page 9
Capital Works Monthly Review > September 2018
2.4. Key Contracts Approved for October
A list of key contracts that have been finalised and approved for the month is given below. In total these
contracts are valued at ~ $988,000. There are smaller packages of works (not included below) and ancillary
contracts that have also been awarded for the month of October linked to capital.
Contract Design /
Construction
Amount
Award
(ex GST)
Contractor
MRC 2019-006 Gross Pollutant Traps
Cleaning
Construction $ 67,814 Cleanwater Constructions Pty Ltd
MRC 2019-019 Manhole Relining and
Repair
Construction $ 87,932 FlowPro Pty Ltd
MRC 2019-020 Mackay Entertainment
and Convention Centre – Lighting
Upgrade
Construction $509,582 Kennedy Amplifier Hire Service
MRC 2019-025 MECC Integration of Fire
Panels
Construction $ 97,801 Premier Fire Pty Ltd
Quote 2019-026 West Mackay Drainage
Study
Design $ 42,660 AECOM Australia Pty Ltd
SQ 2019-012 Supply of Concrete
Drainage Components – Rocky
Waterholes Culvert Replacement
Construction $ 36,715 Rocla Pty Ltd
SQ 2019-013 Supply and Install
Guardrail – Schmidtkes Road
Construction $ 45,950 Ontime Guardrail
SQ 2019-014 Chain Street Drain Repairs Construction $ 99,950 Haber Excavation Pty Ltd
Total $988,404
![Page 10: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/10.jpg)
Page 10
Capital Works Monthly Review > September 2018
MAJOR PROJECT UPDATES
3.1 Renewable Energy - Small Scale Solar Installation
Overview
Council has identified 21 sites across the region that will have solar systems installed to reduce our
electricity consumption. The project is expected to save ratepayers nearly $17 million in electricity costs
over the next two decades. Contract awarded to Brisbane based company Akcome Power Pty Ltd.
The sites identified are;
Bluewater Lagoon – 25kw Main Admin Building – 70kw
Pioneer Swim Centre – 12kw Artspace – 100kw
Paget WTS – 50kw MECC Auditorium – 70kw
Paget Laboratory – 30kw MECC Convention Centre – 100kw
Mt Bassett SPS – 30kw Wellington Street – 45kw
Sydney Street Pump Station – 12kw Mirani STP – 50kw
Sarina Admin Centre – 16kw Sarina STP 80kw
Gordon White Library – 50kw Mackay South STP – 200kw
Mirani Depot – 40kw Mackay North STP – 200kw
Paget Depot – 100kw Nebo Road WTP – 420kw
The Dome – 30kw
Project Overview Design for Ergon application started on the 6th August 2018 with approvals filtering through. The procurement phase of the invertors and panels complete with their arrival I Mackay on the 8th October 2018.
Activity Start
Date
Installation Completion
Date
Power Connection
Date
Connectivity Connection
Date
Comments
Bluewater Lagoon 16/10/2018 19/10/2018 22/10/2018 12/11/2018
Paget Laboratory 22/10/2018 26/10/2018 TBC TBC Waiting for Switchboard upgrade
for new lab fit out.
Sydney Street Pump Station
18/10/2018 22/10/2018 TBC TBC Waiting for scheduled power shutdown on site
Sarina Admin Centre 19/10/2018 23/10/2018 02/11/2018 12/11/2018
Mt Bassett SPS 24/10/2018 15/11/2018 15/11/2018 15/11/2018
Artspace 5/11/2018 16/11/2018 20/11/2018 21/11/2018
Paget WTS 12/11/2018 20/11/2018 20/11/2018 21/11/2018
Wellington Street 26/11/2018 01/12/2018 02/12/2018 3/12/2018
The Dome 03/12/2018 7/12/2018 10/12/2018 11/12/2018
Paget Depot 14/12/2018 20/12/2018 21/12/2018 22/12/2018
![Page 11: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/11.jpg)
Page 11
Capital Works Monthly Review > September 2018
Project Activities
✓ Discussions held last week regarding cost effective plan to run cable from array to the switchboard.
✓ Sarina Plant – Quotes are out for trenching & security fence installation.
✓ Mirani Plant – Final plan to complete this week. Tendering next week
✓ Mackay North & South – Installer to provide plan for tendering after discussion with site electrician.
✓ Nebo Rd – Installer to provide plan for tendering. Tree removal quote received.
✓ Meeting next week with IS regarding connectivity resources & planning.
Figure 1 - Bluewater Lagoon Installation
Figure 2 - Sarina Admin Bob Wood Hall
![Page 12: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/12.jpg)
Page 12
Capital Works Monthly Review > September 2018
3.2 Mackay Regional Sports Precinct
Project Overview
Activity Delivery Start
Date
Completion Date
Budget Actual
to date
% Complete
Preliminary Design External 01/03/17 30/09/17
$23,798k $17,533*
100
Detailed Design External 13/11/17 01/06/18 100
Construct External 19/12/17 16/01/19 74
Commissioning External 04/12/18 Feb 19 0
Projected Facility Opening
Feb 19 0
*includes projected October claim Recent Project Activities
✓ Athletics Building – External Paint complete;
✓ Athletics Track – Spurtan running track 85% complete;
✓ Aquatic Change Room – External painting commenced, internal sheeting complete;
✓ Aquatic Café/Reception – Internal sheeting complete, painting commenced;
✓ LTS pool – Roof Completed;
✓ LTS pool – All tiling 90% complete;
✓ 25m Pool – Roof 80% complete;
✓ 25m Pool – Floor tiling commenced;
✓ 50m Pool – Wall tiling complete;
✓ Sewer rising main installation complete to CQU pump station; and
✓ Carparks – 50% complete.
Figure 3 - Athletic Building
![Page 13: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/13.jpg)
Page 13
Capital Works Monthly Review > September 2018
Figure 4 - LTS pool & Storeroom
Figure 5 – Spurtan track being laid
![Page 14: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/14.jpg)
Page 14
Capital Works Monthly Review > September 2018
ROADS & TRANSPORT PROJECT UPDATES
4.1 Camilleris Road Causeway Reconstruction
Overview
Camilleris Road Causeways Reconstruction project is funded by Queensland Government’s Works for
Queensland (Round 2) program. Major project works includes upgrade of two causeways to improve flood
immunity and accessibility for the residents living along Camilleris Road.
The driver for the project was direct representations from the residents to Councillors highlighting risk and
access restriction during rainfall especially for medical reasons and for picking up their children after
schools.
Project Overview
Activity Delivery Start Date End Date Budget Actual % Complete
Design Internal 01/10/2017 01/03/2018 $75,000 $67,000 100%
Construction External 09/07/2018 30/12/2018 $1,211,000 $673,500 50%
Recent Project Activities ✓ Causeway 1 concrete pour completed for the causeway and the cut off wall.
✓ Causeway 2 pavement and cut off wall concrete pour preparation in progress.
✓ Stabilised pavement subbase and subgrade works planned for the next fortnight for both the culverts.
✓ Geotech assessment completed and option analysis finalised for additional stability works at the
embankment for Culvert 2. Variation approved and works planned for the week starting 29 October
2018.
![Page 15: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/15.jpg)
Page 15
Capital Works Monthly Review > September 2018
Figure 1 – Causeway 1 culverts placed and concrete poured for the causeway.
Figure 2 – Causeway 2 culverts installed, wingwall/headwall poured, concrete causeway pour preparation in progress.
![Page 16: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/16.jpg)
Page 16
Capital Works Monthly Review > September 2018
4.2 Bakers Creek Ferris Gully Ch 3350-4200 Landscaping Works
Overview
Bakers Creek Ferris Gully Ch 3350-4200 Landscaping Works (North of Schmidtkes Road and south of
Sports Precinct) project is part of the “Bakers Creek Stockroute Road East” (BCSRE) Catchment
Stormwater Trunk Infrastructure. It consists of a low flow open channel stormwater drain designed using
the principles of water sensitive urban design (WSUD). Initial works involved the channel excavation and
these works are for the landscape/revegetation works as part of the water quality management system.
The project aligns with Council’s strategy to address trunk drainage requirements for the ultimate
development of the Bakers One Catchment providing an appropriate level of service and flood immunity
for land and property during weather events (up to 100-year ARI event).
To facilitate development of the Sports Precinct Council acquired drainage corridors through adjacent land
to formalise and construct downstream trunk drainage.
Project Overview
Activity Delivery Start Date End Date Budget Actual % Complete
Design External 01/03/2016 01/02/2017 $300,000 $300,000 100%
Construction (land acquisition, earthworks and drain)
External 09/07/2018 30/12/2018 $3,880,000 $4,049,000 100%
Landscaping External 15/02/2018 15/12/2018 $2,050,000 $1,399,979 68%
Recent Project Activities
✓ All concrete works are complete.
✓ All amelioration and topsoil works complete.
✓ 95% of Coir matting has been installed.
✓ Zone A Planting 100% complete.
✓ Zone B Planting 60% complete.
✓ Zone E Planting 100% complete.
✓ Zone F Planting 100% complete.
✓ Zone C and D Turfing commenced 17 Oct 18.
✓ Irrigation system installed 60% and operational. Remaining installation will progress with planting.
All irrigation works to be completed by early Nov18.
✓ Small trees and shrubs to be planted by end of Oct18.
✓ Project Completion Date 18 Dec 18.
✓ Total plants supplied from the nursery (MRC):
o June to date planted= 82,879 nos.
o Remaining to plant Zone B, D & F= 13,143
![Page 17: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/17.jpg)
Page 17
Capital Works Monthly Review > September 2018
Figure 1 – Control line A- Zone C and Zone D Turfing in progress.
Figure 2 – Control line B Planting and coir matting for Zone E and F completed
![Page 18: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/18.jpg)
Page 18
Capital Works Monthly Review > September 2018
TER & SEWERAGE PROJECT UPDATES
WATER & SEWERAGE PROJECT UPDATES
5.1 60080-rwi-New Eton Bore
Overview
Mackay Regional Council (Council) manages water supply schemes for several small townships within the
region including Eton. These water supply schemes generally consist of raw water drawn from bores, a
water pump station, chlorination system, treated water storage and reticulation network.
Following engagement with the Eton community in late 2016 the aesthetic water hardness was identified
as a key concern to which Council made a commitment to find a solution. The proposed project works
includes a new production bore drilled to access better quality water from a shallow aquifer and direct
treatment with raw water being softened with the use of an ion exchange softening process. In addition to
this, chemical dosing equipment to bring about PH correction/adjustment will also be installed.
The geotechnical investigations, trial bores and construction of a new production bore were completed in
May 2018.
Project Overview
Activity Delivery
Start
Date
Completion
Date Budget Actual %
Complete
Project Management & Supervision
Internal 1/07/2017 31/06/2019 $43,615 $19,731 65%
Internal Design - Bore and Treatment Plant
Internal 1/07/2017 31/07/2018 $68,809 $63,709 100%
External Design - Bore and Treatment Plant
External 1/10/2017 21/11/2018 $132,768 $132,768 100%
Bore Construction External 12/02/2018 15/05/2018 $169,550 $169,950 100%
Treatment Plant Design and Construct and Commission
External 18/06/2018 21/11/2018 $875,850 $346,347 58%
Additional funds have been obtained from 55277- W4Q2 Koumala Water Upgrades W4Q2, increasing the
Construction Contract Budget to $875,850.
Recent Project Activities
✓ Process equipment, pipework, fittings and instrumentation is being procured to CRS premises.
✓ Detailed site layout design for the associated civil structures is complete.
✓ The structural design of the all - weather tanker access track is finalised
✓ Container fit out with process equipment is underway at the factory.
✓ Contractor is negotiating with a local Civils Subcontractor for commencement of the Civils work in
November.
![Page 19: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/19.jpg)
Page 19
Capital Works Monthly Review > September 2018
Figure 1 – Existing bore pump station and treatment facility
Figure 2 – Detailed Layout Plan
![Page 20: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/20.jpg)
Page 20
Capital Works Monthly Review > September 2018
5.2 Sewer Renewals - Replacement: Mackay and Sarina
Overview
As a part of maintaining the condition of the sewer reticulation network, Mackay Regional Council has a program to inspect its gravity sewer mains through Closed Circuit Television (CCTV) works. CCTV work undertaken has identified several sewer mains that require repair works. The most cost- effective approach to sewer renewals is to insert a structural liner into the existing sewers which restores the sewer to as new condition. Relining has the added benefit of sealing all pipe joints reducing the ingress of groundwater which is a major component of inflow and infiltration that leads to surcharging within the sewerage networks. The intent of the Contract is to rehabilitate assets by “no dig” methods via in-situ lining of deteriorated sections of gravity sewer in order to restore the structural integrity, hydraulic capacity and efficiency of the network. This rehabilitation constitutes a key part of the efficient and systematic management of the sewer system by minimising replacement costs and minimising the risk of emergency repair costs, damage to property and the receiving environment and related service disruptions. The sewer repair sites are located at various sites within the Mackay and Sarina regions. The methods of repair include junction sealing and both point patching and full relining. The works include all necessary customer consultation, CCTV inspections, relining, clean up, removal of all construction items, and the restoration of property and other related work where required.
• 21.3 km of CCTV inspection in Mackay
• 3.4 km of sewer relining in Sarina (part funded by W4Q2)
• 8.9 km of sewer relining in Mackay The works have been Contracted to Interflow Pty Ltd for relining commencement in November 2018. Project Overview
Activity Delivery Start
Date
Completion Date
Budget Actual % Complete
Project Management incl, Supervision and internal Design
Internal 01/07/2017 31/07/2019 $167,555 $99,286 59%
Sarina (W4Q2) Construction
External 24/10/2018 28/02/2019 $390,000 $0 0%
Mackay Construction incl. Sarina works cross subsidy
External 24/10/2018 28/06/2018 $2,308,298 $0 0%
Construction Internal 01/07/2017 28/06/2019 $22,240 $2,440 10%
Recent Project Activities
✓ Possession of Site granted (24 October 2018) for initial works with date for Practical Completion of
28 February 2018.
✓ Contractor Mobilisation to site for investigation and reconnaissance.
![Page 21: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/21.jpg)
Page 21
Capital Works Monthly Review > September 2018
5.3 Mirani STP Effluent Storage Expansion
Overview
License conditions for the Mirani Sewerage Treatment Plant only allow for wet weather discharges from
the existing 60ML effluent storage dam when a dilution rate of 5:1 is achieved in the adjacent cane drain –
this is generally only when there is a significant rain event. Under current inflow conditions, the 60ML dam
frequently reaches capacity due to the restrictions on discharging and the existing recycled water users
(the adjacent cane farm and the Pioneer Valley Golf Course) having limited capacity for use. A water
balance assessment concluded that, in order to limit the risk of out of license discharges, storage capacity
needed to be increased from 60ML to 360ML.
This project is being partly funded by the State Government through the Local Government Grants and
Subsidies Program and incudes construction of a new 300ML effluent storage dam as well as a transfer
pump station at the existing 60ML dam and a pipeline between the two dams.
Project Overview
Activity Delivery Start
Date
Completion Date
(Target)
Budget Actual % Complete
Project Management
Internal 01/07/2015 (01/12/2019) $221,000 $168,925.00 85%
Land Acquisition Internal 11/10/2016 22/12/2017 $400,000 $359,500 100%
Design External 16/10/2017 19/03/2018 $115,000 $146,250 100%
Construction External 20/06/2018 (22/11/2018) $3,206,000 $2,609,126.00 85%
Recent Project Activities
✓ All embankments at finished fill height and topsoiling and hydro-mulching complete.
✓ Outlet pipe installation complete and valve pit construction in progress.
✓ install of rip-rap for the western and northern embankment protection complete, overflow spillway in
progress.
✓ Ground surface treatment and compaction of the dam floor complete.
✓ Transfer main installation approx. 95% complete.
✓ Construction of transfer pumpstation shed commenced with slab and switchboard installed.
![Page 22: Capital Works Monthly Review - City of Mackay · year break is a known trend and to try and mitigate this the team is engaging with the supervisors ... an appropriate corrective measure](https://reader033.vdocuments.us/reader033/viewer/2022050112/5f497a33ec3b0f115a5df8c0/html5/thumbnails/22.jpg)
Page 22
Capital Works Monthly Review > September 2018
Figure 1 – 300ML Dam Latest aerial photo (18/10/18) looking east
Figure 2 – Transfer pump station –shed slab and switchboard (30/10/18)