cairo metro project e14155 - presentation to jv 23 dec 2014

36
1 December 2014

Upload: ahmed-gehad

Post on 16-Apr-2017

44 views

Category:

Documents


3 download

TRANSCRIPT

1 December 2014

2

Contents

• First Depot design and construction item• Number of Design Stages• Design Delivery Schedule• Design Phase 4A/4b Boundary Limits for Groups G1 to G6 

• Comparative  Structural  designs

3

FIRST DEPOT DESIGN AND CONSTRUCTION ITEM

4

First Depot design and construction• After site clearance, the first design and construction item for the depot, will be an equipment low point and inspection trench drainage design. 

• This will be from the lowest points in the depot, the bogie drop and the wheel grinding lathe, plus all of the inspection trenches in the various buildings.

• There will possibly need to be a low point sump and pump for this drainage to sewer.

• There will be separate shallower stormwater (if required) or sanitary drainage systems.

5

Where has the bogie drop gone to?

6

NUMBER OF DESIGN STAGES

7

JV proposal – October 2014

8

JV proposal – October 2014

9

Stage 1 – typical stations and viaduct

Stage 2 – Adly Mansour station

Stage 3 ‐ Depot

DAR proposal – December 2014

10

Which Depot buildings need to be ready for test and commissioning?

11

DESIGN DELIVERY SCHEDULE

12

Draft JV and JV designer DAR detailed design review comments process from IPP issue by DAT to IFA issue by DAR for approval by NAT

13

Proposed DAR Design Delivery Schedule

14

DESIGN PHASE 4A/4B BOUNDARY LIMITS FOR GROUPS G1 TO G6 

15

Group 2 – Civil and Structural Engineering with station and viaduct architectural (arrangement), electrical, plumbing and fire fightingGroup 3 – Power Supply, Electromechanical and Mechanical with depot (workshop) architectural (arrangement), electrical, plumbing and fire fightingGroup 6 ‐ Toll (ticketing) Equipment Red text design and installation items by Phase 4a in a Phase 4b station

El Nozha 2 Station

16

COMPARATIVE STRUCTURAL DESIGNS –based on current information only

17

Geotechnical comments on pile foundationsDisadvantages of using Mono‐piles (2.4m diameter) in lieu of a group of 1.2m diameter piles to support the columns of viaduct and stations:

• Reduction of allowable concrete pile structural carrying capacity 

• Reduction of allowable concrete pile geotechnical carrying capacity by about 25%

• Tolerance of deviation of pile centerline should not exceed 0.1 of the equivalent pile diameter and its effect if any should be considered in pile/ pile cap design.

• Pile load tests frequency should be 1 test for each 50 piles.

• More costly load testing configuration for both preliminary and working piles

• Nondestructive tests should be performed on all Mono‐piles.

• Strict precautions should be taken during construction.

• Limited previous local experience with construction of 2.4m diameter piles

• Costly remedial solutions in case of non acceptance of mono‐pile after its construction

18

Comparison Between MonoPile & Multi Piles Foundations

19

Comparison Between Pre-tensioned& Post-tensioned U Girder

20

Precast Alternative For Typical Stations Cross-beams

21

Precast Alternative For Typical Stations Cross-beams

22

Precast Alternative For Typical Stations Cross-beams

23

Precast Alternative For Typical Stations Cross-beams

24

Precast Alternative For Typical Stations Cross-beams

25

GENERAL ARRANGEMENT OF STEEL BEAMS viaduct

26

STEEL BEAMS PROFILES viaduct

27

OPTION‐I OF CONSTRUCTION  viaduct

28

Continue OPTION‐I  viaduct

29

OPTION‐II OF CONSTRUCTION  viaduct

30

Continue OPTION‐II  viaduct

31

GENERAL ARRANGEMENT OF STEEL BEAMS station

32

STEEL BEAMS PROFILES station

33

OPTION‐I OF CONSTRUCTION  station

34

Continue OPTION‐I  station

35

OPTION‐II OF CONSTRUCTION  station

36

Continue OPTION‐II  station