business skills for project managers

8
Business Skills for Project Managers Tracking Project Budgets Burn Rate vs. EVM Tom McGreal, PMP

Upload: easter

Post on 05-Jan-2016

25 views

Category:

Documents


0 download

DESCRIPTION

Business Skills for Project Managers. Tracking Project Budgets Burn Rate vs. EVM Tom McGreal, PMP. Tracking Project Budgets. Burn Rate Simple, straightforward Based on tracking hours worked vs. allocated Earned Value Management (EVM) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Business Skills for Project Managers

Business Skills for Project Managers

Tracking Project BudgetsBurn Rate vs. EVM

Tom McGreal, PMP

Page 2: Business Skills for Project Managers

Tracking Project Budgets

Burn Rate Simple, straightforward Based on tracking hours worked vs. allocated

Earned Value Management (EVM) Used to track value “earned” at each stage vs.

planned budget costs and actual reported costs

Requires accurate breakdowns and effort estimations of work tasks to be effective

Requires knowledge of cost/hr for each resource type

Page 3: Business Skills for Project Managers

Burn Rate

Pro: Based on tallying pro-rated hours worked against plan

estimates Can assign $$ cost/hour Can pro-rate % of a resource’s time to a project Simple to calculate, good rule of thumb

Con: Does not give accurate indication of value created Does not provide an indication of resource productivity Does not allow ‘apples-to-apples’ comparison of cost

and schedule variances, hence difficult to determine where the trade-offs should be made.

Page 4: Business Skills for Project Managers

Earned Value Management (EVM) Required for US Gov contracts, DoD, NASA etc.

Pro: Normalizes and quantifies ‘cost variance’ and ‘schedule

variance’; allows meaningful comparisons of the two to determine optimal tradeoffs

Provides indication of productivity if actual costs available (e.g. from separate accounting system)

Gives indication of “value created” to stakeholders

Con: Needs accurate estimation of project tasks (Work Breakdown

Structure) Productivity calculations only available if accounting/payroll logs

charged hours on a per-project basis.

Page 5: Business Skills for Project Managers

EVM Basics Metrics all relate to a given date or milestone

Planned Value (PV) Quantity of work ($) planned to have completed to date (in

terms of baseline budget) Actual Cost (AC)

Amount of money spent on the project to date as determined from charges to Accounting or Payroll system

Earned Value (EV) Value of Work actually accomplished to date (in terms of

baseline budget)

Schedule Variance (SV) Planned Value (PV) – Earned Value (EV)

Cost Variance (SV) Actual Cost (AC) – Earned Value (EV)

Page 6: Business Skills for Project Managers

More EVM metrics…. Schedule Performance Index (SPI)

Ratio of EV / PV Gives an indication of progress – If > 1; then project is ahead of

schedule. Cost Performance Index (CPI)

Ratio of EV / AC Gives an indication of productivity – If > 1; then value is being created

with less cost than anticipated.

Example 1 CPI is > 1 and SPI is < 1 This implies that the project may be understaffed: Productivity is high,

but progress is slow.

Example 2 CPI < 1 and SPI < 1 This may imply that the there is too much unplanned work (bad

estimation) or scope changes have occurred that have not been accounted for in the PV.

Page 7: Business Skills for Project Managers

Projections based on EVM

Estimate at Completion (EAC) (Original Budget) / CPI Gives an estimate of the actual cost of completing the

project based on current value of CPI. If CPI consistently > 1; then project should finish below budget

($500,000) / 1.12 = $446,429 [~11% under budget]

Alternative EAC calculation (Original Budget) / (CPI * SPI) Gives an estimate of the actual cost of completing the

project based on current values of both cost and schedule variance (assuming schedule will not be allowed to slip).

(S500,000) / (0.9 * 0.81) = $685,871 [~37% over budget]

Page 8: Business Skills for Project Managers

Conclusions… Burn rate calculations usually sufficient for

most smaller, short-term projects.

EVM gives a more accurate picture, but only if the company’s accounting structure supports it. Designed initially for larger projects – Defense, NASA etc

EVM is still worthwhile in smaller projects if accurate data is available, can be easily calculated via spreadsheet.