business skills for project managers
DESCRIPTION
Business Skills for Project Managers. Tracking Project Budgets Burn Rate vs. EVM Tom McGreal, PMP. Tracking Project Budgets. Burn Rate Simple, straightforward Based on tracking hours worked vs. allocated Earned Value Management (EVM) - PowerPoint PPT PresentationTRANSCRIPT
Business Skills for Project Managers
Tracking Project BudgetsBurn Rate vs. EVM
Tom McGreal, PMP
Tracking Project Budgets
Burn Rate Simple, straightforward Based on tracking hours worked vs. allocated
Earned Value Management (EVM) Used to track value “earned” at each stage vs.
planned budget costs and actual reported costs
Requires accurate breakdowns and effort estimations of work tasks to be effective
Requires knowledge of cost/hr for each resource type
Burn Rate
Pro: Based on tallying pro-rated hours worked against plan
estimates Can assign $$ cost/hour Can pro-rate % of a resource’s time to a project Simple to calculate, good rule of thumb
Con: Does not give accurate indication of value created Does not provide an indication of resource productivity Does not allow ‘apples-to-apples’ comparison of cost
and schedule variances, hence difficult to determine where the trade-offs should be made.
Earned Value Management (EVM) Required for US Gov contracts, DoD, NASA etc.
Pro: Normalizes and quantifies ‘cost variance’ and ‘schedule
variance’; allows meaningful comparisons of the two to determine optimal tradeoffs
Provides indication of productivity if actual costs available (e.g. from separate accounting system)
Gives indication of “value created” to stakeholders
Con: Needs accurate estimation of project tasks (Work Breakdown
Structure) Productivity calculations only available if accounting/payroll logs
charged hours on a per-project basis.
EVM Basics Metrics all relate to a given date or milestone
Planned Value (PV) Quantity of work ($) planned to have completed to date (in
terms of baseline budget) Actual Cost (AC)
Amount of money spent on the project to date as determined from charges to Accounting or Payroll system
Earned Value (EV) Value of Work actually accomplished to date (in terms of
baseline budget)
Schedule Variance (SV) Planned Value (PV) – Earned Value (EV)
Cost Variance (SV) Actual Cost (AC) – Earned Value (EV)
More EVM metrics…. Schedule Performance Index (SPI)
Ratio of EV / PV Gives an indication of progress – If > 1; then project is ahead of
schedule. Cost Performance Index (CPI)
Ratio of EV / AC Gives an indication of productivity – If > 1; then value is being created
with less cost than anticipated.
Example 1 CPI is > 1 and SPI is < 1 This implies that the project may be understaffed: Productivity is high,
but progress is slow.
Example 2 CPI < 1 and SPI < 1 This may imply that the there is too much unplanned work (bad
estimation) or scope changes have occurred that have not been accounted for in the PV.
Projections based on EVM
Estimate at Completion (EAC) (Original Budget) / CPI Gives an estimate of the actual cost of completing the
project based on current value of CPI. If CPI consistently > 1; then project should finish below budget
($500,000) / 1.12 = $446,429 [~11% under budget]
Alternative EAC calculation (Original Budget) / (CPI * SPI) Gives an estimate of the actual cost of completing the
project based on current values of both cost and schedule variance (assuming schedule will not be allowed to slip).
(S500,000) / (0.9 * 0.81) = $685,871 [~37% over budget]
Conclusions… Burn rate calculations usually sufficient for
most smaller, short-term projects.
EVM gives a more accurate picture, but only if the company’s accounting structure supports it. Designed initially for larger projects – Defense, NASA etc
EVM is still worthwhile in smaller projects if accurate data is available, can be easily calculated via spreadsheet.