RATE ANALYSIS FOR BRICKWOR Downloaded from TheConstructor Wall Dimensions Length Width Height Half Brick Wall 0.0 m 0.0 m 1.0 m 0.0 Full Brick Wall 1.0 m 1.0 m 1.0 m 1.0 C/S Mortar Ratio 1 :4 Dry Mortar Qty 0.36 MATERIAL Bricks Cement Bags LABOUR With Hand Mixing of Mortar MASON LABOUR BAHISHTI (Water Carrier) Prime Cost 3867.90 Scafolding @2% of prime cost Sundries @3% of prime cost CONTRACTOR PROFIT Contractor Profit TOTAL COST (Rs.) Area m 2 Sand m 3

Upload: chakrapanithota

Post on 01-Sep-2015

20 views

Category:

Documents


2 download

DESCRIPTION

Brick Masonry Rate Analysis

TRANSCRIPT

Sheet1RATE ANALYSIS FOR BRICKWORKDownloaded from TheConstructor.Org

Wall DimensionsLengthWidthHeightArea m2Vol. m3Half Brick Wall0.0 m0.0 m1.0 m0.00.000

Full Brick Wall1.0 m1.0 m1.0 m1.01.000

C/S Mortar Ratio1:4

Dry Mortar Qty0.36
Emran: For full B.W by vol,25% of cement mortar is used.And for half B.W by vol, 30% of cement mortar is used.

MATERIAL Qty.Rs. /UnitAMT (Rs.)SUBTOTAL (Rs.)Bricks49441976.00Cement Bags 3.27250818.44Sand m30.45900408.963203.40

LABOUR With Hand Mixing of Mortar Days

MASON 0.94300282LABOUR 1.37250343BAHISHTI (Water Carrier)0.2020040

664.50Prime Cost3867.90

Scafolding @2% of prime costAmount77.3677.36 Sundries@3% of prime costAmount116.04116.04CONTRACTOR PROFITContractor Profit15%609.19

TOTAL COST (Rs.)4,670.49