Page 1: BPP SAP Service Sheet

STEP: 01

Create customer Inquiry in the system T.Code: Via Menus Logistics>Sales and

Distribution>Sales>Inquiry>Create,Change,DisplayVia Transaction Code VA11,VA12,VA13

Enter Inquiry type, Sales organisation, Distribution channel and division.

Click on enter icon

Page 2: BPP SAP Service Sheet

Enter sold to party, Deliver Plant, Description.

Save the Inquiry.Following Enquiry Number gets generated.

STEP: 02 Create Document for InquiryT.Code: Via Menus Logistics>Project System>Documents>Document Management

System>Document>Create,Change,DisplayVia Transaction Code CV01N,CV02N,CV03N

Deliver Plant

Customer Code

Description

Page 3: BPP SAP Service Sheet

Enter Document type ZCW and press icon.

Page 4: BPP SAP Service Sheet

Enter description of the document and click on create original icon Enter the file location path in the original field.

Click check original icon and save the transaction. Document number will be generated.

Description field

Create original icon

Page 5: BPP SAP Service Sheet

STEP: 03 Assignment of document to Inquiry. T.Code: VA12 – Change.

Enter the Inquiry number and press enter icon. Select one line item and the follow the below path to attach the documents.

Page 6: BPP SAP Service Sheet

Enter the document number which is created in step2 and save the transaction.

Mail to different departmentsT.Code: SBWP (SAP Mail)

Send mail to respective departments to get inputs for cost sheet preparation. Mention the inquiry number and different scopes names in the mail.Inquiry Number: 1300007

Page 7: BPP SAP Service Sheet

Scope: FR Studies-FRSScope: Post award Services-PAS etc.STEP: 04 T.Code: SBWPMail to Concerned departments for cost sheet inputs

STEP: 05Creation of base planning objectT.CodeVia Menus Logistics>Project System > Financials >Planning>Costs in WBS>Costs in

WBS>Base planning objectVia Transaction Code KKE1,KKE2,KKE3

Each department creates base planning objects based on Inquiry number, scope, and year.

Inputs: Enter Base Planning Object Number and Press Enter.

Page 8: BPP SAP Service Sheet

Inputs: Base Unit of Measure: ea Company code: 1000 Description

Then Click on cost estimate icon and select costing variant as BP01 in the popup screen

you will find unit Cost estimate screen. Select header screen icon and enter the date. Select

icon so that you can come to Unit cost estimate screen.

Inputs: Category: E Department: Respective cost center Activity Type: Required cost head Quantity :

Page 9: BPP SAP Service Sheet

Then select save and back icons.Step 06: Information to marketing about base planning objects.T.Code: SBWP (SAP mail). Inputs approver sends mail to marketing dept specifying the competed base planning objects.Inputs of the Marketing Dept in the BPOT.Code: ZSDBPO

Select KKE2 Change base planning object and select execute

Enter the Base planning object for which changes are required. Say enter.

Page 10: BPP SAP Service Sheet

Click on change cost estimate icon and do the required changes in the Unit cost estimate.

Step 07: Creation of QuotationT.Code:

Via Menus Logistics>Sales and Distribution>Sales>Quotation>Create,Change,Display

Via Transaction Code VA21,VA22,VA23

Marketing department creates Quotation and compiles all base planning objects for cost sheet preparation.

Page 11: BPP SAP Service Sheet

Enter the Inputs. Sales organisation, Distribution channel and division.

If it is required to create Quotation with respect to Inquiry click on icon and enter Inquiry number.

Page 12: BPP SAP Service Sheet

Inputs: Sold to Party, Deliver Plant, Material and description.Enter always material as Scope and enter description manually.Double click on line item FR Studies (scope), it takes you to item data screen. Click on Costing icon

Following popup screen appears.

Click on Unit costing and enter costing variant as PC04, press enter. It takes you to Unit cost estimate screen.

Page 13: BPP SAP Service Sheet

Inputs: Category : B (Base planning object) V (For marketing inputs) Resource: Base planning object Description: For marketing inputs, description must be maintained manually. Quantity: Always enter quantity as 1 for base planning objects. Price Total: For marketing inputs Price must be maintained manually.

Similarly for each scope we can compile base planning objects.

Attach the offer document to the first line item of the quotation.

Page 14: BPP SAP Service Sheet

Click on save button .

Step 07: Cost sheet ReportT.code ZCWCS

Page 15: BPP SAP Service Sheet

1.Enter the Quotation Number and Execute.

2. In the report we can find scope wise and cost head wise details. If it requires to see the scope wise details double click on scope column.

Page 16: BPP SAP Service Sheet

3. Here we can find the cost head wise and year wise details. If it requires see the report department wise and year wise double click on cost head.

4. We can see the grade wise report of particular dept by double clicking on department.

Step 08 Create ProjectCreate a new project on receipt of order from the customer. Create the project a fresh or create with reference from an existing project. Click open number to view the next open number. Create the project with the required project profile.

T.Code:

Page 17: BPP SAP Service Sheet

Access transaction by:

Via Menus Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Create

Via Transaction Code CJ01

1. On screen “Create Project: Initial Screen”, enter information specified in the table below:

You can enter Project code directly or by finding through next open number.

Field Name Description R/O/C User Action and Values Comments

Project Definition

Enter the project definition ID R Enter a unique project definition ID

Project Profile

Enter the project profile R Enter the relevant project profile

(Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional)

2. Click to find the current open number. To copy from template, in the template area enter the standard project definition or project

definition to copy from.

3. Click to find the proposed open number; subsequently click to use the new open project ID.

4. In the project definition enter data as below:

Field Name Description R/O/C User Action and Values Comment

Page 18: BPP SAP Service Sheet

sProject Definition Description

Enter the project definition description

R Enter the project description for the required project

Basic DataBusiness Area

Enter the business area R Choose from the dropdown the required business area

Plant Enter the plant O Choose from the dropdown the required plant

Location Enter project location O Choose from the dropdown the location

Functional Area

Enter the functional Area O Choose from the dropdown the required functional area

Profit Center

Enter the profit center R Choose from the dropdown the required profit center

(Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional)

4. Enter the WBS Element detail by clicking on in the project definition

Page 19: BPP SAP Service Sheet

Level Enter the level in the project hierarchy

R Enter the level of the WBS element. Enter only one WBS element at level 1. All other WBS elements should be entered below this on levels viz. 2,3,4,5.

WBS Element Enter the WBS element unique ID

R Enter WBS element ID as per the project coding mask.

Planning Element

Check or uncheck the check box

O Check the ‘PE’ box wherever cost planning has to be carried out. If the box is not checked system will not allow cost planning for the WBS element.

Account Assignment

Check or uncheck the check box

O Check the ‘Acct’ box wherever network / activities or actual cost has to be booked

Note: If ‘Acct’ box is ticked then maintain investment profile for the WBS element.

Billing Element Check or uncheck the check box

O Check the ‘Bill’ box wherever revenue or sales document has to be assigned

Assignments Tab pageBusiness Area Enter the business area O Choose from the dropdown the

required business area for the WBS element i.e. only if the Business area is different than the business area as defined in the project definition

Plant Enter the plant O Choose from the dropdown the required plant for the WBS element i.e. only if the plant is different than the plant as defined in the project definition

Location Enter the location O Choose from the dropdown the required location for the WBS element i.e. only if the WBS location is different than the location as defined in the project definition

(Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional)

5. Use entry tool to enter WBS elements.

Page 20: BPP SAP Service Sheet

Press enter button.

6.All WBS Elements are on level one. To correct hierarchy follow the below path.

You can find the WBS Elements are arranged in hierarchy automatically.

Page 21: BPP SAP Service Sheet

7. Maintain operative indicators:

1) Planning Element: To allow planning in WBS elements2) Account assignment element: To allow actual and commitment postings 3) Billing: To allow assignment to sales & billing documents

Page 22: BPP SAP Service Sheet

8. To see the Project in hierarchy graphic, click the icon .

Step 09 Create Resource allocation sheetT.code ZPSO281. Enter the Quotation number, Select Create/Update icon and execute to prepare the resource allocation sheet.

Page 23: BPP SAP Service Sheet

2. In the above screen you can find the cost sheet vaules year wise. Buy putting Percentage for each year and cost head resource allocation sheet values will be prepared automatically. For the ManMonth cost head WBS Element need to be maintained so that quantity check takes place at the time of execution.Save and click on back button.

3. To see the Cost sheet vs. Resource allocation sheet display report, select report radio button and execute and select cost sheet radio button. In this report you can not change any values.Click on back icon.

Page 24: BPP SAP Service Sheet

Click on back icon.4. To see the Resource allocation sheet display report, select report radio button and execute and select Resource allocation sheet radio button. In this report you can not change any values.

Step 10 Copy Cost sheet values to Project cost planning

Via Menus Project System > Project >Financials>Budgeting>Planning>Costs in WBS>Overall values>Change

Via Transaction Code CJ40

Enter Project definition and version.

Page 25: BPP SAP Service Sheet

Say enter

Enter the plan values against each WBS element by referring to cost sheet.Total the values by selecting top level WBS Element and by following Edit>total Up.

Page 26: BPP SAP Service Sheet

Say Enter

Step11 Copy Resource allocation sheet values to Project budget.

Via Menus Project System > Project >Financials>Budgeting>Original budgetVia Transaction Code CJ30

Page 27: BPP SAP Service Sheet

Copy the values from Resource allocation sheet values to Project budget manually.

Total the values by selecting top level WBS Element and by following Edit>total Up.

Page 28: BPP SAP Service Sheet

Save the budget.

Step12: User status to Project Definition

Put User status RFAP to Project definition.

Select Project definition icon to go to Project definition overview screen. First user status will be INIT.In this status Project can not be released. Marketing dept puts the user status to Project

Page 29: BPP SAP Service Sheet

definition which will trigger workflow to Group head, HOD (Marketing), HOCW.Then HOCW puts user status APPD. That means Resource allocation sheet is approved. Then only we can release the Project.

Step 13 Creation of Sales Order

T.code.Via Menus Logistics>Sales and

Distribution>Sales>Order>Create,Change,DisplayVia Transaction Code VA01,VA02,VA03

Recording receipt of Advance from Customer

Page 30: BPP SAP Service Sheet

Inputs: Sales Organization: 1000 Distribution channel: 10 Division: 02Say enters and provide the Following inputs.

Customer : 10000001 (Pick up from the drop down)Delivering Plant: 1002Material : ADVWBS Element : CW-09855-1 (say)

Page 31: BPP SAP Service Sheet

Fill in the Text:

Go to Line Item- Conditions Tab

Page 32: BPP SAP Service Sheet

Fill up the condition type ZADP wit the Advance Cheque Value and Press enter.

Go to tab and choose the relevant Bill to Party

Press Save

Note the order No and go to Transaction VF01

Type the order no in the Document No Column , choose document type FAZ and enter billing date.

Page 33: BPP SAP Service Sheet

Press enter to arrive at the following screen:

Press save button to generate Down Payment Request No.

Go to transaction VF03 and type the document no:

Press the document Flow Icon to see the document flow:

Page 34: BPP SAP Service Sheet

Please note the accounting document No ( eg; 2400000113)

Go to F-29 transaction:

Fill in relevant date fields , company code data (1000) currency (INR) Customer Code, Bank Account No in SAP & Business Area as 1002. Fill- in Cheque No and Date in the Assignment Field and Cheque Particulars in the Text Field.

Fill-in value 1 in the amount field and press button.

Page 35: BPP SAP Service Sheet

You will see the following screen.

Choose the relevant Down Payment request line created earlier and press tab.

You will come to the following screen:

Page 36: BPP SAP Service Sheet

Enter the tax amount as suggested in the footer..

and press the

overview button: Withholding Tax screen will pop-up for you to enter any TDS amount else press enter:

Page 37: BPP SAP Service Sheet

Press enter till you come to this screen:

Double click the Bank line item and replace the value of 1 with * , this will copy the value of the Down Payment Request to the Bank Line Item, Press Overview icon again and you will come to this screen:

Page 38: BPP SAP Service Sheet

From Menu choose Document- simulate to populate the additional line items as shown below:

Page 39: BPP SAP Service Sheet

Press save icon to post the payment document. Message at the footer will confirm the transaction as shown below:

Step14: Notification for Nomination of Project Manager

Via Menus Logistics>Project System > Notifications>General Notification>Create

Via Transaction Code IQS1

Page 40: BPP SAP Service Sheet

Enter Notification type and enter

Inputs:

Page 41: BPP SAP Service Sheet

Description: Subject Long text Document type: Document No:

Step15

Creation of Network Activities and scheduling

Via Menus Project System > Project >Project BuilderVia Transaction Code CJ20n

Click on Open icon and enter the Project definition in the popup window. Click on enter button

.

Here we can define two types of network networks.1. Network with costs: Normally these networks are created for time sheet neworks.Here each department is defined as an activity. Work and work center will be mentioned in the activity. During time sheet entry employee enters hours against this activity, which will be approved and transferred to project by the project manager. As a result cost also updated in the project.In case of shared manpower, Project manager defines separate network activities and confirms the activities which posts costs as well. Network type: CW01,Network Profile: CW000012. Network without costs: For scheduling activities separate network will be created. In case of site deployment actual cost will be booked through personnel master. But actual man month will be updated through activity confirmation with out any cost updation.Network type: CW02,

Page 42: BPP SAP Service Sheet

Network Profile: CW00002

Timesheet Network

Select WBS Element for which timesheet activities need to be created and right click the mouse and select create network. Enter Network profile and network type.

Select activity overview and enter description the duration, work, work center

Scheduling Network

Page 43: BPP SAP Service Sheet

Select WBS Element for which scheduling activities need to be created and right click the mouse and select create network. Enter Network profile and network type.

Select activity overview and enter description the duration. After saving the transaction network numbers will be generated automatically.To create capacity requirements for the activities select the capacity requirements indicator in the network header (basic data tab page) and perform the network scheduling.Select the network header and go to Edit->Dates->Schedule. Capacity requirements will be generated for the network.Creation of Milestones:Select the activity or WBS Element to which Milestone need to be created and double click on Milestone object in the template area.

Page 44: BPP SAP Service Sheet

Enter the Milestone description, Milestone Usage, Invoice Percentage, Fixed date or Offset to activitySales document date.

Page 45: BPP SAP Service Sheet

Making a Sales Order for the Purpose of Billing a Customer

T.code.Via Menus Logistics>Sales and Distribution>Sales>Order>Change,DisplayVia Transaction Code VA02,VA03

Create sales order ( change mode) after getting order from the customer. While creating sales order, Payment terms with the customer must be taken in to consideration like lump sum, actual Man month, Actual tours etc.

Take the Sales Order no against which advance has been taken and run transaction VA02. Give the order No and press Enter.

Page 46: BPP SAP Service Sheet

Enter the followingPlant:1002Material: Lumpsum (Say)WBS Element: CW-90000-1 (say)

Press Enter and type Plant Code = 1002Type the Material code LUMPSUM (say)And give the relevant WBS no.

Page 47: BPP SAP Service Sheet

Double click on Line item of Material Line item -- it takes you to Line item detail screen.Click the Conditions tab .

Manually select the Condition ZPR0 and enter the LUMPSUM amount.

Page 48: BPP SAP Service Sheet

Press Enter.

ZPR0 line with amount will move up and the taxes will be calculated accordingly.

Select the tab. There will be a pop-up screen and select the WBS .

Page 49: BPP SAP Service Sheet

This will lead to the Milestone Billing Plan Screen and you can copy dates from the WBS by pressing

or manually create the milestones

In normal case the Invoice Percentage should be 100.00

Press the back button from the top menu and save the order.

Step 16 Manual confirmations of the activities.

Via Menus 1.Logistics>Project System > Project > > Project Builder2. Logistics>Project System>Progress>Confirmation>Individual/Collective

Page 50: BPP SAP Service Sheet

Confirmation

Via Transaction Code CJ20n,CN25,CN27

In case of site deployment actual cost of the manpower will be updated through payroll. But actual ManMonth will not be updated. To update actual ManMonth, manual confirmation for the activity needs to be carried out.In case of shared manpower utilization also manual confirmation need to be carried out. Prerequisite for confirmation is activity should be released.

To do confirmation select an activity and follow the below mentioned path.

Page 51: BPP SAP Service Sheet

Enter the Inputs like Personnel number, work center, actual work, posting date and select the back icon and save the transaction.

BILLING A CUSTOMER POST ACTIVITY/MILESTONE CONFIRMATION USING SALES ORDER:

Transaction VA02: Change Sales Order.Give the order no and press enter.Choose the relevant line item , say LUMPSUM and go to its Billing Plan Tab

Page 52: BPP SAP Service Sheet

On milestone confirmation in Project System the Billing Block in Sales Order Billing Plan Line will be automatically removed.

Press Back button and save the Order.

Enter Transaction Code VF01 and give type the Sales Order No in the Document Field Choose Billing Type ZCON and enter the Date of Billing and Press Enter

Page 53: BPP SAP Service Sheet

Chose the line item and double click to see its details

Go to its Texts Tab and enter the item details.

Page 54: BPP SAP Service Sheet

Press Back Button and go to Header Texts by clicking the icon

Go to the text Tab and re-enter the texts relevant for the billing.

Page 55: BPP SAP Service Sheet

Press Back Button and Save the document ---. This will post the document to FI module.

Successful message will be flashed on the footer:

Go to Billing Document- display and Press the document flow Icon

Cross check that automatically accounting document has been generated.

Page 56: BPP SAP Service Sheet

This completes Successful Billing in SAP System

Step 17Workforce planning There are two way of doing workforce planninga) Project view b) Work center view

Via Menus Logistics>Project System > Resources>Workforce Planning> Project View

Via Transaction Code CMP2

Page 57: BPP SAP Service Sheet

Select the project in which you want to do the workforce planning. Enter the profile for workforce planning and the planning period (start and the end date of the planning).

Press the 'Execute' button . It will display the project view. Assignment of the workforce to the activities is to be done.

Page 58: BPP SAP Service Sheet

Select the activity and press 'Create Assignment ' button . Assign the resource/ resources to the activities.

To see the availability of the resources, press the 'Availability Personal Resource' tab

Distribute the quantum of work assigned to the activity to the resources in the open to enter fields for the required periods. The assignment displays ‘Total work’ allocated to the activity, ‘To be distributed’ which indicates the work still to be distributed. Distribute the quantum of work in the activity to the periods.

Page 59: BPP SAP Service Sheet

Press save and go back to save assignment.

b)

Via Menus Project System > Resources>Workforce Planning> Work Center View

Via Transaction Code CMP3

Page 60: BPP SAP Service Sheet

Select the work center at which you want to do the workforce planning. Enter the work center, plant, and profile for workforce planning and the planning period (start and the end date of the planning).

Press ‘execute’ button This gives the Workforce Planning, Work center view.

Page 61: BPP SAP Service Sheet

This screen has two sections; the upper section gives the personal resources assigned to the work center and the lower section displays the activities in which the work center have been assigned.

To assign resource to the activity select the activity and press create assignment tab . The activities and the resources will be displayed on the upper screen. Distribute work in the open to entry fields as per the quantum of work in the project activity.

Page 62: BPP SAP Service Sheet

Press save and go back to save assignment. c) Reporting for capacity planning Via Menus Project System > Information System >Resources>Capacity

Load > Work Center ViewVia Transaction Code CMP9

Page 63: BPP SAP Service Sheet

Select the project for which you want to see the workforce planning report. Enter the profile for workforce planning and the planning period (start and the end date of the planning). If you want to see the availability of the resource, then tick the checkbox with the availability personnel resources.

Press execute button . It will lead to the report for the workforce planning.Step 18: Time Sheet Entry

Via Menus Project System > Progress>Confirmation>Time Sheet .CATS Classic>Record Working Time

Via Transaction Code CAT2

Page 64: BPP SAP Service Sheet

Enter the data entry profile, the date from which you enter the data and the personal no of the resource for which the time sheet data entry is to be made.

Press the Enter Times button It will show the Time Sheet Data entry view

Data entry screen have two parts,The upper section shows the work list for the employee.

Select the activity for which you want to enter the working hours and select the copy tab from the menu. After this it can be seen in the Data Entry Area. Enter the Activity Type, Task Level, and Task Component. Enter the working hours for different days.

Page 65: BPP SAP Service Sheet

After entering the working hours, release the time sheet by pressing Release View button

Then release the by selecting the activity and releasing it by selecting Edit > Release from the menu bar.Once the timesheet is released, it is ready for the approval.Step 19: Approval of the working time

Via Menus Project System > Progress > Confirmation > Approval > Approve Working Times

Via Transaction Code CATS_APPR_LITE

Page 66: BPP SAP Service Sheet

In the Approve Working Time screen enter the network no. for which activities are to be approved.

Press executes .It leads to the Approve Working Times Screen.

Page 67: BPP SAP Service Sheet

This screen displays the date and the no. of hours entered for different resource/resources. Select

the activities which is to be approved and press the approve tab

I f you don't want to approve any activity, then select the activities and press the reject tab. Once you press this tab, the system will ask for the rejection reason. Pick the suitable reason. It will give a pop-up window in which texts about the rejection reason can be entered.

Enter the text and press enter .

The rejection of the activity will initiate a workflow. Through the workflow the resource whose time sheet entry is rejected will get a mail in his inbox. The mail will contain the document which will explain the rejection reason.

Page 68: BPP SAP Service Sheet

Step 20 : Transfer of entry in the time sheet to the projectVia Menus Project System > Progress > Confirmation > Transfer >Project

System > TransferVia Transaction Code CAT5

Enter the Personnel number. If there is a need to see the log then selects the Log check box.

Page 69: BPP SAP Service Sheet

If you want to see the result without transferring them to the project pick the Test Run check box

also. Press Execute .

If the log is checked then the above screen will show the details of the transferred data. Once the time data is transferred it can be seen in the project. Open the project in the Project Builder and pick the activity and its Dates tab. In the details of the Dates tab see the Actual Date's entry.

Page 70: BPP SAP Service Sheet

1. Creation of Purchase requisition:

OverviewA requisition defines the need for a material or service. It is the primary instrument for identifying materials or services that must be either procured outside the company or manufactured internally. It authorizes the Purchasing department to purchase materials in specific quantities within a specified time frame. It is an internal document and is not used outside of the company.

Requisitions can be created for materials with or with out a material master. When creating the requisition with a material master, the part number must be referenced, and a flag must be placed in the account assignment field. This will bring up a pop-up window to assign the material to an account.

Requisitions do not need a material master. If processing a requisition for material that does not have a material master, the account assignment must be flagged with the proper key to charge the item to a cost center, project, or an order.

Purchase order can be created by

Via Menus a) Logistics>Production>DRP>Execution>Purchase Requisition>Create

Via Transaction Code ME51

Page 71: BPP SAP Service Sheet

On screen “Create Purchase Requisition: Initial Screen”: enter information specified in the table below:

Fields Description R/O/C User Action and Values Comments

Document Type

Defines whether a requisition or agreement is to be created

R Enter type (ZP12) for regular purchase requisition for the project

Purchase requisition

Number that uniquely identifies a requisition

O Leave blank. Number assigned by system.

Source determination

Flag that determines whether automatic sourcing of materials from a vendor is to be used

O

Item Category

Denotes specific features of an item (example - material is consignment)

O

Account assignment

key specifying whether accounting for an item is to be effected via an auxiliary Account

R Choose either Project,(P) Projects

Delivery date Date on which the goods are to be delivered. If delivery date is sooner than the system calculated lead time,

R Enter date material is required

date format may vary by configuration

Page 72: BPP SAP Service Sheet

a warning will be issuedPlant Plant requiring material R Enter plant where material is

to be shippedStorage location

Key for determining storage location for a specific plant

O

Purchasing Group

The Buyer responsible for purchasing the specific requisition/item

R Identify the buyer who will purchasematerial

Material group

Grouping of several materials with similar features

R Enter material group code

Req. tracking number

This number can be used to facilitate the monitoring of material procurement

O

Requisitioner Indicates for whom the material is ordered

R

Shipping Plant

The plant from which ordered material is supplied

O

R = Required, O = Optional, C = Conditional

On screen “Create Purchase Requisition: Item Overview”: enter information specified in the table below:

Page 73: BPP SAP Service Sheet

Fields Description R/O/C User Action and Values CommentsItem Number that uniquely

identifies an item within a purchase requisition

R Defaults

I Denotes specific features of an item (example - material is consignment)

O

A key specifying whether accounting for an item is to be effected via an auxiliary Account

O Choose either Project,(P Projects, orders and cost centers will have assigned numbers

Material Name or number that uniquely identifies a material

R Enter name

Short Text Description of Material O Required for materials with no material master

Qty requested

Quantity to be ordered R Enter number of units required

UN Unit of measure in which the requested material is to be ordered

R Defaults from material master

Page 74: BPP SAP Service Sheet

C Category of delivery date (indicates whether the date format is day, week or month)

R Select from the drop-down list

Delivery date Date on which the goods are to be delivered. If delivery date is sooner than the system calculated lead time, a warning will be issued

R Enter date material is required date format may vary by configuration

PGr Purchasing Group R Defaults from material masterMatl Group Material Group O Enter material groupPlant Plant requiring material R Enter plant where material is

to be shipped to Storage location

Key for determining storage location for a specific plant

O Do not enter a location.

SPlt Supplying Plant O

Click on the save folder to produce a numbered requisition, or hit Control + S.

Overview

Trigger:

A purchase order needs to be created, and the vendor is known.

Business Process Procedure OverviewA purchase order is a legal document used to record an individual purchase (negotiated terms, conditions and pricing) with the vendor or arrange for a delivery based on prior agreement. It also provides the vendor with a reference document to link to shipping (goods receipt) and invoicing (invoice verification) processes. The purchase order is a commitment to a vendor for a given material, in a specified quantity at a predetermined price and delivery date.

The steps you must perform to copy a document or convert it into a purchase order are identical.To create a requisition or purchase order by adopting an existing document, you can either select the desired document in the document overview or adopt it in the current purchase order in the right-hand area of the screen using the ADOPT button. In addition you can drag it onto the shopping basket symbol with the left-hand mouse button. A prerequisite is that the relevant documents can be displayed in the document overview.

Click the Personal Settings button on the tool bar, this function is for default information for purchase order header data and also purchase order item data. This will reduce the amount of redundancy in the data entry, i.e. plant, company code.

One Purchase Order may be created for several purchase requisitions.

Page 75: BPP SAP Service Sheet

Via Menus Logistics>Materials Management>Purchasing>Purchase Order> Create>Vendor/Supplying Plant KnownLogistics>Sales and Distribution>Foreign Trade/Customs>General Foreign Trade Processing>Environment>Purchase-Import>Purchasing>Purchase Order>CreateLogistics>Production>KANBAN>Environment>Purchasing>Purchase Order>Create

Via Transaction Code ME21N

On screen “Create Purchase Order”, enter information in the fields as specified in the table below:

Page 76: BPP SAP Service Sheet

Field Name Description R/O/C User Action and Values Comments

Shopping Cart Symbol

Order type R System defaults in Standard PO. Use pull down to change if necessary

Purchasing document number

Number can be internally or externally

assigned

O Leave blank if internally

assigned; fill in if external assignment

Vendor Vendor number R Vendor number known or via match code search

Doc. date Purchase order date R Date PO created (defaults to today’s date)

Header Section Header

Purchasing Organization

Purchasing organization code

R Purchasing Organization known or via match code search

Purchasing Group

Purchasing group code R

Company Code

Company code for purchase R Enter if not defaulted in from purchasing org or group

Item Overview

Item Overview

Item number Item number within document

R Will default by system

Acct. assignment category

Account where costs are allocated

For a consumable material. For a stock material it is not required

C Leave blank for stock item, enter if a consumable material

Choose either Project (P), Order (F), or Cost Center (K) to charge costs Projects, orders and cost centers will have assigned numbers

Page 77: BPP SAP Service Sheet

Item category Type of purchase C Leave blank for standard purchase

Material Material number R Use match code search if needed

External numbering may be used.

Short text Text from the material master record

R Default from master record

PO Quantity Required units / quantity R Enter quantity

Unit of measure

Unit that good or service is purchased

R Enter unit of measure

Category of delivery date

Indicates whether the delivery date is to be entered and displayed as a calendar day, week or month.

R default

Delivery Date Date material is required R Enter delivery date

Net Price Vendor selling price for good or service

R Enter price

Currency Currency used for plant R Default

Per Price per unit R Default

Order unit The unit of measure for which material is purchased

R Default

Material group

Grouping together of materials by characteristics

R Enter material group

Plant Facility where goods or services are produced or sold.

R Enter plant

Storage Location

Location where stock is stored

R Enter storage location Required for stock item

tracking number

Number that facilitates monitoring of the procurement of required

O Enter if known Can be used in List display to list all PO’s created

Page 78: BPP SAP Service Sheet

materials by a certain buyer. Potential entry is employee number.

Page 79: BPP SAP Service Sheet

Requisitioner To whom material or service is ordered

O

Info Record Purchasing information record informal price agreement that may be updated with each purchase

O Default if good or service was purchase from vendor previously or info record created manually

Returns Item Specifies if good or service are returns

C

Free Free goods C

Texts Texts exist if checked C

Purchase req Reference document number C Use tool bar button to reference other purchasing documents

Outline Agreement

Reference document number C Use tool bar button to reference other purchasing documents

Agreement Item

Item number C Item number within purchasing document

RFQ Reference document number C Use tool bar button to reference other purchasing documents

RFQ item Item number C Item number within purchasing document

Purchasing doc

Reference document number C Use tool bar button to reference other purchasing documents

item Item number C Item number

Page 80: BPP SAP Service Sheet

within purchasing document

Higher level item

Item number of higher-level item to which this item belongs (in a hierarchical arrangement).

C

Sub-item category

Indicates the nature of the sub-item (for example, discount in kind).

C

(Note: On above table, in column “R/O/C”; “R” = Required, “O” = Optional, “C” = Conditional)

Click on the Enter button.

On the ‘Item Details’ screen, click the Services tab for Item. Enter information in table below:

Page 81: BPP SAP Service Sheet

Field Name Description R/O/C User Action and Values

Comments

Service No. Enter the service defined in the Service master

0

Short Text Description of the Service C, if no Service no. is maintained

G/L Account General Ledger Account C

Quantity Quantity of the of the service ordered

C

Gross price Price of the service C

On the ‘Item Details’ screen, click the Limits tab for Item. Enter information in table below:

Field Name Description R/O/C User Action and Values Comments

Page 82: BPP SAP Service Sheet

Overall limit Enter the overall purchase value

O

Expected value

Enter the expected value of the purchase

C

Actual Value The actual purchase value C

No limit checkbox

If there is no limit on the overall purchase order value

O

On the ‘Item Details’ screen, click the Account Assignment tab for Item. Enter information in table below:

Page 83: BPP SAP Service Sheet

Field Name Description R/O/C User Action and ValuesComments

Quantity Enter quantity that will be expensed

C

Unloading point

Location for delivery O

G/L Account General Ledger Account C

Controlling area

May include one or more company codes

C

WBS Element

Enter the WBS element for which PO is being made

C

Recipient Individual to receive delivery O

(Note: On above table, in column “R/O/C”; “R” = Required, “O” = Optional, “C” = Conditional)

Click on the Enter button.

The Purchase Order may be posted by clicking on the Save button.

A message will be displayed stating that the purchase order was saved, with the purchase order number.

b) PO release

Page 84: BPP SAP Service Sheet

Via Menus Material management >Purchasing > Purchase Order >Release > Individual Release

Via Transaction Code ME29N

In the screen select the status and release the PO.

Page 85: BPP SAP Service Sheet

Business Process Description OverviewThis document describes the procedure for creating a service entry sheet. Within purchasing, this service entry sheet document is designed for the recording of the services that have been performed by the service provider. The service entry sheet is a list of all planned services that have actually been performed. It can also be used to list and specify unplanned services that have been performed and whose precise scope and nature were unknown at time of planning phase.

Input Required Fields Field Value/Comments

Purchase Order Number for Services Enter the purchase order you wish to reference(Item Category = D)

Page 86: BPP SAP Service Sheet

BUSINESS PROCESS PROCEDURE

Title: I-1Organization/Area: Project Systems

File Name : PS_01 Release: ECC 6.0Responsibility: Status:

Output - Results CommentsService Entry Sheet

Access transaction by:Via Menus a) Accounting> Project System> Resources> Capacity

Requirements Planning> Requirements> Maintenance Order> Completion Confirmation> Servicesb) Logistics> Customer Service> Service Processing> Confirmation> Activitiesc) Logistics> Plant Maintenance> Maintenance Processing> Completion Confirmation> Servicesd) Logistics> Production> Capacity Planning> Requirements> Maintenance Order> Completion Confirmation> Services

Via Transaction Code ML81

Select the other Purchase Order tab and enter the PO number for service.

Select the Create Entry Sheet tab

Field Name Description R/O/C

User Action and Values Comments

Purchase Order Number

Enter Purchase Order Number for Services

R Enter Purchase Order Number. Match code (F4) may be used to help.

Purchase Order Item

PO line item of service O Enter PO item number

Entry Sheet Number

Number of entry sheet in system

O Enter entry sheet number

Selection Criteria:

Section Heading

Person resp : (ordering party)

Name of person responsible for ordering service

O Enter name

Person resp : (contractor)

Name of person responsible at contractors office

O Enter name

Reference Date Date when the price was put on the service entry sheet

O Enter date

Only open sheets

To select only open sheets.

O Check this if the selection should be limited to open sheets.

Last changed on: Last changed by: Version: 1.0 Page:05.04.2007 Sharad Gupta 86 of 88

Page 87: BPP SAP Service Sheet

BUSINESS PROCESS PROCEDURE

Title: I-1Organization/Area: Project Systems

File Name : PS_01 Release: ECC 6.0Responsibility: Status:

Location service performed

Location at which service was performed.

O Enter location

Short Text To select using short text. O Enter short text.Adoption of Planned Services

Adopt planned service from PO into service entry sheet

O Check box if you wish all planned services to be adopted into service entry sheet from PO

Percentage for quantities

% of planned services adopted from PO

O Set percentage of planned services to be adopted

Model Service Specifications

Number of a set of model service specifications

O Choose one

Sequential Control

OverviewDetailsAdd

R Choose one

(Note: On above table, in column “R/O/C”; “R” = Required, “O” = Optional, “C” = Conditional)Click on the Enter button.Click on the Create Entry Sheet button.On Screen “ (Entry Sheet Number): Create Entry Sheet”: enter the information in the fields as specified in the table below:

Field Name

Description R/O/C

User Action and Values Comments

Service No. Key which uniquely defines service(service master number)

R Enter Service number

Short Text Description of Service O Field populates when service no. entered

Quantity Qty of service performed R Enter qty of service performed

Last changed on: Last changed by: Version: 1.0 Page:05.04.2007 Sharad Gupta 87 of 88

Page 88: BPP SAP Service Sheet

BUSINESS PROCESS PROCEDURE

Title: I-1Organization/Area: Project Systems

File Name : PS_01 Release: ECC 6.0Responsibility: Status:

Un of Measure

Unit of Measure for service O Field populates when service no. entered

Price Price of service performed R Enter price of service performed(Note: On above table, in column “R/O/C”; “R” = Required, “O” = Optional, “C” = Conditional)Click on the Enter button.

Save the sheet.

Now select the service and enter the Accept tab on the toolbar.

Last changed on: Last changed by: Version: 1.0 Page:05.04.2007 Sharad Gupta 88 of 88