b & k field balancing set working for the power engineer · b & k field balancing set...

2
B & K Field Balancing Set Working for the Power Engineer DYNBAL and a pocket calculator speed up commissioning of Norwegian Hydro-electric Generator Difficulties and delay are often were mounted on magnets and posi- Biiil^^^B^ ^^^^^^^^^^^^H experienced when commissioning tioned on the upper and lower bear- B^Bl^^^B ^^^^B-^^^^^^^^M hydro-electric plant because the in- ing housings with their main axes ^Bli|^^B ^^^^BS^^^^^^IIB itial unbalance of the rotating parts of sensitivity horizontal, to measure BBII^^^B ^^^^■^S^^^^B^B of the generating set proves tricky radial vibrational motion (Fig.4). To ^^^Bi^^H ^^^^^BiilSS^^^p^E to eliminate by trial and error meth- provide a shaft rotation reference, a ^^Bi^^B ^^^^B^^^^^PIPI ods. The sheer size and mass of the magnetic proximity probe was ^^^^^^^B ^^^^^B^Bi^WB^B generator rotor, together with the ef- mounted adjacent to the main shaft ^^^^^^^B : ^^^^^^^^^^»^P^ fects of the coupled turbine, make it on a bed of Plasticine. A high-perm- ^^^R^^^B ^^^^^^^^^^HW^ important that field balancing be car- eability magnetic disc was taped to j|B j ried out — i.e., the complete set the shaft so as to activate the prox- ^Hp^^^^^^^^^^^^^^^^ffi must be balanced in situ. Using sui- imity probe once per revolution. The ^^^HL_J |; o S rIp^^^^^^^^^^^^^BI:|M table portable balancing instru- proximity probe and each of the two BIB^^^^^^P^^J^^^^^^^^Siffi ments, such as the B & K Field Bal- sensors were on different levels of ^^fc^^^^^^^^^^^^^^R|^§ ancing Set Type 9500 (Fig.1), a the building, and long cables were ^^fe^ r::i , ^^^^^^^^^B «?81 task which might take weeks using needed to connect these monitoring ^^^Ss*p2^^^^^^^^^^BMIP conventional methods can be com- devices to the Balancing Set. ^^^^^^^^^^^^^^^^^^^^^H formed recently at one of the NEBB To prevent any risk of damage to iH^^ power stations in Norway. the generating set, the first stage of irf'^.^ balancing was carried out at the re- i§i«iia^ The set to be balanced was a ver- duced speed of 250 RPM. The set F, 9- 1 - The B&K Potable Balancing Set tically-mounted 150-MW 200- was run up, and the unbalance vi- T u ype 95oa insta,led near the shaft of . 7 - 1 1 tne generating set tonne installation, with a Francis bration velocity and phase were Turbine at the lower end of the measured and recorded for each cor- shaft and a motor at the upper end rection plane in turn. The set was added to each correction plane in (see Fig.2). The bearings were lo- then shut down, and trial weights turn, running the set up, measuring cated at the top and bottom of the generator, and were separated by approximately 4 m (13 ft). The de- sign speed for the set was 375 RPM. Provision was made for bolt- ing on standard 10 kg weights for correcting unbalance in two planes through the rotor (Fig.3). Unbalance in the rotor of a ma- chine manifests itself as vibration, transmitted to the foundation via the bearings. The principle of the Portable Field Balancing Set deve- loped by B & K is to measure the phase and magnitude of the vibra- tion at each bearing, correlate it with the rotation of the shaft, and use this information to calculate the amount and position of the correc- tion mass to be attached to the ro- tor in each correction plane. The Balancing Set uses a pair of piezoelectric sensors to measure the vibration at the bearings. At the Fig.2. Cut-away drawing of the NEBB hydro-electric generating set, showing the relative posi- NEBB power Station the sensors tions of the equipment and the transducers used to perform the balancing operation 18—217

Upload: lamanh

Post on 25-Apr-2019

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: B & K Field Balancing Set Working For the Power Engineer · B & K Field Balancing Set Working for the Power Engineer ... fects of the coupled turbine, ... B & K Field Balancing Set

B & K Field Balancing Set Working for the Power Engineer DYNBAL and a pocket calculator speed up commissioning of Norwegian Hydro-electric Generator

Difficulties and delay are often were mounted on magnets and posi- B i i i l ^ ^ ^ B ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ H experienced when commissioning tioned on the upper and lower bear- B ^ B l ^ ^ ^ B ^ ^ ^ ^ B - ^ ^ ^ ^ ^ ^ ^ ^ M hydro-electric plant because the in- ing housings with their main axes ^ B l i | ^ ^ B ^ ^ ^ ^ B S ^ ^ ^ ^ ^ ^ I I B itial unbalance of the rotating parts of sensitivity horizontal, to measure B B I I ^ ^ ^ B ^ ^ ^ ^ ■ ^ S ^ ^ ^ ^ B ^ B of the generating set proves tricky radial vibrational motion (Fig.4). To ^ ^ ^ B i ^ ^ H ^ ^ ^ ^ ^ B i i l S S ^ ^ ^ p ^ E to eliminate by trial and error meth- provide a shaft rotation reference, a ^ ^ B i ^ ^ B ^ ^ ^ ^ B ^ ^ ^ ^ ^ P I P I ods. The sheer size and mass of the magnetic proximity probe was ^ ^ ^ ^ ^ ^ ^ B ^ ^ ^ ^ ^ B ^ B i ^ W B ^ B generator rotor, together with the ef- mounted adjacent to the main shaft ^ ^ ^ ^ ^ ^ ^ B : ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ » ^ P ^ fects of the coupled turbine, make it on a bed of Plasticine. A high-perm- ^ ^ ^ R ^ ^ ^ B ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ H W ^ important that field balancing be car- eability magnetic disc was taped to j | B j ried out — i.e., the complete set the shaft so as to activate the prox- ^ H p ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ f f i must be balanced in situ. Using sui- imity probe once per revolution. The ^ ^ ^ H L _ J | ; o S rIp^^^^^^^^^^^^^BI:|M table portable balancing instru- proximity probe and each of the two B I B ^ ^ ^ ^ ^ ^ P ^ ^ J ^ ^ ^ ^ ^ ^ ^ ^ S i f f i ments, such as the B & K Field Bal- sensors were on different levels of ^ ^ f c ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ R | ^ § ancing Set Type 9500 (Fig.1), a the building, and long cables were ^ ^ f e ^ r : : i , ^^^^^^^^^B «?81 task which might take weeks using needed to connect these monitoring ^ ^ ^ S s * p 2 ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ B M I P conventional methods can be com- devices to the Balancing Set. ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ H

formed recently at one of the NEBB To prevent any risk of damage to i H ^ ^ power stations in Norway. the generating set, the first stage of i r f ' ^ . ^

balancing was carried out at the re- i§ i« i ia^ The set to be balanced was a ver- duced speed of 250 RPM. The set F,9-1- T h e B & K Potable Balancing Set

tically-mounted 150-MW 200- was run up, and the unbalance vi- Tu

ype 9 5 o a i n s t a , l e d nea r t h e s h a f t o f

. 7 - 1 1 t n e generating set tonne installation, with a Francis bration velocity and phase were Turbine at the lower end of the measured and recorded for each cor-shaft and a motor at the upper end rection plane in turn. The set was added to each correction plane in (see Fig.2). The bearings were lo- then shut down, and trial weights turn, running the set up, measuring cated at the top and bottom of the generator, and were separated by approximately 4 m (13 ft). The de­sign speed for the set was 375 RPM. Provision was made for bolt­ing on standard 10 kg weights for correcting unbalance in two planes through the rotor (Fig.3).

Unbalance in the rotor of a ma­chine manifests itself as vibration, transmitted to the foundation via the bearings. The principle of the Portable Field Balancing Set deve­loped by B & K is to measure the phase and magnitude of the vibra­tion at each bearing, correlate it wi th the rotation of the shaft, and use this information to calculate the amount and position of the correc­tion mass to be attached to the ro­tor in each correction plane.

The Balancing Set uses a pair of piezoelectric sensors to measure t h e v i b r a t i o n at t h e b e a r i n g s . A t t h e Fig.2. Cut-away drawing of the NEBB hydro-electric generating set, showing the relative posi-N E B B p o w e r S ta t i on t h e s e n s o r s tions of the equipment and the transducers used to perform the balancing operation

18—217

Page 2: B & K Field Balancing Set Working For the Power Engineer · B & K Field Balancing Set Working for the Power Engineer ... fects of the coupled turbine, ... B & K Field Balancing Set

Fig.3. The top of the machine rotor, show- Fig.4. One of the sensors secured to a bearing housing ing the unbalance correction weights in position for Plane 1

b ' ■ ■

the effect, shutting down and re- added at the calculated positions, considerable improvement was ob-moving the trial weight in each and the generating set run up served. The vibration severity at the case. The initial measurement per- again. Measurement showed a sub- upper bearing, which had been mitted approximate determination of stantial reduction in unbalance — at 0,53 mm s ~ 1 at the higher speed, the required correction mass, but the upper bearing, where the vibra- was now down to 0 ,18 mm s _ 1 , not position. For this generating set tion had been more severe, the corresponding to approximately 20 kg and 40 kg were used as trial severity had been reduced from 5/im (0,2 thou) displacement. The weights. 0,45 mm s ~ 1 RMS to 0,13 mm permissible residual was 10/im. In

s ~ 1 RMS. fact the overall vibration level in the The generating set was run up range 3 -1000 Hz was now 0,8 mm

again, and the new values of phase It was now judged safe to run the s — 1 , approximately four t imes and velocity were measured and re- set up to its design speed of 375 higher than the component due to corded. These values made it possi- RPM. At this speed the sensors re- unbalance. ble to calculate the effect of a given corded as much vibration from correction mass at a given position other sources as from the unbal- The B & K Portable Field Balan-in each plane; and thus calculate ance components of the main rotor, cing Set enables the balancing oper-the actual masses and fixing posi- so the narrow bandwidth of the f i l - ation to be performed under nor-tions needed to cancel out the un- ter incorporated in the Balancing mal, as-installed conditions. The op-balance measured during the first Set was switched in, to filter out eration can be carried out quickly run. the most interfering vibrations. and systematically. This is a great

advantage where high-cost capital Al l these calculations can be car- The measurements of unbalance equipment is being installed be-

ried out on a programmable pocket were taken at the higher speed, and cause it speeds up commissioning, calculator. B & K has a standard pro- then repeated with trial masses of minimises the risks of damage gramme to calculate correction val- 10 kg and 20 kg in the respective caused by initial unbalance, and ues, called DYNBAL. DYNBAL is ac- planes. A second calculation was cuts down charges for skilled la-commodated on a single magnetic made on the pocket calculator, and bour. The Balancing Set incorpor-card for a Texas Instruments or this called for correction masses of ates a general-purpose vibration me-Hewlett Packard calculator. The Tl 32 kg and 22 kg in the upper and ter and a tunable filter as wel l as a 59 was used to calculate that the lower planes respectively. The gene- phase meter so it is also useful for required correction masses were rating set was shut down, some vibration monitoring, fault tracing, 80 kg at the upper plane and 75 kg standard weights were divided to diagnostic checks, and on-condition at the lower plane. make up the total masses required, maintenance of rotating machinery.

and the new correction made. The calculated masses were When the set was run up again a