assignment-green building-case study

Upload: smcsaminda

Post on 14-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Assignment-Green building-case study

    1/25

    1

    Cover Page

  • 7/30/2019 Assignment-Green building-case study

    2/25

    2

    Table of Contents

    Introduction -------------------------------------------------------------Pg 04

    1.0 Management --------------------------------------------------------Pg 06

    - Credit 1.1.Building Tuning----------------------------------------Pg 06

    - Credit 1.2 Building Users Guide---------------------------------Pg 06

    2.0 Sustainable Sites--------------------------------------------------------Pg 06

    -Credit 2.1 Site Selection--------------------------------------------Pg 07

    -Credit 2.2 Development Density and----------------------------Pg 07

    Community Connectivity

    -Credit 2.3 Brownfield Redevelopment---------------------------Pg 07

    - Credit 2.4 Alternative Transportation----------------------------Pg 08

    -Credit 2.5 Reduced Site Disturbance------------------------------Pg 08

    -Credit 2.6 Storm Water Design, quantity control----------------Pg 08

    -Credit 2.7 Storm Water Design, quality control------------------Pg 09

    -Credit 2.8 Heat Island Effect, Non-Roof---------------------------Pg 09

    -Credit 2.9 Heat Island Effect, Roof---------------------------------Pg 10

    -Credit 2.10: Light Pollution Reduction----------------------------Pg 10

    3.0 Water Efficiency-----------------------------------------------------------Pg 10

    -Credit 3.1 Water Efficient Landscaping---------------------------Pg 10

    -Credit 3.2: Water Efficiency in Air Conditioning---------------Pg 10

    -Credit 3.3: Innovative Wastewater Technologies--------------Pg 11

    -Credit 3.4: Water Use Reduction-----------------------------------Pg 11

    -Credit 3.5: Innovative Water Transmission----------------------Pg 12

    4.0 Energy and Atmosphere----------------------------------------------------Pg 12

    -Credit4.4: Optimize Energy Performance--------------------------Pg 14

    -Credit 4.5: Renewable Energy------------------------------------------Pg 14

  • 7/30/2019 Assignment-Green building-case study

    3/25

    3

    - Credit 4.6: Additional Commissioning------------------------Pg 15

    -Credit 4.4: Ozone Depletion-------------------------------------Pg 15

    -Credit 4.5: Measurement and Verifications------------------Pg 15

    5.0 Materials and Resources-----------------------------------------------Pg 16

    -Credit 5.1: Building Reuse-----------------------------------------Pg 16

    - Credit 5.2, 5.3: Construction Waste Management,-----------Pg 17

    Resource Reuse & Recycling

    - Credit 5.4: Recycled Content Used---------------------------------Pg 19

    - Credit 5.5: Local/Regional Materials Used-----------------------Pg 19

    -Credit 5.6: Rapidly Renewable Materials--------------------------Pg 19

    6.0 Indoor Environmental Quality-------------------------------------------Pg 19

    -Credit 6.1: Outdoor Air Delivery Monitoring-------------------Pg 20

    -Credit 6.2: Increased Ventilation-----------------------------------Pg 20

    -Credit 6.4: Low Emitting Materials---------------------------------Pg 20

    -Credit 6.6: Controllability of Systems-------------------------------Pg 20

    -Credit 6.7: Thermal Comfort, Design-------------------------------Pg 21

    -Credit 6.8: Thermal Comfort, Verification--------------------------Pg 21

    -Credit 6.9: Daylight & Views-------------------------------------------Pg 21

    7.0 Innovation in Design---------------------------------------------------------Pg 21

    8.0 Social and Cultural Awareness---------------------------------------------Pg 21

    -Credit 8.1 Social Wellbeing, Public Health & Safety--------------Pg 21

    Conclusion---------------------------------------------------------------------------Pg 22

  • 7/30/2019 Assignment-Green building-case study

    4/25

    4

    IntroductionOur Company ABS Consultants was hired by Mr. D.S.J. Hewavitharana of Leaf Holdings(Pvt)

    Ltd., a tea Export Company,to build his new office building complex at Dematagoda,

    Colombo. This building will not only serve its commercial purpose of an office space but it

    also seeks to exemplify the standards of a Green Building in Sri Lanka. This report willanalyse the buildings features in terms of its cost, compliance to environmental standards

    and design features which make it suitable to be rated according to the GREENSL

    Ratingsystem.

    Background

    The site is located in the commercial side of Dematagoda, Colombo, and is accessed via

    Baseline Road. It has a maximum rainfall of 400cm of rain per month, humidity levels which

    can range from 70-90% and temperature that rises up to an average of 30C.

    Building

    The building is set to have 3 floors and 1 below shows the various functions of the building

    at each level (Refer to Annexes for schematic drawings and project program).

    Table 1. Building Functions

    Ground Level 1. Reception Lounge & Public Area

    2. Office Spaces

    3. Conference Room

    4. Miniature Auditorium

    5.

    Cafeteria

    6. Recreation Lounge

    7. Kitchen

    8. Service Area

    9. Washrooms

    10.Engineering Workshop

    11.Garbage Collecting Points

    12.Open Parking Area

    13.Vegetable & Fruit Plantations

    14.Bioremediation Area

    First Level 1.

    Office Spaces

    2. Office Area for Divisional Heads

    3. Executive Area

    4. Recreation Lounge

    5. Services Area

    6. Washrooms

    Second Level 1. Office Spaces

    2. Washrooms

    3. Club House

    4. Rain Water Harvesting Tanks

    5.

    Vegetated Roof Garden

  • 7/30/2019 Assignment-Green building-case study

    5/25

    5

    A BOQ done on the building showed the total approximate rate per m2

    to beRs. 58,971.65/m2, a

    summary is shown in Fig. 1 below (refer to Annexes for detailed BOQ).

    Fig. 1 BOQ Summary

  • 7/30/2019 Assignment-Green building-case study

    6/25

    6

    Assessment of site using the GREENSL Rating Tool

    The following analysis will describe the features of the building in accordance to the criteria

    which are applicable to our building and site, in addition to the ones that need to be

    addressed in the GREENSL

    Rating tool system.

    1.0ManagementPrerequisite 1: Green Building Accredited Professional

    A Green Building Accredited Professional was commissioned for the project to work with the

    team to achieve the required GREEN Standards.

    Prerequisite 2: Commissioning Clauses

    The following documents were submitted to the client to be used during the operation of

    the building: Document of Design Intent

    As-Built Drawings

    Operations and Maintenance Manual

    Building Management Staff Training Manual

    Credit 1.1: Building Tuning

    In order to ensure optimum Occupant Comfort and Energy Efficiency of the systems and

    services of the building, a member of the design team would ensure a monthly monitoring

    and a full recommissioning of the building 12months after practical completion. An

    operational manager for the building was suggested to be appointed by the client; in order

    to provide feedback and a review of the systems during the Building Tuning Period.

    Credit 1.2: Building Users Guide

    The following would be provided to the client to optimize the buildings environmental

    performance during operation:

    Energy and Environment Strategy

    All Building Services Transport Facilities

    Waste Disposal Policies

    2.0 Sustainable Site

    Prerequisite 1: Erosion and Sediment Control

    The site is located on flat land thus the surface run-off of sediment leading to high erosion

    rates remains low. An Erosion Prevention and Sediment Control Planwas prepared taking

    into account erosion control methods such as minimizing disturbed areas, mulching (mulch

    derived from waste wood during construction), by controlling the amount of soil that can

  • 7/30/2019 Assignment-Green building-case study

    7/25

    7

    run-off and by stabilizing exposed soil. Sediment that escapes the erosion control methods

    will be trapped using silt fences around the property, especially to the canal.

    Credit 2.1: Site Selection

    As it was a previously developed industrial site within the commercial belt; all necessaryinfrastructure for development already exist.

    Further, the existing dilapidated buildings have left behind a certain amount of

    contamination on site and the new the development will ensure removal of the

    contamination through a process explained in Credit 2.3.

    The proposed new Green Building is designed to have no interference to any habitat, and

    the site disruption is at its minimal due to its low footprint. Existing vegetation in addition to

    the new, along with the natural canal and open space provide an excellent environment for

    employees to work in a productive manner.

    Credit 2.2: Development Density and Community Connectivity

    All necessary infrastructure facilities of power, water supply and waste disposal are

    available as it is a previously developed site. The area in the immediate vicinity is highly

    dense with mainly housing for the low and middle income and commercial activity

    containing planned industrial zones as well. However, green patches are still in abundance

    within the area, which contributes to balance a fair Biodiversity.

    Further, community facilities such as schools, hospitals, banks, groceries and supermarkets

    are located close to the site. This connects the building and its users to the community and

    its functions.

    It is proposed that the maintenance of the building and all open areas will be carried out by

    the local community;generating income and economic growth in the area.

    Credit 2.3 Brownfield Redevelopment

    The site has a minor local contamination which will be dealt with using bioremediation

    strategies (Dzantor 1999). The main strategy which will be used is called phytoremediation

    where native plants likeKohila(Trianthemadecandra), Kankung(Alternantherasessilis),

    Habarala(Alocasiamacrorrhiza) and Mustard (Brassica juncea)will be planted on the

    contaminated site and used to absorb the contaminants from the soil. These plants then will

    have to replaced every six months, to ensure that the plants continue to remove the

    contaminants from the soil (Somaratne and Weerakone 2012)

    As contamination levels reduce, the area will be used as part of the garden for our office

    building. This is cost effective and environmentally friendly way of redeveloping brownfield

    sites for human use.

  • 7/30/2019 Assignment-Green building-case study

    8/25

    8

    Credit 2.4: Alternative Transportation

    Public Transportation Access:

    The area is close to public transport systems such as: ancillary roadways, pedestrian paths,

    and the Dematagoda Railway Station. Thus we encourage users to adopt public transportinstead of personal vehicles to reduce carbon emissions on site.

    Parking Capacity:

    Ample Parking is provided within the site in order to accommodate not only the vehicles of

    the proposed Green Building, but also the vehicles of the neighbouring occupants and for

    commuters who travel from outstations; who can make use of our parking facilities. This

    would generate revenue to the building and in turn reduce the disruption caused to the

    atmosphere through carbon emissions.

    Credit 2.5 Reduced Site Disturbance

    As the site was a previously developed one the biodiversity of the area was severely

    reduced, thus this building project will seek to rehabilitate the local area with native plant

    species such asAloe vera , Dhaluk (EuphobiaAntiquorum) andBougainvillia(eg:

    Bougainvillea spectabilis)

    Credit 2.6 Storm Water Design, quantity control

    The Existing building had 67% of its surfaces being impervious, which created a lot of stormwater run-off. Bringing it back to 50mm/hr (according to GREEN

    SLRating Guide), required

    the building of several step-like retaining walls; made up of a cement-soil mixture along the

    bank of the canal. Furthermore, shrubs and trees planted on each step will trap storm water

    run off, increase infiltration of water into the groundwater and reduce run-off into the

    canal.

    Design of Rain water Harvesting Tank (quantity control)

    Rain falling on the proposed building will be collected through gutters and into a rainwater

    harvesting tank. The collected water will be then used for landscaping and toilet flushing

    purposes.

    Rain Water Harvesting Quantity Calculation (BS 8515:2009):

    1. 5% of Annual Rain water yield (YR)

    YR = A x e x h x x 0.05

    YR = 755 m2x (e x ) x 2500 mm x 0.05

    YR = 755 x 0.80 x 2500 x 0.05

    YR =75,500l

    Collecting Area = A

    http://en.wikipedia.org/wiki/Bougainvilliahttp://en.wikipedia.org/wiki/Bougainvilliahttp://en.wikipedia.org/wiki/Bougainvilliahttp://en.wikipedia.org/w/index.php?title=Bougainvillea_spectabilis&action=edit&redlink=1http://en.wikipedia.org/w/index.php?title=Bougainvillea_spectabilis&action=edit&redlink=1http://en.wikipedia.org/wiki/Bougainvillia
  • 7/30/2019 Assignment-Green building-case study

    9/25

    9

    Yield Coefficient =e

    Depth of Rainfall =h

    Hydraulic filter efficiency =

    2.

    5% of Annual non potable water demand (DN)DN = PD x n x 365 x 0.05 + A x a

    DN = (50 l x 350 x 365 + 716 m2x 60) x 0.05

    DN = 321,523l

    Daily Requirement per person =PD

    Number of persons =n

    Garden Area =A

    Water Demand For Gardening =a

    Therefore Rainwater Storage Capacity = 76,000 l

    Credit 2.7 Storm Water Design, quality control

    As not much waste water will be generated by an office complex and storm-water was run-

    off was reduced considerable, it was not economical to have a storm-water treatment

    system to improve water quality.

    Credit 2.8: Heat Island Effect, Non-Roof

    Comparatively, only a minimum foot print of built area is utilized for the building withnegligible impact on the microclimate. Every effort is made to enhance the healthy

    livelihood of human and wildlife habitat.

    Vegetated terraces are located on the top terrace level of the building and on the ground

    level wherever possible.

    Vegetables and Fruits are grown on the building so that their produce is utilized for the

    consumption of the building occupants through the meals available at the in-house cafeteria

    for a nominal cost. The vegetation thus not only provides organic food to the employees but

    it also improves their immediate scenery at work.

    Native trees are planted throughout the site wherever possible and the entire parking area

    is shaded by trees.

    A non-impervious mixture from the reuse of debris of the previously demolished building

    was mixed with soil and utilized for all roadways, parking areas and pathways within the

    site. This would enable maximum storm water absorption to the ground without an outflow.

    The durability as well as the strength of this paving method is known to be very high as well

    as cost effective with very little maintenance.

  • 7/30/2019 Assignment-Green building-case study

    10/25

    10

    Credit 2.9: Heat Island Effect, Roof

    Solar panels have been installed on both pitches of the roof to its entire area to obtain solar

    power enough for the energy functions of the building.

    Roofing material has a SRI equal to or greater than the values as in Table 2

    Table 2. SRI for different roof slopes

    Roof Type Slope SRI

    Low-Sloped Roof Slope 2: 12 78

    Steep-Sloped Roof >2: 12 29

    Source: GreenSL

    Rating System for Built Environment Version 1.0

    Credit 2.10: Light Pollution Reduction

    All interior lighting circuits have been driven through a motion base sensor system which

    ensures the automatic operation of the lighting circuits between 5am-10pm. However the

    maximum allowed lighting power portion will be limited in accordance to the Table 2.1

    Lighting Power of Code of Practice on Energy Efficient Buildings of Sri Lanka, published by

    SEASL.

    Exterior Lighting will be operated via automatic controls capable of switching off lights when

    sufficient daylight is available or/and when the lighting is not required. Lighting

    arrangements are in compliance with Table 9.4.5 of ASHRAE/IESNA standard 90.1-2004. The

    Project was identified and categorized under LZ1 (Dark and Rural Setting) and the designs

    were made accordingly.

    3.0 Water Efficiency

    Credit 3.1 Water Efficient Landscaping

    Grass will not be planted in the garden space, and instead will have native shrubs likeAloe

    Vera, Dhaluk (EuphobiaAntiquorum) andBougainvillia(eg:Bougainvillea Spectabilis), which

    will not require a lot of water to be maintained. Mulch will be applied to the soil to prevent

    excess evaporation of water from the soil.

    Finally the water will be supplied to the plant using the drip irrigation method which in turn

    will have water transmitted from the rainwater tank and grey water from kitchens.

    Credit 3.2: Water Efficiency in Air Conditioning

    Under average ambient conditions of a warm humid surrounding, a collection of 60 litres

    water is assumed to be collected through the condensation process of Air Handling Units

    http://en.wikipedia.org/wiki/Bougainvilliahttp://en.wikipedia.org/wiki/Bougainvilliahttp://en.wikipedia.org/wiki/Bougainvilliahttp://en.wikipedia.org/w/index.php?title=Bougainvillea_spectabilis&action=edit&redlink=1http://en.wikipedia.org/w/index.php?title=Bougainvillea_spectabilis&action=edit&redlink=1http://en.wikipedia.org/w/index.php?title=Bougainvillea_spectabilis&action=edit&redlink=1http://en.wikipedia.org/wiki/Bougainvillia
  • 7/30/2019 Assignment-Green building-case study

    11/25

    11

    per day. The collected water will be stored in a tank on a level above the proposed Terrace

    area.

    Credit 3.3: Innovative Wastewater Technologies

    The building will have two waste systems separating the black water from grey. The blackwater will be diverted into a septic tank on site while the grey water will be treated using

    grease traps (Fig. 2)

    Fig.1Representation of the process that occurs in the grease trap. Influent enters the inlet

    pipe and is directed beneath the grease layer by the baffle. Within the grease trap that

    grease is allowed to float to the top while sludge settles to the bottom. Water is allowed topass upwards into the outlet pipe toward the filter. The connection at the outlet pipe

    prevents grease from exiting with the effluent.(source: Glassman et al 2009)

    The sludge can be dried and used as manure for the plants in the garden.

    The rainwater tank will be used to provide water for landscaping and flushing in toilets, thus

    reducing the demand for portable water. The plants on the building will be watered using

    the water generated from Air conditioning system.

    Credit 3.4: Water Use Reduction

    The two main uses of water identified in the building are for toilet purposes and cooking

    purposes in the canteen. As it is not possible to reduce the amount of water used for

    cooking, it was decided that the toilets be retrofitted with gravity-fed low flow toilets, which

    have a half or full flush option fitted into them (Rodriguez 2012).

    Rainwater from the entire roof area is collected to rain water harvesting tanks which are

    located on the 2nd

    level of the building. They are then distributed to the use of the building

    functions such as toilet flushing and landscaping purposes.

  • 7/30/2019 Assignment-Green building-case study

    12/25

    12

    The storm water which falls on to ground is absorbed through its non-impervious mixture

    used on the paved areas as described in Credit 2.8: Heat Island Effect, Non-Roof. The rest of

    the storm water will be diverted to for landscaping purposes.

    Credit 3.5: Innovative Water Transmission

    The water tanks will be placed on the second level, with very little use of the pumps will be

    and instead gravity will be used as an effective means of transferring water from the tank to

    the sites where it would be needed. Our solar panels will provide the additional energy

    required by the pumps.

    4.0 Energy and Atmosphere

    Prerequisite 1: Fundamental Building System Commissioning

    In order to verify the design, installation and calibration of fundamental building elements, a

    Commissioning Report was submitted to a third party commissioning team after following

    all the procedures as intended by the GREEN Rating system. The development and

    utilization of the commissioning plan, verifications of installation, functional performance,

    training, operation and maintenance documentation were carried out in prior to the

    creation of the report.

    Prerequisite 2: Minimum Energy Performance

    The Design of the building project complies with both mandatory provisions ofASHRAE/IESNA standard 90.1-2004, section 5.4, 6.4, 7.4, 8.4, 9.4, 10.4 and section 11 of

    performance requirement.

    The project also complies with the final version of Code of Practice on Energy Efficient

    Buildings of Sri Lanka, published by SEASL.

    The insulation of the building envelop, fenestration, doors and the air leakages of the

    building have been built with reference to the ASHRAE/IESNA standard 90.1-2004, section

    5.4,. Necessary precautions have been taken by the initial design to fulfil the requirements

    found in 5.8.1.1- 5.8.1.9.

    U-values for roofs, fenestrations and facades for determining the corresponding OTTVi

    values were determined from data in Appendix 4 of the Code of Practice on Energy Efficient

    Buildings of Sri Lanka. Furthermore the publication fenestrations and doors have been made

    to limit air leakage, with air infiltration not exceeding 2 litres/s/m2.

    Vestibules which separate conditioned spaces from the exterior shall be protected with self-

    closing devices and designed with a minimum distance between them being no less than 7ft

    when closed.

  • 7/30/2019 Assignment-Green building-case study

    13/25

    13

    Equipment Efficiencies, Verification, Labelling, Load Calculation Controls and HVAC System

    Construction & Insulation were made in accordance with section 6.4 of ASHRAE/IESNA

    Standard 90.1-2004. Minimum Equipment Efficiencies at non-standard conditions were

    designed to meet the minimum full-load COP and IPLV/NPLV in Table 6.8.1H. This would

    leavethe Chiller water temperature to be maintained at 40F to 48F and the Condenserwater temperature to be around 75F to 85F.

    As per SEASL, the indoor conditions of the air-conditioned space was designed for a dry bulb

    temperature of 25 C 1.5 C and relative humidity of 55 % 5 %. The combination of

    suitable high temperatures and humidity are suitable for both at the comfort zone as well as

    for energy saving purposes; provided the conditions maintained herein are agreeable to the

    occupants.

    Each conditioned zone will be individually controlled by thermostat controls and the pre-set

    temperatures will assure the occupants comfort within the zone. The Dead Band of the

    zones thermostatic controls shall be within 5F after which the supply of cooling energy to

    the zone is shut off or reduced to a minimum.

    A centralized automation system (BMS) ensures the functionality of after-hour controls and

    automatic shutdown under different time schedules. Furthermore the system ensures

    setback controls and optimum start controls while maintaining zone temperatures below

    the pre-determined set points which are user adjustable.

    Appropriate air conditioning zoning has been introduced as per the standards and are

    intended to operate non-simultaneously once divided into isolated areas of their own.

    Zones may be grouped into a single isolation area provided it does not exceed 25,000 ft2 of

    conditioned floor area nor include more than one floor.

    As per the section 8.4 Voltage Drop across the Feeders were sized for a maximum voltage

    drop of 2% at design load and 3%maximum for the Branch Circuits. LDP will not exceed 10.8

    w/m2

    as per the Energy Code of SEASL.

    Section 9.4 of ASHRAErefers to the lighting control, exit signs, interior and exterior building

    lights. An automatic control has been introduced by the initial design to on the basis ofoperating occupant sensors that shall turn lighting off within 30 minutes of an occupant

    leaving a space. As per the Energy Code of SEASL, occupancy based controls strategies are

    best suited to spaces that have highly variable and unpredictable occupancy patterns. At

    least one control device has been introduced to independently control the general lighting

    within the space. Each and every device shall be readily accessible while LDP will not exceed

    10.8 w/m2

    as per the Code of Practice on Energy Efficient Buildings of Sri Lanka.

    Exterior Lighting is also on the basis of automatic controls capable of switching off when

    sufficient daylight is available or/and when the lighting is not required.

  • 7/30/2019 Assignment-Green building-case study

    14/25

    14

    While designing Exterior Building Grounds Lighting, all exterior building grounds luminaires

    that operate at greater than 100watts designed to have a minimum efficacy of 60 lm/W

    while fulfilling the requirement of Table 9.4.5 of ASHRAE/IESNA standard 90.1-2004. .

    The building has used the most efficient luminaires/fixtures available in the market

    according to the manufacturer information section of the fixture application. The efficiency

    of a lighting fixture is given by its light output ratio (LOR) which is defined as the ratio of the

    lumens from the luminaire to the sum of the individual lumen values of the lamps inside the

    luminaries(Energy Code of SEASL)

    As per the Mandatory Provisions of section 10.4 Electric Motors will comply with the

    requirements of the Energy Policy Act of 1992, Table 10.8.

    Prerequisite 3: CFC Reduction in HVAC & R Equipment

    The HVAC equipment which caters to the total cooling demand of the building incorporates

    the latest standards and CFC-free operation and thus does not deplete ozone layer.

    Credit 4.1 Optimize Energy Performance

    The Buildings Energy Simulation demonstrates that Option 1 to be in compliance with

    Prerequisite 2. The buildings baseline energy performance was calculated as per the

    ASHRAE/IESNA standard 90.1-2004 Appendix G and it complied with the final version of the

    code of practice on Energy Efficient Buildings published by SLSEA. The energy process cost is

    no less than 25% (about 33%) of the buildings baseline energy cost. According to thecalculations; the new building achieved the minimum energy cost savings of 27.5% and the

    design of the project complies with the mandatory provisions in Standard 90.1-2004 of

    ASHRAE.

    Credit 4.2: Renewable Energy

    Solar wasused as the potential source of renewable energy and it would cover an area of

    330 m2. The entire panel is located at the North-South orientation with a maximum 12

    0

    angle to the South. Table 3 shows calculation made on the buildings renewable energy

    output and savings. In addition to this a series of net-metering strategies put in place to

    monitor the monthly energy usage of the building.

    Table 3. Renewable energy generated onsite and savings in energy costs achieved.

    Peak energy output

    (kWh/month)

    Total energy usage

    of building (kWh)

    Savings per month

    (%)

    5418 39320 13.77

  • 7/30/2019 Assignment-Green building-case study

    15/25

    15

    Credit 4.3: Additional Commissioning

    A detailed review of the design was carried up prior to the construction phase and further

    review of construction documents will be implemented close to completion. A selective

    analysis of the contractor submittals for commissioned equipment wasdone by a third party

    agent.

    The Commissioning Agent will prepare and submit a re-commissioning management manual

    and review the project close to the end of the warranty. The Commissioning Process of the

    ASHRAE GUIIDE LINE will be referred to and used as a supporting document.The

    information and instructions, published in the Table D-1, Documentation Matrix of the

    above publication was also referred to.

    Credit 4.4:Ozone Depletion

    The Chiller operates with 'near zero' emissions refrigerant while using recently developed

    HCFC as the refrigerant which has very low ozone depleting potential.

    Chiller includes improved gasket materials and minimizes the use of threaded fittings. The

    low-pressure chiller design ensures that air will typically leak into the machine instead of

    refrigerant leaking out. The new purge systemson offer in these Chillers release less

    refrigerant per pound of air. The use of integrated microprocessor-based controls enable

    the monitoring of purge operation leaks, plus monitoring of equipment room refrigerant

    concentrations up to one part per million.

    Finally the fire suppression system of the building does not contain HCFC or Halons which

    have ozone depletion potentials.

    Credit 4.5: Measurement and Verifications

    M & V plan of the designed project is developed with reference to the International

    Performance Measurement & Verification Protocol Volume III.

    Documentation and specification of the baseline including a listing of all important

    assumptions and supporting documents were prepared.

    A dedicated person was appointed to implement the M&V plan for the projected time

    duration of time over which Quality Assurance procedures need to be reported on.

    The calculation of the building base load was important. Therefore, option C of Table 1, and

    Overview of New Construction M&V Options of the volume III were used to identify

    buildings similar to ours so we can use their values of; projected baseline energy use, data

    on building function, location and operation to calculate our own values.

  • 7/30/2019 Assignment-Green building-case study

    16/25

    16

    The equation below was used to determine the energy savings of the building and the well-

    equipped sub metering program was followed thereafter to calculate the building energy

    usage in operation.

    Energy Savings = Projected Baseline Energy Use - Post-Construction Energy Use

    5.0 Materials and Resources

    The increasing scarcity of resources and the high and fluctuating prices of raw materials can

    lead to major economic and social dislocation in every country on earth; increasing material

    and resource efficiencies can limit all these problems.

    Waste management during all stages of demolition, construction and operation play a very

    important role in effective usage of materials and resources. The following options

    demonstrate an efficient technique of the waste management process:1. Reduce (Prevention of waste generation)

    2. Reuse (Reuse of reusable materials)

    3. Recycle

    4. Recovery

    Prerequisite 1:Storage & Collection of Recyclables

    An effective waste management plan was required due to high waste generation of the

    building during its operational stage. The following actions will be implemented as part of

    the waste management strategy:1) Training and education of staff on reuse strategies.

    (Ex. Use both sides of paper, Use Reusable Plastic case for Foods and

    Beveragesetc.)

    2) Each staff member will be responsible for ensuring that the waste they generate is

    disposed into the correct bin:

    Paper & Cardboards - sent off to be recycled

    Plastics - Recycled Locally (For ease of recycling, different type of

    plastic resin need to be kept separate)

    Compost {Foods} - Should be composted on site and will be a source of fertilizer

    for the plants.

    3) Maintain garbage collection and transport services from all parts of the building.

    4) All waste (other than compost) will be collected by theColombo Municipal Council

    (or via a private contractor) from garbage room.

    Credit 5.1: Building Reuse

    The existing buildings were in a poor state of repair and were slated for demolition.

  • 7/30/2019 Assignment-Green building-case study

    17/25

    17

    Credit 5.2, 5.3: Construction Waste Management, Resource Reuse & Recycling

    Credit 5.2: Recycle and / or salvage - 85% (by weight)

    Credit 5.3: Resource Reuse - 12%

    Preliminary Demolition Plan (Material & Resource management)

    The Preliminary Demolition Plan will be used to ensure that demolition activities on site do

    not adversely affect the health, safety, traffic or the environment of public and neighbouring

    properties.

    Demolition methods

    The strip out and removal of non-structural elements will be undertaken utilizing manual

    labour and small plantswhich include bobcats and excavators.

    During the demolition process erosion control measures will be established. These will

    include treatment of dust and management of discharge into storm water systems.Material handling

    On-site storage of reusable materials will occur at the northern boundary of the land.

    Recycling and disposal containers will also be accommodated at a separate location at the

    northern boundary of the land to be collected by collection vehicles.

    Hazardous materials will be treated separately.A hazardous materials inspection will be

    undertaken by an accredited consultant and removed in accordance with standards.

    A preliminary assessment of the existing building showed the resources which can be

    reused, recycled or disposed of in an appropriate manner (Table 4).

    Table 4. Resources which can recycled, reused or disposed of in a safe manner

    Resource Resource

    Reuse (%)

    Waste

    Reuse (%)

    Description

    Clay Burnt Bricks 30 70 30% of Clay Burnt Bricks can

    be taken as undivided and

    uncrushed bricks during

    proper demolition and

    reused in walls. (Credit 5.3)

    The remaining divided and

    crushed bricks can be used

    for landscaping, preparation

    of access roads and parking

    areas. (Credit 5.2)

    Crushed Concrete Debris

    0 100 100% Concrete debris reused

    for base preparation on

    roads, ground floor and for

    cement blocks made onsite.

  • 7/30/2019 Assignment-Green building-case study

    18/25

    18

    (Credit 5.3)

    Structural Steel Sections

    (UB)

    60 (recycled) 40 (sold to

    as scrap to

    be recycled)

    80% of the existing roof

    structure (by weight) consists

    of universal beam sections,hence 75% of it can be

    reused as roof trusses for

    new building with minor

    modifications in place (i.e.

    sand blasting with the

    application of a Zinc

    Phosphate primer). (Credit

    5.3)

    The remaining 20% of steel

    debris will be sold as scrap

    metal to be recycled. (Credit

    5.2)

    Roofing Materials 0 0 Existing roof structure

    consists of old (>5 years old)

    asbestos roof sheets and

    these sheets are categorized

    as hazardous. Thus careful

    removal and disposal to

    government approved

    disposal sites will be

    required. (Credit 5.2)

    Glass Wool, Electronic

    waste

    0 0 Categorized as a hazardous

    and disposal to government

    approved disposal sites will

    be required. (Credit 5.2)

    Glass, Paper, Timber,

    etc

    0 100

    (recycle)

    All recycling items like glass,

    paper and timber, etc need

    to be collected separately

    and sold to recycling

    companies. (Credit 5.2)

    Construction Plan (Material & Resource management)

    Waste generation during construction is relatively low when compared to the operational

    stage of the building. Moreover properly trained and experienced site staff along with

    proper construction techniques can be used to minimize the waste generated onsite duringconstruction. Apart from these factors the most common construction wastes come

  • 7/30/2019 Assignment-Green building-case study

    19/25

    19

    fromreinforcement off-cuts, cement bags, wooden parts from formwork, excessive

    foodsetc.; all of which can be recycled or got rid of in a cost-effective manner.

    Credit 5.4: Recycled Content Used - 25%

    The following recycled materials will be used in the new building to reduce the demand forvirgin materials.

    1. Recycled Reinforcement

    2. Recycled Polythene

    3. Reuse/Recycled cement blocks with concrete debris

    4. Soil Blocks

    Credit 5.5: Local/Regional Materials Used- 25%

    The following materials will be sourced locally:

    1.

    Concrete with locally made cement2. Locally made Paint and other accessories

    3. Locally made tiles for floor finish

    4. Locally made asbestos for Roof

    5. Locally made Recycled Polythene

    6. Recycled cement blocks made onsite and locally made soil blocks.

    7. Recycled Reinforcement made locally

    Credit 5.6: Rapidly Renewable Materials

    Dura Panels were used for all internal, non load bearing partition walls. Dura is made out of

    Paddy Straw Fibres and the process produced no toxic waste, volatile organic compounds

    and it does not contain any formaldehyde.

    6.0 Indoor Environmental Quality

    Prerequisite 1: Minimum IQA Performance

    Special eatables in ventilation system controls, stair and shaft vents shall be equipped with

    motorized dampers that are operated according to the needs of the fire and smokedetection systems and monitored through the BMS. All outdoor air supply and exhaust

    hoods will automatically control and shut-off the outdoor air supply. Once the preoccupancy

    building warm-up, cool down and setback reach the outdoor air supply level and exhaust air

    dampers benchmark specified by Section 6.4.3.4 of ASHRAE; the exhaust and ventilation

    systems that are equipped with motorized dampers will automatically shut down. The

    maximum leakage rate will be as indicated in Table 6.4.3.4.4. of ASHRAE.

    Ventilation controls shall be in compliance with ASHRAE Standard 62 and Energy Code of

    SEA. Friction losses and pressure drops across the system will be no less than the specified

    levels in the Local Energy Code.

  • 7/30/2019 Assignment-Green building-case study

    20/25

    20

    Under HVAC System Construction and Insulation, insulation of all supply and return ducts

    installed as part of an HVAC air distribution system shall be thermally insulated in

    accordance with Tables 6.8.2A and 6.8.2B.of ASHRAE/IESNA standard 90.1-2004.

    Precautions for the leakages of relevant air ducts were taken and the Lmax was assured to

    be maintained below the specified level.

    Prerequisite 2: Smoke (ETS) Control:

    Company policy prevents smoking inside the building; however occupants are welcome to

    smoke at designated areas outside the building.

    Credit 6.1: Outdoor Air Delivery Monitoring

    In order to maintain building occupants comfort and wellbeing, a CO2 monitoring system is

    installed for the Mechanically Ventilated areas of the building.

    Credit 6.2: Increased Ventilation

    Most areas of the building are naturally ventilated except for the work spaces which have

    provision for air conditioningwhen ever required. This ensures low operational costs in the

    building while maintaining healthy living standards.

    All lobby areas, passageways, links, cafeteria, kitchen area, and washrooms are 100%

    naturally ventilated.

    Credit 6.4: Low Emitting Materials

    Paints and Coatings:

    All Paints and Coatings to be used are Lead free, preventing the release of toxins into the

    environment.

    Carpet System:

    There will not be any carpets used in any area of the building as carpets are known to be

    dust collectors as well as having high maintenance and replacement costs.

    Credit 6.6: Controllability of Systems

    6.6.1: Lighting Controls

    Office area lighting design was completed on the basis of each and every light fixture being

    readily accessiblethrough at least one control device. Individual lighting controls for

    minimum of 90% of the occupants will have their own adjustment controls for their

    individual tasks as well as group needs.

    Credit 6.6.2 :Comfort Controls

    With reference to Section 5.1 (Location and Size of Openings) of ASHRAE Standard 62.1-

    2004; naturally ventilated spaces shall be permanently open to and within 8m of operable

  • 7/30/2019 Assignment-Green building-case study

    21/25

    21

    wall or roof openings. Open spaces constitute a minimum of 4%of the net occupiable floor

    area.

    Operable openings will be readily accessible to building occupants whenever the space is

    required, as specified by Section 5.1.2 (Control and Accessibility) of ASHRAE Standards.

    The comfort controls for the building were assessed taking in consideration Section 5.4 (six

    primary factors of thermal comfort) of ASHRAE Standards.

    Credit 6.7: Thermal Comfort, Design

    A sensitive and thoughtful building design envelop is created for the satisfaction, wellbeing

    and maximum productivity of the occupants. The thermal comfort conditions for human

    occupancy were designed to keep all running and operational costs to a minimal. The design

    meets with the ASHRAE Standard 55-2004.

    Credit 6.8: Thermal Comfort, Verification

    A Thermal Comfort survey is suggested to be conducted 6-18 months after occupancy, to

    ascertain the levels of satisfaction of the occupants.

    Credit 6.9: Daylight & Views

    The entirety of the building obtains 100% natural lighting, reducing the consumption of

    electricity and bringing down building operation costs. However, provision has been made

    for artificial lighting in all areas of the building during days and instances of reduced natural

    light as well as for building functions at night.

    The building sits in a picturesque location facing a water body with abundant fauna and

    flora. Therefore the structure is designed in a manner that obtains maximum views of the

    outsideenvironment. This facility is encouraged even on the upper levels of the building,

    personifying the interior of the building with the natural beauty of the outside environment

    7.0 Innovation in Design

    An exemplary performance is suggested to be attempted on this building in future, once theGREEN

    SLrating has been awarded.

    8.0 Social and Cultural Awareness

    Prerequisite 1: Archaeological Sites and Heritage Buildings

    There are no Archaeological Sites and Heritage Buildingsin the vicinity of the site.

    Credit 8.1: Social Wellbeing, Public Health & Safety

    The quality of life, health and wellbeing is encouraged of the occupants through the self-sustaining aspects of the building complex. The structure invites natural wind, ventilation

  • 7/30/2019 Assignment-Green building-case study

    22/25

    22

    and plenty of sunlight to ensure that occupants inhabit a more comfortable and natural

    space. Social interaction is also encouraged in the public open spaces, increasing the social

    connectivity of the area.

    The building occupants consume the healthiest fresh fruits and vegetables grown within the

    complex; and enjoy walks and physical exercise along the canal and in the beautiful

    landscapes we have created around the building.

    The building is designed as per safety standards and guidelines set out by the UDA and CMC.

    It is also safe for differently abled persons as well.

    Conclusion

    On analysis of the building according to the GREENSL

    Rating system, it was possible to make

    an approximate calculation of the total amount of credits the building qualifies for. Table 5

    shows a summary of the credits.

    Table 5: summary of credits scored by the new building on site

    Credit Point attributed to credit

    1.1 Building Tuning 1

    1.2 Building Users Guide 1

    2.1 Site Selection 1

    2.2 Development Density and Community

    Connectivity

    4

    2.3 Brownfield Redevelopment 1

    2.4 Alternative Transportation 3

    2.5 Reduced Site Disturbance 4

    2.6 Storm Water Design, Quantity Control 3

    2.8 Heat Island Effect, Non-Roof 1

    2.9 Heat Island Effect, Roof 1

    2.10 Light Pollution Reduction 1

    3.1 Water Efficient Landscaping 4

    3.2 Water Efficiency in Air-conditioning

    system

    1

  • 7/30/2019 Assignment-Green building-case study

    23/25

    23

    3.3 Innovative Wastewater Technologies 4

    3.4 Water Use Reduction 3

    3.5 Innovative Water Transmission 1

    4.1 Optimize Energy Performance

    4.2 Renewable Energy 7

    4.3 Additional Commissioning 1

    4.4 Ozone Depletion 1

    4.5 Measurement and Verifications 1

    5.2 Construction Waste Management 2

    5.3 Resource Reuse 2

    5.4 Recycled Content 2

    5.5 Local/Regional Materials 3

    5.6 Rapidly Renewable Materials 1

    6.1 Outdoor Air Delivery Monitoring 1

    6.2 Increased Ventilation 1

    6.4 Low Emitting Materials 3

    6.6 Controllability of Systems 2

    6.7 Thermal Comfort, Design 1

    6.8 Thermal Comfort, Verification 1

    6.9 Daylight and Views 2

    8.1 Social Wellbeing, Public Health and

    Safety

    1

    Total number of Credits 66

    According to the above score sheet, one expects to qualify for a Gold Star GREENSL

    Rating.

  • 7/30/2019 Assignment-Green building-case study

    24/25

    24

    References

    American Society of Heating, Refrigerating and Air-Conditioning Engineers,

    2004,ANSI/ASHRAE Standard 55-2004 Ventilation for Acceptable Indoor Air Quality, Atlanta:

    ASHRAE.

    American Society of Heating, Refrigerating and Air-Conditioning Engineers, 2004,

    ANSI/ASHRAE Standard 90.1-2004 Ventilation for Acceptable Indoor Air Quality, Atlanta:

    ASHRAE.

    American Society of Heating, Refrigerating and Air-Conditioning Engineers,

    2005,ASHRAEGuideline 0-2005 The Commissioning Process, Atlanta: ASHRAE.

    American Society of Heating, Refrigerating and Air-Conditioning Engineers,

    2007,ANSI/ASHRAE Standard 62.1-2007 Ventilation for Acceptable Indoor Air Quality,

    Atlanta: ASHRAE.

    Dzantor, E.K., 1999, Bioremediation of Contaminated Soils: What It Is and How To Do It,

    Maryland Cooperative Extension, Fact Sheet 757, University of Maryland, College Park,

    Maryland.

    Glassman, J., Kanegawa, B., Lee, D., and Martinez, A., 2009, Grey Water Systems, Engineers

    for a Sustainable World, Stanford University, California

    GREEN Building Council Sri Lanka, 2012, GREENSL

    Rating System For Built Environment

    Version 1.0, Green Building Council Sri Lanka, Nugegoda, Sri Lanka

    International Performance Measurement and Verification Protocol (IPMVP), 2003, Concepts

    and options for determining energy savings in new construction, Vol. 3.

    Rodriguez, J, 2012, Low-Flow Fixtures, Available at:

    http://construction.about.com/od/Green/a/Low-Flow-Fixtures.htm, Accessed on the 28th

    of

    September 2012.

    Somaratne, S and Weerakoon, S.R., 2012, A Comprehensive Study on Phytoextractive

    Potential of Sri Lankan Mustard (Brassica Juncea (L.) Czern.&Coss) Genotypes, WorldAcademy of Science, Engineering and Technology, Vol 61, pp. 1266-1270

    Sri Lanka Sustainable Energy Authority, 2009,Code of practice for energy efficient buildings

    in Sri Lanka, Colombo: Design Systems.

    http://construction.about.com/od/Green/a/Low-Flow-Fixtures.htmhttp://construction.about.com/od/Green/a/Low-Flow-Fixtures.htmhttp://construction.about.com/od/Green/a/Low-Flow-Fixtures.htm
  • 7/30/2019 Assignment-Green building-case study

    25/25

    Annexes