Assigning Material and Cost Resources in MS PROJECT 2010 Posted on November 7, 2011 Hi, In this post I will explain how to set up, and assign material resources in MS PROJECT 2010. First I will add three material resources in Resource Sheet: Now I will add two Tasks: O.K. Now, I will assign Paint to the Painting the wall task, and Gasoline, and Concrete to the Pouring the concrete Task: Nenad Trajkovski Assi gning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material... 1 of 11 4/20/2012 1:07 PM

Upload: anwar0000

Post on 29-Sep-2015

3 views

Category:

Documents


0 download

DESCRIPTION

MAT

TRANSCRIPT

  • Assigning Material and Cost Resources in MS PROJECT 2010Posted on November 7, 2011

    Hi,

    In this post I will explain how to set up, and assign material resources in MS PROJECT 2010.

    First I will add three material resources in Resource Sheet:

    Now I will add two Tasks:

    O.K. Now, I will assign Paint to the Painting the wall task, and Gasoline, and Concrete to the Pouring the

    concrete Task:

    Nenad Trajkovski

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    1 of 11 4/20/2012 1:07 PM

  • I put 1000 in the Unit field, because I assume that I will need 1000 liters of paint for painting the wall. MS

    PROJECT 2010 has calculated that the cost is $50.000 (1.000 units X $50 per Unit = $50.000). Remember

    that this cost remains the same, no matter how long will take you to pain the wall. I will show it to you. First I

    will choose the Cost table:

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    2 of 11 4/20/2012 1:07 PM

  • and I will get:

    Now I will change duration for task Painting the wall from 3 to 10 days:

    I will choose the Cost table again, and I will get:

    The Total Cost remains the same.

    O.K. Now, I will assign Gasoline and Concrete to the Task Pouring the concrete:

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    3 of 11 4/20/2012 1:07 PM

  • I need 5.000 units (tons, liters or whatever) of Concrete and I need 20 liters (or gallons) of Gasoline per hour.

    MS PROJECT 2010 has calculated that the cost for the Concrete is $500.000 (5.000 units X $100 per Unit =

    $500.000). For the Gasoline I put in the Unit field 20/h and that means that I will spend 20 liters (or gallons)

    per hour. MS PROJECT 2010 has calculated that the cost for the Gasoline is $4.000 (20 liters per hour X $5

    per Unit X 5 days X 8 hour per day = 20 X $5 X 5 X 8 = $4.000).

    What will happen if I change duration of the task Pouring the concrete from 5 to 10 days? Lets see.

    I will choose the Cost table again and I will get:

    The Total cost is now $508.000. Why? MS PROJECT 2010 has calculated that the cost for the Concrete is

    $500.000 (5.000 units X $100 / Unit = $500.000), and it does not depend of the Task duration, since I put in

    the Unit field 5.000. For the Gasoline I put in the Unit field 20/h and that means that I will spend 20 liters (or

    gallons) per hour. MS PROJECT 2010 has calculated that the cost for the Gasoline is now $8.000 (20 lites per

    hour X $5 per Unit X 10 days X 8 hour per day = 20 X $5 X 10 X 8 = $8.000), and the Total cost for this task is

    $508.000.

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    4 of 11 4/20/2012 1:07 PM

  • So, if you have a Material resource which doesnt depends of the Task duration you should put the number in

    the Unit field when you are assigning Material Resource to the Task.

    If have a Material resource which does depends of the Task duration you should put the number in the Unit

    field and how much do you spend per time (hour, day, week, etc.). This is time depending Material resource.

    Now I will show you how to work with Cost Resources

    First I will define resources needed for my task.

    John the Trainer is Work resource and his standard rate is $100 per hour.

    Airplane ticket is Cost resource and it does not have the defined price yet.

    Now I will define task called Training

    In the first example I will assign only cost resource to the task.

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    5 of 11 4/20/2012 1:07 PM

  • I assign Airplane ticket to the task and I told the MS project that it costs $1000.

    I will now assign John the Trainer to the task.

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    6 of 11 4/20/2012 1:07 PM

  • And I got:

    Duration, Start and Finish date are the same, so everything seems O.K

    Here is another example. Suppose that I assigned only cost resource (Airplane ticket) to the Task (as it is shown

    in 3 picture above). Now I will mark the task as 100% completed.

    Everything looks fine! But, suppose that you forgot to assign John the Trainer to the task AFTER you marked the

    task 100% completed. I will assign John now:

    rd

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    7 of 11 4/20/2012 1:07 PM

  • Now look what happens:

    Duration is now 0 days (milestone???) with unchanged Start and End date?

    It seems like a bug. And you will get the same thing if you assign both resources (Airplane

    ticket and John the Trainer) to the task and then, after you mark the task as

    100% completed, you remove John the Trainer.

    What will happen if you do not have cost resource (airplane ticket) assigned with

    the task, and you assign Work resource (John the Trainer) with the task AFTER you

    mark the task 100% completed? I will assign John now:

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    8 of 11 4/20/2012 1:07 PM

  • and I will get:

    So, obviously the problem is with the cost resource type (in our example the Airplane ticket).

    What is the solution? If you have to add or remove work resource to the task after it is completed (25%, 50%,

    75%, or 100%) first mark the task as 0% completed, then add or remove the resource to the task and after that

    mark task as completed again.

    I will show to you what happens if I add Work resource (John the Trainer) with the task AFTER I marked it as

    50% completed and I already have work resource assigned to the Task. I will assign John now:

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    9 of 11 4/20/2012 1:07 PM

  • About Nenad Trajkovski

    Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in

    Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking,

    manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different

    companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge

    in information technologies and financial services. Today he works as a business consultant for ERP systems (MBS DYNAMICS

    NAV) and as a Project Manager in ESKA d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center

    in Varadin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best

    lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS

    SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI

    Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project

    Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist -

    Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

    and I will get:

    Duration is only 50% of expected (1,5 day instead of 3 days) and this is bug.

    So, once again, first mark the task as 0% completed, and then add or remove the resource to the task and after

    that mark task as completed again.

    Bye!

    Be the first to like this post.

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    10 of 11 4/20/2012 1:07 PM

  • View all posts by Nenad Trajkovski This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management and tagged MS PROJECT, MS PROJECT -Resources, MS PROJECT 2010, PMI, Project Management. Bookmark the permalink.

    Nenad TrajkovskiTheme: Twenty Ten Blog at WordPress.com.

    Assigning Material and Cost Resources in MS PROJECT 2010 | Ne... http://ntrajkovski.wordpress.com/2011/11/07/assigning-material...

    11 of 11 4/20/2012 1:07 PM