Skyway 126 Wind Energy Design and Operations Report

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Appendix IV

Radar and Radio Communications Impact Assessment

Page 2: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy

Potential Impacts on Radio Communication,

Radar and Seismoacoustic Systems

Prepared by: M.K. Ince and Associates Ltd.

Prepared for: Cloudy Ridge Wind Park LP

June 14, 2013

Page 3: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

June 14, 2013

Cloudy Ridge Wind Park LP

c/o WindWorks Power Corp.

346 Waverly Street

Ottawa, Ontario

K2P 0W5

Attention: Dr. Ingo Stuckmann

Reference: Skyway 126 Wind Energy, Radar and Radio Communications Impact

Assessment Report

Dear Dr. Stuckmann,

We are pleased to present a copy of the Radar and Radio Communications Impact Assessment Report for

Skyway 126 Wind Energy project. This report summarizes the findings of M.K. Ince and Associates

Ltd.’s assessment of the potential impacts of Skyway 126 Wind Energy on Radio Communication, Radar

and Seismoacoustic Systems. The assessment methods follow the protocol laid out in the document

Technical Information and Coordination Process Between Wind Turbines and Radiocommunication and

Radar Systems (RABC/CanWEA, 2012), produced jointly by the Radio Advisory Board of Canada and

the Canadian Wind Energy Association.

The results of this assessment indicate that impacts to radio communication, radar and seismoacoustic

system from the Skyway 126 Wind Energy project are anticipated to be limited. It will be included as part

of the Renewable Energy Approval Application package to be submitted to the Ministry of the

Environment for the Skyway 126 Wind Energy project, as an appendix to the Design and Operations

Report.

Please feel free to contact us if you have any questions or concerns.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Martin Ince, P. Eng.

Page 4: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. i June 14, 2013

Table of Contents

SKYWAY 126 WIND ENERGY .................................................................................................................................. 1

1 INTRODUCTION ............................................................................................................................................. 1

1.1 PROJECT OVERVIEW .......................................................................................................................................... 1 1.2 REGULATORY AND REPORTING REQUIREMENTS ....................................................................................................... 1

2 RADIO COMMUNICATION, RADAR AND SEISMOACOUSTIC SYSTEMS IN THE STUDY AREA ............................ 4

2.1 RADIO COMMUNICATION SYSTEMS....................................................................................................................... 4 2.2 ENVIRONMENT CANADA WEATHER RADAR ............................................................................................................ 4 2.3 SEISMOACOUSTIC STATIONS ................................................................................................................................ 4 2.4 AIR TRAFFIC CONTROL RADAR AND AIRFIELDS ........................................................................................................ 4 2.5 ADDITIONAL CONSULTATION ............................................................................................................................... 4

3 CONSULTATION ZONES FOR RADIOCOMMUNICATION SYSTEMS .................................................................. 5

3.1 POINT TO POINT SYSTEMS .................................................................................................................................. 5 3.2 BROADCAST TRANSMITTERS ................................................................................................................................ 5 3.3 OVER-THE-AIR RECEPTORS ................................................................................................................................. 5 3.4 CELLULAR, LAND MOBILE, AND POINT TO POINT SYSTEMS BELOW 890 MHZ ............................................................... 6 3.5 SATELLITE GROUND STATIONS ............................................................................................................................. 6 3.6 VHF OMNIRANGE BEACONS ............................................................................................................................... 6

4 CONSULTATION ZONES FOR SKYWAY 126 WIND ENERGY.............................................................................. 7

4.1 MANDATORY CONSULTATIONS ............................................................................................................................ 7 4.2 ANALYSIS OF SPECTRUM DIRECT DATABASE SEARCH RESULTS .................................................................................... 8

5 CONCLUSIONS & RECOMMENDATIONS ....................................................................................................... 10

5.1 RECOMMENDATIONS ....................................................................................................................................... 10

6 QUALIFICATIONS AND LIMITATIONS ........................................................................................................... 11

7 REFERENCES ................................................................................................................................................ 12

List of Figures FIGURE 1-1: SKYWAY 126 WIND ENERGY PROJECT – PROJECT OVERVIEW MAP ............................................................................ 2 FIGURE 1-2: SKYWAY 126 WIND ENERGY PROJECT -- RADAR AND RADIO COMMUNICATION SYSTEMS MAP ....................................... 3

List of Tables TABLE 4-1 SUMMARY OF MANDATORY CONSULTATIONS ........................................................................................................... 7 TABLE 4-2 IMPACT ON RADIOCOMMUNICATION AND RADAR SYSTEMS ......................................................................................... 8

List of Appendices Appendix A Radio Communication Systems in the Project Area Appendix B Consultation

Page 5: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 1 June 14, 2013

1 INTRODUCTION

1.1 Project Overview

Cloudy Ridge Wind Park LP (the Proponent) proposes to build the Skyway 126 Wind Energy project, a

10 MW Class 4 Wind Energy Generation Facility, on privately-owned agricultural lands within the

Municipality of Grey Highlands near the town of Badjeros. It will consist of five (5) REpower MM92

wind turbines of 2 MW each, located in five (5) proposed locations. The REpower MM92 has a sound

power level of 103.2 dB(A). The turbines are three bladed horizontal axis wind turbine generators that

will be mounted on 100 m hubs and have blade diameters of 92.5 m, for a maximum total height of

146.25 m above grade. Figure 1-2 depicts all radar and radio communication systems within the project

area. The project turbines will be bounded to the north by South Line C, to the east by Grey Road 9, to the

South by Grey Road 9, and to the west by Road 57A. In addition, project cabling will be constructed

along South Line C, Road 63, and 4th Concession B Road. A Power Purchase Agreement (PPA) has been

acquired for the project under Ontario’s Feed-In Tariff (FIT) Program.

1.2 Regulatory and Reporting Requirements

The Green Energy and Green Economy Act, passed in the Province of Ontario in 2009, mandates a

Renewable Energy Approval (REA) process under the Environmental Protection Act, Ontario Regulation

359/09 for specified classes of renewable energy projects. The Skyway 126 Wind Energy project is

subject to this process, which will evaluate the project’s environmental impacts and propose measures to

mitigate or avoid them.

This report summarizes the findings of M.K. Ince and Associates Ltd.’s assessment of the potential

impacts of the Skyway 126 Wind Energy project on Radio Communication, Radar and Seismoacoustic

Systems. The assessment methods follow the protocol laid out in the document Technical Information

and Coordination Process Between Wind Turbines and Radiocommunication and Radar Systems

(RABC/CanWEA, 2012), produced jointly by the Radio Advisory Board of Canada and the Canadian

Wind Energy Association.

The RABC/CanWEA document outlines the procedure for determining consultation zones with respect to

Radio Communication, Radar and Seismoacoustic Systems based on the characteristics of each system. In

the event of an overlap between the project area and the consultation zone of a communication system,

consultation with the system operator is recommended.

Page 6: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 2 June 14, 2013

Figure 1-1: Skyway 126 Wind Energy Project – Project Overview Map

Page 7: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 3 June 14, 2013

Figure 1-2: Skyway 126 Wind Energy Project -- Radar and Radio Communication Systems Map

Page 8: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 4 June 14, 2013

2 RADIO COMMUNICATION, RADAR AND SEISMOACOUSTIC

SYSTEMS IN THE STUDY AREA

2.1 Radio Communication Systems

The Spectrum group of Industry Canada manages the use of the electromagnetic spectrum in Canada.

Their database was searched on November 26, 2012 for all stations within 60 km of the project site. The

analysis of the search results is discussed in Section 4.2. Radio communication systems surrounding the

project area are depicted in Figure 1-2, with further details on the system included in Appendix A.

2.2 Environment Canada Weather Radar

The nearest Environment Canada weather radar station is WKR, located in King City, ON. This station is

approximately 65 km from the nearest turbine in the Skyway 126 Wind Energy project. The WKR station

is located well outside the 50 km consultation zone specified in the RABC/CanWEA document.

2.3 Seismoacoustic Stations

The Natural Resources Canada seismoacoustic station closest to the site is the SADO station, located near

Sadowa, ON. This station is approximately 150 km from the Skyway 126 Wind Energy project. The

proposed wind farm is outside the recommended 50 km consultation zone for this station.

2.4 Air Traffic Control Radar and Airfields

The consultation zone around a military or civilian airport is a minimum of 10 km as outlined in the

RABC/CANWEA Guidelines and could extend up to 80 km depending on the type of Air Traffic Control

(ATC) radar present. The nearest airport for which records were found in MKI’s desktop analysis is the

Collingwood Regional Airport, approximately 30 km northeast of the project site. NAV Canada was

contacted and supplied with a turbine layout to ensure no potential for interference with the equipment or

operations at this or any other air traffic control radars. NAV Canada has indicated that no impacts are

anticipated.

2.5 Additional Consultation

RABC and CanWEA mandate correspondence with certain agencies to coordinate the assessment of

possible wind turbine effects on telecommunication and radar systems. These agencies include:

The Department of National Defense

Royal Canadian Mounted Police

Canadian Coast Guard

Environment Canada.

Public Safety Agencies

Page 9: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 5 June 14, 2013

Responses from correspondence with these agencies are outlined in Section 4.1 and included in

Appendix B.

3 CONSULTATION ZONES FOR RADIOCOMMUNICATION SYSTEMS

3.1 Point to Point Systems

The RABC/CanWEA document prescribes the consultation zone for a point to point link as being a 1 km

radius around the transmission and reception sites, and a cylinder around the signal path with a diameter

defined as:

Where Lc = Diameter of the cylinder, m

D = Path length, km

F = Signal frequency, GHz

R = Rotor Diameter, m

The data from the Spectrum Direct database search were used to determine how closely each signal

passes by the project area. All link stations transmitting and receiving within 60 km of the project area

centre were mapped. Consultation zones were calculated for any signal paths passing near or through the

project area.

Rogers Communication Partnership operates one point-to-point system within the consultation zone of

the proposed project and was contacted with the turbine coordinates. Discussions with Rogers

Communications initially identified potential impacts to one microwave path which have since been

addressed by shifting the proposed turbine locations outside the anticipated zone of interference. Further

information regarding the point to point systems and license holder are summarized in Figure 1-2 and

Appendix A. A summary of correspondence is included in Appendix B.

3.2 Broadcast Transmitters

As recommended by the RABC/CanWEA document, TV or radio broadcast transmitters have a

consultation zone of 2 km for FM and TV stations, and 15 km for an AM directional antenna system and

5 km for an omnidirectional AM antenna system. The proposed Skyway 126 Wind Energy project is

within the consultation zone of Bayshore Broadcasting Corporation’s proposed FM radio broadcast

station with the call sign CFDC-FM, identified in the Industry Canada’s Spectrum Direct Database.

Consultation with Bayshore Broadcasting Corporations has indicated that this station has not yet been

constructed and that due to its separation distance from the Skyway 126 Wind Energy project, no impacts

would be anticipated.

3.3 Over-the-Air Receptors

For broadcast receivers, which MKI assumes to be any residence, the consultation zone is defined as:

Page 10: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 6 June 14, 2013

1. 15 km for Analog TV receivers

2. 10 km for Digital TV receivers.

There are several nearby communities within these consultation zones. Should reception problems arise

after construction of the wind farm, mitigation measures will need to be discussed with the affected

residents.

3.4 Cellular, Land Mobile, and Point to Point Systems below 890 MHz

The RABC document prescribes a 1 km radius consultation zone for cellular networks, land mobile

networks, and point to point systems below 890 MHz. No such systems exist within 1 km of the proposed

wind farm site, and therefore no consultation is required.

3.5 Satellite Ground Stations

Wind turbines may also interfere with a satellite link if located between the satellite and a ground station

receiver. The RABC/CanWEA guidelines recommend a 500 m radius consultation zone around satellite

ground stations. Beyond 500 m, the consultation zone is a cone extending up to 10 km along the

transmission path, with a width defined by the following:

Where D= Distance from the ground satellite antenna, km

F= Signal frequency, GHz

B= Turbine rotor diameter, m

There are no satellite ground stations within 10 km of any of the proposed turbines. No interference issues

are anticipated.

There could, however, be satellite TV receivers at some of the residences within 10 km of the project site.

If reception issues arise after construction of the proposed turbines, mitigation measures will have to be

discussed with affected residents on a case-by-case basis.

3.6 VHF OmniRange Beacons

VHF OmniRange (VOR) is a type of short-range air navigation beacon. The RABC/CanWEA document

prescribes a consultation zone of 15 km around these facilities. No VOR beacons exist within 15 km of

the Skyway 126 Wind Energy project.

Page 11: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 7 June 14, 2013

4 CONSULTATION ZONES FOR SKYWAY 126 WIND ENERGY

4.1 Mandatory Consultations

The Department of National Defense (DND), Royal Canadian Mounted Police (RCMP), Environmental

Canada, Canadian Coast Guard and various public safety agencies were contacted and supplied with a

turbine layout. The results of these consultations are summarized in Table 4-1 below and included in

Appendix B.

Table 4-1 Summary of Mandatory Consultations

Agency Consulted Response

DND – Radar, air defense, ATC, airport and NAVAIDS No impacts anticipated

DND – Radiocommunication systems No impacts anticipated

Environment Canada No impacts anticipated

Canadian Coast Guard No impacts anticipated

RCMP No response received as of June 14, 2013

NAV Canada No impacts anticipated

Ontario Provincial Police No impacts anticipated

Grey Highlands Fire Department No response received as of June 14, 2013

Page 12: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 8 June 14, 2013

4.2 Analysis of Spectrum Direct Database Search Results

Table 4-2: Impact on Radiocommunication and Radar Systems

System Type Recommended

Consultation Zone around

system

Overlap

with

Consultation

Zones

Comments Effect Assessment

Point-to-Point Systems above

890 MHz: Microwave Links

1 km around the tower, Cylinder

of Lc around between the

transmit and receive locations

N Turbine 4 was initially within the

consultation zone of the following point-to-

point link owned by Rogers:

XJV217-XJV210

Following consultation

with Rogers, Turbine 4

was moved to mitigate

impacts.

Broadcast transmitters AM, FM

and TV stations Multi-channel

Multipoint Distribution Service

(MMDS) Systems

AM Station: 5 km for an

omnidirectional antenna system

and 15 km for a directional

antenna system

FM Station: 2.0 km

TV Station: 2.0 km

Y All turbines are within 5 km of a FM

Broadcast transmitter, with the call sign

CFDC-FM.

Consultation with the

tower operators

(Bayshore Broadcasting

Corporation) indicates

that no impacts are

anticipated.

Over-the-Air Reception TV

off-air pickup Consumer TV

receivers

Analog TV station: 15 km

Digital TV station: 10 km

Y There could be residences receiving over-

the-air TV service near the project site.

Television reception

issues at local residences

are possible; if issues

arise, mitigation will be

required.

Cellular type networks, Land

Mobile Radio networks and

Point-to-Point Systems below

890 MHz

1 km around call towers

Cylinder of Lc around the path

between the transmit and receive

locations

N There are no cellular type networks within 5

km of any turbines.

There are no Land Mobile Radio networks

within 15 km of any turbines.

There are no point to point systems below

890 MHz within 5 km of any turbines.

The turbines have no

foreseeable impacts on

cellular type networks,

land mobile radio

networks and point to

point systems below 890

MHz.

Page 13: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 9 June 14, 2013

System Type Recommended

Consultation Zone around

system

Overlap

with

Consultation

Zones

Comments Effect Assessment

Satellite Systems

Direct-to-Home (DTH),

Satellite Ground Stations

500 m

Beyond 500m, a cone of width

Lc extending up to 10 km from

the satellite ground station

Y There are no satellite ground stations within

10 km of any turbines. However, there may

be residences within 10 km receiving

satellite TV service.

The turbines have no

foreseeable impacts on

the satellite systems.

VHF OmniRange (VOR) 15 km N There are no VOR systems within 15 km of

any turbines.

The turbines have no

foreseeable impacts on

VOR systems.

Page 14: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 10 June 14, 2013

5 CONCLUSIONS & RECOMMENDATIONS

Industry Canada’s Spectrum database was searched for radiocommunication systems near the Project

Location. Rogers Communications Partnership and Bayshore Broadcasting Corporation both operate

infrastructure within the consultation zones recommended by RABC/CanWEA and have been contacted

and informed of the proposed turbine locations to discuss potential impacts to communications resulting

from the Skyway 126 Wind Energy project. Rogers Communications initially identified potential

interference with its network, however, through consultation, the proposed layout has been altered to

mitigate any impacts. Bayshore Broadcasting has indicated that no impacts are anticipated.

Various public agencies were also consulted as mandated by RABC and CanWEA. No negative impacts

have been identified by these agencies to date; however, several responses are still pending as of June 14,

2013, at the time of this assessment. Appendix B includes a summary of the parties contacted for

consultation, with their contact information and any responses received with regards to the Skyway 126

Wind Energy .

The results of this assessment indicate that impacts to radio communication, radar and seismoacoustic

system from the Skyway 126 Wind Energy project are anticipated to be limited.

5.1 Recommendations

Based on the results of this study, the following recommendations were made:

Complaints of degraded quality related to direct-to-home satellite receivers, television and FM

radio receivers within 15 km of the wind farm should be monitored and if need be mitigated post-

construction by movement of receiver dish or other means agreed upon by the proponent and

impacted party.

Continue ongoing consultation with public and private agencies.

Page 15: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 11 June 14, 2013

6 QUALIFICATIONS AND LIMITATIONS

M. K. Ince & Associates Ltd. (MKI) has prepared this report in accordance with its proposal and

information provided by its Client. The information and analysis contained herein is for the sole benefit of

the Client and save for regulatory review purposes may not be relied upon by any other person.

MKI’s assessment was made in accordance with guidelines, regulations and procedures believed to be

current at this time. Changes in guidelines, regulations and enforcement policies can occur at any time

and such changes could affect the conclusions and recommendations of this report.

The reports, maps and related documents may rely on information provided to MKI by the Client. This

information may include but is not limited to manufacturer and construction specifications and other

related information. Maps are created using a Geographic Information System (GIS) that compiles

records, information, and data from various sources which may contain errors. While we have referred to

and made use of reports, maps and geospatial data and specifications prepared by others, we assume no

liability for the accuracy of the information contained within.

Maps and documents made available by MKI are not legal surveys and are not intended to be used as

such. No original surveying is included as part of these maps. If any contradictions exist between this

document and relevant municipal, provincial or federal laws, regulations, codes, or policies, the text of the

laws, regulations, codes or policies will be the legal authority.

Page 16: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. 12 June 14, 2013

7 REFERENCES

Industry Canada, Spectrum Management and Telecommunications. (2012). Spectrum Direct Database.

Retrieved , November 26, 2012, from Industry Canada:

https://sd.ic.gc.ca/pls/engdoc_anon/web_search.geographical_input

Radio Advisory Board of Canada (RABC)/Canadian Wind Energy Association (CanWEA). (2012).

Technical Information and Coordination Process Between Wind Turbines and

Radiocommunication and Radar Systems

Page 17: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Appendix A: Radio Communication Systems in Project Area

Page 18: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Radio Communication Systems illustrated in Figure 1-3

System Call Sign Link

Call Sign

Tx

Frequency

(MHz)

Rx

Frequency

(MHz)

Tx Antenna

Azimuth

(deg)

Rx Antenna

Azimuth

(deg)

Licensee Consultation

Radius (m)

Distance

(m)

Point to Point

Signal Path

XJV217 XJV210 14770 15245 187.1 187.1 Rogers

Communications

Partnership

75 180

Point to Point

Signal Path

XJV217 CIN445 18662.5 15245 7.1 7.1 Rogers

Communications

Partnership

66 >1500

Point to Point

Signal Path

XJV217 VEL678 6113.2 6365.3 162.2 162.2 Rogers

Communications

Partnership

90 >1500

Point to Point

(Cellular)

SITE703716 - 869 824 - - Rogers

Communications

Partnership

1000 >1500

Broadcast Shelburne - 104.9 - - - Bayshore

Broadcasting

Corporation

2000 1100

Page 19: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Appendix B: Consultation

Page 20: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Summary of Mandatory Consultation

Party to Consult Contact Signal Type Call Sign Response

Recommended Consultations

Rogers

Communication

Corporation

Milan Vujosevic Point to point XJV210 to XJV217 No impacts

anticipated

Bayshore

Broadcasting

Corporation

Robert Coyne FM Broadcasting

Station

Shelburne No impacts

anticipated

Mandatory Consultations

Department of

National Defense

(DND)

Mario Lavoie Radiocommunication

Systems

- No impacts

anticipated

Adin Switzer Military Air Defense

and ATC Radars

- No impacts

anticipated

Royal Canadian

Mounted Police

- Radar - No response

received

Canadian Coast

Guard

Martin Grégoire Vessel Traffic System

Radars

- No impacts

anticipated

Environment

Canada

Carolyn J. Rennie Weather Radars - No impacts

anticipated

NAV Canada Diane Levesque Civilian Radar and Air

Navigation Equipment

- No impacts

anticipated

Ontario Provincial

Police

Mark Fox Ground

Communications

- No impacts

anticipated

Grey Highlands

Fire Department

- Ground

Communications

- No response

received

Page 21: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Bayshore Broadcasting

Page 22: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Carolyn Truong <[email protected]>

Wind farm

Robert Coyne <[email protected]> Mon, Nov 19, 2012 at 11:42 AM

To: [email protected]

Hi Carlyn

Sorry for the late reply on your request but at this time Bayshore Broadcasting has not commenced a broadcasting

operation at this location the tower site is only proposed. But as the the wind farm is over 1000 meters from this site

I see no impact to the operation of a transmitter site at this location. We operation a site in Bruce county with a wind

farm that is the same as the proposed site with no effect on our operation.

Robert Coyne

Bayshore Broadcasting Corp.

Mkince.ca Mail - Wind farm https://mail.google.com/mail/u/0/?ui=2&ik=f451843616&view=pt&searc...

1 of 1 11/19/2012 12:34 PM

Page 23: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Query Regarding Potential Impacts of Skyway 126 Wind Farm on Bayshore Broadcasting

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Nov 19, 2012 at 10:24 AM

To: [email protected]

Cc: Carolyn Truong <[email protected]>, David Barrie <[email protected]>

Hi Robert,

I would like to check in on this issue as we have not yet received a response from Bayshore Broadcasting. Please let me know if you require

further information from us or if there is perhaps someone else that would be a more appropriate point of contact.

I have attached the turbine coordinates in this message. Thanks for your time and cooperation!

Best Regards,

Carolyn Truong

On Thu, Aug 23, 2012 at 10:04 AM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:

Hi Robert,

I'd just like to follow up on my previous email sent July 16, 2012 regarding the potential for interference of communications at Bayshore

Broadcasting as a result of the proposed Skyway 126 Wind Farm in the Municipality of Grey Highlands.

Please advise if you foresee any impacts resulting from the proposed wind farm.

Best Regards,

Carolyn Truong

On Mon, Jul 16, 2012 at 12:09 PM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:

Good morning Robert,

My name is Carolyn, I am contacting you on behalf of M. K. Ince and Associates Ltd, a consulting firm that has been retained to conduct

environmental studies for the proposed Skyway 126 Wind Farm in the Municipality of Grey Highlands, Ontario. According to the

Spectrum Direct database, Bayshore Broadcasting Corporation manages and operates communications infrastructure near the

proposed project area.

The Spectrum Direct database indicates that the following FM Broadcast station is in the vicinity of the proposed project:

Call Sign: Shelburne

Lat/Long (NAD83): 44°14'09"/-80°17'19"

The turbine coordinates are attached.

Please advise if you foresee any potential impacts to your telecommunications network as a result of the proposed wind farm.

Best Regards,

Carolyn Truong

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Mkince.ca Mail - Query Regarding Potential Impacts of Skyway 126 Win... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

1 of 2 11/19/2012 12:35 PM

Page 24: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Query Regarding Potential Impacts of Skyway 126 Win... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

2 of 2 11/19/2012 12:35 PM

Page 25: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Coast Guard

Page 26: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

XNCR, Windfarm Coordinator <[email protected]> Fri, May 25, 2012 at 9:53 AM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>Cc: Genevieve Brown <[email protected]>, Karla Klein <[email protected]>

Hello, I apologize for the delay in responding to you. Since the transfer of the Wind Farm Coordinator reponsibility to me, I was not given e-mailaccess right away.

The closest CCG system is a communication site located 25 km from your proposed wind farm (Skyway 126). Therefore, we do not

anticipate any interference problems.

Regards,

Martin Grégoire, P. EngCanadian Coast Guard

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: April 27, 2012 2:18 PM

To: XNCR, Windfarm Coordinator

Cc: Genevieve Brown; Karla Klein

Subject: Re: Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

Hello,

Since we last contacted you on April 19th regarding potential interference due to the Skyway 126 Wind Farm, a sixth turbine has beenadded to the wind farm. Please find attached the coordinates of all six turbines.

Please contact us if you have any concerns with respect to the proposed turbines.

Thank you,

Genevieve Brown

On Thu, Apr 19, 2012 at 2:02 PM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:

Dear coordinator,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines onradio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince iscompleting a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposedSkyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm containsfive turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your help,

Genevieve Brown

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Mkince.ca Mail - Skyway 126 Wind Farm - Impacts on Radar and Radio... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

1 of 1 11/19/2012 12:43 PM

Page 27: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Department of National Defense

Page 28: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

6/3/13 Mkince.ca Mail - Fwd: Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros, Ont - REVISED LAYOUT - WTA-2056

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=inbox&msg=13efbc553c23e43f 1/1

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros, Ont - REVISEDLAYOUT - WTA-2056

[email protected] <[email protected]> Fri, May 31, 2013 at 2:06 PMTo: [email protected]

Thank you. Project revision noted.

Adin SwitzerCaptAEC Liaison OfficerCCISF/ESICCATESS/ESTTMADéfense nationale | National Defence8 Wing Trenton, Astra, ON K0K 3W0TEL: 613 392-2811 Ext4834 (CSN: 827-4834)FAX: 613 965-3200Gouvernement du Canada | Government of Canada

ü Please consider the environment before printing this email | S'il vous plaît pensez à l'environnement a

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]] Sent: Tuesday, 28, May, 2013 11:34 AMTo: Switzer Capt AB@ATESS@TrentonCc: Hanna VovkSubject: Re: Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros, Ont - REVISED LAYOUT - WTA-2056

[Quoted text hidden]

[Quoted text hidden]

[Quoted text hidden]

Please consider the environment before printing this email | S'il vous plat pensez l'environnement a

-- Carolyn Truong, E.I.T.

M.K. Ince and Associates Ltd.11 Cross Street, Dundas, ON L9H 2R3Phone: 905-628-0077 ext. 246Fax: 905-628-1329Email: [email protected]

--

M.K. Ince and Associates Ltd.11 Cross St., Dundas, ON L9H 2R3Phone: 905-628-0077Fax: 905-628-1329*http://*www.mkince.ca

Page 29: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - Fwd: Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros, Ont - REVISED LAYOUT - WTA-2056

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebc68e5265e99 1/1

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros, Ont - REVISEDLAYOUT - WTA-2056

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, May 28, 2013 at 11:34 AMTo: [email protected]: Hanna Vovk <[email protected]>

Dear Adin,

Please be advised that the project layout for the Skyway 126 Wind Energy project located near Badjeros, Ont (WTA-2056) has beenupdated since our last correspondence (December 3, 2012). Turbine 6 has been dropped. Turbines 1-5 remain in the same position. Arevised layout is attached.

If you have any questions or concerns, please do not hesitate to contact us.

Thank you,

M.K. Ince and Associates Ltd.

[Quoted text hidden]

--

M.K. Ince and Associates Ltd.11 Cross St., Dundas, ON L9H 2R3Phone: 905-628-0077Fax: 905-628-1329http://www.mkince.ca

Skyway 126 Wind Energy Project -- Turbine Coordinates (2013-05-28).pdf168K

Page 30: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros Ont -WTA-2056

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Nov 19, 2012 at 12:57 PM

To: [email protected]

Cc: Carolyn Truong <[email protected]>, [email protected]

Hi Adin,

Please be advised that since our last correspondence, the turbine layout of the proposed Skyway 126 Wind Farm has

been revised. The coordinates of several turbines have been altered and I have attached the new turbine locations to

this message. We are in the process of finalizing this project and do not anticipate any further revisions to the layout at

this point.

Thanks for your continued time and cooperation. Please confirm that the proposed project is not anticipated to impact

DND radar and flight operations.

Best Regards,

Carolyn Truong

[Quoted text hidden]

[Quoted text hidden]

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Detailed Analysis - No Interference - Skyway 126 Win... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&q=s...

1 of 1 5/27/2013 6:40 PM

Page 31: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros Ont -WTA-2056

[email protected] <[email protected]> Thu, May 10, 2012 at 1:35 PM

To: [email protected], [email protected]

Cc: [email protected]

Genevieve,

We have completed the detailed analysis of your proposed site, Skyway 126 Wind Farm, located near Badjeros, Ont

(WTA-2056). The results of our detailed analysis have shown that there is likely to be minimal interference with DND

radar and flight operations.

Therefore, as a result of these findings we have no objections with your project as submitted (attached).

When confirmed, we would ask that you advise this office of the construction date for subject project in order to advise

our flying operations at CFB Borden.

If however, the layout were to change/move, please re-submit that proposal for another assessment using the

assigned WTA number listed above. The concurrence for this site is valid for 24 months from date of this email. If the

project should be cancelled or delayed during this timeframe please advise this office accordingly.

It should be noted that our office looks at each submission on a case by case basis and as such, concurrence on this

submission in no way constitutes a concurrence for similar projects in the same area, nor does it indicate that similar

concurrence might be offered in another region.

Finally, the concurrence offered in this email extends only to the subject projects and current proponent. Should the

project or any part of it be altered, or be sold to another developer, this office must be notified and we reserve the right

to reassess the project.

Thank you for your patience on this matter and for considering DND radar and airport facilities in your project

development process.

If you have any questions feel free to contact me.

Thank you.

<<Turbine Information 2012-04-27.pdf>>

Adin Switzer

Capt

AEC Liaison Officer

CCISF/ESICC

ATESS/ESTTMA

Défense nationale | National Defence

8 Wing Trenton, Astra, ON K0K 3W0

TEL: 613 392-2811 Ext4834 (CSN: 827-4834)

FAX: 613 965-3200

Gouvernement du Canada | Government of Canada

ü Please consider the environment before printing this email | S'il vous plaît pensez à l'environnement a

Turbine Information 2012-04-27.pdf

166K

Mkince.ca Mail - Detailed Analysis - No Interference - Skyway 126 Win... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&q=s...

1 of 1 5/27/2013 6:34 PM

Page 32: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Thomas Bernacki <[email protected]>

Feedback re. lighting of turbines at Skyway 126

Katie Meyer-Beck <[email protected]> Sat, Dec 8, 2012 at 9:26 PM

To: Thomas Bernacki <[email protected]>

Cc: Collin Branton <[email protected]>

Hi Tom:

as I mentioned to you earlier this week, on Dec. 5, 2012 at 12:37 p.m. I received a call from Rod Miskey from the

400th Squadrant of Borden near Feversham. His email address is [email protected]

MKI (Karla Klein) sent a request for feedback with a topographical map and a land use proposal on April 5, 2012.

Miskey reports that he is responsible for the helicopter operations out of the facility nearby to the project. Helicopter

fly-ins or approaches often happen at night with night vision goggles or under cloud cover. He also noted that

helicopters fly low -- approximately 50 feet over the tree tops.

he noted that often turbines are equipped with red LED lights, however, the issue with thos is that they are not visible

at night via night vision goggles

He requested that 1.) the turbine is equipped with at least one incandescent light; 2.) He mentioned that sometime

turbine manufacturers equip the turbines with three lights; could one of the three sockets be an infrared light?

We requested information about construction timelines. I indicated to him that while the precise timelines are

unknown, notifications will be placed in the local newspaper when the REA documents are ready, which will include

more information at that time.

Collin: please log this communication. Tom I trust you will include this in the REA reporting as required. I will notify

Ingo.

Thanks,

Katie

--

Katie Meyer-Beck

Renewable Energy Project Manager

M.K. Ince and Associates Ltd.

11 Cross Street

Dundas, Ontario, L9H 2R3

Tel: 905-628-0077 ext. 242

Fax: 905-628-1329

E-mail: [email protected]

www.mkince.ca

P Please consider the environment before printing this e-mail.

1 of 1

Page 33: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Carolyn Truong <[email protected]>

Detailed Analysis - No Interference - Skyway 126 Wind Farm, Badjeros, Ont -

REVISED LAYOUT - WTA-2056

[email protected] <[email protected]> Mon, Dec 3, 2012 at 8:46 AM

To: [email protected]

Cc: [email protected]

Carolyn,

We have completed the detailed analysis of your proposed site revised layout, Skyway 126 Wind Farm, located

near Badjeros, Ont (WTA-2056). The results of our detailed analysis have shown that there is likely to be minimal

interference with DND radar and flight operations.

Therefore, as a result of these findings we have no objections with your project revised layout as submitted

(attached).

If however, the layout were to change/move, please re-submit that proposal for another assessment using the

assigned WTA number listed above. The concurrence for this site is valid for 24 months from date of this email. If

the project should be cancelled or delayed during this timeframe please advise this office accordingly.

It should be noted that our office looks at each submission on a case by case basis and as such, concurrence on

this submission in no way constitutes a concurrence for similar projects in the same area, nor does it indicate that

similar concurrence might be offered in another region.

Finally, the concurrence offered in this email extends only to the subject projects and current proponent. Should the

project or any part of it be altered, or be sold to another developer, this office must be notified and we reserve the

right to reassess the project.

As with our previous correspondence, we would kindly ask that you advise this office of the construction date for

subject project in order to advise our flying operations at CFB Borden.

Thank you for your patience on this matter and for considering DND radar and airport facilities in your project

development process.

If you have any questions feel free to contact me.

Thank you.

<<Turbine Information 2012-11-16.pdf>>

Adin Switzer

Capt

AEC Liaison Officer

CCISF/ESICC

ATESS/ESTTMA

Défense nationale | National Defence

8 Wing Trenton, Astra, ON K0K 3W0

TEL: 613 392-2811 Ext4834 (CSN: 827-4834)

FAX: 613 965-3200

Gouvernement du Canada | Government of Canada

ü Please consider the environment before printing this email | S'il vous plaît pensez à l'environnement a

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Detailed Analysis - No Interference - Skyway 126 Wind... https://mail.google.com/mail/u/0/?ui=2&ik=f451843616&view=pt&searc...

1 of 1 12/3/2012 9:43 AM

Page 34: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm Impacts on Radar and Radio Communication

[email protected] <[email protected]> Mon, Nov 19, 2012 at 1:49 PM

To: [email protected]: [email protected]

I have reviewed your proposal in respect to DND's radio communication systems, and I have no objections or concerns.

Thank you for coordinating with DND.

Have a good Day.

Mr. Mario Lavoie

Spectrum Engineering Technician

National Defence | Défense nationale

Ottawa, Canada K1A 0K2

[email protected]

Telephone | Téléphone 613-992-3479

Facsimile | Télécopieur 613-991-3961

Government of Canada | Gouvernement du Canada

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Monday, 19, November, 2012 13:33 PM

To: Lavoie MJ@ADM(IM) J6 Coord@Ottawa-Hull

Cc: +WindTurbines@ATESS@TRENTON; Carolyn Truong; David Barrie

Subject: Re: FW: FW: Skyway 126 Wind Farm Impacts on Radar and Radio Communication

Hi Mario,

Please be advised that since our last correspondence, the turbine layout of the proposed Skyway 126 Wind Farm has been revised. Thecoordinates of several turbines have been altered and I have attached the new turbine locations to this message. My apologies for all theback and forth, but we are currently in the process of finalizing this project and do not anticipate any further revisions to the layout at thistime.

Thanks for your continued time and cooperation. Please confirm that the proposed project is not anticipated to impact DND radiocommunications systems.

Best Regards,Carolyn Truong

On Fri, Apr 27, 2012 at 2:22 PM, <[email protected]> wrote:

I have reviewed your proposal in respect to DND's radio communication systems, and I have no objections or concerns.

Thank you for coordinating with DND.

Have a good Day.

Mr. Mario LavoieSpectrum Engineering TechnicianNational Defence | Défense nationaleOttawa, Canada K1A [email protected] | Téléphone 613-992-3479Facsimile | Télécopieur 613-991-3961Government of Canada | Gouvernement du Canada

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]Sent: Friday, 27, April, 2012 14:14 PM

Mkince.ca Mail - Skyway 126 Wind Farm Impacts on Radar and Radio ... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 3 11/22/2012 10:45 AM

Page 35: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

To: Lavoie MJ@ADM(IM) J6 Coord@Ottawa-HullCc: Karla Klein; Genevieve BrownSubject: Re: FW: Skyway 126 Wind Farm Impacts on Radar and Radio Communication

Hello,

Since we last contacted you on April 19th regarding potential interference due to the Skyway 126 Wind Farm, a sixth turbine has beenadded to the wind farm. Please find attached the coordinates of all six turbines.

Please contact us if you have any concerns with respect to the proposed turbines.

Thank you,

Genevieve Brown

On Fri, Apr 20, 2012 at 7:51 AM, <[email protected]> wrote:

I have reviewed your proposal in respect to DND's radio communication systems, and I have no objections or concerns.

Thank you for coordinating with DND.

Have a good Day.

Mr. Mario LavoieSpectrum Engineering TechnicianNational Defence | Défense nationaleOttawa, Canada K1A [email protected] | Téléphone 613-992-3479

Facsimile | Télécopieur 613-991-3961Government of Canada | Gouvernement du Canada

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Thursday, 19, April, 2012 13:58 PM

To: Lavoie MJ@ADM(IM) J6 Coord@Ottawa-Hull; +WindTurbines@ATESS@TRENTON

Cc: Karla Klein; Genevieve Brown

Subject: Skyway 126 Wind Farm Impacts on Radar and Radio Communication

Dear coordinator,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of windturbines on radio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MKInce is completing a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. Theproposed Skyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The windfarm contains five turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your help,

Genevieve Brown

--M.K. Ince and Associates Ltd.11 Cross St., Dundas, ON L9H 2R3Phone: 905-628-0077Fax: 905-628-1329***http://***www.mkince.ca

--

M.K. Ince and Associates Ltd.

Mkince.ca Mail - Skyway 126 Wind Farm Impacts on Radar and Radio ... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

2 of 3 11/22/2012 10:45 AM

Page 36: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

*http://*www.mkince.ca

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Skyway 126 Wind Farm Impacts on Radar and Radio ... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

3 of 3 11/22/2012 10:45 AM

Page 37: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Initial Analysis Consultation Zone Infringement - Skyway 126 Wind Farm -

Badjeros, Ont - WTA-2056

Approvals M. K. Ince and Associates Ltd. <[email protected]> Fri, Apr 27, 2012 at 2:15 PM

To: [email protected]

Cc: Karla Klein <[email protected]>, Genevieve Brown <[email protected]>

Hello,

Since we last contacted you on April 19th regarding potential interference due to the Skyway 126 Wind Farm, a sixth

turbine has been added to the wind farm. Please find attached the coordinates of all six turbines.

Please contact us if you have any concerns with respect to the proposed turbines.

Thank you,

Genevieve Brown

[Quoted text hidden]

Turbine Information 2012-04-27.pdf

166K

Mkince.ca Mail - Initial Analysis Consultation Zone Infringement - Skywa... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 4/27/2012 2:28 PM

Page 38: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Initial Analysis Consultation Zone Infringement - Skyway 126 Wind Farm -

Badjeros, Ont - WTA-2056

[email protected] <[email protected]> Thu, Apr 26, 2012 at 9:40 AM

To: [email protected], [email protected]

Genevieve,

We have completed the initial analysis of the proposed wind farm under the project name Skyway 126 near

Badjeros, Ont. We have assigned a DND case number of WTA-2056, please include this number in any future

requests related to this site.

Our analysis has shown that the proposal falls within one (or more) of the DND consultation zones as outlined on our

website [ http://www.airforce.forces.gc.ca/8w-8e/units-unites/page-eng.asp?id=692 ] and in the RABC/CanWEA

document Technical Information and Coordination Process Between Wind Turbines and Radio Communication and

Radar Systems. As such this proposal will require a further more detailed analysis to determine any possible

effects/impact to the sites in question. The typical turn around time for a detailed analysis is from 2-6 weeks

depending upon the size and complexity of the site in question.

Thank you for your patience on this matter and for considering DND radar and airport facilities in your project

development process.

If you have any questions feel free to contact me otherwise, I will be in touch with you within a few weeks time with

our results.

Thank you.

Adin Switzer

Capt

AEC Liaison Officer

CCISF/ESICC

ATESS/ESTTMA

Défense nationale | National Defence

8 Wing Trenton, Astra, ON K0K 3W0

TEL: 613 392-2811 Ext4834 (CSN: 827-4834)

FAX: 613 965-3200

Gouvernement du Canada | Government of Canada

ü Please consider the environment before printing this email | S'il vous plaît pensez à l'environnement a

Mkince.ca Mail - Initial Analysis Consultation Zone Infringement - Skywa... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 4/26/2012 9:39 AM

Page 39: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Thu, Apr 19, 2012 at 1:57 PM

To: "mario.lavoie2" <[email protected]>, windturbines <[email protected]>

Cc: Karla Klein <[email protected]>, Genevieve Brown <[email protected]>

Dear coordinator,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the

impact of wind turbines on radio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary

stage of investigations and MK Ince is completing a communications impact assessment for the project as outlined

by RABC and CanWEA in their guidelines. The proposed Skyway 126 Wind Farm is located near the communities

of Badjeros, within the Municipality of Grey Highlands . The wind farm contains five turbines; the proposed

coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your help,

Genevieve Brown

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

2 attachments

Skyway 126_DND_2012-04-19.xls

69K

Skyway 126 Turbine Information 2012-04-19.pdf

165K

Mkince.ca Mail - Skyway 126 Wind Farm Impacts on Radar and Radio ... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 4/19/2012 2:06 PM

Page 40: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Environment Canada

Page 41: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Weather Radars Contact,National Radar Program [Ontario] <[email protected]>Thu, May 30, 2013 at 9:18

AM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>, "Weather Radars Contact,National Radar

Program [Ontario]" <[email protected]>

Cc: Hanna Vovk <[email protected]>

To whom it may concern,

Thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada, regarding your

wind energy intentions.

Our preliminary assessment of the information provided to us via e-mail on May 28, 2013 indicates that any potential

interference that may be created by the Skyway 126 Wind Energy Project in Grey County will not be severe. Although

we would prefer our radar view to be interference free, this is not always reasonable. As a consequence, we do not

have strong objections to the current proposal.

If your plans are modified in any manner (e.g. number of turbines, height, placement or materials) this analysis would

no longer be valid. An updated analysis must be conducted.

Please contact us at: [email protected].

Thank you for your ongoing cooperation and we wish you success.

Best Regards,

Carolyn

______________________Carolyn Wilson (Rennie)

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Toronto, Ontario M3H 5T4

Office : 3N-WS12

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&sear...

1 of 2 5/30/2013 10:32 AM

Page 42: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebb2ed6c58081 1/1

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, May 28, 2013 at 11:12 AMTo: "Weather Radars Contact,National Radar Program [Ontario]" <[email protected]>Cc: Hanna Vovk <[email protected]>

Dear Carolyn,

Please be advised that the project layout for the Skyway 126 Wind Energy project has been updated since ourlast correspondence (November 23, 2012). Turbine 6 has been dropped. Turbines 1-5 remain in the sameposition. A revised layout is attached.

Thank you,

M.K. Ince and Associates Ltd.

[Quoted text hidden]

Skyway 126 Wind Energy Project -- Turbine Coordinates (2013-05-28).pdf168K

Page 43: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Nov 19, 2012 at 12:22 PM

To: "Weather Radars Contact,National Radar Program [Ontario]" <[email protected]>

Hi Carolyn,

Please be advised that the proposed layout of the Skyway 126 Wind Farm has been altered slightly since we last

contacted you. Turbine 4 has been shifted approximately 50m east. I have attached the most recent turbine

coordinates to this message.

Can we confirm that this revised layout is still acceptable with regard to limited impacts to communications of the

Meteorological Service of Canada?

Thanks for your time and continued cooperation!

Best Regards,

Carolyn Truong

[Quoted text hidden]

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&cat...

1 of 1 5/24/2013 10:50 AM

Page 44: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Weather Radars Contact,National Radar Program [Ontario] <[email protected]>Tue, Nov 20, 2012 at 10:12

AM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>

Dear Mrs. Carolyn Truong,

Thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada, regarding your

wind energy intentions.

The information you have provided will be analyzed and we will endeavor a response to you as soon as possible.

We will aim to complete our analysis within 2-3 weeks.

If you require any additional information or clarification please do not hesitate to contact us at

[email protected] .

Best Regards,

______________________Carolyn Rennie

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Toronto, Ontario M3H 5T4

Office : 3N-WS12

[email protected]

Phone : 416-739-4931

-------------------------------------------------------

Carolyn Rennie

Le Programme Nationale de Radar

Service météorologique du Canada

Environnement Canada

4905, rue Dufferin

Toronto, Ontario M3H 5T4

Bureau : 3N-WS12

[email protected]

Téléphone : 416-739-4931

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&cat...

1 of 2 5/24/2013 10:49 AM

Page 45: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Weather Radars Contact,National Radar Program [Ontario] <[email protected]> Fri, Nov 23, 2012 at 8:36 AM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>, "Weather Radars Contact,National Radar Program [Ontario]"<[email protected]>

Dear Mrs. Carolyn Truong,

Thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada, regarding your wind energy intentions.

Our preliminary assessment of the updated information provided to us via e-mail on November 19, 2012 indicates that any potentialinterference that may be created by the Skyway 126 Wind Farm in Grey County will not be severe. Although we would prefer our radar

view to be interference free, this is not always reasonable. As a consequence, we do not have strong objections to the current proposal.

If your plans are modified in any manner (e.g. number of turbines, height, placement or materials) this analysis would no longer be valid. An updated analysis must be conducted.

Please contact us at: [email protected].

We would also be interested to know where the project is in terms of approval process (FIT/REA).

Thank you for your ongoing cooperation and we wish you success.

Best Regards,

Carolyn Rennie

______________________Carolyn Rennie

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Toronto, Ontario M3H 5T4

Office : 3N-WS12

[email protected]

Phone : 416-739-4931

-------------------------------------------------------

Carolyn Rennie

Le Programme Nationale de Radar

Service météorologique du Canada

Environnement Canada

4905, rue Dufferin

Toronto, Ontario M3H 5T4

Bureau : 3N-WS12

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 6 11/23/2012 9:43 AM

Page 46: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

[email protected]

Téléphone : 416-739-4931

______________________

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Monday, November 19, 2012 12:23 PM

To: Weather Radars Contact,National Radar Program [Ontario]

Subject: Re: Skyway 126 - Impacts on Radar and Radio Communication

Hi Carolyn,

Please be advised that the proposed layout of the Skyway 126 Wind Farm has been altered slightly since we last contacted you. Turbine4 has been shifted approximately 50m east. I have attached the most recent turbine coordinates to this message.

Can we confirm that this revised layout is still acceptable with regard to limited impacts to communications of the Meteorological Serviceof Canada?

Thanks for your time and continued cooperation!

Best Regards,Carolyn Truong

On Tue, Aug 14, 2012 at 3:33 PM, Weather Radars Contact,National Radar Program [Ontario] <[email protected]> wrote:

Dear Ms. Hannah Ince,

First of all, thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada, with an update of theSkyway 126 wind farm layout.

Our preliminary assessment of the updated information provided to us via email on August 14, 2012 indicates that any potentialinterference that may be created by the Skyway 126 Wind Farm in Grey County will not be severe. Although we would prefer our radarview to be interference free, this is not always reasonable. As a consequence, we do not have strong objections to the current proposal.

If your plans are modified in any manner (e.g. number of turbines, height, placement or materials) this analysis would no longer be valid. An updated analysis must be conducted.

Please contact us at: [email protected].

Thank you for your ongoing cooperation and we wish you success.

Best Regards,

______________________

Carolyn Rennie

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

2 of 6 11/23/2012 9:43 AM

Page 47: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Toronto, Ontario M3H 5T4

Office : 3N-WS12

[email protected]

Phone : 416-739-4931

Cell : 289-221-1084

-------------------------------------------------------

Carolyn Rennie

Le Programme Nationale de Radar

Service météorologique du Canada

Environnement Canada

4905, rue Dufferin

Toronto, Ontario M3H 5T4

Bureau : 3N-WS12

[email protected]

Téléphone : 416-739-4931

Cellulaire : 289-221-1084

______________________

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Tuesday, August 14, 2012 11:49 AM

To: Weather Radars Contact,National Radar Program [Ontario]

Subject: Re: Skyway 126 - Impacts on Radar and Radio Communication

Hello,

Since we last contacted you on April 27, the layout for the proposed Skyway 126 Wind Farm has shifted slightly. Please find attached thecoordinates of all the turbines.

If you have any questions or concerns about the proposed turbines please do not hesitate to ask us.

Thank you for you time,Hannah Ince

On Mon, Apr 30, 2012 at 9:45 AM, Weather Radars Contact,National Radar Program [Ontario] <[email protected]> wrote:

Dear Ms. Genevieve Brown,

Thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada, regarding your wind energy intentions.

Our preliminary assessment of the updated information provided to us via email on April 27, 2012 indicates that any potential interferencethat may be created by the Skyway 126 Wind Farm in Grey County will not be severe. Although we would prefer our radar view to beinterference free, this is not always reasonable. As a consequence, we do not have strong objections to the current proposal.

If your plans are modified in any manner (e.g. number of turbines, height, placement or materials) this analysis would no longer be valid. An updated analysis must be conducted.

Please contact us at: [email protected].

Thank you for your ongoing cooperation and we wish you success.

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

3 of 6 11/23/2012 9:43 AM

Page 48: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Best Regards,

______________________

Carolyn J. Rennie

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Toronto, Ontario M3H 5T4

Office : 3N-WS12

[email protected]

Phone : 416-739-4931

Cell : 289-221-1084

-------------------------------------------------------

Carolyn J. Rennie

Le Programme Nationale de Radar

Service météorologique du Canada

Environnement Canada

4905, rue Dufferin

Toronto, Ontario M3H 5T4

Bureau : 3N-WS12

[email protected]

Téléphone : 416-739-4931

Cellulaire : 289-221-1084

______________________

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Friday, April 27, 2012 2:13 PM

To: Weather Radars Contact,National Radar Program [Ontario]

Cc: Karla Klein; Genevieve Brown

Subject: Re: Skyway 126 - Impacts on Radar and Radio Communication

Hello,

Since we last contacted you on April 19th regarding potential interference due to the Skyway 126 Wind Farm, a sixth turbine has beenadded to the wind farm. Please find attached the coordinates of all six turbines.

Please contact us if you have any concerns with respect to the proposed turbines.

Thank you,

Genevieve Brown

On Thu, Apr 19, 2012 at 3:13 PM, Weather Radars Contact,National Radar Program [Ontario] <[email protected]> wrote:

Dear Ms. Genevieve Brown,

Thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada, regarding your wind energy intentions.

Our preliminary assessment of the information provided to us via email on April 19, 2012 indicates that any potential interference thatmay be created by the Skyway 126 Wind Farm in Grey County will not be severe. Although we would prefer our radar view to beinterference free, this is not always reasonable. As a consequence, we do not have strong objections to the current proposal.

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

4 of 6 11/23/2012 9:43 AM

Page 49: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

If your plans are modified in any manner (e.g. number of turbines, height, placement or materials) this analysis would no longer be valid. An updated analysis must be conducted.

Please contact us at: [email protected].

Thank you for your ongoing cooperation and we wish you success.

Best Regards,

______________________

Carolyn J. Rennie

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Toronto, Ontario M3H 5T4

Office : 3N-WS12

[email protected]

Phone : 416-739-4931

Cell : 289-221-1084

-------------------------------------------------------

Carolyn J. Rennie

Le Programme Nationale de Radar

Service météorologique du Canada

Environnement Canada

4905, rue Dufferin

Toronto, Ontario M3H 5T4

Bureau : 3N-WS12

[email protected]

Téléphone : 416-739-4931

Cellulaire : 289-221-1084

______________________

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Thursday, April 19, 2012 2:04 PM

To: Weather Radars Contact,National Radar Program [Ontario]

Cc: Karla Klein; Genevieve Brown

Subject: Skyway 126 - Impacts on Radar and Radio Communication

Dear coordinator,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines onradio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince iscompleting a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposedSkyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm containsfive turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your help,

Genevieve Brown

M.K. Ince and Associates Ltd.

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

5 of 6 11/23/2012 9:43 AM

Page 50: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&searc...

6 of 6 11/23/2012 9:43 AM

Page 51: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Weather Radars Contact,National Radar Program [Ontario] <[email protected]>Tue, Aug 14, 2012 at 3:33

PM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>, "Weather Radars Contact,National Radar

Program [Ontario]" <[email protected]>

Dear Ms. Hannah Ince,

First of all, thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada, with an

update of the Skyway 126 wind farm layout.

Our preliminary assessment of the updated information provided to us via email on August 14, 2012 indicates that

any potential interference that may be created by the Skyway 126 Wind Farm in Grey County will not be severe.

Although we would prefer our radar view to be interference free, this is not always reasonable. As a consequence,

we do not have strong objections to the current proposal.

If your plans are modified in any manner (e.g. number of turbines, height, placement or materials) this analysis would

no longer be valid. An updated analysis must be conducted.

Please contact us at: [email protected].

Thank you for your ongoing cooperation and we wish you success.

Best Regards,

______________________

Carolyn Rennie

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Toronto, Ontario M3H 5T4

Office : 3N-WS12

[email protected]

Phone : 416-739-4931

Cell : 289-221-1084

-------------------------------------------------------

Carolyn Rennie

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 2 16/08/2012 10:03 AM

Page 52: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Le Programme Nationale de Radar

Service météorologique du Canada

Environnement Canada

4905, rue Dufferin

Toronto, Ontario M3H 5T4

Bureau : 3N-WS12

[email protected]

Téléphone : 416-739-4931

Cellulaire : 289-221-1084

______________________

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Tuesday, August 14, 2012 11:49 AM

To: Weather Radars Contact,National Radar Program [Ontario]

[Quoted text hidden]

[Quoted text hidden]

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&searc...

2 of 2 16/08/2012 10:03 AM

Page 53: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, Aug 14, 2012 at 11:48 AM

To: "Weather Radars Contact,National Radar Program [Ontario]" <[email protected]>

Hello,

Since we last contacted you on April 27, the layout for the proposed Skyway 126 Wind Farm has shifted slightly.

Please find attached the coordinates of all the turbines.

If you have any questions or concerns about the proposed turbines please do not hesitate to ask us.

Thank you for you time,

Hannah Ince

[Quoted text hidden]

--

[Quoted text hidden]

Turbine Information 2012-08-14.pdf

162K

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 16/08/2012 10:02 AM

Page 54: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Fri, Apr 27, 2012 at 2:13 PM

To: "Weather Radars Contact,National Radar Program [Ontario]" <[email protected]>

Cc: Karla Klein <[email protected]>, Genevieve Brown <[email protected]>

Hello,

Since we last contacted you on April 19th regarding potential interference due to the Skyway 126 Wind Farm, a sixth

turbine has been added to the wind farm. Please find attached the coordinates of all six turbines.

Please contact us if you have any concerns with respect to the proposed turbines.

Thank you,

Genevieve Brown

[Quoted text hidden]

Turbine Information 2012-04-27.pdf

166K

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 4/27/2012 2:27 PM

Page 55: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Weather Radars Contact,National Radar Program [Ontario] <[email protected]>Thu, Apr 19, 2012 at 3:13

PM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>, "Weather Radars Contact,National Radar

Program [Ontario]" <[email protected]>

Cc: Karla Klein <[email protected]>, Genevieve Brown <[email protected]>

Dear Ms. Genevieve Brown,

Thank you for contacting the Meteorological Service of Canada, a branch of Environment Canada,

regarding your wind energy intentions.

Our preliminary assessment of the information provided to us via email on April 19, 2012 indicates that

any potential interference that may be created by the Skyway 126 Wind Farm in Grey County will not be

severe. Although we would prefer our radar view to be interference free, this is not always reasonable. As

a consequence, we do not have strong objections to the current proposal.

If your plans are modified in any manner (e.g. number of turbines, height, placement or materials) this

analysis would no longer be valid. An updated analysis must be conducted.

Please contact us at: [email protected].

Thank you for your ongoing cooperation and we wish you success.

Best Regards,

______________________

Carolyn J. Rennie

National Radar Program

Meteorological Service of Canada

Environment Canada

4905 Dufferin Street

Toronto, Ontario M3H 5T4

Office : 3N-WS12

[email protected]

Phone : 416-739-4931

Cell : 289-221-1084

-------------------------------------------------------

Carolyn J. Rennie

Le Programme Nationale de Radar

Service météorologique du Canada

Environnement Canada

4905, rue Dufferin

Toronto, Ontario M3H 5T4

Bureau : 3N-WS12

[email protected]

Téléphone : 416-739-4931

Cellulaire : 289-221-1084

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 2 4/19/2012 3:22 PM

Page 56: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

______________________

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Thursday, April 19, 2012 2:04 PM

To: Weather Radars Contact,National Radar Program [Ontario]

Cc: Karla Klein; Genevieve Brown

Subject: Skyway 126 - Impacts on Radar and Radio Communication

[Quoted text hidden]

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

2 of 2 4/19/2012 3:22 PM

Page 57: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Thu, Apr 19, 2012 at 2:04 PM

To: "Weather Radars Contact,National Radar Program [Ontario]" <[email protected]>Cc: Karla Klein <[email protected]>, Genevieve Brown <[email protected]>

Dear coordinator,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines onradio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince iscompleting a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposedSkyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm containsfive turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your help,

Genevieve Brown

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Skyway 126 Turbine Information 2012-04-19.pdf

165K

Mkince.ca Mail - Skyway 126 - Impacts on Radar and Radio Communication https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 4/19/2012 2:09 PM

Page 58: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Local Police and Fire

Page 59: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - Skyway 126 Wind Farm - Communication Impacts

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebc2348a05ce1 1/1

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm - Communication Impacts

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, May 28, 2013 at 11:29 AMTo: [email protected], [email protected]: Hanna Vovk <[email protected]>

Good morning,

Please be advised that the project layout for the Skyway 126 Wind Energy project has been updated since ourlast correspondence (November 19, 2012). Turbine 6 has been dropped. Turbines 1-5 remain in the sameposition. A revised layout is attached.

Thank you for your time and assistance.

M.K. Ince and Associates Ltd.

[Quoted text hidden]

Skyway 126 Wind Energy Project -- Turbine Coordinates (2013-05-28).pdf168K

Page 60: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm - Communication Impacts

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Nov 19, 2012 at 1:42 PM

To: [email protected], [email protected]: Carolyn Truong <[email protected]>

Hello,

Please be advised that since our last correspondence, the turbine layout of the proposed Skyway 126 Wind Farm has been revised. Thecoordinates of several turbines have been altered and I have attached the new turbine locations to this message for your assessment. Weare in the process of finalizing this project and do not anticipate any further revisions to the Skyway 126 layout at this point.

Thanks for your time and assistance, it is much appreciated!.

Best Regards,Carolyn Truong

On Wed, Aug 8, 2012 at 9:38 AM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:Good morning,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines onradio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince iscompleting a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposedSkyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm containssix turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your assistance,Hannah Ince--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Skyway 126 Wind Farm - Communication Impacts https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

1 of 1 11/22/2012 11:36 AM

Page 61: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Ministry of Government Services

Page 62: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - Re: Skyway 126 Wind Farm - Communication Impacts

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebdbf76c450b7&dsqt=1 1/3

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Re: Skyway 126 Wind Farm - Communication Impacts

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, May 28, 2013 at 11:57 AMTo: "Fox, Mark (MGS)" <[email protected]>Cc: "Guido, Sandra (ENE)" <[email protected]>, Hanna Vovk <[email protected]>

Dear Mark,

As follow-up to the revised information below, please find attached a KML file of the turbine locations for your viewing.

Thank you,M.K. Ince and Associates Ltd.

On Tue, May 28, 2013 at 11:25 AM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:

Dear Mark,

Please be advised that the April 27, 2012 project layout for the Skyway 126 Wind Energy project has been updated since our lastcorrespondence (January 4, 2013). Minor modifications to the turbine locations have been made. Turbine 6 has been dropped. A revisedlayout is attached.

Please contact us if you have any concerns with respect to the proposed wind turbine locations.

Thank you,M.K. Ince and Associates Ltd.

On Fri, Jan 4, 2013 at 9:48 AM, Fox, Mark (MGS) <[email protected]> wrote:

Hi Hannah;

Based upon the attached April 27, 2012 Skyway 126 turbine placements, this project has been determine unlikely to affect the operationsof Ontario’s public safety mobile radio network. Please be advised that this network is only utilized by provincial ministries (ie OPP,MOHLTC, MTO, etc) and not utilized by federal, regional or local public safety organizations and that a reassessment will be requiredshould turbine placements change.

Kindly update your records to forward future Ontario’s Public Safety Radio system wind farm impact assessments to my attention.

I have included Sandra Guido from the Ministry of the Environment in my response to ensure awareness of our analysis results.

If you have any questions, you can contact me at 416-327-0383 or by email at [email protected].

Regards,

Mark Fox, P. Eng.

Network Radio Engineer

Government Mobile Communications Branch

Infrastructure Technology Services

Page 63: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - Re: Skyway 126 Wind Farm - Communication Impacts

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebdbf76c450b7&dsqt=1 2/3

Ministry of Government Services

155 University Ave, 14th Floor, Toronto, ON M5H 3B7

Email: [email protected]

Phone: 416-327-0383

FAX: 416-327-0353

Blackberry: 416-524-6547

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]] Sent: August 8, 2012 9:38 AMTo: Grelik, Alina (JUS); [email protected]: Skyway 126 Wind Farm - Communication Impacts

Good morning,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines onradio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince iscompleting a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposedSkyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm containssix turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your assistance,Hannah Ince--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

--

M.K. Ince and Associates Ltd.11 Cross St., Dundas, ON L9H 2R3Phone: 905-628-0077Fax: 905-628-1329http://www.mkince.ca

--

M.K. Ince and Associates Ltd.11 Cross St., Dundas, ON L9H 2R3Phone: 905-628-0077Fax: 905-628-1329http://www.mkince.ca

Page 64: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - Re: Skyway 126 Wind Farm - Communication Impacts

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebdbf76c450b7&dsqt=1 3/3

2 attachments

Skyway 126 Wind Energy Project -- Turbine Coordinates (2013-05-28).pdf168K

S126 Turbines 2012-12-18.kml2K

Page 65: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Subject: Re: Skyway 126 Wind Farm - Communication Impacts

From: "Fox, Mark (MGS)" <[email protected]>

Date: Fri, 4 Jan 2013 14:48:46 +0000

To: "[email protected]" <[email protected]>

CC: "Guido, Sandra (ENE)" <[email protected]>

Hi Hannah;

Based upon the attached April 27, 2012 Skyway 126 turbine placements, this project has been determine

unlikely to affect the operations of Ontario’s public safety mobile radio network. Please be advised that this

network is only utilized by provincial ministries (ie OPP, MOHLTC, MTO, etc) and not utilized by federal,

regional or local public safety organizations and that a reassessment will be required should turbine

placements change.

Kindly update your records to forward future Ontario’s Public Safety Radio system wind farm impact

assessments to my attention.

I have included Sandra Guido from the Ministry of the Environment in my response to ensure awareness of

our analysis results.

If you have any questions, you can contact me at 416-327-0383 or by email at [email protected].

Regards,

Mark Fox, P. Eng.Network Radio Engineer

Government Mobile Communications Branch

Infrastructure Technology Services

Ministry of Government Services

155 University Ave, 14th Floor, Toronto, ON M5H 3B7

Email: [email protected]

Phone: 416-327-0383

FAX: 416-327-0353

Blackberry: 416-524-6547

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]Sent: August 8, 2012 9:38 AMTo: Grelik, Alina (JUS); [email protected]: Skyway 126 Wind Farm - Communication Impacts

Good morning,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the

impact of wind turbines on radio communication and radar systems. The Skyway 126 Wind Farm is at a

preliminary stage of investigations and MK Ince is completing a communications impact assessment for the

project as outlined by RABC and CanWEA in their guidelines. The proposed Skyway 126 Wind Farm is

located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm

Re: Skyway 126 Wind Farm - Communication Impacts

1 of 2

Page 66: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

contains six turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your assistance,

Hannah Ince

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Turbine Information 2012-04-27.pdf

Content-Description: Turbine Information 2012-04-27.pdf

Content-Type: application/pdf

Content-Encoding: base64

Re: Skyway 126 Wind Farm - Communication Impacts

2 of 2

Page 67: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Ontario Public Safety Radio Wind Farm communication impact assessmentrequests

Fox, Mark (MGS) <[email protected]> Tue, Nov 27, 2012 at 10:25 AM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>

Cc: Carolyn Truong <[email protected]>

Hi Carolyn;

Thank you for providing the attached revised proposed Skyway 126 wind farm turbine layout. We will conduct an

impact assessment on the Ontario Government Public safety radio network and provide an impact statement. Please

be advised that this radio network is utilized exclusively for the following provincial ministries: OPP, MOHLTC, MTO,

MNR MOE, CISO, MOR, MCYS and MCS.

Please contact directly any regional/local Public safety radio systems managers (eg fire, police, local operations, etc)

within the vicinity of this proposed wind farm to conduct similar impact assessments to their networks.

Thanks,

Mark Fox, P. Eng.

Network Radio Engineer

Government Mobile Communications Branch

Infrastructure Technology Services

Ministry of Government Services

155 University Ave, 14th Floor, Toronto, ON M5H 3B7

Email: [email protected]

Phone: 416-327-0383

FAX: 416-327-0353

Blackberry: 416-524-6547

Mkince.ca Mail - Ontario Public Safety Radio Wind Farm communicatio... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&q=...

1 of 2 5/27/2013 4:04 PM

Page 68: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Ontario Public Safety Radio Wind Farm communication impact assessmentrequests

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Nov 19, 2012 at 1:38 PM

To: "Fox, Mark (MGS)" <[email protected]>

Cc: Carolyn Truong <[email protected]>

Hi Mark,

Please be advised that since our last correspondence, the turbine layout of the proposed Skyway 126 Wind Farm has been revised. The

coordinates of several turbines have been altered and I have attached the new turbine locations to this message for your assessment. We

are in the process of finalizing this project and do not anticipate any further revisions to the Skyway 126 layout at this point.

Thanks for your time and assistance, it is much appreciated!.

Best Regards,

Carolyn Truong

[Quoted text hidden]

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Ontario Public Safety Radio Wind Farm communicatio... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&q=...

1 of 1 5/27/2013 4:03 PM

Page 69: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Ontario Public Safety Radio Wind Farm communication impact assessment

requests

Fox, Mark (MGS) <[email protected]> Wed, Aug 8, 2012 at 12:35 PM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>

Hi Hannah;

As discussed, kindly direct all Government of Ontario Public Safety Radio Wind Farm communica on impact

assessment requests to my a#en on.

If possible, please provide the geographical study area with LAT/LONG coordinates or a Google Earth kml file to

accommodate future turbine placement changes as required within the study area.

Jeff Cook has recently forwarded the following Wind Farm communica on impact assessment requests:

Grey Highland Clean Energy project

Grey Highlands Zero Emission People (ZEP) project

Skyway 125 Wind Farm

ZEP Wind Farm Ganaraska Project

Skyway 126 Wind Farm

Snowy Ridge Wind Park

Se#lers Landing Wind Park

We will proceed with the assessments of each and provide a Government of Ontario Public Safety Radio impact

statement.

Thanks,

Mark Fox, P. Eng.

Network Radio Engineer

Mkince.ca Mail - Ontario Public Safety Radio Wind Farm communication... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

1 of 2 11/19/2012 12:37 PM

Page 70: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Government Mobile Communications Branch

Infrastructure Technology Services

Ministry of Government Services

155 University Ave, 14th Floor, Toronto, ON M5H 3B7

Email: [email protected]

Phone: 416-327-0383

FAX: 416-327-0353

Blackberry: 416-524-6547

Mkince.ca Mail - Ontario Public Safety Radio Wind Farm communication... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

2 of 2 11/19/2012 12:37 PM

Page 71: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm - Communication Impacts

Approvals M. K. Ince and Associates Ltd. <[email protected]> Wed, Aug 8, 2012 at 11:31 AM

To: [email protected]

Good morning,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines onradio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince iscompleting a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposedSkyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm containssix turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your assistance,Hannah Ince--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Turbine Information 2012-04-27.pdf

166K

Mkince.ca Mail - Skyway 126 Wind Farm - Communication Impacts https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 16/08/2012 10:19 AM

Page 72: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

NAV CANADA

Page 73: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

12-3322: 6 wind turbines (Skyway 126) - Badjeros, ON

Tranter, Melanie <[email protected]> Thu, May 30, 2013 at 2:00 PM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>

Cc: Hanna Vovk <[email protected]>

Hello,

We appreciate the update and at this �me we will not send a revised le�er. Please advise us 10 days in advance at

the start of construc�on and upon comple�on of the project as per our original email sent on January 10, 2013.

Thank you,

MelanieTranter

LandUseOf�ice

AeronauticalInformationServices(AIS)

tel(613)248-3909

e-mail:[email protected]

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: May-28-13 11:41 AM

To: Tranter, Melanie

Cc: Hanna Vovk

Subject: Re: 12-3322: 6 wind turbines (Skyway 126) - Badjeros, ON

[Quoted text hidden]

---------- Forwarded message ----------

From: "Tranter, Melanie" <[email protected]>

To: Hannah Vovk <[email protected]>

Cc: "Ontario Region, Transport Canada" <[email protected]>

Date: Thu, 10 Jan 2013 08:40:04 -0500

Subject: 12-3322 LTP

Hello Hannah,

Please find attached a letter from NAV CANADA regarding your 6 wind turbines (Skyway 126) submitted on

2012-08-15.

We ask that you notify us at least 10 business days prior to the start of construction and upon completion. These

Mkince.ca Mail - 12-3322: 6 wind turbines (Skyway 126) - Badjeros, ON https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&sear...

1 of 2 5/30/2013 2:50 PM

Page 74: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - 12-3322: 6 wind turbines (Skyway 126) - Badjeros, ON

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebcca7d87909e 1/1

Approvals M. K. Ince and Associates Ltd. <[email protected]>

12-3322: 6 wind turbines (Skyway 126) - Badjeros, ON

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, May 28, 2013 at 11:40 AMTo: "Tranter, Melanie" <[email protected]>Cc: Hanna Vovk <[email protected]>

Good morning Melanie,

Please be advised that the project layout for the Skyway 126 Wind Energy project has been updated since our last correspondence(January 10, 2013). Turbine 6 has been dropped. Turbines 1-5 remain in the same position. A revised layout is attached. Similarinformation has been sent to Transport Canada.

Please let us know if a new letter from NAV CANADA is required.

Thank you,

M.K. Ince and Associates Ltd.

[Quoted text hidden]

--

M.K. Ince and Associates Ltd.11 Cross St., Dundas, ON L9H 2R3Phone: 905-628-0077Fax: 905-628-1329http://www.mkince.ca

Skyway 126 Wind Energy Project -- Turbine Coordinates (2013-05-28).pdf168K

Page 75: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 <[email protected]>

Notice of Final Public Meeting for Skyway 126 Wind Energy

Katie Meyer-Beck <[email protected]> Wed, Feb 20, 2013 at 9:11 AM

To: [email protected], Chris Csatlos <[email protected]>

Cc: [email protected], Skyway 126 <[email protected]>

Dear Mr. Csatlos:

Please find herein a Notice of Final Public Meeting for Skyway 126 Wind Energy as per O.Reg 359/09. In

addition, the notice was sent to your address last week via mail.

The notice was also available on the project website (www.zeroemissionpeople.com), along with a copy of

the draft Renewable Energy Approval reports and technical studies for the proposed Skyway 126 Wind Energy

project.

We welcome any questions or feedback on the proposed project.

Best,

Katie

[Quoted text hidden]

2 attachments

S126 - Notice of Final Public Meeting_2013-02-14 FINAL.pdf

154K

NAV Canada Notice of Final Public Meeting EMAIL copy_2013-02-15 FINAL.pdf

77K

Page 76: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

February 19, 2013

Christopher Csatlos

AIS Data Collection Unit and Land Use Office

NAV CANADA

1601 Tom Roberts Road

P.O. Box 9824, Station T

Ottawa, ON K1G 6R2

Sent via email:

[email protected]

[email protected]

Attention: Christopher Csatlos

Reference: Notice of Final Public Meeting for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

Dear Christopher Csatlos:

M.K. Ince and Associates Ltd., on behalf of the project proponent Cloudy Ridge Wind Park LP, informs

you of a Final Public Meeting under the Renewable Energy Approval (REA) process for the Skyway 126

Wind Energy project. The project, which will consist of up to five (5) 2.0 MW wind turbines and

associated access roads and cabling, is to be located within the Municipality of Grey Highlands, near the

community of Badjeros, Ontario.

A Notice of Final Public Meeting is enclosed. This notice is also available on the project website

(www.zeroemissionpeople.com), along with a copy of the draft Renewable Energy Approval reports and

technical studies for the proposed Skyway 126 Wind Energy project. In addition, a hard copy of the

notice was sent to your address via mail last week.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy project. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Bill York c/o Cloudy Ridge Wind Park LP

Page 77: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

NOTICE OF FINAL PUBLIC MEETING Distributed by Cloudy Ridge Wind Park LP regarding a

Proposal to Engage in a Renewable Energy Project

Project Name: Skyway 126 Wind Energy Proponent Name: Cloudy Ridge Wind Park LP Project website: www.zeroemissionpeople.com Project Location: On privately-owned agricultural lands within the Municipality of Grey Highlands, near the community of Badjeros,

Ontario Dated at the Municipality of Grey Highlands this the 20th of February, 2013

The proponent, Cloudy Ridge Wind Park LP, is planning to engage in a renewable energy project in respect of which the issuance of a Renewable Energy Approval (REA) is required. The proposal to engage in the project and the project itself is subject to the provisions of the Environmental Protection Act (Act) Part V.0.1 and Ontario Regulation 359/09 (Regulation). This notice must be distributed in accordance with section 15 of the Regulation prior to an application being submitted and assessed for completeness by the Ontario Ministry of the Environment. On Wednesday, April 24th, 2013, a public meeting will be held related to the Skyway 126 Wind Energy project:

Project Description: Pursuant to the Act and Regulation, the facility, in respect of which this project is to be engaged in, is considered to be a Class 4 Wind Energy Generation Facility. If approved, this facility would have a total maximum name plate capacity of 10 MW. The project location is described in the map below. Documents for Public Inspection: The Draft Project Description Report entitled Skyway 126 Wind Energy Description Report (Draft) describes the project as consisting of

of up to five (5) REpower MM92 wind turbines of 2 MW per turbine, wind turbine foundations, transformers, gravel access roads, underground electrical cabling, substation and other ancillary works. Further, the applicant has prepared the following documents in order to comply with the requirements under subsection 16 (5) of O. Reg. 359/09:

Project Description Report

Natural Heritage Assessment Reports, including: Records Review, Site Investigation Report,

Evaluation of Significance Report, Environmental Impact Study; Ministry of Natural

Resources (MNR) confirmation letter

Construction Plan Report

Decommissioning Plan Report

Water Bodies Assessment Report

Water Bodies Impact Assessment Report

Wind Turbine Specifications Report

Environmental Noise Impact Report

Design and Operations Report, including: Site Plan, Heritage Assessment Report with Ministry of Tourism, Culture and Sport (MTCS) confirmation letter, Shadow Flicker Report, Radar and Radio Communications Impact Assessment, Natural Heritage Environmental Effects Monitoring Plan, Archaeological Assessment Report with MTCS confirmation letter

The reports may be found online at www.zeroemissionpeople.com. Hard copies are available for viewing at:

Project Contacts and Information:

Project Contacts and Information:

To learn more about the project proposal, public meetings, or to communicate concerns, please contact: Bill York, Project Manager Cloudy Ridge Wind Park LP c/o Zero Emission People 346 Waverley Street Ottawa, ON K2P 0W5 Phone: (613) 827-7605 Email: [email protected]

OR

Katie Meyer-Beck, Project Manager M.K. Ince and Associates, Ltd. 11 Cross Street Dundas, Ontario L9H 2R3 Tel: (905) 628-0077 E-mail: [email protected]

Municipal Office of Grey Highlands 206 Toronto St S., Unit 1 POBox 409 Markdale, ON N0C 1H0

Flesherton Public Library 101 Highland Drive POBox 280 Flesherton, Ontario N0C 1E0

AND

Meeting Location: DATE: Wednesday, April 24th, 2013

TIME: 6:00 p.m. to 9:00 p.m. PLACE: Osprey Community Hall

494196 Grey Road 2 Maxwell, Ontario

FORMAT: Presentations, and Question and Answer 6:00 p.m. Presentation by the Proponent 6:15 p.m. Questions and Answers - the audience will have an opportunity to ask questions and receive answers in

a public forum. A moderator will be on hand to act as a neutral facilitator and ensure that all voices and viewpoints are heard. While we cannot guarantee that all questions can be answered at that time, we do guarantee that all questions submitted at the public meeting will be addressed in the Consultation Report, to be submitted as part of the Renewable Energy Approval application. 8:30 p.m. Open House - posters and one-on-one discussion

Please note, correspondence will form part of the public record related to the project and will be included in the Public Consultation Report. Please let us know if you would like correspondence kept confidential. We encourage comments, questions,

and concerns to be raised in written form and sent via e-mail.

Page 78: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

February 15, 2013

Christopher Csatlos

AIS Data Collection Unit and Land Use Office

NAV CANADA

1601 Tom Roberts Road

P.O. Box 9824, Station T

Ottawa, ON K1G 6R2

Attention: Christopher Csatlos

Reference: Notice of Final Public Meeting for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

Dear Christopher Csatlos:

M.K. Ince and Associates Ltd., on behalf of the project proponent Cloudy Ridge Wind Park LP, informs

you of a Final Public Meeting under the Renewable Energy Approval (REA) process for the Skyway 126

Wind Energy project. The project, which will consist of up to five (5) 2.0 MW wind turbines and

associated access roads and cabling, is to be located within the Municipality of Grey Highlands, near the

community of Badjeros, Ontario.

A Notice of Final Public Meeting is enclosed. This notice is also available on the project website

(www.zeroemissionpeople.com), along with a copy of the draft Renewable Energy Approval reports and

technical studies for the proposed Skyway 126 Wind Energy project.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy project. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Bill York c/o Cloudy Ridge Wind Park LP

Page 79: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 <[email protected]>

Notice of Draft Site Plan for Skyway 126 Wind Energy

Katie Meyer-Beck <[email protected]> Wed, Jan 30, 2013 at 3:53 PM

To: Chris Csatlos <[email protected]>, [email protected]

Cc: [email protected]

Dear Mr. Csatlos:

Please find attached in this email the following with regards to the Skyway 126 Wind Energy project:

1. Cover letter

2. Notice of Draft Site Plan for Skyway 126 Wind Energy

This notice has also been sent to your office earlier this week. Please do not hesitate to respond with any further

questions.

Best regards,

[Quoted text hidden]

2 attachments

NAV Canada Notice of Draft Site Plan letter EMAIL copy_2013-01-24 FINAL.pdf

75K

Skyway 126 Wind Energy Notice of Draft Site Plan_2013-01-30 FINAL updated.pdf

136K

Page 80: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

January 30, 2013

Christopher Csatlos

AIS Data Collection Unit and Land Use Office

NAV CANADA

1601 Tom Roberts Road

P.O. Box 9824, Station T

Ottawa, ON K1G 6R2

Sent via email:

[email protected]

[email protected]

Attention: Christopher Csatlos

Reference: Notice of Draft Site Plan for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

Dear Christopher Csatlos:

The proponent, Cloudy Ridge Wind Park LP, submits this Notice of Draft Site Plan under the Renewable

Energy Approval (REA) process for the Skyway 126 Wind Energy. The project, which will consist of up

to five (5) wind turbines with a total maximum name plate capacity of up to 10 MW, along with

associated access roads and cabling, is to be located within the Municipality of Grey Highlands, near the

community of Badjeros, Ontario.

As per Ontario Regulation 359/09 (consolidated version, November. 2, 2012), s. 54.1, a Notice of Draft

Site Plan is enclosed to clarify the locations of turbines and other project infrastructure for Skyway 126

Wind Energy. This notice is also available on the project website (www.zeroemissionpeople.com), along

with a copy of the Draft Site Plan and associated appendices. In addition, a copy of the notice was sent to

your address earlier this week via mail.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Cloudy Ridge Wind Park LP

Page 81: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

NOTICE OF DRAFT SITE PLAN SECTION 54.1 ONTARIO REGULATION 359/09

Distributed by Cloudy Ridge Wind Park LP regarding a Proposal to Engage in a Renewable Energy Project

Project Name: Skyway 126 Wind Energy Proponent Name: Cloudy Ridge Wind Park LP Project website: www.zeroemissionpeople.com Project Location: On privately-owned agricultural lands within the Municipality of Grey Highlands, near the community of Badjeros, Ontario Dated at the Municipality of Grey Highlands this the 30th of January, 2013 The proponent, Cloudy Ridge Wind Park LP, is planning to engage in a renewable energy project in respect of which the issuance of a Renewable Energy Approval (REA) is required. The distribution of this Notice of Draft Site Plan (Notice) is subject to the provisions of the Environmental Protection Act (Act) Part V.0.1 and Ontario Regulation 359/09 (Regulation). This Notice is being distributed in accordance with sections 54 and 54.1 of the Regulation prior to an application being submitted and assessed for completeness by the Ministry of the Environment. For the purposes of the 550 meter setback prohibition (subsection 54(1) in O. Reg. 359/09) for the Skyway 126 Wind Energy project, Cloudy Ridge Wind Park LP has considered all noise receptors (as that term is defined in O. Reg. 359/09) existing on the day before this notice of draft site plan is published. The legal effect of this publication is that Cloudy Ridge Wind Park LP is not required to consider any new noise receptors that come into existence after this day. This notice was first published January 30, 2013. Project Description: Pursuant to the Act and Regulation, the renewable energy generation facility, in respect of which this project is to be engaged in, is a Wind Facility, Class 4. If approved, this facility would have a total maximum name plate capacity of up to 10 megawatts (MW). The project location is described in the map below.The project would consist of up to five (5) REpower MM92 wind turbines of 2 MW per turbine. Documents for Public Inspection: The Draft Project Description Report entitled Skyway 126 Wind Energy Draft Project Description Report describes the project as consisting of up to five (5) wind turbine generators, wind turbine foundations, step-up transformers, gravel access roads, underground and/or overhead electrical collection system, substation to connect to Hydro One power line, and temporary construction work spaces, as shown in the map below. The Draft Site Plan, associated appendices, and Environmental Noise Impact Report will be made available for public inspection at the Flesherton Public Library (101 Highland Drive, Flesherton, Ontario N0C 1E0) and on the Project website at www.zeroemissionpeople.com. Project Contacts and Information: To learn more about the project proposal, or to communicate concerns please contact: Bill York, Project Manager Cloudy Ridge Wind Park LP c/o Zero Emission People 346 Waverley Street Ottawa, ON, K2P 0W5 Phone: (613) 827-7605 E-mail: [email protected] OR Katie Meyer-Beck, Project Manager M.K. Ince and Associates Ltd. 11 Cross Street Dundas, Ontario, L9H 2R3 Phone: (905) 628-0077 E-mail: [email protected]

Skyway 126 Wind Energy

Please note, correspondence will form part of the public record related to the project and will be included in the Public Consultation Report. Please let us know if you would like correspondence kept confidential. We encourage comments, questions, and concerns to be raised in written form and sent via e-mail.

Page 82: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

January 28, 2013

Christopher Csatlos

AIS Data Collection Unit and Land Use Office

NAV CANADA

1601 Tom Roberts Road

P.O. Box 9824, Station T

Ottawa, ON K1G 6R2

Attention: Christopher Csatlos

Reference: Notice of Draft Site Plan for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

Dear Christopher Csatlos:

The proponent, Cloudy Ridge Wind Park LP, submits this Notice of Draft Site Plan, Draft Site Plan, and

associated appendices under the Renewable Energy Approval (REA) process for Skyway 126 Wind

Energy. The project, which will consist of up to five (5) wind turbines with a total maximum name plate

capacity of up to 10 MW, along with associated access roads and cabling, is to be located within the

Municipality of Grey Highlands, near the community of Badjeros, Ontario.

As per Ontario Regulation 359/09 (consolidated version, November 2, 2012), s. 54.1, a Notice of Draft

Site Plan is enclosed to clarify the locations of turbines and other project infrastructure for Skyway 126

Wind Energy. This notice is also available on the project website (www.zeroemissionpeople.com), along

with a copy of the Draft Site Plan and associated appendices.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Cloudy Ridge Wind Park LP

Page 83: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

1601 Tom Roberts, P.O. Box 9824 Stn T, Ottawa, ON, K1G 6R2 1601 Tom Roberts, C.P.9824 Succursale T, Ottawa, Ontario, K1G 6R2 Telephone: +1 (866) 577-0247, Fax: +1 (613) 248-4094 Téléphone: +1 (866) 577-0247, Télécopieur: +1 (613) 248-4094

Z-LDU-101 Version 1.0

January 10, 2013

Your file Skyway 126

Our file 12-3322

Ms. Hannah Vovk M.K. INCE and Associates 11 Cross St. Dundas, ON L9H 2R3 RE: Wind Farm: 6 Wind Turbines - Badjeros, ON (See attached spreadsheet for project details) Ms. Vovk, We have evaluated the captioned proposal and NAV CANADA has no objection to the project as submitted provided that the wind turbines do not exceed the maximum total height of 2200ft above sea level (ASL) as per the attached spreadsheet. In the interest of aviation safety, it is incumbent on NAV CANADA to maintain up-to-date aeronautical publications and issue NOTAM as required. To assist us in that end, we ask that you notify us at least 10 business days prior to the start of construction and upon completion. These notification requirements can be satisfactorily met by returning completed, signed copies of the attached forms by e-mail at [email protected] or fax at 613-248-4094. In the event that you should decide not to proceed with this project or if the structure is dismantled, please advise us accordingly so that we may formally close the file. If you have any questions, contact the Land Use Department by telephone at 1-866-577-0247 or e-mail at [email protected]. NAV CANADA's land use evaluation is valid for a period of 12 months. Our assessment is limited to the impact of the proposed physical structure on the air navigation system and installations; it neither constitutes nor replaces any approvals or permits required by Transport Canada, Industry Canada, other Federal Government departments, Provincial or Municipal land use authorities or any other agency from which approval is required. Industry Canada addresses any spectrum management issues that may arise from your proposal and consults with NAV CANADA engineering as deemed necessary. Yours truly,

Melanie Tranter for David Legault Manager, Data Collection Aeronautical Information Services cc ONTR - Ontario Region, Transport Canada

Page 84: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and RadioCommunication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Dec 3, 2012 at 11:17 AM

To: Land Use <[email protected]>

Hi Diane,

My apologies for the delay in getting back to you. Please find attached, the spreadsheet and map as requested.

Best Regards,

Carolyn Truong

[Quoted text hidden]

2 attachments

S126 Topographic Map for NavCanada 2012-11-30.pdf

3033K

Skyway 126_Nav Canada Wind_Farm_2012-10-02.xls

244K

Mkince.ca Mail - Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impact... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&cat...

1 of 1 5/28/2013 5:32 PM

Page 85: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and RadioCommunication

Land Use <[email protected]> Mon, Nov 19, 2012 at 6:24 PM

To: "[email protected]" <[email protected]>

Hello Carolyn,

Please re-send the attached spreadsheet and send us a new map.

Thank you.

Diane Levesque

Land Use

AIS Data Collection, NAV CANADA

Toll free: 1-866-577-0247

Fax: (613) 248-4094

Email: [email protected]

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: November 19, 2012 2:09 PM

To: Land Use

Subject: Re: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

[Quoted text hidden]

Copy of Skyway 126_Nav Canada Wind_Farm_2012-10-02.xls

244K

Mkince.ca Mail - Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impact... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&cat...

1 of 1 5/28/2013 5:30 PM

Page 86: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and RadioCommunication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Nov 19, 2012 at 2:09 PM

To: Land Use <[email protected]>

Hello,

Please be advised that since our last correspondence, the turbine layout of the proposed Skyway 126 Wind Farm has

been revised. The coordinates of Turbine 4 have been altered and I have attached the new turbine locations to this

message for your assessment. We are in the process of finalizing this project and do not anticipate any further

revisions to the Skyway 126 layout at this point.

Thanks for your time and assistance, it is much appreciated!.

Best Regards,

Carolyn Truong

[Quoted text hidden]

Copy of Skyway 126_Nav Canada Wind_Farm_2012-10-02.xls

244K

Mkince.ca Mail - Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impact... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&cat...

1 of 1 5/28/2013 5:30 PM

Page 87: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and RadioCommunication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, Aug 14, 2012 at 11:33 AM

To: Land Use <[email protected]>

Hello,

There has been another change in the layout for the Skyway 126 Wind Farm, the turbines have been adjusted slightly.

Please find attached the coordinates of all six turbines as well as the a map of the current layout.

If you have any questions or concerns about the proposed turbines please contact us.

Thank you for your time,

Hannah Ince

[Quoted text hidden]

--

[Quoted text hidden]

2 attachments

Skyway 126 Working Current Layout Map 1 2012-07-25.pdf

2761K

Skyway 126_Nav Canada Wind_Farm_2012-08-14.xls

243K

Mkince.ca Mail - Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impact... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&cat...

1 of 1 5/28/2013 5:28 PM

Page 88: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and RadioCommunication

Genevieve Brown <[email protected]> Fri, Apr 20, 2012 at 9:00 AM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>

-------- Original Message --------

Subject:FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

Date:Thu, 19 Apr 2012 20:29:41 -0400

From:Land Use <[email protected]>

To:[email protected] <[email protected]>

CC:[email protected] <[email protected]>

Hello,

Please note the Land Use file no. is 12-1499 for this project. For multiple obstacles, please use the spreadsheet attached.

Also, please identify the turbines on the map and re-send another map.

Thank you.

Diane Levesque

Land Use

AIS Data Collection, NAV CANADA

Toll free: 1-866-577-0247

Fax: (613) 248-4094

Email: [email protected]

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: April 19, 2012 2:07 PM

To: Land Use

Cc: Karla Klein; Genevieve Brown

Subject: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

Dear coordinator,

Mkince.ca Mail - Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impact... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&cat...

1 of 2 5/28/2013 4:55 PM

Page 89: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and Radio

Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Fri, Apr 27, 2012 at 3:19 PM

To: Land Use <[email protected]>

Cc: Karla Klein <[email protected]>, Genevieve Brown <[email protected]>

Hello,

Since we last contacted you on April 19th regarding potential interference due to the Skyway 126 Wind Farm, a sixth

turbine has been added to the wind farm. Please find attached the coordinates of all six turbines.

Please contact us if you have any concerns with respect to the proposed turbines.

Thank you,

Genevieve Brown

[Quoted text hidden]

3 attachments

Skyway 126_Nav Canada Wind_Farm_2012-04-27.xls

252K

Skyway 126 Topo Map 2012-04-27.pdf

646K

Turbine Information 2012-04-27.pdf

166K

Mkince.ca Mail - Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts ... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

1 of 1 4/27/2012 3:19 PM

Page 90: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts on Radar and Radio

Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Fri, Apr 20, 2012 at 9:07 AM

To: Land Use <[email protected]>

Cc: Genevieve Brown <[email protected]>, Karla Klein <[email protected]>

Hello,

Please find attached all files including the excel file and map with turbine labels.

Thank you,

Genevieve Brown

[Quoted text hidden]

4 attachments

Skyway 126_Nav Canada Wind_Farm_2012-04-19.xls

252K

Skyway 126 Turbine Information 2012-04-19.pdf

165K

Skyway 126_NAV Canada Submission_Form_2012-04-19.doc

133K

Skyway 126 Topo Map 2012-04-20.pdf

895K

Mkince.ca Mail - Fwd: FW: 12-1499 - Skyway 126 Wind Farm - Impacts ... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 4/20/2012 9:20 AM

Page 91: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Thu, Apr 19, 2012 at 2:07 PM

To: Land Use <[email protected]>Cc: Karla Klein <[email protected]>, Genevieve Brown <[email protected]>

Dear coordinator,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines onradio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince iscompleting a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposedSkyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm containsfive turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your help,

Genevieve Brown

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

3 attachments

Skyway 126 Topo Map 2012-04-19.png

965K

Skyway 126_NAV Canada Submission_Form_2012-04-19.doc

133K

Skyway 126 Turbine Information 2012-04-19.pdf

165K

Mkince.ca Mail - Skyway 126 Wind Farm - Impacts on Radar and Radio... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 1 4/19/2012 2:14 PM

Page 92: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Royal Canadian Mounted Police

Page 93: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebb8ca8cb9373 1/1

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, May 28, 2013 at 11:19 AMTo: windfarm_coordinator <[email protected]>Cc: Hanna Vovk <[email protected]>

Dear Coordinator,

Please be advised that the project layout for the Skyway 126 Wind Energy project has been updated since ourlast correspondence (November 19, 2012). Turbine 6 has been dropped. Turbines 1-5 remain in the sameposition. A revised layout is attached.

Thank you,

M.K. Ince and Associates Ltd.

[Quoted text hidden]

Skyway 126 Wind Energy Project -- Turbine Coordinates (2013-05-28).pdf168K

Page 94: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Skyway 126 Wind Farm - Impacts on Radar and Radio Communication

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, Nov 19, 2012 at 1:44 PM

To: windfarm_coordinator <[email protected]>

Cc: Carolyn Truong <[email protected]>

Hello,

Please be advised that since our last correspondence, the turbine layout of the proposed Skyway 126 Wind Farm has been revised. The

coordinates of several turbines have been altered and I have attached the new turbine locations to this message for your assessment. We are

in the process of finalizing this project and do not anticipate any further revisions to the Skyway 126 layout at this point.

Thanks for your time and assistance, it is much appreciated!.

Best Regards,

Carolyn Truong

On Fri, Apr 27, 2012 at 2:17 PM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:

Hello,

Since we last contacted you on April 19th regarding potential interference due to the Skyway 126 Wind Farm, a sixth turbine has been

added to the wind farm. Please find attached the coordinates of all six turbines.

Please contact us if you have any concerns with respect to the proposed turbines.

Thank you,

Genevieve Brown

On Thu, Apr 19, 2012 at 2:00 PM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:

Dear coordinator,

On behalf of the Skyway 126 Wind Farm, M.K. Ince and Associates, would like to request consultation for the impact of wind turbines on

radio communication and radar systems. The Skyway 126 Wind Farm is at a preliminary stage of investigations and MK Ince is

completing a communications impact assessment for the project as outlined by RABC and CanWEA in their guidelines. The proposed

Skyway 126 Wind Farm is located near the communities of Badjeros, within the Municipality of Grey Highlands . The wind farm contains

five turbines; the proposed coordinates and heights of the turbines are attached in this email.

Please contact us if you have any concerns with respect to the proposed wind turbines.

Thank you for your help,

Genevieve Brown

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Mkince.ca Mail - Skyway 126 Wind Farm - Impacts on Radar and Radio... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

1 of 2 11/19/2012 1:41 PM

Page 95: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Turbine Information 2012-11-16.pdf

272K

Mkince.ca Mail - Skyway 126 Wind Farm - Impacts on Radar and Radio... https://mail.google.com/mail/u/2/?ui=2&ik=f1ba1b1184&view=pt&q=sk...

2 of 2 11/19/2012 1:41 PM

Page 96: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Request for confirmation3 messages

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, Jun 12, 2012 at 2:07 PM

To: windfarm_coordinator <[email protected]>

Hi,

This is a follow up to our phone conversation we just had. During this conversation you mentioned that the wind farm coordinator is notcurrently filled and there will be longer wait times as a result. Could you respond to confirm this information for our records?

Thank you for your help,Hannah Ince

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, Jun 12, 2012 at 2:31 PM

To: [email protected]

---------- Forwarded message ----------From: Approvals M. K. Ince and Associates Ltd. <[email protected]>

Date: Tue, Jun 12, 2012 at 2:07 PMSubject: Request for confirmationTo: windfarm_coordinator <[email protected]>

Hi Alex,

This is a follow up to our phone conversation we just had. During this conversation you mentioned that the wind farm coordinator position

is not currently filled and there will be longer wait times as a result. Could you respond to confirm this information for our records?

Thank you for your help,Hannah Ince

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

[Quoted text hidden]

Alex Beckstead <[email protected]> Tue, Jun 12, 2012 at 3:06 PM

To: "Approvals M. K. Ince and Associates Ltd." <[email protected]>

That is correct. It will hopefully be filled in the coming months. Thank you

Alex BecksteadRadio Spectrum Engineer - Ingénieur du spectre radio

Mkince.ca Mail - Request for confirmation https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&searc...

1 of 2 06/07/2012 9:57 AM

Page 97: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Mobile Communication Services - Services de communication mobileRCMP - GRCtel.: 613-949-4519fax.: [email protected]>>> "Approvals M. K. Ince and Associates Ltd." <[email protected]> 6/12/2012 2:31 PM >>>[Quoted text hidden]

Mkince.ca Mail - Request for confirmation https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&searc...

2 of 2 06/07/2012 9:57 AM

Page 98: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Rogers Communications Partnership

Page 99: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

5/28/13 Mkince.ca Mail - FW: Query Regarding Potential Impacts of Skyway 126 Wind Farm on Rogers Communications

https://mail.google.com/mail/u/1/?ui=2&ik=f1ba1b1184&view=pt&search=sent&msg=13eebb51ef14eafb 1/1

Approvals M. K. Ince and Associates Ltd. <[email protected]>

FW: Query Regarding Potential Impacts of Skyway 126 Wind Farm on RogersCommunications

Approvals M. K. Ince and Associates Ltd. <[email protected]> Tue, May 28, 2013 at 11:15 AMTo: Milan Vujosevic <[email protected]>Cc: Hanna Vovk <[email protected]>

Dear Milan,

Please be advised that the project layout for the Skyway 126 Wind Energy project has been updated since ourlast correspondence (November 16, 2012). Turbine 6 has been dropped. Turbines 1-5 remain in the sameposition. A revised layout is attached.

Thank you,

M.K. Ince and Associates Ltd.

[Quoted text hidden]

Skyway 126 Wind Energy Project -- Turbine Coordinates (2013-05-28).pdf168K

Page 100: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Carolyn Truong <[email protected]>

Fwd: FW: Query Regarding Potential Impacts of Skyway 126 Wind Farm on Rogers

Communications

Carolyn Truong <[email protected]> Fri, Nov 16, 2012 at 4:26 PM

To: Milan Vujosevic <[email protected]>Cc: "Approvals M. K. Ince and Associates Ltd." <[email protected]>, Katie Meyer-Beck <[email protected]>, ChristineHomuth <[email protected]>

Hi Milan,

Further to our correspondence in August, the turbine layout of the proposed Skyway 126 Wind Farm has been changed to mitigate anyimpacts to Rogers Communications. Turbine 4 has been shifted approximately 50 m east, the revised turbine coordinates are attached tothis message.

Please advise of any remaining issues or concerns regarding anticipated impacts to Rogers communications resulting from the proposedSkyway 126 project.

Best Regards,Carolyn Truong

On Fri, Aug 24, 2012 at 4:54 PM, Milan Vujosevic <[email protected]> wrote:

Carolyn,

Here is the required info.

Regards,

m

Rogers Site Call Sign Long Lat

C0121 XJV217 80° 17' 21.5"W 44° 13' 50.2"N

C0104 XJV210 80° 15' 43"W 44° 23' 34.2"N

From: Milan Vujosevic

Sent: Wednesday, August 22, 2012 11:20 AMTo: 'Carolyn Truong'

Cc: Cristian DraghiciSubject: RE: FW: Query Regarding Potential Impacts of Skyway 126 Wind Farm on Rogers Communications

Hi Carolyn,

Mkince.ca Mail - Fwd: FW: Query Regarding Potential Impacts of Skywa... https://mail.google.com/mail/u/0/?ui=2&ik=f451843616&view=pt&searc...

1 of 5 11/19/2012 10:41 AM

Page 101: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Yes, we will provide the coordinates of our sites shortly.

Cris-an,

Please provide coordinates of two sites connected with microwave link in ques-on.

Regards,

m

From: Carolyn Truong [mailto:[email protected]]

Sent: Wednesday, August 22, 2012 11:12 AM

To: Milan VujosevicCc: Christine Homuth; Approvals M. K. Ince and Associates Ltd.

Subject: Re: FW: Query Regarding Potential Impacts of Skyway 126 Wind Farm on Rogers Communications

Hi Milan,

Thanks for your response, we are looking into this issue. Would it be possible for you to provide the coordinates and call sign of the 2problematic point-to-point stations?

We are performing our analysis using Industry Canada's Spectrum Direct Database and the nearest stations that we have found have callsigns XJV217and XJV210. The identifiers C0121 Shelburne and C0104 Collingwood do not appear to show up in our search, and wewould like to ensure that our data is consistent with yours.

Best Regards,

Carolyn

On Tue, Aug 21, 2012 at 3:32 PM, Approvals M. K. Ince and Associates Ltd. <[email protected]> wrote:

---------- Forwarded message ----------From: Milan Vujosevic <[email protected]>

Date: Tue, Aug 21, 2012 at 10:19 AMSubject: FW: Query Regarding Potential Impacts of Skyway 126 Wind Farm on Rogers CommunicationsTo: "Approvals M. K. Ince and Associates Ltd." <[email protected]>

Good morning Carolyn,

The results of our analysis show that there will be indeed an impact of the proposed turbine T4 on Rogers’ exis-ng microwave path. As shown

in the a6achment, the distance between T4 and centerline of microwave beam is only 44.5m (not included poten-al inaccuracy). The turbine

blade diameter is 92.5m and it will definitely cut the Fresnel zone of microwave beam. According to the CANWEA guideline, minimum required

distance between turbine and centerline of the beam in this case should be 92m.

Please relocate the posi-on of the turbine T4 to meet this requirement. We hope that you can s-ll meet your project objec-ves.

Mkince.ca Mail - Fwd: FW: Query Regarding Potential Impacts of Skywa... https://mail.google.com/mail/u/0/?ui=2&ik=f451843616&view=pt&searc...

2 of 5 11/19/2012 10:41 AM

Page 102: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Best regards,

Milan Vujosevic

647-747-4692

From: Cristian Draghici

Sent: Monday, July 16, 2012 4:54 PMTo: Milan VujosevicSubject: RE: Query Regarding Potential Impacts of Skyway 126 Wind Farm on Rogers Communications

Hi Milan,

According to the list of 6 wind turbines and coordinates supplied in a6ached file, the proposed “Skyway126 Wind Farm” have impact with

exis!ng Rogers MW Network.

The distance between wind turbine T4 and C0121 Shelburne – C0104 Collingwood hop is only 44.5m, as in a6ached file.

T4 wind turbine has the blade diameter equal with 92.5m. In this case, wind turbine blade cut the Fresnel Ellipsoid more than 50% (my

es-ma-on is 60%).

Minimum distance according with CANWEA guideline formula is: Lc/2=92m.

Thanks,

Cris-an

From: Approvals M. K. Ince and Associates Ltd. [mailto:[email protected]]

Sent: Monday, July 16, 2012 11:43 AM

To: Milan VujosevicCc: Carolyn Truong; Christine Homuth

Subject: Query Regarding Potential Impacts of Skyway 126 Wind Farm on Rogers Communications

Good morning Milan,

M. K. Ince and Associates Ltd is consulting for Cloudy Ridge Wind Park LP, the developer of the Skyway 126 Wind Farm within theMunicipality of Grey Highlands, Ontario. According to the Spectrum Direct database, you represent the contact for Rogers WirelessPartnership for some antennas near the proposed project area.

The Spectrum Direct database indicates that there is a link between the following Roger’s Wireless antennas for this wind farm asfollows:Call Sign: XJV217Lat/Long (NAD83): 44°13'49"/-80°17'26"

The turbine coordinates are attached.

Please advise if you foresee any potential impacts to your telecommunications network as a result of the proposed wind farm.

Best Regards,

Carolyn Truong--

Mkince.ca Mail - Fwd: FW: Query Regarding Potential Impacts of Skywa... https://mail.google.com/mail/u/0/?ui=2&ik=f451843616&view=pt&searc...

3 of 5 11/19/2012 10:41 AM

Page 103: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 Wind Energy Communications Impact Assessment

M.K. Ince and Associates Ltd. Appendix June 14, 2013

Transport Canada

Page 104: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Approvals M. K. Ince and Associates Ltd. <[email protected]>

Transport Canada Submission: Skyway 126 Wind Energy project

Approvals M. K. Ince and Associates Ltd. <[email protected]> Mon, May 27, 2013 at 3:31 PM

To: CASO-SACO <[email protected]>

Cc: Sameer Shah <[email protected]>, Thomas Bernacki <[email protected]>, Hanna Vovk <[email protected]>

Good afternoon,

Please attached the Aeronautical Assessment Form for Obstruction and Lighting application for the Skyway 126 Wind Energy project

located near the town of Badjeros, Ontario. In addition to this attached document, please find attached:

1) A cover letter

2) A table of turbine locations and proposed lighting

3) A map illustrating turbine locations and lighting

Please provide your approval or comments at the earliest convenience. Similar information has been sent to NAV Canada.

Best regards,

M.K. Ince & Associates Ltd.

--

M.K. Ince and Associates Ltd.

11 Cross St., Dundas, ON L9H 2R3

Phone: 905-628-0077

Fax: 905-628-1329

http://www.mkince.ca

4 attachments

Skyway 126 Wind Energy Project -- Turbine Lighting Map (2013-05-24).pdf

1534K

Skyway 126 Wind Energy Project -- Transmittal Letter.pdf

135K

Signed Aeronautical Assessment Form for Obstruction -- Skyway 126 Wind Energy.pdf

865K

Skyway 126 Wind Energy Project -- Turbine Coordinates and Elevation.pdf

177K

Mkince.ca Mail - Transport Canada Submission: Skyway 126 Wind Ener... https://mail.google.com/mail/u/0/?ui=2&ik=f1ba1b1184&view=pt&sear...

1 of 1 5/28/2013 1:37 PM

Page 105: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 <[email protected]>

Notice of Final Public Meeting for Skyway 126 Wind Energy

Katie Meyer-Beck <[email protected]> Wed, Feb 20, 2013 at 9:09 AM

To: [email protected]

Cc: [email protected], Skyway 126 <[email protected]>

To Whom It May Concern:

Please find herein a Notice of Final Public Meeting for Skyway 126 Wind Energy as per O.Reg 359/09. In

addition, the notice was sent to your address last week via mail.

The notice was also available on the project website (www.zeroemissionpeople.com), along with a copy of

the draft Renewable Energy Approval reports and technical studies for the proposed Skyway 126 Wind Energy

project.

We welcome any questions or feedback on the proposed project.

Best,

Katie

--

Katie Meyer-Beck

Renewable Energy Project Manager

M.K. Ince and Associates Ltd.

11 Cross Street

Dundas, Ontario, L9H 2R3

Tel: 905-628-0077 ext. 242

Fax: 905-628-1329

E-mail: [email protected]

www.mkince.ca

� Please consider the environment before printing this e-mail.

2 attachments

Transport Canada Notice of Final Public Meeting EMAIL copy 2013-02-15 FINAL.pdf

77K

S126 - Notice of Final Public Meeting_2013-02-14 FINAL.pdf

154K

Page 106: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

February 19, 2013

Transport Canada, Civil Aviation

Ontario Region

300-4900 Yonge Street

Toronto ON M2N 6A5

Sent via email:

[email protected]

Reference: Notice of Final Public Meeting for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

To Whom It May Concern:

M.K. Ince and Associates Ltd., on behalf of the project proponent Cloudy Ridge Wind Park LP, informs

you of a Final Public Meeting under the Renewable Energy Approval (REA) process for the Skyway 126

Wind Energy project. The project, which will consist of up to five (5) 2.0 MW wind turbines and

associated access roads and cabling, is to be located within the Municipality of Grey Highlands, near the

community of Badjeros, Ontario.

A Notice of Final Public Meeting is enclosed. This notice is also available on the project website

(www.zeroemissionpeople.com), along with a copy of the draft Renewable Energy Approval reports and

technical studies for the proposed Skyway 126 Wind Energy project. In addition, a hard copy of the

notice was sent to your address via mail last week.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy project. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Bill York c/o Cloudy Ridge Wind Park LP

Page 107: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

NOTICE OF FINAL PUBLIC MEETING Distributed by Cloudy Ridge Wind Park LP regarding a

Proposal to Engage in a Renewable Energy Project

Project Name: Skyway 126 Wind Energy Proponent Name: Cloudy Ridge Wind Park LP Project website: www.zeroemissionpeople.com Project Location: On privately-owned agricultural lands within the Municipality of Grey Highlands, near the community of Badjeros,

Ontario Dated at the Municipality of Grey Highlands this the 20th of February, 2013

The proponent, Cloudy Ridge Wind Park LP, is planning to engage in a renewable energy project in respect of which the issuance of a Renewable Energy Approval (REA) is required. The proposal to engage in the project and the project itself is subject to the provisions of the Environmental Protection Act (Act) Part V.0.1 and Ontario Regulation 359/09 (Regulation). This notice must be distributed in accordance with section 15 of the Regulation prior to an application being submitted and assessed for completeness by the Ontario Ministry of the Environment. On Wednesday, April 24th, 2013, a public meeting will be held related to the Skyway 126 Wind Energy project:

Project Description: Pursuant to the Act and Regulation, the facility, in respect of which this project is to be engaged in, is considered to be a Class 4 Wind Energy Generation Facility. If approved, this facility would have a total maximum name plate capacity of 10 MW. The project location is described in the map below. Documents for Public Inspection: The Draft Project Description Report entitled Skyway 126 Wind Energy Description Report (Draft) describes the project as consisting of

of up to five (5) REpower MM92 wind turbines of 2 MW per turbine, wind turbine foundations, transformers, gravel access roads, underground electrical cabling, substation and other ancillary works. Further, the applicant has prepared the following documents in order to comply with the requirements under subsection 16 (5) of O. Reg. 359/09:

Project Description Report

Natural Heritage Assessment Reports, including: Records Review, Site Investigation Report,

Evaluation of Significance Report, Environmental Impact Study; Ministry of Natural

Resources (MNR) confirmation letter

Construction Plan Report

Decommissioning Plan Report

Water Bodies Assessment Report

Water Bodies Impact Assessment Report

Wind Turbine Specifications Report

Environmental Noise Impact Report

Design and Operations Report, including: Site Plan, Heritage Assessment Report with Ministry of Tourism, Culture and Sport (MTCS) confirmation letter, Shadow Flicker Report, Radar and Radio Communications Impact Assessment, Natural Heritage Environmental Effects Monitoring Plan, Archaeological Assessment Report with MTCS confirmation letter

The reports may be found online at www.zeroemissionpeople.com. Hard copies are available for viewing at:

Project Contacts and Information:

Project Contacts and Information:

To learn more about the project proposal, public meetings, or to communicate concerns, please contact: Bill York, Project Manager Cloudy Ridge Wind Park LP c/o Zero Emission People 346 Waverley Street Ottawa, ON K2P 0W5 Phone: (613) 827-7605 Email: [email protected]

OR

Katie Meyer-Beck, Project Manager M.K. Ince and Associates, Ltd. 11 Cross Street Dundas, Ontario L9H 2R3 Tel: (905) 628-0077 E-mail: [email protected]

Municipal Office of Grey Highlands 206 Toronto St S., Unit 1 POBox 409 Markdale, ON N0C 1H0

Flesherton Public Library 101 Highland Drive POBox 280 Flesherton, Ontario N0C 1E0

AND

Meeting Location: DATE: Wednesday, April 24th, 2013

TIME: 6:00 p.m. to 9:00 p.m. PLACE: Osprey Community Hall

494196 Grey Road 2 Maxwell, Ontario

FORMAT: Presentations, and Question and Answer 6:00 p.m. Presentation by the Proponent 6:15 p.m. Questions and Answers - the audience will have an opportunity to ask questions and receive answers in

a public forum. A moderator will be on hand to act as a neutral facilitator and ensure that all voices and viewpoints are heard. While we cannot guarantee that all questions can be answered at that time, we do guarantee that all questions submitted at the public meeting will be addressed in the Consultation Report, to be submitted as part of the Renewable Energy Approval application. 8:30 p.m. Open House - posters and one-on-one discussion

Please note, correspondence will form part of the public record related to the project and will be included in the Public Consultation Report. Please let us know if you would like correspondence kept confidential. We encourage comments, questions,

and concerns to be raised in written form and sent via e-mail.

Page 108: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

February 15, 2013

Transport Canada, Civil Aviation

Ontario Region

300-4900 Yonge Street

Toronto ON M2N 6A5

Reference: Notice of Final Public Meeting for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

To Whom It May Concern:

M.K. Ince and Associates Ltd., on behalf of the project proponent Cloudy Ridge Wind Park LP, informs

you of a Final Public Meeting under the Renewable Energy Approval (REA) process for the Skyway 126

Wind Energy project. The project, which will consist of up to five (5) 2.0 MW wind turbines and

associated access roads and cabling, is to be located within the Municipality of Grey Highlands, near the

community of Badjeros, Ontario.

A Notice of Final Public Meeting is enclosed. This notice is also available on the project website

(www.zeroemissionpeople.com), along with a copy of the draft Renewable Energy Approval reports and

technical studies for the proposed Skyway 126 Wind Energy project.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy project. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Bill York c/o Cloudy Ridge Wind Park LP

Page 109: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

Skyway 126 <[email protected]>

Notice of Draft Site Plan for Skyway 126 Wind Energy

Katie Meyer-Beck <[email protected]> Wed, Jan 30, 2013 at 4:10 PM

To: [email protected]

Cc: [email protected], Skyway 126 <[email protected]>

To whom it may concern:

Please find attached in this email the following with regards to the Skyway 126 Wind Energy project:

1. Cover letter

2. Notice of Draft Site Plan for Skyway 126 Wind Energy

This notice has also been sent to your office earlier this week. Please do not hesitate to respond with any further

questions.

Best regards,

Katie

[Quoted text hidden]

2 attachments

Skyway 126 Wind Energy Notice of Draft Site Plan_2013-01-30 FINAL updated.pdf

136K

Transport Canada Notice of Draft Site Plan letter EMAIL copy_2013-01-24 -FINAL.pdf

74K

Page 110: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

January 30, 2013

Transport Canada, Civil Aviation

Ontario Region

300-4900 Yonge Street

Toronto ON M2N 6A5

Sent via email:

[email protected]

Reference: Notice of Draft Site Plan for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

To Whom It May Concern:

The proponent, Cloudy Ridge Wind Park LP, submits this Notice of Draft Site Plan under the Renewable

Energy Approval (REA) process for Skyway 126 Wind Energy. The project, which will consist of up to

five (5) wind turbines with a total maximum name plate capacity of up to 10 MW, along with associated

access roads and cabling, is to be located within the Municipality of Grey Highlands, near the

community of Badjeros, Ontario.

As per Ontario Regulation 359/09 (consolidated version, November 2, 2012), a Notice of Draft Site Plan

is enclosed to clarify the locations of turbines and other project infrastructure for Skyway 126 Wind

Energy. This notice is also available on the project website (www.zeroemissionpeople.com), along with a

copy of the Draft Site Plan and associated appendices. In addition, a copy of the notice was sent to your

address earlier this week via mail.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Cloudy Ridge Wind Park LP

Page 111: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

NOTICE OF DRAFT SITE PLAN SECTION 54.1 ONTARIO REGULATION 359/09

Distributed by Cloudy Ridge Wind Park LP regarding a Proposal to Engage in a Renewable Energy Project

Project Name: Skyway 126 Wind Energy Proponent Name: Cloudy Ridge Wind Park LP Project website: www.zeroemissionpeople.com Project Location: On privately-owned agricultural lands within the Municipality of Grey Highlands, near the community of Badjeros, Ontario Dated at the Municipality of Grey Highlands this the 30th of January, 2013 The proponent, Cloudy Ridge Wind Park LP, is planning to engage in a renewable energy project in respect of which the issuance of a Renewable Energy Approval (REA) is required. The distribution of this Notice of Draft Site Plan (Notice) is subject to the provisions of the Environmental Protection Act (Act) Part V.0.1 and Ontario Regulation 359/09 (Regulation). This Notice is being distributed in accordance with sections 54 and 54.1 of the Regulation prior to an application being submitted and assessed for completeness by the Ministry of the Environment. For the purposes of the 550 meter setback prohibition (subsection 54(1) in O. Reg. 359/09) for the Skyway 126 Wind Energy project, Cloudy Ridge Wind Park LP has considered all noise receptors (as that term is defined in O. Reg. 359/09) existing on the day before this notice of draft site plan is published. The legal effect of this publication is that Cloudy Ridge Wind Park LP is not required to consider any new noise receptors that come into existence after this day. This notice was first published January 30, 2013. Project Description: Pursuant to the Act and Regulation, the renewable energy generation facility, in respect of which this project is to be engaged in, is a Wind Facility, Class 4. If approved, this facility would have a total maximum name plate capacity of up to 10 megawatts (MW). The project location is described in the map below.The project would consist of up to five (5) REpower MM92 wind turbines of 2 MW per turbine. Documents for Public Inspection: The Draft Project Description Report entitled Skyway 126 Wind Energy Draft Project Description Report describes the project as consisting of up to five (5) wind turbine generators, wind turbine foundations, step-up transformers, gravel access roads, underground and/or overhead electrical collection system, substation to connect to Hydro One power line, and temporary construction work spaces, as shown in the map below. The Draft Site Plan, associated appendices, and Environmental Noise Impact Report will be made available for public inspection at the Flesherton Public Library (101 Highland Drive, Flesherton, Ontario N0C 1E0) and on the Project website at www.zeroemissionpeople.com. Project Contacts and Information: To learn more about the project proposal, or to communicate concerns please contact: Bill York, Project Manager Cloudy Ridge Wind Park LP c/o Zero Emission People 346 Waverley Street Ottawa, ON, K2P 0W5 Phone: (613) 827-7605 E-mail: [email protected] OR Katie Meyer-Beck, Project Manager M.K. Ince and Associates Ltd. 11 Cross Street Dundas, Ontario, L9H 2R3 Phone: (905) 628-0077 E-mail: [email protected]

Skyway 126 Wind Energy

Please note, correspondence will form part of the public record related to the project and will be included in the Public Consultation Report. Please let us know if you would like correspondence kept confidential. We encourage comments, questions, and concerns to be raised in written form and sent via e-mail.

Page 112: Appendix IV Radar and Radio Communications Impact Assessmentzeroemissionpeople.com/wp-content/uploads/projects... · 2015. 1. 29. · Skyway 126 Wind Energy Communications Impact

M.K. Ince and Associates Ltd.

January 28, 2013

Transport Canada, Civil Aviation

Ontario Region

300-4900 Yonge Street

Toronto ON M2N 6A5

Reference: Notice of Draft Site Plan for Skyway 126 Wind Energy, near Badjeros in the

Municipality of Grey Highlands

To Whom It May Concern:

The proponent, Cloudy Ridge Wind Park LP, submits this Notice of Draft Site Plan, Draft Site Plan, and

associated appendices under the Renewable Energy Approval (REA) process for Skyway 126 Wind

Energy. The project, which will consist of up to five (5) wind turbines with a total maximum name plate

capacity of up to 10 MW, along with associated access roads and cabling, is to be located within the

Municipality of Grey Highlands, near the community of Badjeros, Ontario.

As per Ontario Regulation 359/09 (consolidated version, November 2, 2012), s. 54.1, a Notice of Draft

Site Plan is enclosed to clarify the locations of turbines and other project infrastructure for Skyway 126

Wind Energy. This notice is also available on the project website (www.zeroemissionpeople.com), along

with a copy of the Draft Site Plan and associated appendices.

We encourage you to contact us with any questions or concerns regarding the proposed Skyway 126

Wind Energy. Thank you for your assistance and cooperation. We look forward to your response.

Sincerely,

M. K. INCE AND ASSOCIATES LTD.

Katie Meyer-Beck

Encl.

cc. Cloudy Ridge Wind Park LP