appendix e of part 75 - envirosys.com
TRANSCRIPT
Am I a Peaking Unit? – Part 75, Appendix E An Alternative to CEMS Analyzers
Lucas L. Schneider, Senior Environmental Scientist
November 14, 2017
Presentation Overview
2
• Appendix E – Does this apply to my unit(s)?
• Appendix E – How to comply with Appendix E.
• Appendix E – Q & A
What is a Peaking Unit?
3
For a unit that reports emissions data year-round, peaking unit qualification depends on the annual capacity factor of the unit.
According to 40CFR-Part 72, a combustion unit is a peaking unit if it has:
- An average capacity factor of 10.0 percent or less over the past three years
- And, an annual capacity factor of 20.0 percent or less in each of the those three years
Definitions
4
• Capacity Factor –
• (1) The ratio of the unit’s actual annual electrical output to the nameplate capacity times 8,760 hours.
• (2) The ratio of the unit's actual annual heat input to the maximum design heat input times 8,760 hours.
Appendix E Methodology
5
• What is Appendix E?
• Pertains only to the monitoring of NOx emission rate
• Alternative methodology to monitor NOx emission rate, in lieu of installing CEMS.
Appendix E Methodology
6
• What is required to use Appendix E?
• A correlation curve of NOx emission rate vs heat input rate must be derived from emission testing.
• The hourly unit heat input rate must be measured using the Appendix D methodology
• Hourly NOx emission rate must be determined from the correlation curve
Appendix E Methodology
7
• When may Appendix E be used?
• If a unit is in one of the following program(s):
• Acid Rain Program
• CSAPR NOx Trading Program
• And, meets the definition of a “peaking unit”
• And, qualifies as oil-fired or gas-fired
What's Required for Appendix E?
8
• Appendix D methodology must be used to measure hourly unit heat input
• Heat Input Rate (mmBtu/hr) = Fuel Flow Rate x Fuel GCV x Unit Conversion Factor
• Emission testing must be performed at four different loads to develop a correlation curve of NOx Emissions Rate to Heat Input Rate
Correlation Curve
9
• Derived from emission test results
• Use Reference Method & 7E for combustion turbines
• Four-load NOx emission rate test for each type fuel combusted
• Four evenly-spaced load points ranging from minimum to maximum unit operating load
• Three runs performed at each load level
• Two years historical data used to establish minimum and maximum operating loads
Correlation Curve
10
• Heat input rate must be determined using the fuel GCV and readings from a fuel flowmeter
• Fuel flowmeter must meet the requirements of Part 75, Appendix D
• Four parameters indicative of the unit’s NOx formation characteristics are monitored and acceptable ranges established during testing.
• If the unit uses water injection for NOx control, then water-to-fuel ratio must be one of the monitored parameters
Correlation Curves
11
• NOx emission and Heat input rate are averaged at each load level
• Correlation curve of NOx emission rate vs heat input rate is constructed
• Curve segments are programmed into the data acquisition system
How are Hourly NOx Emissions Determined?
12
• NOx emission rate (lb/mmBtu)
• Following data must be collected
• Fuel flow rate must be continuously monitored using an Appendix D fuel flowmeter
• And, periodic fuel sampling is required to determine GCV according to Appendix D
• Perform the following calculations
• Use measured fuel flow rates and GCV to determine hourly heat input rate
• Select from the correlation curve the NOx emission rate that corresponds to the measured hourly heat input rate
How are Hourly NOx Emissions Determined?
13
• NOx mass emissions (lb)• Following data must be collected
• Fuel flow rate must be continuously monitored using an Appendix D fuel flowmeter
• And, periodic fuel sampling is required to determine GCV according to Appendix D
• Unit operating time must be monitored
• Perform the following calculations• Use measured fuel flow rates and GCV to determine hourly heat
input rate
• Select from the correlation curve the NOx emission rate that corresponds to the measured hourly heat input rate
• Multiply hourly heat input rate, NOx emission rate from the correlation curve and the unit operating time
Fuel Sampling Requirements
14
• Pipeline Natural Gas• Annual sampling of total sulfur content
• Monthly determination of GCV
• Fuel Oil• Daily Sampling
• Or, composite sampling for up to 168 hours, using hourly flow-proportional sampling or continuous drip sampling
• Or, sampling after each addition of oil to the storage tank
• Or, sampling each delivery or Lot of fuel ( Sample may be taken from supplier’s storage tank or from the shipment tank upon receipt
Quality Assurance Requirements
15
• Parameter Monitoring
• Hourly monitoring of the parameters that were monitored during the baseline emission testing.
• Missing data substitution must be used for NOx emission rate when:
• Any parameter is missing
• Any parameter is invalid
• Any parameter is outside the acceptable ranges established during the baseline emission testing
Data Acquisition System Console View
16
17
Quality Assurance Requirements
18
• Re-Testing
• Periodic Re-Testing
• Required once every 5 years (20 calendar quarters) to determine new correlation curves
• Unscheduled Re-Testing
• Required if any of the parametric data is outside the acceptable ranges determined during baseline emission testing for more than 16 consecutive unit operating hours
Appendix E Testing
19
20
Quality Assurance Requirements
21
• QA Plan
• Owner or Operator is required to develop and implement a quality assurance plan. Contents of the plan are specified in section 1.3.6 of Part 75, Appendix B and section 4 of Appendix E
Quality Assurance Requirements
22
• QA Plan• Minimum requirements
• Include data and results from the initial and most recent NOx emission rate testing, including parametric data
• Include written record of the procedures used to perform the NOx emission rate testing
• Include quality-assurance parameters that are monitored and the acceptable values and ranges
• Include records of the monitored parametric data for each unit operating hour
• Fuel flowmeter must meet the on-going QA requirements of Appendix D
Loss of Peaking Status
23
• A unit will lose its peaking status if the capacity factors have not been met for an Appendix E unit
• Loss of peaking status requires installation and certification of a NOx -diluent monitoring system by December 31 of the calendar year following the year in which peaking status is lost.
• A unit which has lost peaking status may qualify again for peaking status in a subsequent year only if capacity factor data for a three year period following the loss of peaking status show that the unit once again meets the requirements stated earlier.
Testing Requirements (2 units)
24
• 4 Loads
• 3 Test Runs Required
• 3 Hours / Run
• ~ 2 Hour for Tester Calibrations and Other Work
• ~12 - 14 Hours / Test
25
Questions?