Annandale Public School. The Team. Local Sponsors Preservation Planner Historical Architect Structural Engineer Mechanical Engineer Cost Estimator Financial Analyst. The Process. Assess rehab potential Talk to stakeholders Identify obstacles and opportunities Evaluate alternatives - PowerPoint PPT PresentationTRANSCRIPT
Annandale Public School
The Team• Local Sponsors• Preservation Planner• Historical Architect• Structural Engineer• Mechanical Engineer• Cost Estimator• Financial Analyst
The Process• Assess rehab potential• Talk to stakeholders• Identify obstacles and opportunities• Evaluate alternatives• Prepare schematic designs• Assign costs• Work the numbers
Disposition Alternatives• Continued School Use• Demolition• Do Nothing• Interim Use• Phased Rehabilitation• Full Rehabilitation
Parameters• Find a productive reuse of the
building• Serve a community purpose• Reduce burden on School District• Find a compatible use• Anticipate future of site• Maximize use of incentives• Minimize cost to taxpayers
Use Alternatives• Community Center• Technology Center• Affordable Housing• Upscale Condominiums
Scenarios• Interim Use—Core of a Community
Center• Community Center/Affordable
Housing• Community Center/Upscale
Condominiums
Interim Use
Community Center
Dwelling Units-Level 1
Dwelling Units-Level 2
Site Plan
Costs• Interim Use: $12,000-$30,000
(Prep only—does not include operating costs)
• Partial-Community Ctr: $4,573,000-$6,338,000(Reduces amount of incentives available)
• Full-Community Ctr/Affordable: $6,000,000
• Full-Community Ctr/Condos: $7,960,000• Site Work: $665,000-$861,000
(Included in overall costs, includes garages)
Financial and OwnershipKey Themes for Funding:• Partnerships• Taxability• Phasing
-
Project Finance Tools• Federal and State Tax Credits• TIF/Tax Abatement• Grants• Private Lending
ComparisonsCommunity/AffordableCOST: $7,000,001LI Tax Credit $ 2,565,000Fed Tax Credit$1,260,000State Tax Credit $1,260,000TIF Finance $ 269,825Private Donation $ 500,000Private Lending $ 600,000GAP: $ 544,893
Both assume dollar sale School District Funds not Included
Community/CondosCOST: $7,000,001Fed Tax Credit$1,260,000State Tax Credit$1,260,000TIF Finance $ 269,825Sale of Units $1,317,450Private Donation $ 500,000Private Lending$1,030,000GAP: $1,362,726
Examples• Orono Discovery Center
• Central Square-Glenwood
Examples• Chatfield Center for the Arts
• Glencoe Civic Center
Examples• Detroit Lakes Community Center
• Central Park Bluff View Suites– Red Wing
Next Steps• Establish an organization• Buy time• Implement measures for interim use• Develop programs• Articulate a case statement• Seek partners• Raise funds