Annandale Public School. The Team. Local Sponsors Preservation Planner Historical Architect Structural Engineer Mechanical Engineer Cost Estimator Financial Analyst. The Process. Assess rehab potential Talk to stakeholders Identify obstacles and opportunities Evaluate alternatives - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Annandale Public School

Annandale Public School

Page 2: Annandale Public School

The Team• Local Sponsors• Preservation Planner• Historical Architect• Structural Engineer• Mechanical Engineer• Cost Estimator• Financial Analyst

Page 3: Annandale Public School

The Process• Assess rehab potential• Talk to stakeholders• Identify obstacles and opportunities• Evaluate alternatives• Prepare schematic designs• Assign costs• Work the numbers

Page 4: Annandale Public School

Disposition Alternatives• Continued School Use• Demolition• Do Nothing• Interim Use• Phased Rehabilitation• Full Rehabilitation

Page 5: Annandale Public School

Parameters• Find a productive reuse of the

building• Serve a community purpose• Reduce burden on School District• Find a compatible use• Anticipate future of site• Maximize use of incentives• Minimize cost to taxpayers

Page 6: Annandale Public School

Use Alternatives• Community Center• Technology Center• Affordable Housing• Upscale Condominiums

Page 7: Annandale Public School

Scenarios• Interim Use—Core of a Community

Center• Community Center/Affordable

Housing• Community Center/Upscale

Condominiums

Page 8: Annandale Public School

Interim Use

Page 9: Annandale Public School

Community Center

Page 10: Annandale Public School

Dwelling Units-Level 1

Page 11: Annandale Public School

Dwelling Units-Level 2

Page 12: Annandale Public School

Site Plan

Page 13: Annandale Public School

Costs• Interim Use: $12,000-$30,000

(Prep only—does not include operating costs)

• Partial-Community Ctr: $4,573,000-$6,338,000(Reduces amount of incentives available)

• Full-Community Ctr/Affordable: $6,000,000

• Full-Community Ctr/Condos: $7,960,000• Site Work: $665,000-$861,000

(Included in overall costs, includes garages)

Page 14: Annandale Public School

Financial and OwnershipKey Themes for Funding:• Partnerships• Taxability• Phasing

-

Page 15: Annandale Public School

Project Finance Tools• Federal and State Tax Credits• TIF/Tax Abatement• Grants• Private Lending

Page 16: Annandale Public School

ComparisonsCommunity/AffordableCOST: $7,000,001LI Tax Credit $ 2,565,000Fed Tax Credit$1,260,000State Tax Credit $1,260,000TIF Finance $ 269,825Private Donation $ 500,000Private Lending $ 600,000GAP: $ 544,893

Both assume dollar sale School District Funds not Included

Community/CondosCOST: $7,000,001Fed Tax Credit$1,260,000State Tax Credit$1,260,000TIF Finance $ 269,825Sale of Units $1,317,450Private Donation $ 500,000Private Lending$1,030,000GAP: $1,362,726

Page 17: Annandale Public School

Examples• Orono Discovery Center

• Central Square-Glenwood

Page 18: Annandale Public School

Examples• Chatfield Center for the Arts

• Glencoe Civic Center

Page 19: Annandale Public School

Examples• Detroit Lakes Community Center

• Central Park Bluff View Suites– Red Wing

Page 20: Annandale Public School

Next Steps• Establish an organization• Buy time• Implement measures for interim use• Develop programs• Articulate a case statement• Seek partners• Raise funds

Page 21: Annandale Public School

Annandale Public School