PHASE: _________________
ACTIVITY LEVEL INTEGRATED WORK PLAN FOR:___________________Spectrum Specialty Builders
ACTIVITY PERFORMED BY:_________________________
Schedule Description
Predecessor Activity Prime Walls
Start Date 24-Sep 25-Sep 26-Sep 29-Sep 30-Sep
Milestone #1 Level 2 Acrovyn
Milestone #2 Level 3 Acrovyn
Milestone #3
Milestone #4
End Date
Successor Activity
Page 1 of __
SAFETY 1. All is from floor elevation without the use of ladders. 2. Typical hazard is hand and finger cut from knifes. 3. Only electrical tool is an easy edger for cutting sheet. Note: This section to include issues such as access, scaffold information, typical hazards and mitigation, additional PPE, etc.
Required Crew: 1 to 2 Work Hours: 8 Hours Productivity Requirements Complete one restroom in d days Max.
Quality 1. GWB must be primed and dust free for good adhesion. 2. Temporary lighting may be nesscary for detail cuts and transitons at wall protection. 3. Measuring and cutting of ot plumbing penetrations should be within tolerances so that sechucheon plates cover the cut. Hole saw may be required. Moldings are to be used where reuqired.
Revision History Date 9-19-14 ORIGINAL PLAN
Prepared by: Name Company Dan Pridemore Spectrum
Reference Documents 1 Spectrum Shop Drawing
Tools / Equipment Adhesive trowls Easy edger
Crew Name Signature
Materials Quantity Acrovyn 30 sheets FRP 10 Sheets Sheet material must be laid flat
Task List 1. Handle material ot laydown area 2. Inspect wall surfaces 3. Measure sheets for size and penetrations 4. Install adhesive and sheets .
CONTACTS Emergency 911 Mortenson - Superintendent Mortenson - Quality Manager Subcontractor?
Typical plan for sheet on Levels 2 and 3 refer to "Foreman" shop drawings for locations on Level 1