spectrum wall prot - iwp

1
PHASE: _________________ ACTIVITY LEVEL INTEGRATED WORK PLAN FOR:__ Spectrum Specialty Builders ACTIVITY PERFORMED BY:_________________________ Schedule Description Predecessor Activity Prime Walls Start Date 24-Sep 25-Sep 26-Sep 29-Sep 30-Sep Milestone #1 Level 2 Acrovyn Milestone #2 Level 3 Acrovyn Milestone #3 Milestone #4 End Date Successor Activity Page 1 of __ SAFETY 1. All is from floor elevation without the use of ladders. 2. Typical hazard is hand and finger cut from knifes. 3. Only electrical tool is an easy edger for cutting sheet. Note: This section to include issues such as access, scaffold information, typical hazards and mitigation, additional PPE, etc. Required Crew: 1 to 2 Work Hours: 8 Hours Productivity Requirements Complete one restroom in d days Max. Quality 1. GWB must be primed and dust free for good adhesion. 2. Temporary lighting may be nesscary for detail cuts and transitons at wall protection. 3. Measuring and cutting of ot plumbing penetrations should be within tolerances so that sechucheon plates cover the cut. Hole saw may be required. Moldings are to be used where reuqired. Revision History Date 9-19-14 ORIGINAL PLAN Prepared by: Name Company Dan Pridemore Spectrum Reference Documents 1 Spectrum Shop Drawing Tools / Equipment Adhesive trowls Easy edger Crew Name Signature Materials Quantity Acrovyn 30 sheets FRP 10 Sheets Sheet material must be laid flat Task List 1. Handle material ot laydown area 2. Inspect wall surfaces 3. Measure sheets for size and penetrations 4. Install adhesive and sheets . CONTACTS Emergency 911 Mortenson - Superintendent Mortenson - Quality Manager Subcontractor? Typical plan for sheet on Levels 2 and 3 refer to "Foreman" shop drawings for locations on Level 1

Upload: spectrum-specialty-builders

Post on 03-Apr-2016

214 views

Category:

Documents


0 download

DESCRIPTION

 

TRANSCRIPT

PHASE: _________________

ACTIVITY LEVEL INTEGRATED WORK PLAN FOR:___________________Spectrum Specialty Builders

ACTIVITY PERFORMED BY:_________________________

Schedule Description

Predecessor Activity Prime Walls

Start Date 24-Sep 25-Sep 26-Sep 29-Sep 30-Sep

Milestone #1 Level 2 Acrovyn

Milestone #2 Level 3 Acrovyn

Milestone #3

Milestone #4

End Date

Successor Activity

Page 1 of __

SAFETY 1. All is from floor elevation without the use of ladders. 2. Typical hazard is hand and finger cut from knifes. 3. Only electrical tool is an easy edger for cutting sheet. Note: This section to include issues such as access, scaffold information, typical hazards and mitigation, additional PPE, etc.

Required Crew: 1 to 2 Work Hours: 8 Hours Productivity Requirements Complete one restroom in d days Max.

Quality 1. GWB must be primed and dust free for good adhesion. 2. Temporary lighting may be nesscary for detail cuts and transitons at wall protection. 3. Measuring and cutting of ot plumbing penetrations should be within tolerances so that sechucheon plates cover the cut. Hole saw may be required. Moldings are to be used where reuqired.

Revision History Date 9-19-14 ORIGINAL PLAN

Prepared by: Name Company Dan Pridemore Spectrum

Reference Documents 1 Spectrum Shop Drawing

Tools / Equipment Adhesive trowls Easy edger

Crew Name Signature

Materials Quantity Acrovyn 30 sheets FRP 10 Sheets Sheet material must be laid flat

Task List 1. Handle material ot laydown area 2. Inspect wall surfaces 3. Measure sheets for size and penetrations 4. Install adhesive and sheets .

CONTACTS Emergency 911 Mortenson - Superintendent Mortenson - Quality Manager Subcontractor?

Typical plan for sheet on Levels 2 and 3 refer to "Foreman" shop drawings for locations on Level 1