RSOC System Testing Status - 1
• RSOC System Test Concept– Covered in RO-EST-PL-5013– Status to be presented at key system reviews (GSRR)
• Connectivity Tests– Covered by tests in RO-EST-TP-3051
• Interface Tests– Based on Pointing & Interference Scenario inputs
• End-to-end Tests– Based on GLEP operations used for SFT
• Short-term Schedule
RSOC System Testing Status - 2
• RSOC System Test Concept– Covered in RO-EST-PL-5013
• Document defines the overall system level test plan for RSOC
• Corresponding System Test Report will summarise status
• Copy will be made available on ‘livelink’
• Specific instructions will be given to PI-teams for each test
– Status to be presented at key system reviews (GSRR)• Status at GSRR will establish following readiness criteria
– RSOC Interfaces tested (PI-RSOC-RMOC)– RSOC End-to-end data flow is verified for routine ops.– Draft Interference and Pointing Scenarios are available
• End of RSOC Commissioning Phase will establish– RSOC system has been fully validated– ‘Knowledge-base’ available at RSOC is adequate for Mission
RSOC System Testing Status - 3
• Connectivity Tests– Covered by tests defined in RO-EST-TP-3051 – Tests conducted over the last few weeks– Results reported in RO-EST-TR-3063
– In summary ---> All ran OK !
RSOC System Testing Status - 4
• Interface Tests– Based on Pointing & Interference Scenario inputs
• Two REAL Scenarios will be used (Pointing & Interference).
• PI-teams will provide draft inputs for these scenarios (ITL files defining the operations and EDF files containing all necessary TC-sequences.
• These inputs (with modifications made by RSOC) will be used to perform detailed interface testing between RSOC and RMOC.
• These inputs will be collated and used as the basis for the actual Pointing and Interference scenarios to be executed at the end of the S/C commissioning phase. (First real operations of payload performed using RSOC provided inputs). Availability of these draft scenarios must be confirmed at the GSRR.
RSOC System Testing Status - 5
• End-to-end Tests– Based on GLEP operations used for SFT
• RSOC will provide PI teams with files to use for this test :– TC-Sequence.edf containing definitions of TC sequences needed
to perform GLEP operations.– RSDB.edf containing the command definitions for each instrument
(this RSDB.edf is invoked within in the TC-Sequence.edf and is derived from the RMOC database).
– A draft OIOR.itl to be used as the operational input file for the end-to-end test.
– PI teams will perform pre-defined actions on these files and transfer them to RSOC.
– RSOC will consolidate all inputs and transfer them to RMOC as a POR file.
– RMOC will execute this POR file on the PFM during SVT 1.2 (tbc)– PI-teams can retrieve data from DDS and confirm success.
RSOC System Testing Status - 6
SFT-GLEPITL’s
OIOR.itlTC-SEQ.edf
RSDB
RSDB.edf
‘livelink’
TC-SEQ.edf
OIOR.itl
RSDB.edf
TC-SEQ.edf
OIOR.itl
Add PING-SEQ
Add PING-SEQ
RSOC E2E Step 1 - prepare test files from SFT PI’s E2E Step 2 - prepare test files
RSOC System Testing Status - 7
CS update
OIOR.itlTC-SEQ.edf
RSDB.edf
OIOR.itlTC-SEQ.edf
Local EPS
D D S
POR file
OIOR.itlTC-SEQ.edf
RSOC EPS
RSDB.edf
PI’s E2E Step 3 - provide test input RSOC E2E Step 4 - consolidate files
Update Cycle
Planning Cycle
RSOC System Testing Status - 8
TM files
RMOC
DDS
POR file
PI TM Analysis
ReferenceSFT GLEP ITL
CS update
RSDB
PFMS/C
TCStack
Test ReportALL OK !
RMOC E2E Step 5 - process POR for SVT PI’s E2E Step 6 - retrieve TM from DDS & check
RSOC System Testing Status - 9
• Short-term Schedule– Source test-files needed by PI-teams for end-to-end test will be available on
‘livelink’ on 28th June 2002.– PI-teams will make simple modifications to test files and transfer them to
RSOC as a TC-Sequence -Update-Request (EDF file) and an OIOR (ITL file) by 5th July 2002.
– RSOC will generate TC-Sequence-Update files for ESOC (Excel files) and a consolidated POR expressing the GLEP operations for the whole payload. (Due 15th July 2002).
– ESOC will perform these GLEP operations as part of SVT 1.2 (first week August 2002)
– PI-teams will retrieve TM data from DDS and analyse it to confirm expected GLEP operations were performed. Results will be reported by 16th August 2002.
– Draft Pointing & Interference inputs from PI-teams shall be available by TBD in July.