mice rf system - status
DESCRIPTION
MICE RF System - Status. Alan Bross Fermilab. RF Cavities for MICE I . Eight 201-MHz cavities in the MICE cooling channel First five cavities arrived at LBNL last year and have been measured Second batch of five cavities will be complete by Oct. 2010 . RF Cavity Design Parameters. - PowerPoint PPT PresentationTRANSCRIPT
MICE RF System - Status
Alan BrossFermilab
RF Cavities for MICE I
Eight 201-MHz cavities in the MICE cooling channel
• First five cavities arrived at LBNL last year and have been measured
• Second batch of five cavities will be complete by Oct. 2010 Page 2MICE Project Board September 23, 2010 Alan
Bross
RF Cavity Design Parameters• The cavity design parameters
– Frequency: 201.25 MHz– β = 0.87– Shunt impedance (VT2/P): ~ 22 MΩ/m– Quality factor (Q0): ~ 53,500– Be window diameter and thickness: 42-cm and 0.38-mm
• Nominal parameters for MICE and (cooling channels) in a neutrino factory or muon collider – 8 MV/m (~16 MV/m) peak accelerating field– Peak input RF power: 1 MW (~4.6 MW) per cavity – Average power dissipation per cavity: 1 kW (~8.4 kW)– Average power dissipation per Be window: 12 watts (~100 watts)
Page 3MICE Project Board September 23, 2010 Alan Bross
• Cavity has been tested successfully without magnetic fields• Be windows can withstand high RF power in strong magnetic
field without damage
NCRF Cavity for Muons
Page 4MICE Project Board September 23, 2010 Alan Bross
RF cavities for MICE III
•
• Production of the second batch of five MICE cavities going well at Applied Fusion Company in California
Nose ringsPort extruding and flangesBrazing water cooling tubes Modified extruding techniqueExperimented using the test cavityNeed argon gas purge to prevent oxidation of cavity surfaceMeasure oxidation layer thickness
Page 5MICE Project Board September 23, 2010 Alan Bross
The RF Cavity at LBNL
Page 6MICE Project Board September 23, 2010Alan Bross
CMM Scans of MICE Cavity• Special probe to measure the
inside profile of the cavity• Cavity interior profile being
measured with special probe ( 1,800 points per scan)• The profile will be used to verify
cavity RF models
-650 -600 -550 -500 -450 -400 -350 -300 -250 -200 -150
-50
0
50
100
150
200
250
Page 7MICE Project Board September 23, 2010Alan Bross
RF Measurements, Results
S11 measurements
S21 measurements
Page 8MICE Project Board September 23, 2010Alan Bross
Measurement Results• Two cavities have been measured in different
window configurations using Be windows #1 and #2• MICE cavity #1: S21 measurements (2 probes) with all
ports shorted: Q 44,000 – 44, 600 (over 80% of the design Q)
• MICE cavity #4: S21 measurements (2 probes) with all ports shorted: Q 43,600 – 44, 000 (over 80% of the design Q)
Window 1) 2) 1) (2 (1 (2 (2 (1Frequency 200.990
MHz199.786
MHz201.179
MHz201.179
MHz
Window 1) 2) 1) (2 (1 (2Frequency 200.642
MHz199.454 MHz
200.839 MHz
Page 9MICE Project Board September 23, 2010Alan Bross
RF Cavity Electro-polishingNext Crucial Step
Page 10MICE Project Board September 23, 2010Alan Bross
•The inside surface of each RF cavity will be electropolished
•Discussions under way with local company
Electro-polish tank dimensions: 12' Long x 5' Wide x 6' Deep
Large SS piping weldment at AET
RF Cavity Frequency Tuners
Page 11MICE Project Board September 23, 2010Alan Bross
• 24 Dynamic Cavity Frequency Tuners per Module• Tuner Actuator
•Tuners operate in a bi-directional “push - pull” mode (±2mm)•Tuning automatically achieved through a frequency feedback loop
Cavity Frequency Tuner Components
• Dual – action actuator
• Flexure tuner arm
• Actuator is
screwed intothe
tuner arm• Fixed
connection
• Forces are transmitted to the stiffener ring by means of “push-pull” loads applied to the tuner lever arms by the dual action actuator assembly
•Tuner/actuators are thermally independent of the vacuum vessel
12MICE Project Board September 23, 2010
Alan Bross
RF Cavity Frequency Tuner Progress Summary
• Tuner design is complete• ¼ scale model has been fabricated to test flexure
concept• One full size tuner arm (for testing the system) has
been fabricated• Aluminum test cylinder (1/6 of cavity) has been
fabricated• Actuator mechanical components have been
fabricated• Actuator bellows have been delivered to LBNL• Assembly of an actuator has begun at LBNL• Control system components have been delivered to
LBNL 13MICE Project Board September 23, 2010
Alan Bross
Cavity RF Coupler
Section view of cavity RF coupler
•Based on successful SNS design with a Toshiba window•Detailed fabrication drawings of the major components are
complete
14MICE Project Board September 23, 2010
Alan Bross
Cavity RF Coupler Design Summary
• Detail drawings of major components are complete
• Sources for fabrication materials (e.g. 4” outer coax tube) have been identified
• Assembly method has been determined
15MICE Project Board September 23, 2010
Alan Bross
Schedule Summary
16MICE Project Board September 23, 2010
Alan Bross
RF Power Systems
17MICE Project Board September 23, 2010
Alan Bross
RF system components
Andrew Moss
2 MW Amplifier
2 MW Amplifier
Master OscillatorControls etc
201 MHz Cavity Module
2 MW Amplifier
2 MW Amplifier
201 MHz Cavity Module
LBNL CERN
300 kW Amplifier
300 kW Amplifier
300 kW Amplifier
300 kW Amplifier
HT Supplies
HT Supplies
Daresbury
DL Test SystemAt present
Auxiliary Systems
Auxiliary Systems
Not found
Test system at Daresbury
Andrew Moss
Amplifier status
Andrew Moss
• First medium power (300kW) amplifier and power supply system tested 2008
• Refurbishment and rebuild of first high power (2MW) amplifier complete October 2009
• Power supplies for first 2MW amp 95% complete• Two further 300kW amplifiers awaiting repair• Two refurbished 2MW CERN amplifiers partly
tested, awaiting assembly and high power test• Still need to build 3 more sets of power supplies• One more 300kW amplifier to buy/acquire
Current status of components
Andrew Moss
Predicted hall layout for RF components
Andrew Moss
Hall design in progress• Working with 3D CAD engineer to plan layout between the
amplifiers and cavities• Measurements of system dimensions at Daresbury have been
taken • First step is a simple block diagram showing all components
and how they are interconnected• Then understand how to optimise components with the layout
of the hall and the space available• Result will be a complete parts list required for each cavity
that we can go out for tender for when appropriate
Andrew Moss
Future plans for this year• Test of first large amplifier is priority - expected this month• Amplifier testing likely to take 4 – 6 weeks to optimise the
system using old tubes, then replace with new MICE tubes and repeat tests carefully
• Assembly of the first CERN amplifier, refurbished unit however many small parts, CERN have offered to send two people for a few days to aid with the assembly of the unit – we will take up this offer
• Would need to buy more coax components to test this amplifier in our system – coax bends, straights and a combiner
• Test of CERN amplifier scheduled for March 2011• First amplifier will be delivered and installed in the MICE hall
Andrew Moss
Conclusion• Complete RF amplifier system ready for test, results
expected by end September • Design of hall components between amplifiers and
cavities is in progress and will lead to a formal design of the coax system, how it will be supported and the sequence of installation
• Funding will allow building of CERN amplifier and possible refurbishment of other LBNL amplifier systems
Andrew Moss
What about the RF in Magnetic Field Problem?
RF Test Facility
• MuCool Test Area (MTA)– RF power
• 201 MHz (5MW)• 805 MHz (12 MW)
– Class 100 clean room– 4T SC solenoid
• 250W LHe cryo-plant– Instrumentation
• Ion counters, scintillation counters, optical signal, spectrophotometer
– 400 MeV p beam line
Page 27MICE Project Board September 23, 2010Alan Bross
The RF Challenge
• Significant degradation in maximum stable operating gradient with applied B field
• 805 MHz RF Pillbox data– Curved Be windows– E parallel B– Electron current/arcs focused by B
• Degradation also observed with 201 MHz cavity
– Qualitatively, quite different
Page 28MICE Project Board September 23, 2010Alan Bross
805 PillboxPost-Mortem
• Significant damage observed– Iris– RF coupler– Button holder
• However– No damage to
Be window
Page 29MICE Project Board September 23, 2010Alan Bross
201 MHz Cavity TestTreating NCRF cavities with SCRF processes
• The 201 MHz Cavity – Achieved 21 MV/m– Design gradient – 16MV/m – At 0.75T reached 10-12 MV/m However, No observed damage!
Page 30MICE Project Board September 23, 2010Alan Bross
201 MHz Cavity RunningSpark Data
Page 31MICE Project Board September 23, 2010Alan Bross
0.00E+00 2.00E+06 4.00E+06 6.00E+06 8.00E+06 1.00E+07 1.20E+070
5
10
15
20
25
GradientSparksB
Number of pulses
Num
ber o
f spa
rks,
gra
dien
t MV/
m a
nd M
agne
tid fi
eld
in T
esla
x10
in T
B=0 Running
Design Gradient
MICE Gradient
201 MHz Prototype
Note: Stored energy available to sparks » 100J (100X that of 805)
Page 32MICE Project Board September 23, 2010Alan Bross
Coupler Ceramic
Page 33MICE Project Board September 23, 2010Alan Bross
TiN CoatedCeramic
201 MHz Cavity B Field TestsSummary
• Sparking @ B=0 did condition the 201 cavity• Sparking @ B ¹ 0 causes damage (B relatively low)• Re-conditioned @ B=0.• But upon inspection of the cavity
– No observed damage in cavity• SCRF processing techniques help
– Some “arcing” evidence on ceramic disk of coupler may be indicative and needs further study• Plan to remove and inspect towards the end of this
month
Page 34MICE Project Board September 23, 2010Alan Bross
Conclusions• Work on the 201 MHz cavities is well underway
and progressing nicely• Although we have seen problems with the 201
prototype operating in B, at MICE gradient (8 MV/m) there appear to be no issues– Coupler damage needs to be investigate– Caveat: Not operated in B of MICE lattice yet!
• RF power systems component work is also progressing nicely– Some minor delays due to manpower availability, but
have been resolvedPage 35MICE Project Board September 23, 2010
Alan Bross
Acknowledgements:Derun Li, Steve Virostek (Cavities)
Andy Moss (RF Power)
MICE Project Board September 23, 2010Alan Bross 36
Backup Slides
MICE Project Board September 23, 2010Alan Bross 37
RF cavities for MICE II
•
• The first five MICE cavities have been measured in three different window configurations using Be windows #1 and #2 (reference windows)
*no water cooling tube brazed to the cavity body
Cavity # 1 2 3 4 5 (spare)*
Freq. (MHz) 201.084 200.888 201.247 200.740 201.707
Page 38MICE Project Board September 23, 2010 Alan Bross
RF measurements, Team Work!
Be window installation
Page 39MICE Project Board September 23, 2010Alan Bross
RF Cavity Tuner System Schematic
40MICE Project Board September 23, 2010
Alan Bross
Actuator Design
•Actuator design incorporates a sealed enclosure between vacuum and air.
• Actuator is mounted to the tuner arm only
• Bellows allows angular movement for actuator
• Piston plates are joined at the perimeter
• Piston plates incorporate hard stops
41MICE Project Board September 23, 2010
Alan Bross
Cavity RF Coupler Future Work
•16 Toshiba windows (plus spares) need to be ordered soon because of long lead times
• Myat RF couplers need to be purchased• Prototype of the outer coax will be fabricated to verify assembly method
• Vendor selection process will be started
42MICE Project Board September 23, 2010
Alan Bross
2MW amplifier summery
• Final electrical checks September 2010 – crowbar/cathode modulator systems
• Amplifier connected to test load via coax
• Water system, air blowers and compressed air have all been on
• Filament test to 500A on tube• HT system /earth system
checked out and signed off• Safety paperwork needs
completing before we power system
Andrew Moss
Coax layout for each cavity
Andrew Moss
Damage to Coupler Ceramic Window?
Page 45MICE Project Board September 23, 2010Alan Bross
201 MHz Cavity RunningSummary I (B=0)
Design Gradient
Limited by RFPower
Page 46MICE Project Board September 23, 2010Alan Bross