its building project - progress update 7

Post on 23-Jan-2017

472 Views

Category:

Education

3 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Progress Update (Nr. 7)Week ending 18th December

Programme Update - ITS For Period : Mon 7th December – Friday 18th December

- Completed external steelwork installation

- Completed installation of ground floor slab

- Commenced installation of external system scaffold around new steelwork structure

- Completed overboarding of existing ceilings to all floors within existing building

- Continued internal builders work within existing building

- Commenced internal plastering works to walls within existing building

Progress Photos – External

Completed external steelwork installation

Progress Photos – External

Completed external steelwork installation

Progress Photos – External

Poured ground floor concrete slab of extension

Progress Photos – External

Ground floor slab shuttering stripped and perimeter ‘stoned up’ in preparation for scaffold

Progress Photos – Internal

Commenced wiring to sockets of rooms within existing building

Progress Photos – Internal

Commenced lining of internal walls within basement

Progress Photos

UoL external hoarding graphics installed

Next Few Weeks………..A look ahead to works commencing within the next 2 weeks :

- Complete installation of external system scaffold around new steelwork structure

- Commence below ground brickwork

- Complete intumescent sprayed coating to external steel frame

- Complete new wall linings to basement

- Complete internal builders work within existing building

- Continue plastering works to walls and ceilings within existing building

top related