Flood Diversion Authority October Report

Presented by

Program Management Consultant (PMC) Team

1

October 10, 2013

Outline

Schedule Update

– OHB Levee

– In-Town Levees

Supplemental EA Changes

September 2013 Highlights

– Technical

– Other

October Priorities 2

OHB Levee Project Plan

3

OHB Levee Schedule Oct 2013

WP-43A Land

Start: Oct 2013

End: May 2014

Begin acquisition of agricultural land

WP-43C Land

Start: Oct 2013

End: Apr 2016

Begin residential and business acquisition and relocation

4

Borrow area for levees

OHB Levee Schedule Mar 2014

WP-43B Land

Start: Mar 2014

End: Apr 2015

Begin acquisition of

remaining

agricultural land

5

Borrow area for levees

OHB Levee Schedule Summer 2014

WP-43A Land:

Complete

WP-43B Land:

Continues

WP-43C Land:

Continues

WP-43A

Construction:

Summer 2014

6

Borrow areas for levees

Oxbow Development Begins

OHB Levee Schedule Summer 2015

WP-43A

Construction:

Complete

WP-43B

Construction:

Summer 2015

WP-43D - Pump Station

Construction:

Summer 2015

WP-43B Land:

Continues

7

PS

Borrow areas for levees

OHB Levee Schedule Summer 2016

WP-43A, -43B, -43D

Construction:

Complete

WP-43C

Construction:

Summer 2016

8

PS

Borrow areas for levees

OHB Levee Schedule Fall 2016

WP-43A, WP-43B,

WP-43C, WP-43D

Construction:

Complete

9

PS

Stormwater Ponds

In-Town Levees Schedule

Land Acquisition to begin in October for known required

properties

Design is being coordinated with the New City Hall

project

10

Supplemental EA Changes

Northern alignment improvements

Western alignment improvements

VE-13 A improvements

More Flow Through Town

Gates on the Diversion Inlet

Protection for Oxbow, Hickson, and Bakke

11

New Map

12

Bridge Reaches

– Back-checking review comments

– Continuing design on CR-20 bridge

OHB Levee

– Geotechnical and Survey work on-going

– Design has begun on the southern section

Cultural

– Planning activities for Phase 1 cultural field work

In-Town levees

– Coordinating with New City Hall project

Continued to support Corps with H&H and other Work-in-Kind 13

September 2013 Highlights - Technical

JPA Amendment #2 finalized

Corps Environmental Assessment signed and released to the

public

Integral Determination Report authorizing Work-In-Kind credit

for the OHB Levee work approved by USACE

Executive Leadership Council and Joint PM Board meeting

conducted with Authority and Corps leadership

14

September 2013 Highlights – Other Activities

October 2013 Priority Areas

Authorization (WRRDA)

OHB Levee

– Geotechnical

– Cultural

– Design

– Permitting

– Land Acquisition

In-Town Levees

– Coordination with New City Hall Project

– Land Acquisition

15

Next

Corps of Engineers Monthly Update