Flood Diversion Authority October Report Presented by Program Management Consultant (PMC) Team 1 October 10, 2013

Upload: others

Post on 25-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

Flood Diversion Authority October Report

Presented by

Program Management Consultant (PMC) Team

1

October 10, 2013

Page 2: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

Outline

Schedule Update

– OHB Levee

– In-Town Levees

Supplemental EA Changes

September 2013 Highlights

– Technical

– Other

October Priorities 2

Page 3: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

OHB Levee Project Plan

3

Page 4: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

OHB Levee Schedule Oct 2013

WP-43A Land

Start: Oct 2013

End: May 2014

Begin acquisition of agricultural land

WP-43C Land

Start: Oct 2013

End: Apr 2016

Begin residential and business acquisition and relocation

4

Borrow area for levees

Page 5: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

OHB Levee Schedule Mar 2014

WP-43B Land

Start: Mar 2014

End: Apr 2015

Begin acquisition of

remaining

agricultural land

5

Borrow area for levees

Page 6: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

OHB Levee Schedule Summer 2014

WP-43A Land:

Complete

WP-43B Land:

Continues

WP-43C Land:

Continues

WP-43A

Construction:

Summer 2014

6

Borrow areas for levees

Oxbow Development Begins

Page 7: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

OHB Levee Schedule Summer 2015

WP-43A

Construction:

Complete

WP-43B

Construction:

Summer 2015

WP-43D - Pump Station

Construction:

Summer 2015

WP-43B Land:

Continues

7

PS

Borrow areas for levees

Page 8: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

OHB Levee Schedule Summer 2016

WP-43A, -43B, -43D

Construction:

Complete

WP-43C

Construction:

Summer 2016

8

PS

Borrow areas for levees

Page 9: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

OHB Levee Schedule Fall 2016

WP-43A, WP-43B,

WP-43C, WP-43D

Construction:

Complete

9

PS

Stormwater Ponds

Page 10: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

In-Town Levees Schedule

Land Acquisition to begin in October for known required

properties

Design is being coordinated with the New City Hall

project

10

Page 11: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

Supplemental EA Changes

Northern alignment improvements

Western alignment improvements

VE-13 A improvements

More Flow Through Town

Gates on the Diversion Inlet

Protection for Oxbow, Hickson, and Bakke

11

Page 12: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

New Map

12

Page 13: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

Bridge Reaches

– Back-checking review comments

– Continuing design on CR-20 bridge

OHB Levee

– Geotechnical and Survey work on-going

– Design has begun on the southern section

Cultural

– Planning activities for Phase 1 cultural field work

In-Town levees

– Coordinating with New City Hall project

Continued to support Corps with H&H and other Work-in-Kind 13

September 2013 Highlights - Technical

Page 14: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

JPA Amendment #2 finalized

Corps Environmental Assessment signed and released to the

public

Integral Determination Report authorizing Work-In-Kind credit

for the OHB Levee work approved by USACE

Executive Leadership Council and Joint PM Board meeting

conducted with Authority and Corps leadership

14

September 2013 Highlights – Other Activities

Page 15: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

October 2013 Priority Areas

Authorization (WRRDA)

OHB Levee

– Geotechnical

– Cultural

– Design

– Permitting

– Land Acquisition

In-Town Levees

– Coordination with New City Hall Project

– Land Acquisition

15

Page 16: Flood Diversion Authority October Report Presentations/2013... · Bridge Reaches –Back-checking review comments –Continuing design on CR-20 bridge OHB Levee –Geotechnical and

Next

Corps of Engineers Monthly Update

16