FACILITIES MANAGEMENT J anuary 31 , 2020 Capi t a l Con st ru ct ion & Renovat ions Repor t No. 01

CONSTRUCTION PROJECT STATUS REPORT Alderman Library Renewal

160 McCormick Road

Architect: HBRA Architects, Chicago Construction Manager: Skanska USA Building, Inc, Durham

Current Status:

Current Activities Metal shelving being removed and recycled, 50% complete New and Old Stacks abatement start, 5% complete Site fencing, signage, and mark Newcomb Road, 70% complete

Near Future Activities Set construction trailer Install gates Start site utilities

Package 1 (Demo, Site, Abate) NTP January 23, 2020 Alderman Library closes for two years May 9, 2020 Full construction activities start June 8, 2020 Partial library reopens Fall Semester 2022 Construction complete December 2022 Percent complete now 0.5%

FM CC&R Project Team Please feel free to contact any of our team with questions or comments. Kit Meyer 434-531-7094 * Charles Durrer 434-962-4084 * Jesse Kidd 434-987-2170 * Henry Hull 434-270-1574

Ksm2g@virginia.edu ced5q@virgini.edu jrk4d@virginia.edu hmh5xj@virginia.edu

1. Historic photo showing the 4th

floor reference room in 1939,the year that Alderman Libraryopened.

2. 2019 photo showing the currentcondition of the 4th floorreference room.

3. Rendering of the same roomwith sprinklers, code upgraddes,and original features restored.