Sheet1RATE ANALYSIS FOR BRICKWORKDownloaded from TheConstructor.Org

Wall DimensionsLengthWidthHeightArea m2Vol. m3Half Brick Wall0.0 m0.0 m1.0 m0.00.000

Full Brick Wall1.0 m1.0 m1.0 m1.01.000

C/S Mortar Ratio1:4

Dry Mortar Qty0.36
Emran: For full B.W by vol,25% of cement mortar is used.And for half B.W by vol, 30% of cement mortar is used.

MATERIAL Qty.Rs. /UnitAMT (Rs.)SUBTOTAL (Rs.)Bricks49441976.00Cement Bags 3.27250818.44Sand m30.45900408.963203.40

LABOUR With Hand Mixing of Mortar Days

MASON 0.94300282LABOUR 1.37250343BAHISHTI (Water Carrier)0.2020040

664.50Prime Cost3867.90

Scafolding @2% of prime costAmount77.3677.36 Sundries@3% of prime costAmount116.04116.04CONTRACTOR PROFITContractor Profit15%609.19

TOTAL COST (Rs.)4,670.49